This is a meeting summary from a pre-proposal conference held on October 8, 2024 for the Bureau of Indian Affairs' CRIP Main Canal Checks with Lateral 73 project (Solicitation #140A1624R0015). The meeting included representatives from BIA, Colorado River Indian Tribes (CRIT) Tribal Employment Rights Office, and CRIT Water Resources Department, with DOWL serving as the design engineer.

The project involves rehabilitation and replacement work at four sites: MC185 and MC270 check rehabilitations (CLIN 1), MC420 radial gate design (CLIN 2), MC420 check replacement (CLIN 3 - bid additive), MC420 electrical transmission modifications (CLIN 4), and Lateral 73-36 Check 1 replacement (CLIN 5). Key schedule milestones include contractor field measurements during January 2025 dry-up, gates functional at MC185/270 by end of January 2026 dry-up, electrical transmission realignment completion by March 31, 2026, and Lateral 73-36 temporary bypass ready by April 25, 2025. Questions are due October 11, 2024 with BIA responses the following week, and the solicitation deadline is November 1, 2024. The project requires coordination around irrigation dry-up periods and includes specific work restrictions related to environmental concerns and construction limits.

View the file

Other files

File Type Posted
B08__A70_Solicitation_Questions_and_Answers_Log_Final_0010.pdf PDF
Sol_140A1624R0015_Amd_0010.pdf PDF
Sol_140A1624R0015_Amd_0009.pdf PDF
Sol_140A1624R0015_Amd_0008.pdf PDF
Sol_140A1624R0015_Amd_0007.pdf PDF
B08__A68_Second_PreBid_Site_Visit_Minutes_0007.pdf PDF
Sol_140A1624R0015_Amd_0006.pdf PDF
B08__A47_Specifications_Lateral_73_0005.pdf PDF
B08__A62_PreBid_Site_Visit_Agenda_0005.pdf PDF
B08__A65_SF-24_Bid_Bond_Form_0005.pdf PDF
B08__A40_Revised_Solicitation_140A1624R0015_0005.pdf PDF
B08__A57_Geotechnical_Data_Report_Lateral_73_0005.pdf PDF
B08__A42_Statement_of_Work_Main_Canal_Checks_0005.pdf PDF
B08__A55_Historic_Drawings_Owner_Furnished_Gates_0005.pdf PDF
B08__A58_Asbestos_Assessment_Survey_MC185_MC270_MC420_0005.pdf PDF
B08__A54_Historic_Drawings_MC420_0005.pdf PDF
B08__A51_Drawings_MC420_Electrical_Transmission_0005.pdf PDF
B08__A66_SF-25_Performance_Bond_Form_0005.pdf PDF
B08__A52_Drawings_Lateral_73_0005.pdf PDF
B08__A59_Asbestos_Assessment_Survey_Lateral_73_0005.pdf PDF
B08__A44_Specifications_MC185_270_0005.pdf PDF
B08__A43_Statement_of_Work_Lateral_73_0005.pdf PDF
B08__A60_Groundwater_Monitoring_Report_MC185_MC270_MC420_0005.pdf PDF
B08__A63_Solicitation_Questions_and_Answers_Log_0005.xlsx XLSX spreadsheet
B08__A61_DOL_Wage_Rates_AZ20230007___AZ20230037_0005.pdf PDF
B08__A45_Specifications_MC420_0005.pdf PDF
B08__A56_Geotechnical_Data_Report_MC185_MC270_MC420_0005.pdf PDF
Sol_140A1624R0015_Amd_0005.pdf PDF
B08__A49_Drawings_MC270_0005.pdf PDF
B08__A41_Pricing_Schedule_0005.pdf PDF
B08__A67_SF-25A_Payment_Bond_Form_0005.pdf PDF
B08__A46_Specifications_M420_Electrical_Transmission_0005.pdf PDF
B08__A50_Drawings_MC420_0005.pdf PDF
B08__A48_Drawings_MC185_0005.pdf PDF
B08__A53_Historic_Drawings_MC270_0005.pdf PDF
B08__A64_IA_-_IEE_Representation_Form_0005.pdf PDF
Sol_140A1624R0015_Amd_0004.pdf PDF
B08__A31_Solicitation_Questions_and_Answers_Log_Round_Two_Final_0003.pdf PDF
Sol_140A1624R0015_Amd_0003.pdf PDF
B08__A30_Specification_35_22_46_-_Radial_Gates_Rev20241029_0003.pdf PDF
Sol_140A1624R0015_Amd_0002.pdf PDF
Meeting_SignInSheet_20241008_0002.pdf PDF
B08__A23_Solicitation_Questions_and_Answers_Log_Round_One_0002.pdf PDF
Sol_140A1624R0015_Amd_0001.pdf PDF
B08__A1_Pricing_Schedule.pdf PDF
B08__A21_DOL_Wage_Rates_AZ20230007___AZ20230037.pdf PDF
B08__A14_Historic_Drawings_MC420.pdf PDF
B08__A24_IA_-_IEE_Representation_Form.pdf PDF
B08__A22_PreBid_Site_Visit_Agenda.pdf PDF
B08__A5_Specifications_MC420.pdf PDF
Show 40 more

Latest 50 of 72 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MEETING SUMMARY

406-442-0370 ■ 1300 Cedar Street ■ Helena, Montana 59601 ■ www.dowl.com

PROJECT: CRIP Main Canal Checks with Lateral 73

DATE: 10/8/2024

SOLICITATION

NUMBER:

140A1624R0015 TIME: 8:30 a.m.

