SECTION 01 33 00 - SUBMITTAL PROCEDURES
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes requirements for the submittal schedule and administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, and other submittals.
B. Related Sections include, but not limited to:
1. Division 1 Section "Construction Progress Documentation" for submitting schedules and reports, including Contractor's construction schedule and the Submittals Schedule.
2. Division 1 Section "Operation and Maintenance Data" for submitting operation and maintenance manuals.
3. Division 1 Section "Project Record Documents" for submitting record Drawings, record
Specifications, and record Product Data.
4. Division 1 Section "Closeout Procedures" for submitting warranties.
5. Division 1 Section “Design After Award” for design submissions.
6. Division 1 Section “Summary of Work” for submittal of work to be performed by the contractor.
1.3 DEFINITIONS
A. Action Submittals: Written and graphic information and physical samples that require COR’s responsive action. Action submittals are those submittals indicated in individual Specification
Sections as action submittals or identified as submittals for Government approval.
B. Informational Submittals: Written and graphic information and physical samples that do not require COR's responsive action. Submittals may be rejected for not complying with requirements. Informational submittals are those submittals indicated in individual Specification
Sections as informational submittals.
C. Designer of Record Approved Submittals (DOR): Designer of Record approval is required for extensions of design, critical materials, any deviations from the solicitation, the accepted proposal, or the completed design, equipment whose compatibility with the entire system must be checked, and other items as designated by the Contracting Officer. Within the terms of the
Contract Clause, FAR 52.236-1 Alt 1, entitled "Specifications and Drawings for Construction,"
Section 01 33 00-Page 2 they are considered to be "shop drawings." Contractor to provide the Government with the number of copies designated hereinafter of all Designer of Record approved submittals. The
Government may review any or all Designer of Record approved submittals for conformance to the Solicitation and Accepted Proposal. The Government will review all submittals designated as deviating from the Solicitation or Accepted Proposal.
D. Government Approved (GA): Government approval is required for extensions of design, critical materials, deviations, equipment whose compatibility with the entire system must be checked, and other items as designated by the Contracting Officer. Government approval is required for any deviations from the Solicitation or Accepted Proposal and other items as designated by the
Contracting Officer. Within the terms of the Contract Clause entitled "Specifications and
Drawings for Construction," they are considered to be "shop drawings."
E. Government Conformance Review of Design (CR): The Government will review all intermediate and final design submittals for conformance with the technical requirements of the solicitation.
Specification DESIGN AFTER AWARD covers the design submittal and review process in detail. Review will be only for conformance with the applicable codes, standards and contract requirements. Design data includes the design documents described in Specifications DESIGN
AFTER AWARD.
F. Designer of Record Approved/Government Conformance Review (DA/CR)
1. Deviations to the Accepted Design: Designer of Record approval and the Government's concurrence are required for any proposed deviation from the accepted design which still complies with the contract before the Contractor is authorized to proceed with material acquisition or installation. Within the terms of the Contract Clause entitled, "Specifications and Drawings for Construction," they are considered to be "shop drawings." If necessary to facilitate the project schedule, the Contractor and the DOR may discuss a submittal proposing a deviation with the Contracting Officer's Representative prior to officially submitting it to the Government. However, the Government reserves the right to review the submittal before providing an opinion, if deemed necessary. In any case, the
Government will not formally agree to or provide a preliminary opinion on any deviation without the DOR's approval or recommended approval. The Government reserves the right to non-concur with any deviation from the design, which may impact furniture, furnishings, equipment selections or operations decisions that were made, based on the reviewed and concurred design.
2. Substitutions: Unless prohibited or provided for otherwise elsewhere in the Contract, where the accepted contract proposal named products, systems, materials or equipment by manufacturer, brand name and/or by model number or other specific identification, and the
Contractor desires to substitute manufacturer or model after award, submit a requested substitution for Government concurrence. Include substantiation, identifying information and the DOR's approval, as meeting the contract requirements and that it is equal in function, performance, quality and salient features to that in the accepted contract proposal.
