Attachment_0001_-_Conant_Bank_DB_SOW_Final.pdf

PDF 326 KB Posted

Attached to
CONANT BANK STABILIZATION
Solicitation number
140L0626R0011
Issued by

About this file

This is a Design-Build Statement of Work for the Conant Bank Stabilization and Parking Area Expansion project issued by the Bureau of Land Management (BLM), Upper Snake Field Office in Bonneville County, Swan Valley, Idaho, dated March 30, 2026.

The Design-Build Contractor (DBC) shall provide complete integrated design and construction services addressing three primary scope components: (1) Bank Stabilization—design and construction of riverbank stabilization along approximately 300 linear feet of the west bank of the South Fork of the Snake River, incorporating natural channel design, bioengineering techniques, and rock structures to accommodate 100-year and 500-year flood events while increasing fish habitat quality; (2) Raft Launch/Take-out Restoration or Relocation—restoration or relocation of the existing raft launch/take-out to restore safe access and eliminate hazardous vertical banks; and (3) Parking Area Expansion—design (Option #1) and/or construction (Option #2) to reconfigure and expand the raft launch/take-out parking area with prioritization of boat trailer parking and incorporation of asphalt pavement for new roadways and connected parking spaces. All instream work must occur during the September 15–October 31 low-flow window per Idaho Department of Fish and Game regulations. The DBC must also maintain and monitor all plantings and seeding for no less than one year following construction completion.

The total Period of Performance is 743 calendar days, with design phases progressing through Schematic Design (by day 65), 35% Design Development (day 125), 65% Design Development/Construction Documents (day 185), 95% Design Development (day 215), 100% Design Development/Construction Documents (day 235), Final Construction Documents (day 245), Pre-Construction Meeting (day 275), Construction completion (day 713), and As-Constructed Drawings submission (day 743). The estimated design start date is October 19, 2026, with design completion June 21, 2027. The DBC shall establish a detailed Critical Path Method project schedule with activities limited to 15 workdays maximum duration, updated monthly with progress reports. All A/E services must be performed by licensed architects and engineers registered in Idaho, with stamped and signed geotechnical reports and survey data required. Design submittals shall include cost estimates and progressively detailed drawings at each phase. Construction requirements include compliance with environmental and sustainability standards, Storm Water Pollution Prevention Plan implementation, construction zone fencing, staging area limitations, accident prevention program submission, quality control daily reports, working hours restricted to 7:00 AM–6:00 PM weekdays unless Government-approved, and servicing/refueling of equipment limited to 150 feet from water sources. Progress payments during design are based on submission and acceptance of design deliverables; construction payments are based on percentage of work completed using an approved Schedule of Values. The Government will serve as Authority Having Jurisdiction, and the BLM Project Inspector will coordinate construction efforts but hold no authority to accept/reject work or obligate the Government for time or money.

View the file

Other files

Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

a

A/E/C Services Statement of Work

Design- Build (DB)

CONANT BANK STABILIZATION

PARKING AREA EXPANSION

BLM Upper Snake Field Office Conant Boat Access

Bonneville County, Swan Valley, Idaho

UNITED STATES DEPARTMENT OF THE INTERIOR

Bureau of Land Management National Operations Center

Architecture & Engineering Branch (OC-671)

