Copy_of_A12_RFP_Questions_and_Answers_Log_-_11-17-25_0003.pdf
PDF 261 KB Posted
- Attached to
- CON Qrts Renovation
- Solicitation number
- 140A2325R0041
About this file
This document is a Questions and Answers Log for a Request for Proposal (RFP), containing three submitted questions from Low Mountain on 11/17/2025. The questions address administrative and technical details related to a renovation project, with responses provided by the Contracting Officer's Representative (COR) on 11/18/2025.
The first question sought clarification on the SF30 form's availability, with a response indicating all forms and amendments are accessible on SAM.gov. The second question inquired about potential work outside the Statement of Work (SOW), to which the COR emphasized that all proposed work should be detailed in project design documents and submitted for approval, with the project's intent being a complete renovation to modernize and ensure building code compliance. The third question concerned asbestos testing protocols, and the response specified that the contractor is responsible for hazardous materials testing, reporting, and disposal, including submission of all relevant permits and receipts.
View the file
Other files
Show all 26
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Number Date Received Contractor Question Date Sent to COR Answer Date Answered
1 11/17/2025 Low Mountain
SF30 form (Amendment Acknowledgement) is not located on SAM, can you please post it. Or can we use form 1442? 11/17/2025
2 11/17/2025 Low Mountain
Will any work outside of the SOW be required, such as roofing, foundation, concrete, landscaping? Or will they be added as change orders on a per unit basis?
11/17/2025
All proposed work should be detailed in the project design documents and submitted to the COR for approval. The intent of the project to completely renovate each building to modernize and bring into compliance with current Building Codes. Change orders should not be considered for scoping purposes 11/18/2025
3 11/17/2025 Low Mountain
If areas outside SOW test positive for asbestos (E.g. entire drywall system), what will be the protocall? Just trying to define scope of work for pricing purposes
11/17/2025
Demolition requirements, including abatement of hazardous materials, are the responsibility of the Contractor and should be outlined in the Pre-Work Submittals. This includes hazardous materials testing of all project buildings and the submission of a formal report. Contractor is also responsible for disposal of all construction debris, including hazardous materials, and submittal of disposal permits, transportation and landfill receipts 11/18/2025
Questions and Answers Log for Request for Proposal i logged into sam.gov and was able to see all forms all amendments are also on sam.gov under Attachments/links
11/18/2025