If the Contract otherwise prohibits substitutions of equal named products, systems, materials or equipment by manufacturer, brand name and/or by model number or other specific identification, the request is considered a "variation" to the contract. Variations are discussed below in paragraphs: "Designer of Record Approved/Government Approved" and "VARIATIONS."
Section 01 33 00-Page 3
3. Designer of Record Approved/Government Approved (DA/GA): In addition to the above stated requirements for proposed deviations to the accepted design, both Designer of
Record and Government Approval and, where applicable, a contract modification is required before the Contractor is authorized to proceed with material acquisition or installation for any proposed variation to the contract (the solicitation and/or the accepted proposal), which constitutes a change to the contract terms. Within the terms of the
Contract Clause entitled, "Specifications and Drawings for construction," they are considered to be "shop drawings." The Government reserves the right to accept or reject any such proposed deviation at its discretion.
G. File Transfer Protocol (FTP): Communications protocol that enables transfer of files to and from another computer over a network and that serves as the basis for standard Internet protocols. An
FTP site is a portion of a network located outside of network firewalls within which internal and external users are able to access files.
H. Portable Document Format (PDF): An open standard file format licensed by Adobe Systems used for representing documents in a device-independent and display resolution-independent fixed-layout document format.
I. Base Manufacturer:
1. The term “base manufacturer” as used in the Specifications refers to a manufacturer of equipment, materials, articles, or patented processes, designated by trade name, make, or catalog number, that have been used as the basis of design.
2. Base manufacturer’s products shall be regarded as establishing a standard of quality and shall not be construed as limiting competition.
1.4 ACTION SUBMITTALS
A. Submittal Schedule: Submit a schedule of submittals, arranged in chronological order by dates required by construction schedule. Include time required for review, ordering, manufacturing, fabrication, and delivery when establishing dates. Include additional time required for making corrections or modifications to submittals noted by the COR and additional time for handling and reviewing submittals required by those corrections.
1. Coordinate submittal schedule with list of subcontracts, the schedule of values, and
Contractor's construction schedule.
2. Format: Arrange the following information in a tabular format:
a. Scheduled date for first submittal.
b. Specification Section number and title.
c. Submittal category: Action, informational.
d. Name of subcontractor.
e. Description of the Work covered.
f. Scheduled date for COR's final release or approval.
g. Scheduled dates for purchasing.
Section 01 33 00-Page 4
h. Scheduled dates for installation.
i. Activity or event number.
1.5 SUBMITTAL ADMINISTRATIVE REQUIREMENTS
A. COR's Digital Data Files: If electronic copies of CAD Drawings of the Contract Drawings are to be provided by the COR for Contractor's use in preparing submittals.
a. COR and Architect make no representations as to the accuracy or completeness of digital data drawing files as they relate to the Contract Drawings.
B. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.
1. Coordinate each submittal with fabrication, purchasing, contractor funded testing, delivery, other submittals, and related activities that require sequential activity.
2. Submit all submittal items required for each Specification Section concurrently unless partial submittals for portions of the Work are indicated on approved submittal schedule.
3. Submit action submittals and informational submittals required by the same Specification
Section as separate packages under separate transmittals.
4. Coordinate transmittal of different types of submittals for related parts of the Work so processing will not be delayed because of need to review submittals concurrently for coordination.
a. COR reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.
C. Processing Time: Allow time for submittal review, including time for resubmittals, as follows.
Time for review shall commence on COR's receipt of submittal. No extension of the Contract
Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing, including resubmittals.
1. Initial Review: Allow 28 calendar days for initial review of each submittal. Allow additional time if coordination with subsequent submittals is required. COR will advise
Contractor when a submittal being processed must be delayed for coordination.
2. Intermediate Review: If intermediate submittal is necessary, process it in same manner as initial submittal.
3. Reprocessing: Allow 14 calendar days for reprocessing each submittal.
4. Re-submittal Review: Allow 14 calendar days for review of each resubmittal.
5. No extension of Contract Time will be authorized because of failure by the Contractor to transmit submittals to the Government sufficiently in advance of the Work to permit processing.
D. Identification and Information: Place a permanent label or title block on each paper copy submittal item for identification.