ORGANIZER: Will McLaughlin SUBJECT: Pre-proposal Conference

On October 8, 2024, BIA held a pre-proposal meeting for the (Colorado River Irrigation Project) CRIP Main Canal Checks with Lateral 73 project. Personnel from the Bureau of Indian Affairs, Colorado River Indian Tribes Tribal Employment Rights Office (TERO), and CRIT Water Resources Department attended the meeting. The meeting sign-in sheet is included as Attachment 1. The design engineer (DOWL) presented a brief presentation (Attachment 2) outlining key project components, the expected work sequence, and anticipated schedules. The slides included in Attachment 2 were distributed to in-person meeting participants as handouts. The notes annotated with each slide in Attachment 2 provide a summary of discussion topics but are not intended to provide a complete transcription of meeting discussions. The first 17 slides in Attachment 2 were discussed in the BIA conference room and the remaining slides were available for reference during the field review of each site. DOWL led a site walkthrough for prospective Bidders to review each of the four sites included in the solicitation. The meeting concluded at approximately 12:00 p.m.

Attachment 1: Sign-in Sheet

Virtual Attendees:

Abri-Gayle Sterlacci BIA – Contract Specialist abri-gayle.sterlacci@bia.gov

Kevin Smith BIA – Contracting Officer’s Representative kevinb.smith@bia.gov

Connie Nevarez DOWL cnevarez@dowl.com

Gabriel Sitapati DOWL gsitapati@dowl.com

Attachment 2: Presentation and Meeting Notes

CRIP MAIN

CANAL CHECK

STRUCTURES

Solicitation: 140A1624R0015

Pre-Bid Meeting

10/8/2024

These slides summarize the pre-bid meeting discussions for the subject solicitation.

Attachment 2, Page 001of 058

Attachment 2

AGENDA

8:30 to 10:00 Project Overview by BIA/DOWL

Introductions

Administrative Procedures (by BIA CO)

Project Overview (by DOWL)

General Q&A

10:00 to 1:00 On-site Field Review

MC185 and MC270 sites (~60 min. total)

MC420 site (~75 min. total)

Lat. 73-36 site (~75 min. total)

1:00 to 2:00 End of Meeting and Additional Q&A

Jeff Olsson (DOWL) briefly outlined the agenda for the pre-proposal meeting. Slides 1 through 17 of this presentation were presented during the “project overview” portion of the meeting. Subsequent slides were briefly discussed on-site at each of the project sites. The field review portion of the meeting concluded early at 12:00 p.m., local time.

Introductions of key BIA and Tribal team meeting participants included: Dillon Esquerra, CRIT Water Resources Director; Theo De La Rosa, CRIT TERO Director; Jonathan Cody, BIA Irrigation Engineer; Gary Colvin, BIA Irrigation Project Manager; Kevin Smith, BIA Contracting Officer Representative (COR); Abri-Gayle Sterlacci standing in for William McLaughlin who is the BIA Contracting Officer (CO); and Jeff Olsson, DOWL (BIA’s design A/E consultant) Project Manager and Engineer of Record.

Attachment 2, Page 002of 058

TRIBAL EMPLOYMENT RIGHTS OFFICE (TERO)

TERO Director Theo De La Rosa Email: theo.delarosa@crit-nsn.gov Phone: (928) 669-1380 Alt.: (928) 669-1390

Address: 26600 Mohave Road Parker, AZ 85344 https://crit-nsn.gov/crittero/

The TERO Director was in attendance at the meeting and confirmed the contact information shown here-in. Interested parties are encouraged to contact the TERO Office for more information on requirements that apply to this project and to individual contractors/subcontractors.

Attachment 2, Page 003of 058

ADMINISTRATIVE PROCEDURES &

BIDDING PROCESS

Bid/Proposal submittal overview (refer to Sections L and M)

• Volume 1 – Price Proposal

• Volume 2 - Technical Proposal

• Technical Approach

• Key Project Management/Technical Support

• Proposed Summary Schedule

• Relevant Experience and Past Performance

• Example Projects

Bid addenda process

Procedures for Question

• Verbal Q&A is non-binding

• Use the Q&A form in the solicitation

• Questions due October 11, 2024

• BIA Responses the following week

Solicitation Deadline – November 1, 2024 (unless modified through addenda)

Abri-Gayle Sterlacci presented this brief overview of the administrative procedures specific to this solicitation.

