SOW-INP17PD01351_0005.pdf

PDF 2 MB Posted

Attached to
NAMA WWII Memorial Operations and Maintenance IDIQ
Solicitation number
140D0424Q0127
Issued by

About this file

This document outlines the scope of work for a maintenance services contract at the National World War II Memorial. The contractor will provide ongoing operations and preventative maintenance, as well as emergency and non-emergency repairs. Services include lighting system maintenance, electrical system upkeep performed by licensed electricians, plumbing fixture repairs, fountain system compliance, groundwater treatment adherence to EPA standards, and responding to service calls within two hours. The contractor must also remove snow and ice, treat pool and fountain water, and maintain the granite, bronze, and computer systems. Quality control and assurance programs oversee contract performance.

View the file

Other files

File Type Posted
QnA_Government_Response_v3_Amend_8_0008_0008.pdf PDF
Sol_140D0424Q0127_Amd_0008.pdf PDF
AMEND_8_140D0424Q0127_0008_0008.pdf PDF
Attch_2_PWS_WWII_Preventative_Maintenance_TO_14May2024_0007.pdf PDF
QnA_Government_Response_v2_1_Amend_7_0007_0007.pdf PDF
Sol_140D0424Q0127_Amd_0007.pdf PDF
Attch_1_PWS_WWII_Memorial_Operations_and_Maintenance_14May2024_0007.pdf PDF
AMEND_7_140D0424Q0127_0007_0007.pdf PDF
QnA_Government_Response_v2_1_Amend_6_0006.pdf PDF
Sol_140D0424Q0127_Amd_0006.pdf PDF
Attch_3_Pricing_Sheet_Amend_6_0006.xlsx XLSX spreadsheet
AMEND_6_140D0424Q0127_0006.pdf PDF
Attch_1_PWS_WWII_Memorial_Operations_and_Maintenance_Amend_5_0005.pdf PDF
Attch_2_PWS_WWII_Preventative_Maintenance_TO_Amend_5_0005.pdf PDF
Sol_140D0424Q0127_Amd_0005.pdf PDF
AMEND_5_140D0424Q0127_0005.pdf PDF
QnA_Government_Response_v2_Amend_5_0005.pdf PDF
Sol_140D0424Q0127_Amd_0004.pdf PDF
AMEND_4_140D0424Q0127_0004.pdf PDF
WWII_Site_Visit_Sign_In_Sheet__0004.pdf PDF
Sol_140D0424Q0127_Amd_0003.pdf PDF
AMEND_3_140D0424Q0127_SOL_NAMA_WWII_0003.pdf PDF
Attch_9_Site_Visit_Parking_Map_0003.pdf PDF
QnA_Government_Response_Amend_2_0002.pdf PDF
Exhibit_7_Operations_and_Maint_Manuals_List_0002.pdf PDF
Attch_3_Pricing_Sheet_Amend_2_0002.xlsx XLSX spreadsheet
Sol_140D0424Q0127_Amd_0002.pdf PDF
Attch_1_PWS_WWII_Memorial_Operations_and_Maintenance_Amend_2_0002.pdf PDF
Exhibit_9_NPS_Identification_0002.pdf PDF
Exhibit_4_-_NPDES_Discharge_Permit_0002.pdf PDF
AMENDMENT_2_140D0424Q0127_SOL_NAMA_WWII_0002.pdf PDF
Exhibit_2_-_NPS_WWII_Equipment__Systems__and_Maintenance_Items_0002.xlsx XLSX spreadsheet
Attch_2_PWS_WWII_Preventative_Maintenance_TO_Amend_2_0002.pdf PDF
Exhibit_8_-_Quality_Assurance_Surviellance_Plan_-_WWII_Memorial_0002.pdf PDF
Exhibit_1_Safety_Health_Environ_Plan_0002.pdf PDF
AMEND_1_140D0424Q0127_SOL_NAMA_WWII_0001.pdf PDF
Sol_140D0424Q0127_Amd_0001.pdf PDF
Attch_5_Past_Performance_Questionnaire.docx DOCX document
Attch_4_Limitations_on_Subcontracting_Worksheet.xlsx XLSX spreadsheet
140D0424Q0127_SOL_NAMA_WWII.pdf PDF
Attch_6_QnA_Template.xlsx XLSX spreadsheet
Attch_8_Organizational_Conflict_of_Interest_Certificate.pdf PDF
Attch_7_Wage_Determination_2015-4281.pdf PDF
Attch_2_PWS_WWII_Preventative_Maintenance_TO.pdf PDF
Attch_1_PWS_WWII_Memorial_Operations_and_Maintenance.pdf PDF
Attch_3_Pricing_Sheet.xlsx XLSX spreadsheet
Sol_140D0424Q0127.pdf PDF
Show all 47