03/30/2026

Conant Bank Stabilization & Parking Area Expansion

Upper Snake Field Office Design-Build Statement of Work

03/30/2026

CONTENTS

1 OVERVIEW 5

1.1 Project Introduction and Background

1.2 Project Scope

1.2.1 Bank Stabilization (Required)

1.2.2 Raft Launch/Take-out Restoration or Relocation (Required):

1.2.3 Parking Area Expansion Design – Option #1:

1.2.4 Parking Area Expansion Construction – Option #2:

1.3 Design-Build Contractor Scope

1.4 Value Engineering (VE)

1.5 Government Furnished Information and Materials

2 GENERAL PROJECT REQUIREMENTS 8

2.1 Progress Payments

2.1.1 Design Phase:

2.1.2 Construction Phase:

2.2 Project Schedule

2.2.1 General:

2.2.2 Purpose:

2.2.3 Software:

2.2.4 Schedule Development:

2.2.5 Value Engineering and Design Optimization Coordination

2.2.6 Project Schedule Updates

2.2.7 Progress Payments:

2.3 Forms

3 DESIGN PARAMETERS 11

3.1 General

3.2 Compliance & Authority Having Jurisdiction (AHJ)

3.3 Site Design

4 DESIGN DELIVERABLES & SERVICES 12

4.1 Overview

4.2 Project Administration & Management Services

4.3 pre-design (pd) & SCHEMATIC DESIGN (SD) Deliverables & Services

4.3.1 Deliverables & Services (PD/SD)

4.4 Design Development (DD) & Construction Document (CD) Deliverables & Services

4.4.1 Deliverables and Services (DD/CD)

4.5 Construction Administration

5 CONSTRUCTION REQUIREMENTS 14

5.1 Overview

5.2 Environmental and Sustainability Requirements

5.2.1 Sustainability Requirements:

Design-Build Statement of Work

03/30/2026

5.2.2 Minimize Construction Impacts:

5.2.3 Air and Water Pollution Control:

5.3 Schedule of Values

5.4 Construction Support

5.4.1 Staging Areas

5.4.2 Structures

5.4.3 Construction Zones

5.4.4 Parking of Construction Vehicles

5.5 Submittals During Construction

5.5.1 Applicability

5.5.2 Construction Submittal Types:

5.5.3 Government Review of Construction Submittals

5.5.4 Use for Construction

5.6 Construction Coordination

5.7 Construction Photographic Documentation

5.8 Construction Quality Control

5.9 Working Hours Restrictions

5.10 Temporary Services

5.10.1 Vehicles and Equipment

5.10.2 Hazard Control

5.10.3 Spark Arresters

5.10.4 Smoking

5.10.5 Welding

5.10.6 Water

5.10.7 Sanitary Facilities

5.11 Access

5.12 Preservation of Adjacent Features

5.13 Existing Utilities

5.14 Hauling Restrictions

5.15 Accident Prevention

5.15.1 Accident Prevention Program

5.15.2 Accident Reporting

5.15.3 Quality Assurance

5.15.4 Accident Prevention Products

5.15.5 Training

5.16 Temporary Controls

5.16.1 Housekeeping

5.17 Field Engineering

5.18 Project Close-Out

5.18.1 Project Record Drawings

5.18.2 As-Constructed Drawings

5.18.3 Final Inspection

5.19 Substantial Completion and Final Inspection

6 DELIVERABLE DETAILS 24

6.1 Format Requirements

6.2 Distribution

Design-Build Statement of Work

03/30/2026

6.3 Communication

7 PERIOD OF PERFORMANCE & SCHEDULE 25

7.1 Period of Performance Summary

7.2 Kickoff Meeting and Site Visit

7.3 Site Survey, Geotechnical, and Schematic Design Documents

7.4 35% Design Development Documents

7.5 65% Design Development/CONSTRUCTION Documents

7.6 95% Design Development Documents

7.7 100% Design DevelopmentCONSTRUCTION Documents

7.8 Final Construction Documents

7.9 Construction

7.10 As-Constructed Drawings

8 SUBMITTALS AND MEETINGS 27

8.1 Design Submittals

8.2 Progress Meetings

8.2.1 Progress Meeting Milestones

8.2.2 Design Phase Progress Meetings

8.2.3 Pre-Construction Meeting

8.2.4 Construction Phase Progress Meetings

8.2.5 Meeting Participation

8.3 Quality Control

8.4 Required Reports

9 [NOT USED] 30

Design-Build Statement of Work

03/30/2026

1 OVERVIEW

1.1 PROJECT INTRODUCTION AND BACKGROUND

The Bureau of Land Management (BLM), Idaho Falls District, Upper Snake Field Office (USFO), requires a Design-Build Contractor (DBC) to provide complete and integrated design and construction services for the Conant Bank Stabilization and Parking Area Expansion Project located at the Conant Boat Access site.

The Conant Boat Access is a public recreation site that includes a primary concrete boat ramp with an associated parking area and restroom facilities, as well as a secondary aggregate and timber raft launch/take-out with its own parking area and restroom facilities. The site provides critical recreational access to the South Fork of the Snake River and serves approximately 200,000 visitors annually. Since 2004, ongoing riverbank erosion has compromised the safety and functionality of the raft launch/take-out and the adjacent riverbank, while also contributing to sediment deposition at the primary concrete boat ramp.

The recreation site is in need of riverbank stabilization and restoration or relocation of the associated raft launch/take-out. The site also needs expansion of the raft launch/take-out parking area.

The Statement of Work outlines the design and construction work to be completed by the DBC.

1.2 PROJECT SCOPE

The overall project scope to be designed and constructed by the Design-Build Contractor (DBC) under this Statement of Work shall be as follows:

1.2.1 Bank Stabilization (Required)

The DBC shall design and construct riverbank stabilization along approximately 300 linear feet of the west bank of the South Fork of the Snake River upstream of the primary concrete boat ramp.

The riverbank stabilization design and construction shall be coordinated with the restoration or relocation of the existing raft launch/take-out as necessary to support long-term site stability and safe public use. The Contractor shall be responsible for identifying specific treatments to be implemented to address the riverbank erosion that threatens property and infrastructure.

The DBC shall conduct instream work during low-flow periods and follow IDFG Upper Snake River Region’s South Fork Snake & all tributaries instream work window September 15th – October 31st.

Performance and Design Objectives:

The riverbank stabilization system shall:

1) Comply with the Government furnished Riparian Habitat Restoration EA, NEPA decision documents, Guidelines for a Quality Built Environment, and River Access Planning Guide.

2) Accommodate the 100-year design and 500-year check flood events.

3) Mitigate scour and channel degradation.

4) Reduce sediment deposition at the primary boat ramp.

5) Avoid creation of hazards to river users or the public.

6) Incorporate natural channel design, bioengineering techniques, and/or rock structures as appropriate.

7) Incorporate self-maintaining treatments that increase fish habitat quality and quantity.

Design-Build Statement of Work

03/30/2026

8) Utilize hydraulic and geomorphic analyses appropriate for riverine systems.

9) Maintain compatibility with recreational use and navigation.

10) Maintain and monitor all plantings/seeding incorporated into project construction. Period shall last for no less than 1 year following completion of construction.

1.2.2 Raft Launch/Take-out Restoration or Relocation (Required):

In the Base Schedule the DBC shall design and complete restoration or relocation construction of the existing raft launch/take-out as necessary to restore safe access for rafts, kayaks, and similar watercraft.

Work may include restoration of the existing raft launch/take-out in its existing location if deemed necessary by the riverbank design. Work may also include relocation of the raft launch/take-out if deemed necessary by the bank stabilization design.

Performance and Design Objectives:

The raft launch/take-out restoration or relocation shall:

1) Restoration (if applicable) shall be coordinated with riverbank stabilization measures.

2) Relocation (if applicable) shall be coordinated with riverbank stabilization measures.

3) Eliminate hazardous vertical banks.

4) Provide safe separation from vehicular traffic.

5) Accommodate anticipated river flow conditions and recreational use.

