This is Addendum No. 1 for a contract issued by the Northwest Bergen County Utilities Authority (NBCUA) for the Disposal of Incinerator Ash for the Wastewater Treatment Plant, with Solicitation Reference No. NBCUA-BID-25-003. The bid submission deadline has been extended to September 10, 2025 at 12:00 PM Prevailing Time, pushed back from the original August 19, 2025 deadline. The addendum includes responses to five prospective bidder questions that modify the original bid documents.
Key modifications include the deletion of Section G.24 on Liquidated Damages, which means contractors shall not include any liquidated damages provisions in their bids, and the addition of a new Section G.28 on Force Majeure. The Force Majeure clause provides detailed definitions and conditions under which performance delays may be excused, including events like natural disasters, government-ordered closures, strikes, and declared emergencies. The payment terms remain at NET 60 days, and the existing contract terms regarding consequential damages will stay in effect. Bidders are required to acknowledge receipt of this addendum in their bid submission, and all other terms and conditions of the original Request for Bid remain unchanged except as specifically modified in this addendum.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Northwest Bergen County Utilities Authority
ADDENDUM NO. 1
Solicitation Reference No.: NBCUA-BID-25-003 Contract No.: 25-003
DISPOSAL OF INCINERATOR ASH FOR THE WASTEWATER TREATMENT PLANT
Questions and Answers
IMPORTANT NOTICE – BID SUBMISSION DEADLINE CHANGE
THE BID SUBMISSION DEADLINE HAS BEEN EXTENDED
NEW DEADLINE: SEPTEMBER 10, 2025 at 12:00 PM PREVAILING TIME (Previously: August 19, 2025 at 9:00 AM EDT)
ALL BIDS MUST BE RECEIVED BY THE NEW DEADLINE TO BE CONSIDERED
By order of the Northwest Bergen County Utilities Authority (hereinafter, called the "NBCUA" or "Authority"), all Contractors submitting Bids for the above Contract are hereby given notice that, in accordance with the New Jersey Local Public Contracts Law, the Authority is issuing Addendum No. 1 dated August 9, 2025. This addendum is hereby made part of the contract documents for the above Contract. Please note the revisions described herein and submit bids accordingly.
Questions and Answers
The following questions were submitted by prospective bidders. Questions may have been modified by the Authority for clarity and conciseness.
Q&A TABLE:
Question No.
RFB Section Reference Submitted Question (May be edited for clarity) NBCUA Response
General Conditions, Section G.21
Will the Authority include in the General Conditions of Contract, as a modification to Section G.21, NET 30 payment terms upon receipt of properly formatted invoice from the Contractor (replacing existing 60-day payment terms)?
No change to the existing NET 60 payment terms. The current 60-day payment terms as specified in Section G.21 will remain in effect.
General Conditions, Section G.24
Will the Authority agree to include in Section G.24 (Liquidated Damages) the following clause: “Liquidated Damages shall not be assessed on this Contract if the delay in, or impossibility of performance by the Contractor, is the result of or occasioned by a Force Majeure Event, or circumstance beyond the control of the Contractor.”?
IMPORTANT NOTICE: Section G.24 (Liquidated Damages) SHALL BE DELETED in its entirety from the General Conditions of Contract for NBCUA-BID-25-
003. Contractors shall not include any provisions for liquidated damages in their bids. This section is specifically excluded and will not apply to Contract 25- 003.
3 General Conditions
Will the Authority agree to add a Force Majeure clause as a new section in the General Conditions, substantially in the form proposed by the bidder (including relief for uncontrollable circumstances and change in law)?
Yes. The Authority agrees to add the following as new Section G.28:
FORCE MAJEURE (Section G.28):
(a) Definition: Neither party shall be liable for failure or delay in performance due to causes beyond their reasonable control and without fault or negligence, including:
• Fire, flood, or acts of God directly impacting disposal site or transportation
• Government-ordered closure of disposal facilities or transport routes
• Strikes at disposal facility (excluding Contractor’s employees)
• Declared state of emergency prohibiting trucking
No.
RFB Section Reference Submitted Question (May be edited for clarity) NBCUA Response
(b) Exclusions: Includes but is not limited to:
• Typical regional weather
• Equipment breakdowns
• Financial inability to perform
• Strikes involving Contractor’s personnel
• Changes in disposal site fees or taxes
• Routine permit delays
(c) Notice: Affected party must notify the other within 48 hours, including:
• Event nature and duration
• Mitigation steps
• Revised performance schedule
(d) Mitigation: Contractor must use best efforts to secure NJDEP-approved alternate disposal. Costs during Force Majeure events will be negotiated in good faith.
(e) Duration: Events lasting more than 30 consecutive days may trigger contract termination by Authority.
(f) Payment: Force Majeure does not relieve:
• The Authority from paying for completed, accepted services
• The Contractor from remitting already-paid fees or tipping charges
4 General Conditions
Will the Authority add, as a new General Condition of the Contract, a Mutual Waiver of Punitive and Consequential Damages, substantially in the form proposed by the bidder (“Neither party shall be liable for consequential or punitive
No change. The existing contract terms regarding damages remain in effect.
No.
RFB Section Reference Submitted Question (May be edited for clarity) NBCUA Response damages on any claims arising out of the performance or non-performance of obligations under the Contract.”)?
General Conditions, Section G.24
Can the Authority provide an amount for liquidated damages in Section G.24, as the surety company has requested this information prior to providing the Bid Guarantee?
As stated in Answer to Question 2 above, Section G.24 (Liquidated Damages) has been DELETED from this contract. No liquidated damages provisions apply to Contract 25-003. Bidders shall not include any such amounts in their bids.
SUMMARY OF CHANGES:
1. BID SUBMISSION DEADLINE EXTENDED TO: SEPTEMBER 10, 2025 at 12:00 PM PREVAILING TIME
2. Section G.24 (Liquidated Damages) – DELETED
3. Section G.28 (Force Majeure) – ADDED
4. All other terms and conditions of the original Request for Bid (RFB) for NBCUA Contract No. 25-003 remain unchanged except as specifically modified by this Addendum
Bidders MUST acknowledge receipt of this Addendum in their bid submission.
End of Addendum No. 1