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

National World War II Memorial Maintenance Service Contract

TABLE OF CONTENTS

I. Section 1 • General Requirements Page

1. Scope of Work

2. Contractors On-Site Representation

3. NPS Personnel

4. Identification .......................................................... ,

5. Reporting Requirements .................................................................. -

6. Emergency Requirements

7. Quality Control Program

8. Quality Assurance Plan

9. Maintenance (Non-Recurring Services)

10. Scheduling Work During Emergency Conditions

11. Additional Bid Requirements for Determination of Contractor

Responsibility capabilities

II. Section 2 -Maintenance Requirements

1. General

2. Exclusion

3. Phase-In

4. Staffing/Coverage Requirements

5. Facility Operation Hours

6. Maintenance Reporting Requirements

7. Repairs ............................ :

8. THIS SECTION INTENTIONALLY OMITTED

9. Additional Equipment Added to the Contract .... -

10. Service Calls/Response

11. Overtime Service

12. Water Treatment ................................... -

13. Custodial Services

14. Snow and Ice Removal

Ill. Section 3-System Specific Maintenance Requirements

1. Lighting System .. _ ................. -........... -.............................................. -.. -

2. Electrical System ................................................................................. -

3. Plumbing System ........................................ _

4. Fountain System

5. Groundwater Treatment System ............... -................... -

6. HVAC System·· ···-······ ......... _ ........ _ ............... _ ............................ _

7. Poolwater Treatment System ................... _

8. Granite and Bronze ................................. -

9. Alarm Systems ................................................ _ .......................... _

10. Computer Control Systems

11. Buffding Management System

12. Troubleshooting

13. Emergency Generator and Man-Lift Service

14. Operations and Maintenance Manuals

15. As -Built Drawings

WWII MAINTENANCE SERVICE CONTRACT

rimurphy Typewritten Text

XXXXXXXXXXXXXXX

rimurphy Typewritten Text rimurphy Typewritten Text rimurphy Typewritten Text

XXXXXXXXXXXXXXXXXXXXXXXXXXXX NOT USED

rimurphy Typewritten Text

XXXXXXXXXXXXXXXXXXXXXXXXXXXX NOT USED

rimurphy Typewritten Text

LIGHTING SERVICES

A. The contractor is responsible to notify the COR whenever the contractor becomes aware that facility equipment or systems are non-operational. Fire alarm system malfunctions and power outages must be reported immediately to the COR. In the case of fire alarm activation or a safety emergency the contractor shall immediately report the incident to the United States Park Police (USPP) and the Park Safety Manager. USPP, the Park Safety

Manager and the COR shall be notified immediately when an unauthorized or suspicious person is seen on the premises.

• USPP Emergency Telephone Number is: (202) 619-7505

• Park Safety Manager Contact Number is: 202-245-4667

7. QUALITY CONTROL PROGRAM

A. The contractor shall use a quality control program to ensure the performance standards In the contract are being consistently met or exceeded.

B. At least quarterly, the contractor shall review with the COR an the service calls that occurred during that period.

C. Annually, the contractor will survey all systems In EXHIBIT 2 • Maintenance Schedule to verify that they conform to the specifications in the O&M manuals. At the conclusion of the survey, the contractor will provide the COR with an equipment report and performance evaluation for each individual unit covered by this contract. The report shall indicate all repairs and upgrades for each unit.

D. Annually, the contractor will conduct field audits to maintain quality standards. This report should be made available to the government if requested.

E. In keeping with environmental protection, the contractor shall immediately notify the COR In writing of any hazardous environmental conditions at the site or violation of the NPDES permit.

B. QUALITY ASSURANCE PLAN

A. GENERAL The procedures and methods established in this Quality Assurance Plan will serve as a guide for all parties Involved ensuring that tenants and the NPS receive the services paid for and specified in this contract.

B. PARTNERING. In order to have an effective contract administration program that also ensures a successful business relationship between NPS and the Contractor, all parties involved in the service delivery process must work as a team and foster open and honest communication at all times.

Close coordination and active cooperation on a continuous basis between the Contractor and those representing the Contracting Officer are necessary to ensure a clean, safe and healthy working environment, and well maintained/operated building.

C. PERFORMANCE EVALUATION. The tenns of the contract have been agreed upon by both the Contractor and the Government at the time of contract award. During the life of the contract, Contractor performance will be documented by means of written inspections, minutes of meetings, NPS/customer surveys and records which will be retained as part of the official contract file.

1) Effectiveness of Quality Control

WWII MAINTENANCE SERVICE CONTRACT 5

a. General. The COR shall assess the effectiveness of the Contractor's Quality Control Program through review of reports required of the Contractor, Service Delivery Information, Customer Interaction and by means of NPS inspections.

b. Inspections. NPS will make tours and inspections through the buffding and other areas covered by this contract with the contractor's representative whenever possible, to ascertain the level of services being performed. The Contractor will be informed of less than satisfactory performance.

c. Service Delivery. The quality and timeliness of all aspects of the contractor's (including subcontractor) performance will be used to assess the overall service delivery.

The contractor's service call program will document requests for service and responses. The contractor will make the service call records available for inspection by the COR at all times.

In the event of unsatisfactory service delivery the Government may contract for the services and charge the contractor for all costs incurred, including administrative costs.