6) The raft launch/take-out relocation shall be kept within the construction limits of the riverbank stabilization work.

1.2.3 Parking Area Expansion Design – Option #1:

Option 1 Schedule Pay Item 04 consists of a design to reconfigure and expand the raft launch/take-out parking area to optimize parking for users.

Design may include but is not limited to grading, pavement surfacing, aggregate surface design, markings, wheel stops, signage and associated site features.

Design Objectives:

The parking area expansion design shall:

1) Use existing raft launch/take-out roadway, associated parking area, and surrounding unpaved ground to optimize design.

2) Maximize the number of parking spaces for the available area. Prioritize boat trailer parking over passenger car parking.

3) Incorporate asphalt pavement for new roadway and connected parking spaces. Smaller passenger car parking spaces not directly connect to roadway may be surfaced with aggregate materials.

4) Incorporate raft launch/take-out user rigging area.

1.2.4 Parking Area Expansion Construction – Option #2:

Option 2 Schedule Pay Item 05 consists of the construction to reconfigure and expand the raft launch/take-out parking area according to BLM approved DBC design.

Design-Build Statement of Work

03/30/2026

Work may include but is not limited to grading, drainage, pavement surface construction, aggregate surface construction, markings, wheel stops, signage, and associated site features.

Performance Objectives:

The parking area expansion construction shall:

1) Match up to the existing pavement structure unless otherwise approved by the Government.

2) Leave existing restroom facilities in place.

3) Not impede the public’s use of the primary concrete boat ramp and associated parking area.

4) Maintain and monitor all plantings/seeding incorporated into project construction. Period shall last for no less than 1 year following completion of construction.

1.3 DESIGN-BUILD CONTRACTOR SCOPE

The Design-Build Contractor (DBC) shall be responsible for the design and construction of various improvements to the Conant Boat Access site.

The work will include, but may not be limited to, the following:

• Evaluate the Government Requirements.

• Review Government furnished information and materials.

• Upon award, provide schedule of work, with milestone submittal dates indicated. Coordinate proposed milestone dates with the Government.

• Prepare Topographical Survey and Geotechnical Reports (if applicable).

• The DBC may submit Value Engineering Change Proposals (VECPs) in accordance with FAR

52.248-3 Value Engineering-Construction. Any VECP shall be coordinated with the Government for review and approval prior to implementation.

• Submit DB Design Development and DB Construction Documents for review and approval, as required per milestone dates outlined in the design schedule.

• Provide schedule of construction work. Coordinate proposed milestone dates with Government.

• Secure work area and provide for continued access to the primary concrete boat ramp and associated parking area as technically feasible. Coordinate with the Government regarding which portions of the facility will be accessible to the public throughout the construction phase.

• Construct project.

• Provide Project Record documents and As-Constructed Drawings.

1.4 VALUE ENGINEERING (VE)

The DBC is encouraged to propose improvements in design, methods, or materials that reduce cost, improve quality, or enhance performance. Such proposals shall be submitted as Value Engineering Change Proposals (VECP) in accordance with FAR 52.248-3, Value Engineering- Construction. The Government will evaluate VECPs in accordance with FAR requirements, including cost sharing where applicable.

1.5 GOVERNMENT FURNISHED INFORMATION AND MATERIALS

The Government will provide the following information and materials:

● Attachment-1: Upper Snake Field Office Riparian Habitat Restoration EA.

● Attachment-2: Upper Snake Field Office Riparian Restoration Project Final Biological Assessment.

Commented [TS1]: See my markup. Is that what you’re saying, match new pavement up to the existing pavement edge?

Commented [JB2R1]: Yes, corrected.

Design-Build Statement of Work

03/30/2026

● Attachment-3: Hydraulic Scoping Memorandum with FIRM Maps.

● Attachment-4: Geotechnical Scoping Memorandum with Zone Mapping.

● Attachment-5: Highway Design Memorandum.

● Attachment-6: Final Geotechnical Investigation Results with Appendices.

● Attachment-7: Survey and Modeling Data:

● Attachment-8: Guidelines for a Quality Built Environment.

● Attachment-9: River Access Planning Guide.

● Attachment-10: BMP Handbook – Best Management Practices for Idaho Rural Road Maintenance.

2 GENERAL PROJECT REQUIREMENTS

2.1 PROGRESS PAYMENTS

Progress payments shall be made to the DBC as follows:

2.1.1 Design Phase:

Progress payments during the design phase of the work will be based on submission, review, and acceptance of design deliverables as outlined in this Statement of Work.

2.1.2 Construction Phase:

Progress payments during construction will be based on the percentage of work completed on items listed on the approved schedule of values. Actual construction completed and in place will form the basis for payment. Verification of the percentage of completion shall be initiated by the DBC under the direction of a representative of the Government, unless the Government waives this requirement in a specific instance. The DBC shall make the computations for payment based on the Government’s verification of work completed and in place for any periods for which progress payments are requested. The DBC shall furnish to the Government originals of all field notes and all other records relating to the basis for payment, who shall use them as necessary to determine the final amount of progress payments. The DBC shall retain copies of all such material furnished to the Government.

2.2 PROJECT SCHEDULE

The Project Schedule shall be managed by the DBC as follows:

2.2.1 General:

The DBC shall furnish the project schedule to the Government and provide digital copies after award and before the Design Meetings. The Schedule shall include a detailed design phase with design deliverable submission dates and review periods, as well as a summary construction schedule, with important milestones included for both phases.

The DBC shall fully develop the construction portion of the schedule and submit it to the Government before the Preconstruction Meeting or any construction begins. The project schedule shall be updated every month throughout the entire contract period until project substantial completion. The status date of each schedule update shall be 10 days before the progress payment request date.

