Sol_140L3626R0001_Amd_0003.pdf

PDF 254 KB Posted

Attached to
GAOA SOUTH PRYOR ROADS
Solicitation number
140L3626R0001
Issued by

About this file

This document is Amendment 0003 to a Bureau of Land Management (BLM) solicitation for road construction and maintenance services. The solicitation is administered by BLM MT-State Office (MT935) in Billings, Montana, with an effective date of August 19, 2026. The contract ID is 140L3626R0001, and the period of performance runs from September 4, 2026 to May 7, 2027.

The amendment incorporates questions and answers from interested offerors addressing project-specific technical requirements. Key clarifications include: the finished roadway top width is 15 feet with 2-foot-wide ditches on each side; protruding rocks in the existing road base may be left in place if covered by newly placed aggregate (no more than ½ inch of designed thickness); locally sourced crushed limestone with 12 percent material passing the No. 200 sieve is approved despite specifications calling for 2-8 percent; and contractors are responsible for quality control (QC) testing while the BLM conducts quality assurance (QA) testing. Compaction testing is required at a minimum of one test per 1,000 linear feet, with placed aggregate achieving 92 percent maximum dry density. The project requires erosion control measures (straw wattles preferred), seeding in disturbed areas outside the finished roadway, and turnaround construction only with prior BLM approval. Water for aggregate conditioning is unavailable onsite; contractors must secure sources independently, with previous contractors connecting to fire hydrants in Frannie, Wyoming. Approved aggregate sources include the nearby limestone quarry and Frost Rock Products. Offerors must acknowledge receipt of this amendment prior to the offer submission deadline.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: is not is required copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7.ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

PAGESOF

Contractor

The hour and date specified for receipt of Offers to sign this document and return

Jorge Alvarez

See continuation page

BLM MT-STATE OFC(MT935)

5001 SOUTHGATE DR.

BILLINGS MT 59101

BLM MT STATE OFC(MT935)

5001 SOUTHGATE DR.

BILLINGS MT 59101

LMA

LMA

140L3626R0001

08/19/2026

07/16/2026

1 4

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES

NAME OF OFFEROR OR CONTRACTOR

SUPPLIES/SERVICES

(B)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

OPTIONAL FORM 336 (4-86)

Sponsored by GSA FAR (48 CFR) 53.110

ITEM NO.

(A)

QUANTITY

(C)

NSN 7540-01-152-8067

140L3626R0001/0003

See the pages below for changes incorporated by this amendment.

Period of Performance: 09/04/2026 to

05/07/2027

Description of Changes - This amendment incorporates the following information:

1. The Government is providing the Questions received from interested offerors and the associated Answers provided by the Government.

Acknowledgement - See Block 11 above regarding how to acknowledge this amendment. The Government must receive the acknowledgement at the place designated for receipt of offers (See Block 8 of the Standard Form 1442).

Third Party – If you have given a copy of the solicitation to someone else, please forward this amendment accordingly.

New Questions & Answers

1. On the existing road, there are larger rocks that are protruding through the existing road base on the majority of the route. The plans call for a 3 percent cross slope, however this could be achieved a few different ways. Are we to install road base on top of these areas to achieve grade? Are we to excavate this material and fill with suitable material? Please advise The BLM interprets that some of those rocks will be removed/broken down during the site preparation grading. It would be allowable to install aggregate over those rocks even if they stick up some (no more than ½ the designed aggregate typical thickness) into the newly placed aggregate. This was considered in the design and why this is roughly the areas of the 6" typical section. Additionally, it will be the Contractors means and methods on how to achieve this work.

2. The approved source for the crushed limestone at the nearby limestone quarry said that their material is usually around 12% on the No. 200 sieve......but the specs say it needs to be between 2-8. The ammendment for the project claims that this material would be suitable for the bid. Would this material be acceptable for the work considering the differentiation on the No. 200 Sieve? Please advise.

The BLM will work with contractors on securing local nearby aggregate sources and can modify the gradations. The local limestone source is an approved mix that has been used on past projects. The No.

200 sieve at 12 will be approved if this source is proposed.

3. It appears that materials testing is the responsibility of the contractor, is this the case? Or are you seeking QA testing?

Yes. This is the responsibility of the Contractor. We are seeking Contractor QC testing in the bid. The BLM will conduct their own QA testing, as needed.

Question 1 Is there a water source onsite for conditioning the road aggregate?

Answer 1 No. There is no water source available onsite for conditioning the aggregate. Contractors on previous projects in the area have obtained water by connecting to a fire hydrant in Frannie, Wyoming.

Question 2 Would aggregate supplied from a nearby limestone quarry be acceptable?

Answer 2 Yes. Aggregate supplied from the nearby limestone quarry is an approved source. The other approved aggregate source in the area is Frost Rock Products.

Question 3 What is the required finished top width of the roadway?

Answer 3 The finished top width of the roadway shall be 15 feet, as shown in the roadway typical sections on Sheet 23 of the plan set. The project also includes construction of a 2-foot-wide ditch on each side of the roadway. Vegetation removed during ditch construction shall be bladed to the back of the construction limits and wasted onsite.

Question 4 Can turnarounds be constructed?

Answer 4 Yes. Turnarounds may be constructed but must receive prior approval from the BLM. Several existing turnarounds are located at trailheads along the project corridor, and use of these existing locations is preferred whenever practical.

Question 5 Is compaction testing required for this project?

Answer 5 Yes. Compaction testing of newly placed aggregate is required. Section 300, Page 300-2, of the project specifications requires a minimum of one compaction test per 1,000 linear feet of roadway.

The placed aggregate shall achieve a minimum of 92 percent of the maximum dry density.

Question 6 Are erosion control measures required?

Answer 6 Yes, although erosion control requirements are expected to be minor. Erosion control measures should be implemented at the few small head cuts adjacent to the roadway where disturbance could result in sediment transport. Straw wattles are BLM’s preferred best management practice for this project.

Question 7 Is seeding required?

Answer 7 Yes. Section 700, Page 700-2, of the project specifications contains the seeding requirements.

Seeding shall be limited to disturbed areas outside the finished top width of the roadway and other areas disturbed by construction.

Amendment of solicitation/modification of contract
Contract ID code
Amendment/modification number
Effective date
Requisition/purchase requisition number
Project number
Issued by
Code
Administered by
Code
Name and address of contractor
Code
Facility code
Amendment of solicitation number
Dated
Modification of contract/order number
Dated
This item only applies to amendments of solicitations
Accounting and appropriation data
This item applies only to modifications of contracts/orders.
This change order is issued pursuant to:
The above numbered contract/order is modified to reflect the administrative changes
This supplemental agreement is entered into pursuant to authority of:
Other
Important:
Description of amendment/modification
Name and title of signer
Contractor/offeror
Date signed
Name and title of contracting officer
Signature of Contracting Officer
Date signed
Previous edition unusable
Standard form 30 (rev. 11/2016)
Continuation sheet
Reference Number
Name of Offeror or Contractor
OPTIONAL FORM 336 (4-86))

Sponsored by GSA FAR (48 CFR) 53.110

File details come from the government source that posted it. Updated .