• All questions MUST be submitted in writing and on the Q&A form. All verbal Q&A is non-binding.

• Prospective bidders should review Sections L and M in particular for more detailed information on project-specification proposal information and how BIA will review these proposals.

• Anyone can submit questions through the proper channels and on the proper form.

Attachment 2, Page 004of 058

PROJECT OVERVIEW

CLIN 1: MC 185 & MC 270 Check Rehabilitation

CLIN 2: MC 420 Radial Gate Design

CLIN 3: MC 420 Check Replacement

CLIN 4: MC 420 Electrical Transmission and Distribution Modifications

CLIN 5: Lat. 73-36 Check 1 Replacement

Main Canal Check 185

Main Canal Check 270

Lateral 73-36 Check 1

Main Canal Check 420

This slide shows the four projects that have been bundled together by BIA for bidding and construction purposes:

• MC185 and MC270 – These sites will be rehabilitated on their current footprint and as such no permanent ROW modifications are required. CRIT approved a resolution in

2023 granting a temporary construction easement (TCE) to facilitate construction of these features.

• MC420 – This site is in worse condition than the two upstream sites and has the least remaining service life; replacement (i.e., not rehabilitation) is required for this site.

Replacement is not feasible within the current footprint and ROW modifications are required to facilitate construction on a new alignment adjacent the existing. ROW approvals are being coordinated by BIA and CRIT.

• Lateral 73-36 Check 1 – This is a re-bid of an earlier solicitation by BIA. This had previously been considered an emergency repair. No permanent ROW needs at this site. A TCE was approved by CRIT through a Tribal resolution earlier in the year.

Attachment 2, Page 005of 058

PRICING SCHEDULE STRUCTURE

Base Bid CLIN 1: MC 185 & MC 270 Check

Rehabilitation

CLIN 2: MC 420 Radial Gate Design

CLIN 4: MC 420 Electrical Transmission and Distribution Modifications

CLIN 5: Lat. 73-36 Check 1 Replacement

Bid Additive 1 CLIN 3: MC 420 Check Replacement

Main Canal Check 185

Main Canal Check 270

Lateral 73-36 Check 1

Main Canal Check 420

• BIA would like to award the base bid and bid additive. The bid additive is included to allow BIA flexibility in awarding the contract. For example, ROW modifications are ongoing at the time of award, BIA can award the base bid while waiting for final ROW authorizations.

• A key driver in the bidding and award schedule is the need for award in advance of the January 2025 dry-up schedule, as on-site activities by the successful proposer are required in January 2025.

• CLIN 2 includes the design of the MC420 radial gate. The fabrication and installation of this gate is included under CLIN 3.

Attachment 2, Page 006of 058

BASE BID – CLIN1

MC185

KEY WORK ELEMENTS

Radial Gate Replacement

Owner-Furnished Lateral Gates

Selective Demolition

Concrete and Steel Repairs

Walkways and Handrails

Instrumentation and Control Building

Safety Features, Fencing, Signage

Access Road Improvements

Stop Logs

• CRIP has a two-week (generally 14 calendar days) dry-up period in January of each year for routine O&M. Various activities (e.g., final gate measurements) will need to be performed by the successful proposer during this dry-up period. For the 2025 season, irrigation will be shut off Jan 12th and resume Jan 25th. The canal will likely take a few days for the water level to draw down.

• DOWL has identified activities in the plans that could take place prior to the dry-up period. However, the called-out activities may not be inclusive and may be adjusted based on Contractor preference. It will be important to the successful performance of the contract to do as much as possible outside of the very limited dry-up window.

• Unless indicated otherwise through addendum, bidders should assume a two-week dry-up period for bidding purposes; however, BIA and CRIT are reviewing the potential for an extended dry-up in January 2023 to better accommodate this project. Bidders are encouraged to submit a question if they feel completion within the two-week dry-up is infeasible.

• The lateral gates at MC185 are owner-furnished and the actuators require modification (e.g., a motor swap); however, the successful bidder is not obligated to use the owner-furnished equipment.

• The structure will need to be pressure washed during the dry-up period to facilitate crack mapping. This could be done during the January 2025 dry-up, if desired. Another consideration is to perform the crack repairs in January 2025 immediately after the crack mapping to reduce the work required in the January 2026 dry-up period.

• Field measurements of the radial gate and associated anchorage (which will be reused) will need to be taken by the successful proposer during the January 2025 dry-up period.

• Additional photos of the structures can be provided if requested via the Q&A process.

• The successful bidder would need to coordinate with the CRIT building inspector prior to bringing the control building on-line.

• The radial gates are electrically actuated and automated. The lateral slide gates are electrically actuated.