1. Indicate name of firm or entity that prepared each submittal on label or title block.
Section 01 33 00-Page 5
2. Provide a space approximately 4 by 5 inches on label or beside title block to record
Contractor's review and approval markings and action taken by COR.
3. Include the following information for processing and recording action taken:
a. Project name.
b. Date.
c. Name and Address of Architect
d. Name and Address of Contractor
e. Name and Address of Sub-Contractor.
f. Name and Address of Supplier.
g. Name of manufacturer.
h. Submittal number or other unique identifier, including revision identifier.
1) Submittal number shall use Specification Section number followed by a decimal point and then a sequential number (e.g., 061000.01). Resubmittals shall include an alphabetic suffix after another decimal point (e.g., 061000.01.A).
i. Number and title of appropriate Specification Section.
j. Drawing number and detail references, as appropriate.
k. Location(s) where product is to be installed, as appropriate.
l. Other necessary identification.
E. Identification and Information: Identify and incorporate information in each electronic submittal file as follows:
1. Assemble complete submittal package into a single indexed file with links enabling navigation to each item.
2. Name file with submittal number or other unique identifier, including revision identifier.
a. File name shall use project identifier and Specification Section number followed by a decimal point and then a sequential number (e.g., LNHS-061000.01).
Resubmittals shall include an alphabetic suffix after another decimal point (e.g., LNHS-061000.01.A).
3. Provide means for insertion to permanently record Contractor's review and approval markings and action taken by COR.
4. Include the following information on an inserted cover sheet:
a. Project name.
b. Date.
c. Name and Address of Architect
d. Name and Address of Contractor
e. Name and Address of Sub-Contractor.
f. Name and Address of Supplier.
g. Name of manufacturer.
h. Number and title of appropriate Specification Section.
Section 01 33 00-Page 6
i. Drawing number and detail references, as appropriate.
j. Location(s) where product is to be installed, as appropriate.
k. Related physical samples submitted directly.
l. Other necessary identification.
5. Include the following information as keywords in the electronic file metadata:
a. Project name.
b. Number and title of appropriate Specification Section.
c. Manufacturer name.
d. Product name.
F. Options: Identify options requiring selection by the COR.
G. Deviations: Identify deviations from the Contract Documents on submittals.
H. Additional Paper Copies: Unless additional copies are required for final submittal, and unless
COR observes noncompliance with provisions in the Contract Documents, initial submittal may serve as final submittal.
1. Submit one copy of submittal to concurrent reviewer in addition to specified number of copies to COR.
I. Transmittal: Assemble each submittal individually and appropriately for transmittal and handling. Transmit each submittal from Contractor to NIST using a transmittal form. COTR will return submittals, without review, received from sources other than Contractor. Transmittal form:
Use format agreeable to COR
1. Transmittal Form: Provide locations on form for the following information:
a. Project name.
b. Date.
c. Destination (To :).
d. Source (From :).
e. Names of subcontractor, manufacturer, and supplier.
f. Category and type of submittal.
g. Submittal purpose and description.
h. Specification Section number and title.
i. Indication of full or partial submittal.
j. Drawing number and detail references, as appropriate.
k. Transmittal number.
l. Submittal and transmittal distribution record.
m. Remarks.
n. Signature of transmitter.
Section 01 33 00-Page 7
2. On an attached separate sheet, prepared on Contractor's letterhead, record relevant information, requests for data, revisions other than those requested by COR on previous submittals, and deviations from requirements in the Contract Documents, including minor variations and limitations. Include same identification information as related submittal.
J. Resubmittals: Make resubmittals in same form and number of copies as initial submittal.
1. Note date and content of previous submittal.
2. Note date and content of revision in label or title block and clearly indicate extent of revision.
3. Resubmit submittals until they are marked with approval notation from the COR's action stamp.
K. Distribution: Furnish copies of final submittals to manufacturers, subcontractors, suppliers, fabricators, installers, authorities having jurisdiction, and others as necessary for performance of construction activities. Show distribution on transmittal forms.
L. Use for Construction: Use only final submittals that are marked with approval notation from
COR's action stamp.