Design-Build Statement of Work

03/30/2026

Construction work cannot begin until Government approval is obtained for the entire set of 100% Complete Construction Documents.

2.2.2 Purpose:

The purpose of the project schedule is to ensure adequate planning, coordination, scheduling, and reporting during execution of design and construction activities of the DBC. The project schedule will assist the DBC and the Government in monitoring the progress of the work, evaluating proposed changes, and processing the DBC’s monthly progress payment requests.

2.2.3 Software:

Scheduling software shall be the latest version of Microsoft Project or approved equal.

2.2.4 Schedule Development:

The project schedule shall cover the entire contract period. The late finish date of the project schedule shall be the same date as the established completion date of the contract.

The DBC shall use the Critical Path Method (CPM) with limited use of lead or lag durations between scheduled activities. The DBC’s project schedule shall consist of procurement activities (including mobilization, submittal issue and approvals, and the fabrication and delivery of key and long-lead procurement items) and construction activities.

The DBC’s project schedule shall consist of, but not be limited to, the following for each activity:

• Identify each and every activity number with numerical designations (maximum 5-digit).

Number of activities shall be in increments of 10.

• Concise description of the work represented by the activity (maximum 48 characters).

Avoid the use of non-standard abbreviations. The work related to each activity shall be limited to one work trade.

• Activity duration in whole working days with a maximum duration of 15 workdays each, unless otherwise approved by the Government; exceptions may be made for non-construction activities including mobilization, shop drawing and sample submittals, fabrication of materials, delivery of materials and equipment, and concrete curing.

In developing the project schedule, the DBC shall be responsible for ensuring that subcontractor work at all tiers, as well as its own work, is included in the project schedule.

The project schedule, as developed, shall show the sequence and interdependence of activities required for complete performance of the work. The DBC shall be responsible for ensuring all work sequences are logical and the project schedule shows a coordinated work plan, with critical path dependencies clearly delineated. Proposed durations assigned to each activity shall be the DBC’s best estimate of time required to complete the activity considering the scope and resources planned for the activity. Resource loading of each activity shall list all personnel by labor category and equipment type and capacity proposed to complete the activity in the duration shown. Include any permit requirements and constraints. Seasonal weather and river conditions shall be considered and included in the planning and scheduling of all work influenced by high and low river flows, high or low ambient temperatures, wind and/or precipitation, etc. to ensure completion of all work within the contract time.

Design-Build Statement of Work

03/30/2026

2.2.5 Value Engineering and Design Optimization Coordination

The project schedule shall include activities associated with design optimization and Government-led Value Analysis (VA) workshops. If the DBC elects to prepare a Value Engineering Change Proposal (VECP), the DBC shall coordinate such efforts within the project schedule. Submission and review of VECPs shall not delay contract performance unless approved by the Contracting Officer.

2.2.6 Project Schedule Updates

2.2.6.1 Monthly Updates:

The monthly updating of the project schedule shall be an integral part and basic element of the estimate upon which progress payments shall be made under this contract. If, in the judgement of the Government, the DBC fails or refuses to provide a schedule of values and a complete schedule update or revision as specified hereinafter, the DBC shall be deemed to have not provided the required information upon which the progress payment may be made and shall be subject to retainage of a portion of the payment.

2.2.6.2 Progress Report:

The report shall include a brief description of the actual progress made during the update period; actual and potential delaying activities; any impediments to progress; issues related to inclement weather; progress toward established milestones and project float. The report shall include a brief description of the work anticipated to be performed in the next month.

Any minor revisions to the schedule should be identified so they can be evaluated and accepted or rejected.

As the project progresses, indicate Actual Completion percentage for each activity. If the schedule update shows a late finish date after the contract completion date, at a minimum, include the following in the progress report submission:

• Any known delays.

• Actions that will be taken to get back on schedule.

• Pending modifications.

• Impediments or constraints affecting progress.

2.2.7 Progress Payments:

The monthly updating of the currently accepted construction schedule shall be an integral part of the process upon which progress payments will be made under this contract. If the Contractor fails to provide schedule updates or revisions, then a portion of the monthly payment may be retained until such corrections have been made.

Time Impact Analysis for Contract Modifications, Changes, Delays, and Contractor Requests Requirements:

When contract modifications or changes are initiated, delays are experienced, or the DBC desires to revise the project schedule, the DBC shall submit to the Government a written time impact analysis illustrating the influence of each modification, change, delay, or DBC request on the contract time.

Time Extensions:

Design-Build Statement of Work

03/30/2026

Activity delays shall not automatically mean that an extension of the contract time is warranted or due to the DBC. It is possible that a modification, change, or delay will not affect existing critical activities or cause non-critical activities to become critical. A modification, change, or delay may result in only absorbing a part of the available total float that may exist within an activity chain of the project schedule, thereby not causing any effect on the contract time. Time extensions will be granted in accordance with the terms of the contract.

Float: Float is not for the exclusive use or benefit of either the Government or the DBC.

Extension of the contract time will be granted only to the extent the equitable time adjustments to the activity or activities affected by the modification, change, or delay exceeds the total (positive or zero) float available on a particular activity.

2.3 FORMS

The Government will require the DBC to submit the following forms at appropriate intervals and milestones established prior to commencement of project construction:

• Submittal / Transmittal.

• Accident / Property Damage Reports.

• Quality Control Reports.

• Testing Reports.

• Inspection Reports.

• Update / Status Reports.

The actual forms used will be designed by the DBC with input from the Government and approved by the Government.

3 DESIGN PARAMETERS

3.1 GENERAL

The DBC will be responsible for developing an integrated design solution, construction documents, and final construction.