• A set of guides/rails will be installed at each MC site with one set of stop logs that can be used at all the sites. The bulkhead elements could be installed via crane if/when they are needed; these are not part of the

BIA’s typical/annual O&M.

Attachment 2, Page 007of 058

MC270

KEY WORK ELEMENTS

Radial Gate Replacement

Contractor-Furnished Lateral Gates

Selective Demolition

Concrete and Steel Repairs

Walkways and Handrails

Instrumentation and Control Building

Safety Features, Fencing, Signage

Access Road Improvements

Stop Logs Shared With MC 185

Expected Work Sequence Shared with MC 185

• The elements of the MC270 site are very similar to the MC185 site. The main difference between the sites is that the lateral gates for MC270 are CONTRACTOR-furnished.

• Field measurements of the structure will need to be taken during the 2025 dry-up period for the gate design.

• The existing anchorage will be re-used.

• There is flexibility if the successful bidder wants to re-use the existing anchorage or cut it flush and extend the rods – refer to the drawings.

• Although Contractor’s detailed measurements are to be used for shop drawing development and final design, sufficient information is provided in the drawings for bidding purposes. The drawings document the overall gate bay width and require post-installed side rubbing plates and sill plate, providing suitable construction tolerance for fit-up.

• MC185 and MC270 will be completed during the same two-week dry-up period.

Attachment 2, Page 008of 058

MC185/270 KEY CONSIDERATIONS

Annual January Main Canal dry-up (typically 2 weeks)

Contractor required to collect field measurements during January 2025 dry-up

Radial gate: assemble and test hoist as a single assembly in shop, deliver to site prior to dry-up

Contractor should do as much as possible prior to irrigation dry-up

• Radial gate field measurements must be taken and submitted.

• The specs outline the requirements for substantial completion and commissioning at the close of the dry-up period. The gates need to be able to be operated manually and ready for programming.

• The Owner will be providing programming, which is expected to occur immediately after the dry-up period.

• A question was asked about the concrete cure time prior to being under water/pressure. Jeff indicated that an official question should be submitted.

Attachment 2, Page 009of 058

B A

S E

B

ID

C

L

IN

L

A T.

-3

C H

E C

K R

E P

L A

C E

M E

N T

Existing Conditions Proposed Conditions

New Headworks

New Long-Crested Weir Check

Bank Improvements

Existing Check Structure with Integral Headworks

Cast-in-place Check

Precast Headgate

• This structure has been undermined several times and is not in very good condition.

• A new structure will be built slightly downstream of the current structure and a new headworks.

• A temporary check and bypass will be utilized to facilitate construction.

• The bypass will be constructed early in 2025 and will remain deactivated until the 2026 dry-up period.

• If the existing structure fails, the bypass can be activated early to allow irrigation to continue.

• Otherwise, the bypass will be activated during the 2026 dry-up period.

• The Lat. 73-36 check has a primary two-week dry-up period in Jan. (Jan. 12th – 25th in 2025).

• A secondary one-week dry-up period occurs in Feb. (Feb. 16th – 22nd in 2025).

• The headgate structure will be pre-cast and installed during the Jan. dry-up.

• The successful bidder will design and utilize their preferred cofferdam system.

• The plans include a design for the temporary check portion.

Attachment 2, Page 010of 058

EXISTING FACILITY – CHECK 1

A S

E B

ID

C L

IN

L A

T.

-3

A

N T

IC

IP

A

T E

D W

O R

K S

E Q

U E

N C

E

Construct Temp. Check & Bypass Channel

Construct Permanent Check Structure

Construct Headworks & Resume Irrigation

1 2 3

The work sequence depicted on this slide is the design intent that the plans are based on. The Engineer believes this expected work sequence is a reasonable approach with a high likelihood of success. The Contractor may propose an alternate work sequence. Certain aspects of the work (e.g., cofferdam type, method, and timing) are the responsibility of the Contractor. Some aspects of the illustration were based on an alternate construction sequence, but the overall workflow is similar. The general expected workflow is:

• Phase 1: Construct the temporary bypass and check. Sheet pile walls isolates the construction of a bypass channel parallel to the 73-36 lateral. A bank raise upstream of the new check will be required. Some of the sheets are temporary and are intended to be removed when activating the bypass channel. The bypass is expected to be left in this (inactivated) condition from completion in 2025 until the January 2026 dry-up.

• Phase 2: The bypass would be activated during the January 2026 dry-up. The existing check and headworks demolition would also be completed at this time. Water would then flow in the bypass while the new check is being constructed.

• Phase 3: After the permanent check is constructed the bypass would be removed, initiating flow over the new structure for water level control.

Attachment 2, Page 011of 058

BASE BID – CLIN5

LAT. 73-36 KEY TAKEAWAYS

Activating bypass (Cofferdamming and CRIP Coordination)

Foundation dewatering (Isolate Seepage and Active Dewatering)

Demolish existing structure and install headworks (During 2-wk Period)

Bidders are encouraged to give significant attention to these items.

