This is a Statement of Work (SOW) for the Kooskia National Fish Hatchery Rain Gutter Replacement Project. The contractor shall remove existing rain gutters and downspouts from four buildings and install new 5-inch gutter systems with four approximately 20-foot downspouts per building. The four buildings include the Incubation Building (~190 linear feet), Reuse Building (~160 linear feet), Maintenance/Vehicle Storage Building (~260 linear feet), and Chiller Building (~160 linear feet). All listed measurements are approximate, and contractors are required to conduct an on-site inspection prior to bidding to verify measurements and conditions; no additional compensation will be granted for discrepancies discovered after contract award. The contractor shall provide all labor, materials, equipment, and supervision necessary to complete the work and must restore work areas to original condition after installation.

Warranty requirements include a minimum 10-year manufacturer warranty on all gutter materials, downspouts, hangers, and hardware, with warranty documentation provided upon project completion, and a minimum 2-year workmanship warranty covering installation defects, improper fastening, inadequate slope, leakage due to installation error, and contractor workmanship failures. The contractor must disclose any conditions discovered during site inspection that could affect warranty coverage and identify any warranty limitations resulting from existing building component conditions. Safety compliance with OSHA 29 CFR 1910 and 1926, fall protection, proper debris handling, and use of required PPE are mandatory. The period of performance is November 16, 2026 through December 17, 2026. A site visit is scheduled for October 29, 2026, from 10:00 a.m. to 12:00 p.m. local time, and while attendance is not mandatory, it is strongly encouraged. Bid submission requirements include a verification statement acknowledging the approximate measurement disclaimer, proposed materials and specifications, warranty documentation, detailed cost breakdown, and estimated schedule and performance plan. The Contracting Officer is Tiffannie Pannel (tiffannie_pannell@ios.doi.gov, 703-468-828), and the Contracting Officer's Technical Representative is Kurt McCorkle (kurt_mccorkle@fws.gov, 208-400-0002), who requires 48 hours advance notice for site visits.

View the file

Other files

File Type Posted
B03_WAGE_DETERMINGATION-5-18-2026.pdf PDF
Sol_140FF027Q0040.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work (SOW)

Kooskia National Fish Hatchery – Rain Gutter Replacement Project

1. Project Overview

Kooskia National Fish Hatchery is looking for contractors to replace existing rain gutters and downspouts. This project includes installing new 5" gutters and four 20-foot downspouts (approx.)

on each building listed below. The contractor shall provide all labor, materials, equipment, and supervision necessary to complete this project.

• Incubation Building – ~190 linear feet, four 20’ downspouts (approximately)

• Reuse Building – ~160 linear feet, four 20’ downspouts (approximately)

• Maintenance/Vehicle Storage Building – ~260 linear feet, four 20’ downspouts (approximately)

• Chiller Building – ~160 linear feet, four 20’ downspouts (approximately)

All listed measurements are approximate. Contractors must conduct an on-site inspection to verify all measurements and conditions before submitting a bid.

The attached visual reference KNFH RAIN GUTTER IMAGE shall be used for general context only and does not represent final measurements or structural details

2. Scope of Work

• Remove and properly dispose of existing gutters and downspouts.

• Provide and install new 5” gutter systems sized appropriately for each building’s roofline.

• Install four 5” downspouts per building (approx. 20 feet each).

• Ensure gutter systems meet all applicable federal, state, and local codes.

• Ensure all materials and installation methods follow industry standards.

• Restore work areas to original condition after installation.

3. Site Visit Requirement

Contractors are required to visit the site prior to bidding.

No additional compensation will be granted for discrepancies discovered after contract award.

https://doimspp-my.sharepoint.com/personal/kurt_mccorkle_fws_gov/Documents/Microsoft%20Copilot%20Chat%20Files/KNFH%20RAIN%20GUTTER%20IMAGE.pdf

4. Warranty Requirements

Contractors shall provide the following warranties:

4.1 Material Warranty

• All gutter materials, downspouts, hangers, and hardware shall be warranted by the manufacturer for defects in material for a minimum of 10 years.

• Warranty documentation must be provided to the Government upon project completion.

4.2 Workmanship Warranty

• Contractor shall provide a minimum 2-year workmanship warranty covering installation defects, improper fastening, inadequate slope, leakage due to installation error, and any failure resulting from contractor workmanship.

• The contractor should correct, at no additional cost to the Government, any deficiencies discovered during the warranty period.

4.3 Warranty Coordination

Given that warranty conflicts can arise when installing new systems onto older structures the contractor must:

• Disclose any conditions discovered during site inspection that could affect warranty coverage.

• Identify any warranty limitations resulting from the condition of existing building components and provide written notice before proceeding with installation.

5. Safety Requirements

Contractors shall adhere to all applicable federal, state, and local safety regulations, including but not limited to:

5.1 OSHA Compliance

Based on established requirements referenced in prior construction specifications used by the Service contractors must be in,

• Compliance with OSHA 29 CFR 1910 – General Industry Safety and Health Standards.

• Compliance with OSHA 29 CFR 1926 – Safety and Health Regulations for Construction.

5.2 Worksite Safety Controls

• Use of fall protection when working at height.

• Proper handling and disposal of debris.

• Use of PPE including gloves, safety glasses, hard hats, and hearing protection where required.

• Maintain a clean, organized worksite free of hazards.

6. Technical Point of Contact, Contracting Officer and Project location

• Kurt McCorkle, Contracting Officers Technical Representative (COTR)-Site Visit- 48 hours advance notice.

Facility Operations Specialist – kurt_mccorkle@fws.gov; 208-400-0002

• Kayla Warden, KNFH Manager, kaylaw@nezperce.org; 208-935-8798

• Kooskia National Fish Hatchery; 318 Toll Road, Kooskia Idaho 83539

• Tiffannie Pannel, Contracting Officer, tiffannie_pannell@ios.doi.gov , 703-468-828-Email questions and quotes to me.

7. Bid Submission Requirements

• Verification statement acknowledging approximate measurement disclaimer.

• Proposed materials and specifications.

• Warranty documentation for included products.

• Detailed cost breakdown.

• Estimated schedule and performance plan.

8. Period of Performance

• November 16, 2026 through December 17, 2026

9. Site Visit

• A site visit will be conducted on October 29, 2026, from 10:00 a.m. to 12:00 p.m. local time.

Attendance is not mandatory; however, it is Strongly Encouraged. Contractors shall be responsible for considering all information made available during the site visit regardless of attendance.