The contractor wUI develop quality standards that will provide: (a) quantitative benchmarks for standard level of quality upon which Its performance may be measured and compared; (b) a narrative plan outlining what actions the contractor will take if the benchmarks are not met; and (c) actions which the contractor will take to ensure that future failures of quality control do not occur.

9. MAINTENANCE (NON-RECURRING SERVICES)

A. Upon request of the COR, the contractor shall furnish an estimate, detailing the breakdown of in-house labor hours and materials to be utilized for this work. If the use of subcontracts has been authorized, the contractor shall furnish written quotations from three (3) approved subcontractors. The CO may waive the requirement to obtain 3 proposals if time constraints apply. If the price is considered unreasonable, the CO will invite other firms to submit bids to accomplish the work. When authorized to perform Non-Recurring Service, the contractor shall ensure that each employee performing work signs in and out on a contract administration log for that specific project.

10. SCHEDULING WORK DURING EMERGENCY CONDITIONS

A When emergency conditions exist the contractor shall divert his/her workforce, or such part thereof as deemed necessary by the COR, from their normal assigned duties to meet the condition. When the emergency conditions no longer exist, the employees shall be directed by the contractor to return to their normal duties. The contractor shall not be penalized for the portion of the normal daily work which otherwise would have been performed.

WWII MAINTENANCE SERVICE CONTRACT

WWII MAINTENANCE SERVICE CONTRACT 7

7. Repairs

THIS SECTION INTENTIONALLY OMITTED

8. REIMBURSABLE SERVICES

THIS SECTION INTENTIONALLY OMITTED

WWII MAINTENANCE SERVICE CONTRACT 11

9. ADDITIONAL EQUIPMENT ADDED TO THE CONTRACT

A. The Contractor may be asked to provide new estimates for the maintenance of additional equipment that may be added to this contract

B. The Contractor may be asked to provide estimates for the replacement of existing equipment with new equipment.

10. SERVICE CALLS/RESPONSE

B. A "Service Calr is a report of a system malfunction made by customer complaints, COR's request, or contract personnel and the contractor's subsequent response to, and correction of, the problem.

C. The Contractor must have the capability to receive and record requests for service 24 hours per day, 365 days per year. The COR shall immediately be notified of all damaged facility system(s), Government property, disrupted Government operations, and any personal injury.

D. Requests for service may be made by the COR via email, telephone or in-person.

E. The contractor will respond by contacting the COR within a two hour time frame unless in cases of emergency when response time may be shorter.

F. In the event of an electrical outage the Contractor shall respond and arrive on-site within one-hour time frame.

G. For each service call the contractor shall provide to the COR, documentation that contains the following minimum information.

1 ) A description of the problem.

2) The location of the problem.

3) A description of the action taken to resolve the problem.

4) The time and date corrective action was completed.

5) The name of the person who corrected the problem.

H. If the contractor requires a part or material that is not in stock or work cannot be completed during the initial response then the COR who made the service request shall

WWII MAINTENANCE SERVICE CONTRACT 12

SECTION 3

SYSTEM SPECIFIC MAINTENANCE REQUIREMENTS

1. LIGHTING SYSTEM

A. Refer to EXHIBIT 2· Maintenance Schedule for bulb replacement requirements (frequency)

B. In order to evaluate re-lampilg needs for weekly lighting report, assessment will be calculated in annual service contract costs.

C. The contractor is responsible for supplying all components related to the proper maintenance of the lighting system. Includes but is not limited to lamps, ballasts, gaskets, potting material, GFCl's, lenses, receptacles, etc. as described in the EXHIBIT 2 - Maintenance Schedule.

D. Replacement of submerged bulbs should be in accordance with the applicable local and national electrical standards.

2. ELECTRICAL SYSTEM

A. All electrical work to include troubleshooting, repairing, inspection, and all testing will be verified by a licensed electrician in accordance with applicable National Electric Code requirements.

B. The contractor shall utilize the manufacturer or personnel certified by the manufacturer to maintain special equipment as listed below:

1) Major Electrical Testing- (Control Panels, Transfer Switches, Breakers, Switchboards and Transformers)

3. PLUMBING SYSTEM

A. System testing (i.e. back-flow preventer) will be verified in accordance with all federal, state and local plumbing code requirements.

B. Plumbing fixtures listed in EXHIBIT 2- Maintenance Schedule are standard commercial fixtures.

C. Unclogging of fixture may require removal from mount

4. FOUNTAIN SYSTEM

A. Comply with Fountain System Operation and Maintenance requirements.

5. GROUNDWATER TREATMENT SYSTEM

A. Comply the terms and conditions of the EPA NPDES and SWPPP permit (EXHIBITS 4 & 5).

B. Monthly groundwater analysis reports should be submitted to the NPS COR.

C. System testing of groundwater treatment shall be performed in accordance with all federa� state and local requirements; and the Operation and Maintenance requirements for the groundwater treatment system.

WWII MEMORIAL MAINTENANCE 14

File details come from the government source that posted it. Updated .