Attachment 2, Page 012of 058

MC420 WORK RESTRICTIONS SUMMARY

Irrigation Restrictions and Dry-Up Schedule

Environmental Restrictions

Electrical Outage Window

Construction Limits

Construction Limits

Earthwork Borrow Area

Protect Culturally Significant Rock Outcrop

Protect Concrete Wasteway

• This site requires ROW modifications. BIA is working with CRIT to finalize the ROW authorizations for the project.

• Due to this, there might be a staggered award of bid additive 1.

• Work restrictions are included in the specs.

• Clearing and grubbing has to be completed during a specific time-frame to avoid the bird breeding season – refer to the environmental specifications.

• There is an electrical outage window.

• The new electrical transmission lines can be activated during this window with a brief outage or activated “hot”.

• Preliminary pole foundations have been designed. Final foundation designs will be based on the Contractor’s shop drawings and pole reactions provided through submittals. This may necessitate the need for a foundation size adjustment. Refer to the pricing schedule which shows how size adjustments will be handled.

Attachment 2, Page 013of 058

M C

S

IT

E

O V

E R

V

IE

W Proposed Transmission Line Existing

Transmission Line

New Check Structure

Existing Check Structure Drain

Realignment

Canal Realignment

• The final cut/fill for the project is expected to be a net balance; however, not every construction phase will balance. For example, we expect there will be a shortage during Phase 1 construction; to accommodate this, the drawings identify a temporary borrow area. Final excavations during Phase 3 would then be needed to restore this borrow area to pre-disturbance conditions; however, note that the Phase 3 available fill is on the opposite side of the canal from the temporary borrow area.

Attachment 2, Page 014of 058

ID

A D

D

IT

IV

E

M

C

A N

T

IC

IP

A

T E

D W

O R

K S

E Q

U E

N C

E

Construct New Canal Alignment and Check Structure

Tie Into New Alignment During Dry-Up

Resume Irrigation and Remove Existing Canal1 2 3

• The transmission line will need to be realigned prior to canal work.

• Canal realignment will include the three phases detailed above.

Attachment 2, Page 015of 058

EXPECTED PROJECT SCHEDULE SUMMARY

2027202620252024

Q2Q1Q4Q3Q2Q1Q4Q3Q2Q1Q4Q3Event

Awards and Contracting

Lat. 73-36 Bypass and Check Construction

Lat 73-36 Headgate Replacement

MC 185/270 Site Prep Work

MC 185/270 Radial Gate Replacement

MC 185/270

Final Site Work

MC 420 Electrical Transmission and Distribution

MC 420 Canal Realignment and New Check

MC 420 Gate Commissioning and Final Site Work

Jan. 2026 MC Dry-up

Jan. 2027 MC Dry-up

Jan. 2025 Gate Measurements

Temp Check & Bypass Perm. Check

Gate Shop Dwgs. & Fab.

Pole Shop Dwgs. & Fab.

C

LI

N

C

LI

N

C

LI

N

, 3

This schedule illustrated the general relationships between key activities, showing how we expect the work would be completed. The successful proposer may have alternate ideas; however, to be appropriate, any alternate work sequences or schedules need to consider the work restrictions (e.g., vegetation clearing windows, electrical outage periods, irrigation operations, and scheduled annual dry-up periods).

Attachment 2, Page 016of 058

RECOMMENDED CONSTRUCTION

SCHEDULE MILESTONES

Base Bid o CLIN 1 - MC185 and MC270 Check Rehabilitation o Perform Contractor’s on-site measurements during the January 2025 dry-up period o Gates Functional at the end of the January 2026 MC dry-up period o February 13, 2026: MC185 and MC270 Check Rehabilitation Substantial Completion o CLIN 4 - MC420 Electrical Transmission and Distribution Modifications o Perform clearing and grubbing activities and any electrical outages within the defined work restrictions o March 31, 2026: Elec. Transmission Realignment Substantial Completion o CLIN 5 - Lateral 73-36 o April 25, 2025: Temporary Bypass/Check Ready to Activate o Headgate Substantial Completion by the end of the January 2026 MC dry-up period o June 12, 2026: Lat. 73-36 Check 1 Substantial Completion

Bid Additive 1 o CLIN 3 - MC420 Check Replacement o Complete Phase 1 before the January 2027 MC dry-up o Construct Phase 2 during the January 2027 MC dry-up o Gate functional at the end of the January 2027 MC dry-up period

• These recommended construction schedule milestones are included in Addendum 1.