PART 2 - PRODUCTS
2.1 SUBMITTAL PROCEDURES
A. General Submittal Procedure Requirements: Prepare and submit submittals required by individual Specification Sections. Types of submittals are indicated in individual Specification
Sections.
1. Submit submittals via mail or other delivery service to COR for review.
a. COR will return annotated file. Annotate and retain one copy of file as an electronic
Project record document file.
2. Submittals: The Contractor shall prepare submittals in accordance with the Special
Contract Requirements and the Technical Specifications and submit to the COR for approval. Each submittal shall be accompanied with a cover letter signed by the
Contractor. The Contractor shall clearly mark each item proposed to be incorporated into the contract and identify in the submittals, with cross-references to the contract drawings and specifications so as to identify clearly the use for which it is intended. Stamp each sheet of submittal with the Contractor’s certification stamp. Data submitted in a bound volume or on one sheet printed on two sides, may be stamped on the front of the first sheet only. The Contractor’s certification stamp shall be worded as follows
a. “It is hereby certified that the (equipment) (material) shown and marked in this submittal is that proposed to be incorporated into Contract Number
___________________, is in compliance with the Contract drawings and
Section 01 33 00-Page 8 specifications, can be installed in the allocated spaces, and is submitted for
Government approval.
b. Certified by_________________________Date_______________________”
c. The person signing the certification shall be one designated in writing by the
Contractor as having that authority. The signature shall be in original ink. Stamp signatures are not acceptable.
3. Action Submittals: Submit Six (6) paper copies of each submittal, unless otherwise indicated. COR will return two copies.
4. Informational Submittals: Submit Six (6) paper copies of each submittal, unless otherwise indicated. COR will return Two (2) copies.
5. Closeout Submittals and Maintenance Material Submittals: Comply with requirements specified in Division 01 Section "Closeout Procedures."
6. Certificates and Certifications Submittals: Provide a statement that includes signature of entity responsible for preparing certification. Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity.
a. Provide a digital signature with digital certificate on electronically-submitted certificates and certifications where indicated.
b. Provide a notarized statement on original paper copy certificates and certifications where indicated.
7. Test and Inspection Reports Submittals: Comply with requirements specified in Division 1
Section "Quality Requirements."
8. Submittal Status Logs: The Contractor shall utilize the submittal log provided by the COR of Construction. The Contractor shall verify the log for accuracy and completeness, and shall notify the COR, in writing, within seven (7) calendar days with regards to the same.
The Contractor is required to maintain at the job-site an up-to-date log showing the status of all submittals required by the Contract. Use of a numbering system is required.
9. Shop Drawings: These submittals shall be in accordance with the requirements of the clause entitled “Shop Drawings”
10. Manufacturer’s Data: Catalogue cuts, technical data sheets, descriptive literature, and samples shall be submitted in accordance with the clause entitled, “Submittal Procedures”
11. Certified Test Reports: Before delivery of materials and equipment, five (5) certified copies of the reports of all test listed in the technical sections shall be submitted and approved. The contractor funded testing shall have been performed in a laboratory meeting the requirements specified herein. The tests shall have been performed within three (3) years of submittal of the reports for approval. Test reports shall be accompanied by the certificates from the manufacturers certifying that the material and equipment proposed to be supplied is of the same type, quality, manufacture, and make as that tested
12. Manufacturer’s Certificates of Conformance: Before delivery, manufacturer’s certifications shall be furnished by the Contractor as required on items of materials and
Section 01 33 00-Page 9 equipment indicated in the technical sections. Pre-printed certifications will not be acceptable. All certifications shall be in the original. The original of all manufacturers’ certifications shall name the appropriate item of equipment or material, specification, standard, or other document specified as controlling the quality of that item and shall have attached thereto certified copies of test data upon which the certifications are based. All certificates shall be signed by the manufacturer’s official authorized to sign certificates of conformance.
13. Laboratory Reports: Reports shall cite the contract requirements, the test or analysis procedures used, the actual test results, and include a statement that the item tested or analyzed conforms or fails to conform to the specification requirements. Each report shall be conspicuously stamped on the cover sheet in large red letters “CONFORMS” or “DOES
NOT CONFORM” to the specification requirements as the case may be. All test reports shall be signed by a representative of the contractor funded testing laboratory authorized to sign certified test reports. The Contractor shall arrange for immediate and direct delivery of the signed original of all reports, certifications, and other documentation to the
Contracting Officer.