The project design will require review and coordination with the Government. This includes, but is not necessarily limited to riverbank stabilization, raft launch/take-out restoration or relocation, and parking area expansion.

All Architect-Engineer (A/E) Services shall be performed by licensed Architects and Engineers registered in the State of Idaho.

3.2 COMPLIANCE & AUTHORITY HAVING JURISDICTION (AHJ)

The project design shall comply with all applicable codes, regulations, and standards to ensure adherence to safety, structural integrity, and environmental requirements. It is the responsibility of the contractor and associated personnel to ensure that all aspects of design meet these requirements throughout all phases of the project to guarantee public safety and the long-term functionality of the facilities.

The BLM will serve as the Authority Having Jurisdiction (AHJ) on this project. While the BLM will serve as the Authority Having Jurisdiction (AHJ), some of these services may still require coordination with other

Design-Build Statement of Work

03/30/2026 federal agencies as well as state and local agencies (e.g. 404 Permit). The DBC shall prepare the necessary submittal documentation for permits and approvals when needed.

3.3 SITE DESIGN

The DBC shall evaluate the site, consult with the Government, review the information and materials furnished by the Government and perform any additionally required Geotechnical Investigations and Topographical Site Surveys not covered by the information and materials furnished by the Government.

Stamped and signed Geotechnical Reports and Site Survey Data shall be provided to the Government.

After proposed changes are approved by the Government at the conclusion of the Schematic Design, the DBC shall proceed with design development and subsequently prepare construction documents.

Anticipated services include Schematic Design, Design Development, and Construction Documents with each submittal, at the appropriate class level.

4 DESIGN DELIVERABLES & SERVICES

4.1 OVERVIEW

The project design shall be based on the DBC’s evaluation of the site, review of Government furnished information and materials, value analysis and cost optimization, and consultation with the Government.

Consideration shall be given to availability of materials, equipment and labor, construction sequencing and scheduling, user safety and maintenance requirements, and sustainability.

Each set of deliverables shall include appropriately, and progressively developed Drawings and Cost Estimates.

4.2 PROJECT ADMINISTRATION & MANAGEMENT SERVICES

The DBC shall be responsible for administering the following services throughout the project design phases:

1) Project Administration services consisting of administrative functions including:

a) Consultations.

b) Research.

c) Value Analysis and Cost Optimization.

d) Meetings.

e) Communications.

f) Travel Time.

g) Progress Reports and Meeting Minutes.

h) Direction of the Work of In-House Personnel.

2) Overall DBC familiarization with project, including meetings and research as necessary to ensure all disciplines have a thorough understanding of the Government’s programmatic needs and priorities.

3) Disciplines Coordination / Document Quality Assurance and Quality Control:

a) Coordination between the work of all disciplines involved in the Project at appropriate intervals and throughout the design.

b) Review and coordination with existing site development documents and conditions.

c) Review of Project contract documents to ensure accuracy, thoroughness and completeness.

Design-Build Statement of Work

03/30/2026

4) Coordination as necessary with relevant external AHJ’s, including:

a) Research of required applicable permits and other applicable laws, statutes, regulations, and codes of regulating entities.

4.3 PRE-DESIGN (PD) & SCHEMATIC DESIGN (SD) DELIVERABLES & SERVICES

The DBC shall provide the Engineering Deliverables & Services for the Pre-Design and Schematic Design phases as outlined in this Section of the Statement of Work. All disciplines shall develop their respective deliverable packages to detail levels appropriate to the Pre-Design and Schematic Design phases of the project and in accordance with the general industry standards regarding these phases. The DBC shall ensure coordination between each discipline.

4.3.1 Deliverables & Services (PD/SD)

1) Review of Government furnished information and materials.

2) Production of existing conditions site/survey documents, including all existing physical features, utilities (above and below grade), topographic contours, property lines, control points, right of ways, and other information deemed relevant to the project.

3) Site Survey Data (for any additional surveys conducted on site that are required and not covered in the Government furnished information and materials).

4) Geotechnical Reports (for any additional geotechnical investigations required and not covered in the Government furnished information and materials). The Geotechnical Report shall be stamped and signed by the Engineer of Record.

5) Preliminary re-seeding plans, materials and proposed maintaining and monitoring plan.

6) Production of Schematic Design Drawing Set, including construction notes, overall site plan and other drawings deemed relevant to the project.

7) Preliminary Schedule of Values.

4.4 DESIGN DEVELOPMENT (DD) & CONSTRUCTION DOCUMENT (CD)

DELIVERABLES & SERVICES

The DBC shall provide the deliverables & services for the Design Development and Construction Document Phases as outlined in this Section of the Statement of Work. All disciplines shall continue the development of their respective drawing packages to detail levels appropriate to the Design Development and Construction Document phases of the project and in accordance with the general industry standards regarding these phases. The DBC shall ensure coordination between each discipline.

4.4.1 Deliverables and Services (DD/CD)

1) Production of Design Development (35%,65%, 95%, and 100%) and Construction Document

Drawing Sets (65% and 100%) shall include overall site development plans, roadway and parking area plans, grading plans, landscape plans, construction notes, planting schedules and details, and other drawings deemed relevant to the project. Include final stamped Survey drawing sheets.

2) Re-seeding plans, materials and maintaining and monitoring plans.

3) Schedule of Values.

4.5 CONSTRUCTION ADMINISTRATION

The DBC shall be responsible for providing its own Construction / Contract Administration services to ensure A/E oversight and quality control over construction. This may include, but is not limited to:

Design-Build Statement of Work

03/30/2026

1) Regular site visits and documentation.

2) Review of project submittals, Requests for Information (RFI’s), and Requests for Clarification.

3) Management of change orders.