Attachment 2, Page 017of 058

REMINDERS

Review Solicitation Sections L and M

Schedules shown in these slides are for illustration purposes only – refer to the “Recommended Construction Schedule Milestones”

Verbal Q&A is non-binding

All questions must be submitted in writing to the COR

Leaving from the parking lot to MC 185 Check site

• If you get separated from the group call:

Jeff Olsson

406-202-8436 (mobile)

Field logistics & Safety Reminder

Attachment 2, Page 018of 058

C

H E

C K

R E

H A

B

IL

IT

A

T

IO

N

Beginning of slides covered on-site at the MC185 site. Not all of these slides were reviewed in detail during the field review.

Attachment 2, Page 019of 058

Radial Gate

Weir Wall

Lateral 19R Gate

Lateral 19L Gate

Overflow Wasteway

MC 185

SITE OVERVIEW

LATERAL 19L

Attachment 2, Page 020of 058

MC 185 WORK RESTRICTIONS

Dry-Up Schedule

Construction Limits

Environmental Restrictions

Construction Limits

Protect Pedestrian Bridge

Protect Concrete Wasteway

• The construction limits show the extent of the TCE approved by CRIT for the project. Work outside of these areas is not allowed.

Attachment 2, Page 021of 058

MC 185 STRUCTURE MODIFICATIONS

Selective demolition

Structural platforms, walkways, railings

Concrete restoration

Concrete weir wall

Stainless steel stoplogs and bulkhead slots

Brief overview of key structure modifications.

Attachment 2, Page 022of 058

MC 185 RADIAL GATE REPLACEMENT

Gate Hoist Assembly

1. Hoist base

2. Motor and gearing

3. Control panel

4. Cross shaft and wire rope drums

5. Grating and railings

Owner Witness Testing at fabrication shop

Erecting Engineer

Trunnion pins to fit existing anchor rods

Attachment 2, Page 023of 058

MC 185 LATERAL GATE REPLACEMENTS

Owner-furnished stainless steel slide gates

Lateral 19L Headgate Lateral 19R Headgate

Attachment 2, Page 024of 058

S

IT

E

I M

P R

O V

E M

E N

T S

Safety Cable & Ladders

Bollards

Fencing, Signage, & Gates

Road Resurfacing and Widening

All existing fences will be removed and replaced in their entirety.

Attachment 2, Page 025of 058

I

N S

T R

U M

E N

TA

T

IO

N

N

D C

O N

T R

O L S

Staff Gages

Water Level Sensors

Stilling Wells

New Control Building

Gate Instrumentation

Attachment 2, Page 026of 058

MC 185 ANTICIPATED WORK SEQUENCE

Phase 1: Prior to Main Canal Drawdown

Field Measurements (Jan. ‘25)

Selective Demolition

Radial Gate Procurement

Sensor Mounting and Installation

Control Building Installation

Staging and Preparation for Phase 2

All other work that can plausibly be completed before irrigation drawdown

Phase 2: During Main Canal Drawdown

Dewatering

Crack Mapping

Selective Demolition

Radial Gate and Lateral Gate Installation and Testing

Electrical Infrastructure

Structural Upgrades and Repairs

Safety Feature Installation

Concrete Weir Wall

Phase 3: After Main Canal Drawdown

Final Testing and Commissioning

Access Road Rehabilitation

Programming (by Owner) and Systems Integration

All Remaining Tasks

Site Rehabilitation and Demobilization

1 2 3

Attachment 2, Page 027of 058

MC 185 ANTICIPATED TIMELINE

20262025

Q2Q1Q4Q3Q2Q1Event

Field Measurements

Radial Gate Procurement and Fabrication

Site Preparatory Work

Gate Installation and Structure Modifications

Gate Commissioning

Final Site Work and Cleanup

Planned two-week irrigation shutoff in the CRIP Main Canal January 2025 and January 2026

Jan. 2025 Dry-up

Jan. 2026 Dry-up

Phase 1: Prior to Main Canal Drawdown

Phase 2: During Main Canal Drawdown

Phase 3: After Main Canal Drawdown

Attachment 2, Page 028of 058

RADIAL GATE PROCUREMENT FLOWCHART

Contractor Field Measurements (35 22 46-9)

Radial Gate Fabrication

Radial Gate Designer and Manufacturer Qualifications (35 22 46-1)

Radial Gate Approval Drawings and Data (35 22 46-2)

Wire Rope Prestressing Test Results (35 22 46-3)

Radial Gate Factory Acceptance Test Results (35 22 46-4)

Owner-witnessed Factory Acceptance Test Results (35 22 46-5)

Gate Handling and Installation Plan (35 22 46-6)

O&M Manuals and Post-Installation Documents (35 22 46-7 and 35 22 46-8)

Gate Hoist Assembly Fabrication

Ship Components to Site Gate Installation

Gate Commissioning and Testing

Training

Hoist Control Panel Product Data and Wiring Diagrams (40 63 13-1)

Hoist Control Panel Unwitnessed Factory Acceptance Test Results (40 63 13-2)

Hoist Control Panel Fabrication

Ship Panel to Hoist Assembly Shop

Owner’s Inspection of Materials

Notice of Award

Key Milestones

Radial Gate Submittals

Hoist Control Panel Submittals

LEGEND

FABRICATION SHOP(S)

PROJECT SITE

PANEL FACTORY

This flowchart illustrates project requirements. Emphasis on Contractor’s field measurements and Owner’s approval (e.g., gate hoist testing and gate inspection) of equipment. Programming will be by Owner after installation.