14. Tabulation of Tests: Prior to final payment, the Contractor shall obtain from each laboratory a tabulation of all tests it has performed in connection with the construction contract. Conforming, nonconforming, and contractor funded testing shall be tabulated.
The tabulation(s) shall be certified as complete, and signed by the authorized representative of the laboratory, and shall be delivered to the Contracting Officer.
15. Deviations: Deviations from contract requirements require Government approval pursuant to contract Clause FAR 52.236-21 and will be considered where advantageous to
Government. Discussion with Contracting Officer prior to submission will help ensure functional and quality requirements are met and minimize rejections and re-submittals.
When contemplating a variation which results in lower cost, consider submission of the variation as a Value Engineering Change Proposal (VECP).
a. When proposing a deviation, deliver written request to the Contracting Officer, with documentation of the nature and features of the variation and why the variation is desirable and beneficial to Government. If lower cost is a benefit, also include an estimate of the cost savings. In addition to documentation required for variation, include the submittals required for the item. Clearly mark the proposed variation in all documentation.
b. Set forth in writing the reason for any deviations and annotate such deviations on the submittal. The Government reserves the right to rescind inadvertent approval of submittals containing unnoted deviations.
c. When delivering a deviation for approval, Contractor warrants that this contract has been reviewed to establish that the deviation, if incorporated, will be compatible with other elements of work.
d. In addition to normal submittal review period, a period of 10 working days will be allowed for consideration by the Government of any submittals with variations.
Section 01 33 00-Page 10
B. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.
1. If information must be specially prepared for submittal because standard published data are not suitable for use, submit as Shop Drawings, not as Product Data.
2. Mark each copy of each submittal to show which products and options are applicable.
3. Include the following information, as applicable:
a. Manufacturer's catalog cuts.
b. Manufacturer's product specifications.
c. Standard color charts.
d. Statement of compliance with specified referenced standards.
e. Contractor funded testing by recognized testing agency.
f. Application of contractor funded testing agency labels and seals.
g. Notation of coordination requirements.
h. Availability and delivery time information.
4. For equipment, include the following in addition to the above, as applicable:
a. Wiring diagrams showing factory-installed wiring.
b. Printed performance curves.
c. Operational range diagrams.
d. Clearances required to other construction, if not indicated on accompanying Shop
Drawings.
5. Submit Product Data before or concurrent with Samples.
6. Submit Product Data in the following format:
a. PDF electronic file.
b. Three paper copies of Product Data, unless otherwise indicated. COR will return two copies.
C. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base
Shop Drawings on reproductions of the Contract Documents or standard printed data.
1. Preparation: Fully illustrate requirements in the Contract Documents. Include the following information, as applicable:
a. Identification of products.
b. Schedules.
c. Compliance with specified standards.
d. Notation of coordination requirements.
e. Notation of dimensions established by field measurement.
f. Relationship and attachment to adjoining construction clearly indicated.
g. Seal and signature of professional engineer if specified.
Section 01 33 00-Page 11
2. Sheet Size: Except for templates, patterns, and similar full-size drawings, submit Shop
Drawings on sheets at least 8-1/2 by 11 inches but no larger than 30 by 42 inches
3. Submit Shop Drawings in the following format:
a. PDF electronic file.
b. Six copies (bond). COR will return two copies.
D. Samples: Submit Samples for review of kind, color, pattern, and texture for a check of these characteristics with other elements and for a comparison of these characteristics between submittal and actual component as delivered and installed.
1. Transmit Samples that contain multiple, related components such as accessories together in one submittal package.
2. Identification: Attach label on unexposed side of Samples that includes the following:
a. Generic description of Sample.
b. Product name and name of manufacturer.
c. Sample source.
d. Number and title of applicable Specification Section.
