This document is an Addendum (No. 01) for the Hot Well Dunes Recreation Area Improvements project by GLHN Architects & Engineers, Inc., dated September 19, 2025. The addendum includes modifications to contract forms, specifications, and drawings, with key changes involving domestic water piping, photovoltaic collectors, water supply wells, and fencing. Significant technical updates include revising earthwork calculations, adding concrete sidewalk extensions, modifying solar shade canopy details, updating electrical system components such as replacing charge controllers with a pump controller, changing from an automatic transfer switch to a manual transfer switch, and adjusting solar panel and inverter configurations.

The addendum specifies detailed modifications across multiple technical disciplines, including civil, mechanical, electrical, and landscape elements. Notable changes involve solar panel installation specifications (to be installed at 28.1 degrees from horizontal), addition of underground conduits, updates to pump schedules and diagrams, revisions to electrical system layouts, and refinements to fencing details. The attached documents include revised estimated quantities, updated specification sections, and modified drawings dated between 9/3/2025 and 9/19/2025, indicating a comprehensive review and update of the project's technical documentation.

View the file

Other files

File Type Posted
Sol_140L0625B0012_Amd_0008.pdf PDF
Sol_140L0625B0012_Amd_0007.pdf PDF
Sol_140L0625B0012_Amd_0006.pdf PDF
Attachment_15_Q_A_2_0005.pdf PDF
Attachment_18_HWD_Specifications_Addendum_01_2025_09_19_0005.pdf PDF
Attachment_19_HWD_Drawings_Addendum_01_2025_09_19_2_0005.pdf PDF
Sol_140L0625B0012_Amd_0005.pdf PDF
Attachment_17__HWD_Bid_Schedule___Est_Quant_Addendum_01_-_09_19_2025_0005.pdf PDF
Sol_140L0625B0012_Amd_0004.pdf PDF
Sol_140L0625B0012_Amd_0003.pdf PDF
Sol_140L0625B0012_Amd_0002.pdf PDF
Attachment_13__Q_A_1_0001.pdf PDF
Attachment_12_Site_Visit_Sign-In_Sheet_0001.pdf PDF
Sol_140L0625B0012_Amd_0001.pdf PDF
Attachment_14_Pump_House_and_Box_Photos_0001.pdf PDF
Attachment_10_Limitations_on_Subcontracting.xlsx XLSX spreadsheet
Attachment_3_Hot_Well_Dunes_Septic_Design_Rpt.pdf PDF
Attachment_1_Hot_Well_Dunes_Specifications.pdf PDF
Attachment_2d_Hot_Well_Dunes_Drawings_Split_Part_4.pdf PDF
Attachment_2e_Hot_Well_Dunes_Drawings_Split_Part_5.pdf PDF
Attachment_2c_Hot_Well_Dunes_Drawings_Split_Part_3.pdf PDF
Attachment_6_Hot_Well_Dunes_Septic_Permit.pdf PDF
Attachment_2i_Hot_Well_Dunes_Drawings_Split_Part_9.pdf PDF
Attachment_2a_Hot_Well_Dunes_Drawings_Split_Part_1.pdf PDF
Attachment_2b_Hot_Well_Dunes_Drawings_Split_Part_2.pdf PDF
Attachment_2h_Hot_Well_Dunes_Drawings_Split_Part_8.pdf PDF
Sol_140L0625B0012.pdf PDF
Attachment_2g_Hot_Well_Dunes_Drawings_Split_Part_7.pdf PDF
Attachment_2j_Hot_Well_Dunes_Drawings_Split_Part_10.pdf PDF
Attachment_5_Hot_Well_Dunes_Building_Permit_Placard.pdf PDF
Attachment_11_RFI_Form.xlsx XLSX spreadsheet
Attachment_8_HWD_Bid_Schedule___Estimated_Quantities.pdf PDF
Attachment_7_Hot_Well_Dunes_Submittals_Schedule_Final.pdf PDF
Attachment_9_Wage_Determination_AZ20240054.pdf PDF
Attachment_2k_Hot_Well_Dunes_Drawings_Split_Part_11.pdf PDF
Attachment_4_Hot_Well_Dunes_Geotech_Eval_Final.pdf PDF
Attachment_2f_Hot_Well_Dunes_Drawings_Split_Part_6.pdf PDF
Show all 37

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

GLHN ARCHITECTS & ENGINEERS, INC

2939 E Broadway Blvd. | Tucson, AZ 85716 | 520.881.4546

3636 N Central Ave, Suite 160 | Phoenix, AZ 85012 | 602.368.9393 | GLHN.com

Hot Well Dunes Rec Area Improvements

Addendum # 01 Sept. 19, 2025 Page 1 of 2

ADDENDUM | No.: 01

TO: J. Carlos Joya, PE

One N. Central Ave, Suite 800

Phoenix, AZ 85004

DATE: September 19, 2025

REFERENCE: Project Name: Hot Well Dunes Recreation Area Improvements

GLHN Job No.: 20049.06

FROM: GLHN Architects & Engineers, Inc.