Attachment 2, Page 029of 058

MC 185 KEY TAKEAWAYS

Radial gate fabrication and testing requirements

Identify elements of work that can be completed prior to irrigation dry-up

Incorporating owner- and contractor-furnished equipment

Attachment 2, Page 030of 058

C

H E

C K

R E

H A

B

IL

IT

A

T

IO

N

Beginning of slides covered on-site at the MC270 site. Not all of these slides were reviewed in detail during the on-site meeting.

Attachment 2, Page 031of 058

Radial Gate

Spillway

Lateral 27R Gate

Lateral 27L Gate

Overflow Wasteway

MC 270

SITE OVERVIEW

LATERAL 27R LATERAL 27L

3 4

Attachment 2, Page 032of 058

MC 270 KEY

WORK ELEMENTS

Radial Gate Replacement

Selective Demolition

Concrete and Steel Repairs

Walkways and Handrails

Contractor-Furnished Lateral Gates

Instrumentation, and Control Building

Safety Features, Fencing, Signage

Access Road Improvements

Stop Logs Shared With MC 185

Expected Work Sequence Shared with MC 185

Attachment 2, Page 033of 058

C

H E

C K

R E

P L A

C E

M E

N T

Beginning of slides covered on-site at the MC420 site. Not all of these slides were reviewed in detail during the on-site meeting.

Attachment 2, Page 034of 058

Existing MC420 Check Structure

Existing Transmission Line

New Canal Alignment

MC420 Replacement Structure

Temporary Borrow Area

MC 420 SITE OVERVIEW

Attachment 2, Page 035of 058

MC 420 WORK RESTRICTIONS

Dry-Up Schedule

Construction Limits

Environmental Restrictions

Construction Limits

Earthwork Borrow Area

Protect Concrete Wasteway

Protect Culturally Significant Rock Outcrop

Attachment 2, Page 036of 058

E

X P

E C

T E

D W

O R

K S

E Q

U E

N C

E

Construct New Canal Alignment and Check Structure (2026)

Tie Into New Alignment During 2027 Dry-Up

Resume Irrigation and Remove Existing Canal1 2 3

Attachment 2, Page 037of 058

MC 420 EXPECTED TIMELINE

2027202620252024

Q2Q1Q4Q3Q2Q1Q4Q3Q2Q1Q4Event

Work Restrictions: Allowed Vegetative Clearing Window(s)

Work Restrictions: Allowed Transmission Outage Window

Electrical Pole Procurement and Fabrication

Construct Transmission and Distribution Revisions

Radial Gate Procurement and Fabrication

Construct Canal Realignment and New Check

Tie in Connection and Gate Commissioning

Final Site Work and Cleanup

Jan. 2027 Dry-up

Design Fabrication & Installation

CLIN 4 (Base Bid)

CLIN 2 (Base Bid)

CLIN 3 (Bid Additive 1)

Attachment 2, Page 038of 058

F

IN

IS

H E

D S

IT

E

P L A

N Realigned Access Road

Concrete Canal Lining

Relocated Drain Ditch

New MC 420 Check Structure and Security Fencing

Canal Safety Features

Buried Drain Pipe

Attachment 2, Page 039of 058

MC 420: DRAIN REALIGNMENT

Attachment 2, Page 040of 058

R

E P

L A

C E

M E

N T

C H

E C

K S

T R

U C

T U

R E

Attachment 2, Page 041of 058

MC 420 RADIAL GATE

Individual Contract Line Item

Gate Hoist Assembly

Owner-Witness Hoist Assembly Testing at Fabrication Shop

Owner’s Inspection of Radial Gate Before Shipping

Erecting Engineer and Commissioning

Attachment 2, Page 042of 058

Sensors and electrical system for gate controls and flow measurement

Additional instrumentation and controls at Lateral 42L

Electrical system for gate controls not associated with transmission realignment

PLC Programming By Owner

MC 420 CONTROLS AND

INSTRUMENTATION

Control Building

Hoist Control Panel

Existing Electrical Distribution Pole

Stilling Wells

Attachment 2, Page 043of 058

MC 420 ELECTRICAL TRANSMISSION REALIGNMENT

Alignment

Work Sequencing

Foundation Payment Procedures

Attachment 2, Page 044of 058

MC 420 KEY TAKEAWAYS

New Canal Alignment Construction

Radial Gate Commissioning Before Phase 3

Electrical Transmission Realignment

Attachment 2, Page 045of 058

L

T E

R A

L

-3

C

H E

C K

R

P L A

C E

M E

N T

Beginning of slides covered on-site at the Lat. 73-36 site. Not all of these slides were reviewed in detail during the on-site meeting.