4) Budget monitoring.

5) Permit compliance.

6) Providing project updates and progress reports to the Government.

7) Project closeout and punch-list walkthrough.

5 CONSTRUCTION REQUIREMENTS

5.1 OVERVIEW

The DBC shall be responsible for constructing the project as outlined in this Statement of Work and its accompanying attachments. Project construction shall be completed in accordance with all applicable codes, regulations, standards and accepted industry means and methods. Section 5 of this Statement of Work includes all critical Construction Requirements that the DBC shall include and execute. Nothing in this Statement of Work shall be interpreted to limit the DBC’s ability to propose Value Engineering Proposals (VECPs) in accordance with FAR 52.248-3.

5.2 ENVIRONMENTAL AND SUSTAINABILITY REQUIREMENTS

5.2.1 Sustainability Requirements:

Specific sustainability requirements generated in design will dictate more stringent environmental requirements for this project. The following are general requirements:

• Site Disturbance: Minimize the construction limits of the project to reduce the project’s impact on the site.

• Toxic Chemicals: Avoid materials that can leach toxic chemicals into the ground water. Do not allow toxic chemicals to enter sewers or storm drains or contaminate land or any body of water.

• Soil Erosion: Protect against erosion and topsoil depletion in accordance with the Storm Water Pollution Prevention Plan.

• Noise: Minimize noise generation during construction. Operate power equipment in accordance with local noise restrictions.

• Waste Management: Employ processes that ensure the generation of as little waste as possible. Waste disposal in landfills shall be minimized.

5.2.2 Minimize Construction Impacts:

The following mitigation measures shall be implemented to minimize the impacts of construction activities:

• Soil Erosion: Protect against erosion and topsoil depletion. Storm Water Pollution Prevention Plan required.

• Exotic Vegetation and Noxious Weeds: Prevent the introduction and minimize the spread of exotic vegetation and noxious weeds. Incorporate the following procedures:

o Any fill, rock, or additional topsoil needed shall be obtained from a Government approved source.

Design-Build Statement of Work

03/30/2026 o All areas disturbed by construction shall be re-vegetated using approved native seed and/or plants.

5.2.3 Air and Water Pollution Control:

Air quality impacts are expected to be temporary and localized. To minimize these impacts, the following actions shall be taken:

• To reduce tailpipe emissions, construction equipment shall not be left idling any longer than is necessary for safety and mechanical reasons.

• To reduce construction dust, water shall be applied to problem areas. Equipment shall be limited to the fenced project area to minimize soil disturbance and dust generation.

• Take all necessary reasonable measures to reduce air and water pollution by any material or equipment used during construction. Keep volatile wastes in covered containers.

• Storm Water Pollution Prevention Plan (SWPPP): Submit a SWPPP according to the applicable State Water Resources Control Board's (SWRCB) requirements to the Government for approval. (See Technical Requirements) Before starting construction, the DBC shall implement the approved SWPPP.

5.3 SCHEDULE OF VALUES

After contract award and before the Design Meeting, submit a schedule of dollar values based on the Contract Price Schedule.

• Breakdown each lump-sum item into component parts of design deliverables or construction work for which progress payments may be requested.

• In general, component parts shall match the A/E Technical Specifications Index, with line items as necessary to delineate major components, assemblies, and/or construction processes.

• Individual line items shall further break down into materials costs, labor costs, and equipment costs for each.

• The total costs for the component parts of work shall equal the contract line-item amount for that lump-sum item. The Government may request data to verify accuracy of dollar values.

• Include general condition costs, overhead and profit in the total dollar value of unit price items and in the component parts of work for each lump-sum item, as described below. Do not include general condition costs, overhead or profit as a separate item.

• Do not break down unit price items. Use only the contract line-item amount for unit price items.

The total cost of all items shall equal the contract sum. The Schedule of Values will form the basis for progress payments.

An acceptable Schedule of Values shall be agreed upon by the DBC and Government before the first progress payment is processed. A cost loaded project schedule may be an acceptable substitute for a schedule of values in some cases.

Commented [TS3]: What about equipment?

Commented [JB4R3]: Equipment costs added.

Design-Build Statement of Work

03/30/2026

5.4 CONSTRUCTION SUPPORT

5.4.1 Staging Areas

Construction sites will be limited to the smallest feasible area. Ground disturbance and site management will be carefully controlled to prevent undue damage to vegetation, soils, and to minimize air, water, soil, and noise pollution.

Staging is limited to previously disturbed areas directly next to and adjacent to the construction area for a construction office, trailer, construction equipment, vehicles, and material storage. All staging areas shall be returned to pre-construction conditions once construction is complete.

Standards for this, and methods for determining when the standards are met, shall be developed in accordance with FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements.

5.4.2 Structures

The location of trailers, storage containers, field offices, staging areas and sheds shall be approved by the Government. If storage sheds are to be utilized, provide weather tight sheds or other covered facilities for storage of materials subject to weather damage. Field offices shall be of structurally sound construction, and weather tight. The location shall be determined by DBC prior to issuing a Start Work Notice. The location of the staging area for construction equipment shall require Government approval.

If used, all temporary water, sewer, sanitary facilities, and electric utilities shall be completely removed upon project completion. Remove temporary utility connections.

Construction Camp: Establishment of a construction camp within the Government site boundaries will not be permitted.

5.4.3 Construction Zones

Construction zones shall be fenced with Government-approved construction barrier fencing, plastic or portable fencing, before any construction activity begins. The fencing shall define the construction zone and confine activity to the minimum area required for construction. All protection measures shall be clearly stated in the construction documents, and workers will be instructed to avoid conducting activities beyond the construction zone as defined by the construction zone fencing.

