B08_Attachment_2_Quote_Schedule__Price_and_Estimated_Quantities_REVISED_7_30_2026_0001.docx
DOCX document 46 KB Posted
- Attached to
- NORCAL NEW REPAVING HEADWATERS FR TRAIL
- Solicitation number
- 140L1226Q0019
About this file
This is a Quote Price Schedule and Schedule of Work Deliverables template for a pavement repaving project on the Headwaters FR Trail under solicitation 140L1226Q0019 issued by the Department of the Interior Bureau of Land Management California Region.
The project encompasses nine primary tasks: Mobilization, Full Depth Repairs (3,000 SF), Surface Preparation (56,940 SF), Tack Coat application (56,940 SF), Dense-graded HMA asphalt overlay conforming to FHWA FP-14 Section 403 specifications using PG 64-10 binder in a 1.5-inch compacted lift (56,940 SF), Shoulder Backing with 2-inch compacted Class II base and one-foot tapers on either side (11,388 LF), Compaction Testing (8 production days), Quality Control, and Site Restoration/Demobilization. Contractors must provide completed Quote Price Schedules with unit prices and total prices for each CLIN, submit technical proposals, and include GANTT charts showing concurrent and overlapping tasks along with contingency and emergency response plans. Material estimates indicate approximately 750 tons of dense-graded HMA (combining full-depth repairs and overlay), 600 gallons of tack coat, 150 tons of Class II base, and 2,500 pounds of crack seal for areas not designated for full-depth repair. This template requires contractors to elaborate on pricing and scheduling as appropriate for their offeror submittal packages.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION C, UNIFORM CONTRACT FORMAT (UCF)
DESCRIPTION / SPECIFICATION / STATEMENT OF WORK (SOW)
Schedule of Work Deliverables Contractor will fill out and submit in Quote Package along with Technical Proposal, Quote Price Schedule, Contingency and Emergency Response Plan. Contractor will also submit GANTT chart/calendar view of Schedule of Work Deliverables to better represent concurrent and/or overlapping tasks.
| SPECIFIC TASK DELIVERABLE |
| START DATE |
| END DATE |
Task 1 – Mobilization
Task 2 – Full Depth Repairs
Task 3 – Surface Preparation
Task 4 – Tack Coat
Task 5 – Pavement Conformance at HEC Barn
Task 6 – Asphalt Overlay
Task 7 – Shoulder backing
Task 8 – Quality Control
Task 9 – Site Restoration and Demobilization
Quote Price Schedule Contractor shall complete and elaborate on this format as is appropriate for their Offeror Submittal Package.
| CLIN |
| Description |
| Unit |
| Estimated Quantity |
| Unit Price |
| Total Price |
| 0001 |
| Mobilization |
| EA |
| 1 |
| 0002 |
| Full Depth Repairs |
| SF |
| 3000 |
| 0003 |
| Surface Preparation |
| SF |
| 56940 |
| 0004 |
| Tack Coat |
| SF |
| 56940 |
| 0005 |
| Dense-graded HMA conforming to FHWA FP-14 Section 403, using either 3/8-inch or 1/2-inch NMAS, PG 64-10, placed in one uniform 1.5-inch compacted lift. |
| SF |
| 56940 |
| 0006 |
| Shoulder Backing |
· 2” compacted seed free Class II base
· One feet taper on either side of finished paved surface
· 5,694 LF of trail * 2 sides of shoulder = 11,388 LF of shoulder
| LF |
| 11,388 |
| 0007 |
| Compaction Testing |
· 1 per production day
| EA |
| 8 |
| 0008 |
| Site restoration, cleanup, demobilization |
| EA |
| 1 |
| - |
| TOTAL PRICE |
| --------------------------------------------- |
Materials Estimate
| Item |
| Unit |
| Planning Quantity |
| Notes |
| Dense-graded HMA, 3/8-inch or 1/2-inch NMAS, PG 64-10 |
| ton |
| 750 |
| Includes full-depth repair HMA and one 1.5 inch asphalt overlay |
| Tack Coat |
| gallon |
| 600 |
| Layer between existing surface and new overlay |
| Class II base |
| ton |
| 150 |
| Includes full depth repair base and tapered shoulder backing (1.5” at edge, 1-ft taper). Conforming to SOW Task 7 |
| Crack Seal |
| lb |
| 2500 |
| To be applied on cracks ≥ 1/4 inch on areas not marked for Full Depth Repair |
SOW Page 2