• Project Purpose: replacing infrastructure while minimizing interruptions in irrigation service.

• The new check will be an updated version of the existing long-crested weir, which maintains a relatively consistent upstream water level over a wide range of flow rates.

Attachment 2, Page 046of 058

73-36 Check 1

73-36-7 Headworks

Temporary Bypass

Check 1 Replacement

LAT. 73-36 SITE

OVERVIEW

3 4

LA

TE

R A

L

-3

Attachment 2, Page 047of 058

LAT. 73-36 BACKGROUND INFORMATION

Attachment 2, Page 048of 058

LAT. 73-36 WORK RESTRICTIONS

Dry-Up Schedule

Construction Limits

Environmental Restrictions

Construction Limits

Attachment 2, Page 049of 058

EXISTING FACILITY – CHECK 1

L A

T E

R A

L

-3

E

X P

E C

T E

D W

O R

K S

E Q

U E

N C

E

Construct Temp. Check & Bypass Channel

Construct Permanent Check Structure

Construct Headworks & Resume Irrigation

1 2 3

Attachment 2, Page 050of 058

LAT. 73-36 EXPECTED TIMELINE

202620252024

Q2Q1Q4Q3Q2Q1Q4Event

Construct Temporary Check and Bypass

Install Cofferdams

Construct Permanent Check Structure

Fabricate Headgate and Precast Elements

Demolish Existing Check and Install Headgate

Final Site Grading and Cleanup

Annual two-week irrigation shutoff in Main Canal and Sublateral 73-36 January of each year

Additional one-week Lateral 73 shutdown in February of each year

Exact shutdown dates vary by year

Jan. 2026 Dry-up

Optional Permanent Check Construction Window

Attachment 2, Page 051of 058

T

M P

O R

A R

Y C

H E

C K

C O

N S

T R

U C

T

IO

N

A Typical Section Bypass Channel

A

The borrow source for the temporary bypass fill is the adjacent farm field.

Attachment 2, Page 052of 058

TEMPORARY CHECK CONSTRUCTION

Sheet Pile 1

Sheet Pile 2

Sheet Pile 3

A brief discussion on the design intent of the temporary check and bypass. Sheet Pile 1 and Sheet Pile 3 will be removed to activate the bypass channel. Sheet pile 2 is the temporary weir wall check that will stay in place for the duration that the bypass is active. The Contractor could propose an alternate sheet pile or bypass channel configuration.

Attachment 2, Page 053of 058

TEMPORARY CHECK CONSTRUCTION

Sheet Pile 1 Sheet Pile 2

Sheet Pile 2

Sheet Pile 2 manages the upstream water level after the bypass channel is activated. The Contractor can decide how to achieve the specified elevation and length (e.g., overdriving or cutting the sheet pile).

Attachment 2, Page 054of 058

73-36 CHECK 1 CONSTRUCTION

The replacement check is a relatively simple concrete structure, primarily consisting of flatwork and vertical walls with a downstream riprap apron. The Contractor will blend in the canal side slopes with the existing canal.

Attachment 2, Page 055of 058

D

M O

E X

IS

T

IN

G

C H

E C

K

A N

D C

O N

S T

R U

C T

N E

W H

E A

D W

O R

K S

An expected excavation plan is shown on the left and the final grading plan is shown on the right. During the 2-week dry-up, the Contractor will demolish the existing structure and install the pipe, precast headwall, and precast outlet wall. The actual excavation approach will be the Contractor’s decision. Implicit to the design is the idea that the structure can be demolished and the new facility installed during the 2-week drawdown. Bidders are encouraged to review this sequence carefully when preparing their bids.

Attachment 2, Page 056of 058

73-36-7 HEADWORKS CONSTRUCTION

Precast Headworks Fabricated in Three Pieces

B C

A

Embedded Wall Thimble

To improve constructability and allow for installation during the 2-week drawdown, Owner and Engineer selected a precast arrangement for the headwall. The headwall consists of three main precast elements and a concrete cutoff wall. Bidders attention was called to the wall thimble required for the headgate – this will take some coordination. Early development of gate shop drawings and precast design by Contractor and their suppliers is encouraged. The wall thimble is an embedded element requiring coordinated shop drawings and delivery of the wall thimble to the precast manufacturer. The outlet wall (not pictured in this presentation) is a similar precast element without a wall thimble.

Attachment 2, Page 057of 058

LAT. 73-36 CHECK 1 KEY TAKEAWAYS

Activating bypass (Cofferdamming and CRIP Coordination)

Foundation dewatering (Isolate Seepage and Active Dewatering)

Demolish existing structure and install headworks (During 2-wk Period)

Attachment 2, Page 058of 058