Protection of Public: Fence, barricade, or otherwise block off the immediate work area to prevent unauthorized entry. Erect and maintain fencing, barricades, lights, signals, and warning signs in accordance with the most current version of the Manual on Uniform Traffic Control Devices

(MUTCD).

5.4.4 Parking of Construction Vehicles

Parking of vehicles shall be limited to existing roads, in legally designated areas, and within approved staging area(s).

Commented [TS5]: This is vague. What do you mean? Are you saying the construction office trailer may need to be located elsewhere on site? If so, where?

Commented [JB6R5]: Altered to hopefully be less vague.

Design-Build Statement of Work

03/30/2026

5.5 SUBMITTALS DURING CONSTRUCTION

5.5.1 Applicability

The DBC shall be responsible for coordinating construction submittals between the design and construction teams. The Government does not typically require action submittals on all materials in a Design-Build contract but may request involvement in reviewing submittals that will directly impact the functionality or aesthetics of a project (e.g. paint colors, finishes, control systems, hardware, etc.). The DBC shall coordinate with the Government what submittals will require Government action prior to the commencement of construction and shall submit a revised “Submittal List” form accordingly.

5.5.2 Construction Submittal Types:

Where the Government requests involvement in submittal review during construction, there shall be two submittal types that the DBC shall utilize:

5.5.2.1 Action Submittals

Written, graphic information, and physical samples that require Government’s responsive action. Submittal shall include:

• Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.

• Shop Drawings: Prepare project-specific information, drawn accurately to scale.

Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data.

• Samples: Submit Samples for review of kind, color, pattern, and texture for a check of these characteristics with other elements and for a comparison of these characteristics between submittal and actual component as delivered and installed.

• Construction Materials: The DBC is encouraged to submit for approval products made out of recycled or environmentally responsible material. Every effort will be made by the Government to approve these materials.

5.5.2.2 Informational Submittals

Written information that does not require Government’s responsive action. Submittals may be rejected for not complying with requirements.

• General: Prepare and submit Informational Submittals required by individual Specification Sections.

• Informational submittals include but are not limited to Coordination Drawings, Certificates, Test reports, Manufacturer’s instructions, Division 01 Management Plans, etc.

5.5.2.3 Value Engineering Change Proposal (VECP) Submittals

Written value analysis and cost optimization information that require Government’s responsive action. Submittals shall include:

• A description of the difference between the existing contract requirement and that proposed, the comparative advantages and disadvantages of each, a justification

Design-Build Statement of Work

03/30/2026 when an item’s function or characteristics are being altered, and the effect of the change on the end item’s performance.

• A list and analysis of the contract requirements that must be changed if the VECP is accepted, including any suggested specification revisions.

• A separate, detailed cost estimate for:

o The affected portions of the existing contract requirement and o The VECP

The cost reduction associated with the VECP shall take into account the Contractor’s allowable development and implementation costs, including any amount attributable to subcontracts under paragraph (h) of this clause.

• A description and estimate of costs the Government may incur in implementing the VECP, such as test and evaluation and operating and support costs.

• A prediction of any effects the proposed change would have on collateral costs to the agency.

• A statement of the time by which a contract modification accepting the VECP must be issued in order to achieve the maximum cost reduction, noting any effect on the contract completion time or delivery schedule.

• Identification of any previous submissions of the VECP, including the dates submitted, the agencies and contract numbers involved, and previous Government actions, if known.

5.5.3 Government Review of Construction Submittals

5.5.3.1 Processing Time

Allow enough time for submittal review, including time for resubmittals. Time for review shall commence when the submittal is received by the Government and is ready for review.

When the Government has completed their review, the submittal review form will be sent to the DBC indicating the status of submittal approval. No extension of the Contract Time will be authorized because of failure to transmit submittals far enough in advance of the Work to permit processing, including re-submittals.

• Action Submittals: Allow 15 calendar days for initial review of each submittal.

Allow additional time if coordination with subsequent submittals is required.

• Informational submittals: Allow ten (10) calendar days for review of each submittal.

5.5.3.2 Submittal Format

All submittals to the Government shall be electronic. Identify and incorporate information in each electronic submittal file as follows:

• CM-16 Transmittal Form: All submittals shall be transmitted using Bureau of Land Management CM-16 form. The electronic version of the form can be obtained from the Government (or designee). No action will be taken on a submittal item unless accompanied by the CM-16 transmittal form.

o Complete the general information at the top of the form.

o Provide all required information based on the submittal type o Attach all related documents.

Commented [TS7]: Do you have this form? I don’t remember it.

Commented [JB8R7]: Yes, it is the same form that is in your COR Forms folder but labeled 01330a -submittal form. The bottom right corner of the form shows it as CM-16 Rev. 04/00.

Design-Build Statement of Work

03/30/2026 o Sign a hard copy or electronically sign the CM-16 form in the DBC section at the bottom of the form and send the completed form to the Government (or designee).

• Physical samples: Complete the CM-16 form and send the completed form to the Government (or designee). Deliver the physical sample to the Government (or designee) on site for processing. All comments and actions shall be documented on the CM-16 form.

Alternately, with the approval of the Government, a web-based submittal system may be used. Verify with the Government that access can be granted, and the system is accessible to the project stakeholders.

5.5.3.3 Government Review Response

Government will review each submittal, generate comments on corrections or modifications required, and indicate the appropriate action on the CM-16 Transmittal Form.

The submittal will be marked in one of three ways as defined below:

• Approved: Acceptable with no corrections.

• Approved with Notations: Minor corrections or clarifications required. All comments are clear, and no further review is required. The DBC shall address all review comments when proceeding with the work.