3. Disposition: Maintain sets of approved Samples at Project site, available for quality-control comparisons throughout the course of construction activity. Sample sets may be used to determine final acceptance of construction associated with each set.
a. Samples that may be incorporated into the Work are indicated in individual
Specification Sections. Such Samples must be in an undamaged condition at time of use.
b. Samples not incorporated into the Work, or otherwise designated as Contracting
Officer's property, are the property of Contractor.
4. Samples for Initial Selection: Submit manufacturer's color charts consisting of units or sections of units showing the full range of colors, textures, and patterns available.
a. Number of Samples: Submit one full set(s) of available choices where color, pattern, texture, or similar characteristics are required to be selected from manufacturer's product line. COR will return submittal with options selected.
5. Samples for Verification: Submit full-size units or Samples of size indicated, prepared from same material to be used for the Work, cured and finished in manner specified, and physically identical with material or product proposed for use, and that show full range of color and texture variations expected. Samples include, but are not limited to, the following: partial sections of manufactured or fabricated components; small cuts or containers of materials; complete units of repetitively used materials; swatches showing color, texture, and pattern; color range sets; and components used for independent contractor funded testing and inspection.
a. Number of Samples: Submit Four (4) sets of Samples. COR will return one set.
Section 01 33 00-Page 12
1) Submit a single Sample where assembly details, workmanship, fabrication techniques, connections, operation, and other similar characteristics are to be demonstrated.
2) If variation in color, pattern, texture, or other characteristic is inherent in material or product represented by a Sample, submit at least three sets of paired units that show approximate limits of variations.
E. Product Schedule: As required in individual Specification Sections, prepare a written summary indicating types of products required for the Work and their intended location. Include the following information in tabular form:
1. Type of product. Include unique identifier for each product indicated in the Contract
Documents.
2. Manufacturer and product name, and model number if applicable.
3. Number and name of room or space.
4. Location within room or space.
5. Submit product schedule in the following format:
a. PDF electronic file.
b. Three paper copies of product schedule or list, unless otherwise indicated. COR will return two copies.
F. Spare Parts Data:
1. As soon as practicable after approval of the list of equipment, the Contractor shall furnish spare parts data for each different item of equipment listed. The data shall include a complete list of parts and supplies with current unit price and source of supply; a list of parts and supplies that are either normally furnished at no extra cost with the purchase of the equipment, or specified hereinafter to be furnished as part of the Contract and a list of additional items recommended by the manufacturer to assure efficient operation. The foregoing shall not relieve the Contractor of any responsibilities under the guarantee specified hereinafter
G. Contractor's Construction Schedule: Comply with requirements specified in Division 1 Section
"Construction Progress Documentation."
H. Subcontract List: Prepare a written summary identifying individuals or firms proposed for each portion of the Work, including those who are to furnish products or equipment fabricated to a special design. Include the following information in tabular form:
1. Name, address, and telephone number of entity performing subcontract or supplying products.
2. Number and title of related Specification Section(s) covered by subcontract.
3. Drawing number and detail references, as appropriate, covered by subcontract.
4. Submit subcontract list in the following format:
a. Number of Copies: Five (5) paper copies of subcontractor list, unless otherwise indicated. COR will return two copies.
Section 01 33 00-Page 13
I. LEED Submittals:
1. Submit LEED submittals in the following format:
a. Six (6) paper copies of LEED submittals, unless otherwise indicated. COR will return two copies.
J. Coordination Drawings: Comply with requirements specified in Division 1 Section "Project
Management and Coordination."
K. Qualification Data: Prepare written information that demonstrates capabilities and experience of a firm or person. Include lists of completed projects with project names and addresses, contact information of the COR and Contracting Officer, and other information specified.
L. Welding Certificates: Prepare written certification that welding procedures and personnel comply with requirements in the Contract Documents. Submit record of Welding Procedure Specification and Procedure Qualification Record on American Welding Society (AWS) forms. Include names of firms and personnel certified.
M. Installer Certificates: Submit written statements on manufacturer's letterhead certifying that
Installer complies with requirements in the Contract Documents and, where required, is authorized by manufacturer for this specific Project.
N. Manufacturer Certificates: Submit written statements on manufacturer's letterhead certifying that manufacturer complies with requirements in the Contract Documents. Include evidence of manufacturing experience where required.
