Sol_1305M326Q0271_Amd_0003.pdf
PDF 228 KB Posted
- Attached to
- Constructions Services for Staging Space Renovatio Federal contract opportunity
- Solicitation number
- 1305M326Q0271
About this file
This is Standard Form 30 (Amendment 0003) to a federal solicitation for construction services. The amendment was issued on July 30, 2026, by the National Oceanic and Atmospheric Administration (NOAA), Office of Oceanic and Atmospheric Research (OAR), located at 325 Broadway, Boulder, Colorado 80305. The solicitation number is 1305M326Q0271, and this is the third amendment to that solicitation.
The amendment adds answers to nine contractor questions regarding the project scope and requirements. Key clarifications include: abandoned electrical circuits from demolition will be repurposed for six new outlets shown on drawings; no additional electrical circuitry is required; epoxy resin flooring color selection will be made from the contractor's selected manufacturer's standard colors with no impact on pricing; hallway walls do not need to extend to the pan deck to achieve the 1-hour fire rating; existing double doors to be reused are not 1-hour fire-rated; site visit sign-in sheets cannot be published; the Superintendent, Safety and Site Health Officer (SSHO), and Quality Control Manager (QCM) roles may be dual or triple-hatted; all three roles can be performed by a single person; and epoxy flooring is limited to only the staging space floor. The amendment indicates the deadline for acknowledgment and submission of offers is specified in the solicitation or as amended. Section II indicates a CLIN list for supplies or services and pricing information, though specific pricing details are not populated in this document.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 10_Technical_Exhibit_-_Photos_145027-26-0036_0002.pdf | ||
| 9_Questions_from_solicitation_145027-26-0036_0002.pdf | ||
| Sol_1305M326Q0271_Amd_0002.pdf | ||
| 8_Drawing_Set_-_Rev_1_145027-26-0036_0002.pdf | ||
| Sol_1305M326Q0271_Amd_0001.pdf | ||
| Sol_1305M326Q0271.pdf | ||
| 3_Asbestos-Containing_Materials_Certification_1305M326Q0271.pdf | ||
| 2_0_Floor_Plans.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: is not is required copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7.ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
PAGESOF
Contractor
The hour and date specified for receipt of Offers to sign this document and return
JAMIE R. ROSALES
See continuation page
WAD-OAR
325 BROADWAY, SOU6
BOULDER CO 80305
WAD-OAR
1305M326Q0271
07/08/2026
07/08/2026
1 4
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
NSN 7540-01-152-8067
1305M326Q0271/0003
AMENDMENT 0003 (07/30/2026):
ADD ANSWERS TO CONTRACTOR QUESTIONS
1. Is the current electrical receptacle circuit(s) independent per current office configuration? Will the existing circuitry support future use once construction is completed? During demolition of the existing offices, circuitry in the area will be abandoned.
Answer - These abandoned circuits will be repurposed for the 6 new outlets shown on the drawings.
2. Will additional electrical circuitry be required?
Answer - No. Repurpose the abandoned circuitry from demolition.
3. What is the color choice for the final finish of epoxy resin flooring in the corridor and the staging space?
Answer - Color selection has no impact on pricing. The Contractor will submit to the
Government the epoxy flooring manufacturer they intend to use. A final color selection will be made from that manufacturer's available standard colors.
4. It appears that hallway walls do not go all the way up to the pan deck. In order to achieve a 1-hour fire rating, as noted on the drawings, the walls would need to extend all the way up to the pan deck. Are we to completely enclose the lab with 1-hour fire-rated walls all the way up to the pan deck?
Answer – No
5. Are the existing double doors that are to be reused 1-hour fire-rated (in drawing 1)?
Answer – No
6. Please publish the site visit sign-in sheet.
Answer - We cannot publish the sign-in sheet.
7. Can the Superintendent, SSHO, and QCM roles dual or triple hat?
Answer – Yes
8. If dual and triple hatting is allowed, which roles can be performed by a single person?
Answer - All above - single person
9. Epoxy is limited to only the staging space floor.
Continued...
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
NSN 7540-01-152-8067
1305M326Q0271/0003
END OF AMENDMENT 0003
1305M326Q0271 0003
Section II - Supplies or Services and Price/Costs
CLIN List
| Amendment of solicitation/modification of contract |
| Contract ID code |
| Amendment/modification number |
| Effective date |
| Requisition/purchase requisition number |
| Project number |
| Issued by |
| Code |
| Administered by |
| Code |
| Name and address of contractor |
| Code |
| Facility code |
| Amendment of solicitation number |
| Dated |
| Modification of contract/order number |
| Dated |
| This item only applies to amendments of solicitations |
| Accounting and appropriation data |
| This item applies only to modifications of contracts/orders. |
| This change order is issued pursuant to: |
| The above numbered contract/order is modified to reflect the administrative changes |
| This supplemental agreement is entered into pursuant to authority of: |
| Other |
| Important: |
| Description of amendment/modification |
| Name and title of signer |
| Contractor/offeror |
| Date signed |
| Name and title of contracting officer |
| Signature of Contracting Officer |
| Date signed |
| Previous edition unusable |
| Standard form 30 (rev. 11/2016) |
| Continuation sheet |
| Reference Number |
| Name of Offeror or Contractor |
| OPTIONAL FORM 336 (4-86)) |
Sponsored by GSA FAR (48 CFR) 53.110
File details come from the government source that posted it. Updated .