• Disapproved – Resubmit: Rejected as not in accordance with the contract or as requiring major corrections or clarifications. The Government will identify the reasons for disapproval. The DBC shall revise and resubmit with changes clearly identified.

5.5.4 Use for Construction

Use only final submittals with mark indicating “Approved” or “Approved with notations”. Ensure all notations have been incorporated and, at a minimum, keep one copy of the final approved submittal on site for use during construction.

5.6 CONSTRUCTION COORDINATION

The Government will provide all necessary written notification and/or direction to the DBC. An on-site Government Project Inspector (PI) will coordinate the DBC’s construction efforts with the site staff’s daily operations and will transmit and receive correspondence between the Government and the DBC. However, the PI will have no authority to accept or reject work, or to authorize changes to the terms and conditions of the contracts, or to obligate the Government for time or money.

5.7 CONSTRUCTION PHOTOGRAPHIC DOCUMENTATION

The DBC shall use StructionSite or similar software for digital image documentation of progress. The DBC and the Government will develop a photo location plan. Images should be taken weekly. The Government anticipates approximately 50 images per week depending on construction and project complexity. Upon completion of the site, final images and location drawings are to be downloaded and provided to the Government.

5.8 CONSTRUCTION QUALITY CONTROL

The DBC and its construction subcontractors shall operate under a current, appropriate construction contracting licenses issued by State of the project location, in accordance with applicable State regulations.

Commented [TS9]: Why won’t the PI have the authority to reject work?

Commented [JB10R9]: When I was a PI, I never had the authority to accept or reject work or materials. That responsibility was given to the COR. I did go back and verify that with my past Appointment as Project Inspector memo and the COR’s delegation memo.

Commented [TS11R9]: PI’s should always have the authority to reject work for nonconformance with the requirements of the contract and issue Notices of Noncompliance to that effect.

Design-Build Statement of Work

03/30/2026

The quality of all work shall be the responsibility of the DBC. Testing shall be the responsibility of an independent testing laboratory and shall be coordinated by the DBC. Inspect and test all work as needed to ensure that the quality of materials, workmanship, construction, finish, and functional performance is in compliance with applicable specifications and drawings. Quality Control Daily Reports shall be completed by the Quality Control Supervisor. Test reports shall be completed by the person performing the test. The Government may designate additional tests and/or locations of tests if not adequately addressed by the

DBC.

5.9 WORKING HOURS RESTRICTIONS

All work and deliveries shall be limited to the weekday hours of 7:00am to 6:00pm unless otherwise approved by the Government. No work shall occur on Government holidays or weekends without prior approval. Submit request 72 hours in advance of the work to the Contracting Officer for approval.

5.10 TEMPORARY SERVICES

Temporary materials may be used but must be adequate in capacity for the required usage, must not create unsafe conditions, and must not violate requirements of applicable codes and standards.

5.10.1 Vehicles and Equipment

Provide one fire extinguisher on each vehicle or piece of equipment. Extinguishers shall have a minimum UL rating of 2-A:10-B:C. A capable and qualified person shall be placed in charge of fire protection. The responsibilities shall include locating and maintaining fire protective equipment.

Locate internal combustion equipment so that exhausts discharge well away from combustible materials. Locate servicing and refueling areas a minimum of 50ft from buildings and 150ft from water sources. Shut down equipment before refueling.

5.10.2 Hazard Control

Take all necessary precautions to prevent fire during construction. Do not store flammable or combustible liquids in existing structures. Provide adequate ventilation during use of volatile or noxious substances.

5.10.3 Spark Arresters

Equip all gasoline or diesel-powered equipment used in potential forest or grass fire locations with spark arresters approved by the U. S. Forest Service. Written determinations of areas and periods of potential fire hazard will be issued by Government.

5.10.4 Smoking

Smoking within buildings or temporary storage sheds is prohibited.

5.10.5 Welding

Cutting by torch or welding shall be performed only when adequate fire protection is provided.

5.10.6 Water

Potable water is located within the project site and will be accessible to the DBC.

Commented [JB13R12]: Wording added to cover servicing and refueling 150ft away from water sources.

Commented [TS12]: What about servicing and refueling equipment away from water, i.e. the river.

There should be a minimum separation distance.

Design-Build Statement of Work

03/30/2026

5.10.7 Sanitary Facilities

Restroom facilities are located within the project site and will be accessible to the DBC as long as they are maintained in a sanitary condition.

5.11 ACCESS

Coordinate construction efforts with the Government such that there is minimal impact to the work of the Government personnel and the visiting public. During construction of the scheduled work, the DBC shall have limited access to the site. Site access shall be coordinated with the Government.

5.12 PRESERVATION OF ADJACENT FEATURES

Confine all operations to work limits of the project. Prevent damage to natural surroundings. Restore damaged areas outside the work limits, repairing or replacing damaged trees and plants, at no additional expense to the Government.

Provide temporary barriers to protect existing trees, plants and root zones that are to remain in place. Do not remove, injure or destroy trees or other plants without prior approval. Consult with the Government.

Remove agreed upon roots and branches that interfere with construction. Carefully supervise excavation, grading, backfilling, and other construction operations near trees and plants, to prevent damage.

5.13 EXISTING UTILITIES

Disruptions of services shall be kept to a minimum. The DBC shall coordinate with the local utility companies. All disruptions shall be arranged at least 48 hours in advance and must be approved by Government.

Construction procedures will prevent accidental disruptions to facilities outside the project limits by investigation of existing utilities and protection during construction; accidental disruptions shall be remedied at no cost to the Government.

5.14 HAULING RESTRICTIONS

Comply with all legal and local road restrictions in the hauling of materials.

5.15 ACCIDENT PREVENTION

5.15…