O. Product Certificates: Submit written statements on manufacturer's letterhead certifying that product complies with requirements in the Contract Documents.
P. Material Certificates: Submit written statements on manufacturer's letterhead certifying that material complies with requirements in the Contract Documents.
Q. Material Test Reports: Submit reports written by a qualified contractor funded testing agency, on testing agency's standard form, indicating and interpreting test results of material for compliance with requirements in the Contract Documents.
R. Product Test Reports: Submit written reports indicating current product produced by manufacturer complies with requirements in the Contract Documents. Base reports on evaluation of tests performed by manufacturer and witnessed by a qualified contractor funded testing agency, or on comprehensive tests performed by a qualified contractor funded testing agency.
S. Research Reports: Submit written evidence, from a model code organization acceptable to authorities having jurisdiction, that product complies with building code in effect for Project.
Include the following information:
1. Name of evaluation organization.
2. Date of evaluation.
Section 01 33 00-Page 14
3. Time period when report is in effect.
4. Product and manufacturers' names.
5. Description of product.
6. Test procedures and results.
7. Limitations of use.
T. Schedule of Tests and Inspections: Comply with requirements specified in Division 01 Section
"Quality Requirements."
U. Preconstruction Test Reports: Submit reports written by a qualified contractor funded testing agency, on testing agency's standard form, indicating and interpreting results of tests performed before installation of product, for compliance with performance requirements in the Contract
Documents.
V. Compatibility Test Reports: Submit reports written by a qualified contractor funded testing agency, on testing agency's standard form, indicating and interpreting results of compatibility tests performed before installation of product. Include written recommendations for primers and substrate preparation needed for adhesion.
W. Field Test Reports: Submit reports indicating and interpreting results of field tests performed either during installation of product or after product is installed in its final location, for compliance with requirements in the Contract Documents.
X. Maintenance Data: Comply with requirements specified in Division 01 Section "Operation and
Maintenance Data."
Y. Design Data: Prepare and submit written and graphic information, including, but not limited to, performance and design criteria, list of applicable codes and regulations, and calculations.
Include list of assumptions and other performance and design criteria and a summary of loads.
Include load diagrams if applicable. Provide name and version of software, if any, used for calculations. Include page numbers.
Z. Withholding of Payment: Payment for materials incorporated in the work will not be made if required approvals have not been obtained. No payment for materials incorporated in the work will be made if all required Designer of Record or required Government approvals have not been obtained. No payment will be made for any materials incorporated into the work for any conformance review submittals or information only submittals found to contain errors or deviations from the Solicitation or Accepted Proposal.
PART 3 - EXECUTION
3.1 CONTRACTOR'S REVIEW
A. Action and Informational Submittals: Review each submittal and check for coordination with other Work of the Contract and for compliance with the Contract Documents. Note corrections and field dimensions. Mark with approval stamp before submitting to COR.
Section 01 33 00-Page 15
B. Project Closeout and Maintenance/Material Submittals: Refer to requirements in Division 01
Section "Closeout Procedures."
C. Approval Stamp: Stamp each submittal with a uniform, approval stamp. Include Project name and location, submittal number, Specification Section title and number, name of reviewer, date of Contractor's approval, and statement certifying that submittal has been reviewed, checked, and approved for compliance with the Contract Documents.
3.2 COR'S ACTION
A. General: COR will not review submittals that do not bear Contractor's approval stamp and will return them without action.
B. Action Submittals: COR will review each submittal, make marks to indicate corrections or modifications required, and return it. COR will stamp each submittal with an action stamp and will mark stamp appropriately to indicate action.
C. Informational Submittals: COR will review each submittal and will not return it, or will return it if it does not comply with requirements. COR will forward each submittal to appropriate party.
D. Partial submittals prepared for a portion of the Work will be reviewed when use of partial submittals has received prior approval from COR.
E. Incomplete submittals are not acceptable, will be considered nonresponsive, and will be returned without review.
F. Submittals not required by the Contract Documents may not be reviewed and may be discarded.
END OF SECTION 01 33 00