2939 E Broadway Blvd.

Tucson, AZ 85716

This Addendum becomes a part of the Contract Documents and modifies the original bidding documents as noted below.

CHANGES TO CONTRACT FORMS

1. Estimated Quantities: changes to estimated quantities

CHANGES TO SPECIFICATIONS

1. REPLACE Section 221116, Domestic Water Piping: HDPE pipe and fittings added, nonapplicable sections deleted.

2. REPLACE Section 263100, Photovoltaic Collectors: updated to reflect revised selection of equipment.

3. REPLACE Section 332100, Water Supply Wells: revised well pump basis of design and deleted nonapplicable sections.

4. REPLACE Section 322100, Fencing: revised barbed wire and split rail fencing materials.

CHANGES TO DRAWINGS

1. GI002 (dated 9/3/2025): Revised earthwork calculations to clarify cut and fill volumes.

Added Site Furnishings General Notes regarding solar shade structures

2. CV200 (dated 9/3/2025): Corrected scale bar

3. CS100 (dated 9/19/2025): Added concrete sidewalk extensions at information kiosks and dimensions to site furnishings keynote 7

4. CS200 (dated 9/3/2025): Revised callout for solar shade canopy over pump house, adding

2 panels and maintaining clearance over well on west side; added underground conduit for power (new keynote 31); added air release valve to pond water line; revised keynote

5. CS501 (dated 9/3/2025): Details 5 & 6, panel size removed and note added “SOLAR

PANELS TO BE INSTALLED AT 28.1 DEGREES FROM HORIZONTAL OR AS APPROVED BY THE

GOVERNMENT.” Minimum canopy dimensions (12’x12’) added to Detail 5. Solar racking called out and rain water gutter added on Detail 6. Both details refer to Site Furnishings

Notes, sheet GI002

6. CS502 (dated 9/3/2025): Detail 3, Joint Trench deleted

GLHN ARCHITECTS & ENGINEERS, INC

2939 E Broadway Blvd. | Tucson, AZ 85716 | 520.881.4546

3636 N Central Ave, Suite 160 | Phoenix, AZ 85012 | 602.368.9393 | GLHN.com

Hot Well Dunes Rec Area Improvements

Addendum # 01 Sept. 19, 2025 Page 2 of 2

7. CS504 (dated 9/19/2025): Detail 2, Joint Trench added, w/conduits for power; Detail

1canopy minimum dimensions and clearances added and referenced to Site Furnishings

Notes, sheet GI002. Panel size removed and note added “SOLAR PANELS TO BE INSTALLED

AT 28.1 DEGREES FROM HORIZONTAL OR AS APPROVED BY THE GOVERNMENT”

8. P001 (dated 9/3/2025): Updated Pump Schedule.

9. P501 (dated 9/3/2025): Updated detail 1, Well Pump Diagram.

10. ES102 (dated 9/19/2025): Added two 1” conduits running between canopy kiosk and pump house. Now showing location of more equipment in pump house. Inverter, and combiner.

11. E-601(dated 9/19/2025): Changed ATS to MTS. Automatic transfer switch is not necessary.

Updated voltages of panel boards in worksheet and adjusted load. Added note re 10% safety factor.

12. E-602 (dated 9/19/2025): Charge controllers were removed, with one replaced by a pump controller. Microinverters were replaced with a 6.5 kW inverter located in the pump house with batteries. The pump selection has been updated to an AC pump, and the DC disconnect has been changed to an AC disconnect; a third disconnect was added to provide local disconnect to the batteries. Two solar panels added to Pump array.

13. E-701 (dated 9/19/2025): Added a grounding and bonding detail to clarify the connection between support structures and the grounding system.

14. LP-501 (dated 9/3/2025): Revised detail 1 to include the missing brace post details A & B.

Revised detail 2 to clarify the fencing nomenclature for brace panels and posts vs tension post. Replaced detail 3 with a new Split Rail Fencing detail as the previous version shows incorrect materials.

LIST OF DOCUMENTS ATTACHED

1. Revised Estimated Quantities

2. Revised Specifications Sections (listed above)

3. Revised drawings (as dated and listed above)

END OF ADDENDUM

File details come from the government source that posted it. Updated .