AMC-581-1A-Inspection and Preservation of Ground Tackle (4 sheets).pdf

PDF 31 KB Posted

Attached to
1305M223QNMAN0129 - NOAA's Ship Oregon II Drydock FY 2024
Solicitation number
1305M223QNMAN0129
Issued by

About this file

This document provides specifications for inspection, preservation, and marking of anchors and anchor chains for NOAA's Ship Oregon II. Key details include requirements to remove anchors and chains from the ship for sandblasting and coating with epoxy-polymide and silicone alkyd marine paint. Chains and anchors must be inspected for wear, corrosion, and dimensional checks. Detachable links must be disassembled and reassembled with new locking wire and grease. Chains will be marked with wire turns and paint colors at detachable links and 15-fathom intervals. The related solicitation is for drydocking services for NOAA's Ship Oregon II in fiscal year 2024, including inspections and preservation of anchors and chains per the specifications. Offerors should provide past performance and pricing information by the response date.

View the file

Other files

File Type Posted
ATTACHMENT D5 Pricing Schedule O2 DD FY24_Updated.xlsx XLSX spreadsheet
Amendment_0002_1305M223QNMAN0129_Signed.pdf PDF
MRG Pic_2.jpg JPG image
R2_NONE_OT-S22-0-2-1_RevNONE_Sht1 OF 1_N_A_OT-S22-0-2-1.pdf PDF
R2-S92-0-3 Rev K 1989 Ships Service Switch Gear Wiring Diagram_Update.PDF PDF
FY23 Oregon II Life Raft-Immersion Suit _ Life Jacket Inspection Reports.pdf PDF
Oregon II MRG List of Materials_Update.pdf PDF
MRG Pic_1.jpg JPG image
Cooper_Bearing_Manual_2_Update.jpg JPG image
Cooper_Bearing_Manual_1_Update.jpg JPG image
MRG Pic_3.jpg JPG image
Amendment_0001_1305M223QNMAN0129_Signed.pdf PDF
Oregon II MRG List of Materials.pdf PDF
Oregon II Hydraulic Hose List (2)_Update.xlsx XLSX spreadsheet
OT-S48-1-1 (2)_Update.pdf PDF
FY23 Oregon II Register of Lifting Appliance_Update.pdf PDF
R2_NONE_OT-S17-1-3-1_RevNONE_Sht1 OF 1_N_A_OT-S17-1-3-1 (2)_Update.pdf PDF
OT-S48-3-3 Firemain and Sea Service System_Update.pdf PDF
AMC-300-1_Overhaul_of_Electrical_Rotating_Machinery_(10_pages) (1) (2).pdf PDF
0606- Standards for Lifting Appliances on NOAA Ships.doc DOC document
OT-S43-1-1.pdf PDF
FY21 Oregon II Annual Fire Inspection Report.pdf PDF
OT-S11-1-1(P) (1).pdf PDF
ATTACHMENT D2 Past Performance Information Form.docx DOCX document
OT-S11-1-1.pdf PDF
OT-S11-6-1 (1).pdf PDF
R2_NONE_S41-5-5_RevNONE_Sht6_N_OT-S41-5-5-6 (1).pdf PDF
OT-S3801-101 (1).pdf PDF
OT-S48-3-3 Firemain and Sea Service System.pdf PDF
OT-S41-5-5.pdf PDF
ATTACHMENT D6 Accounting System Questionnaire .pdf PDF
NOAA Standard Specification S2906 Arc Welding on Waterborne Vessels _ June 1982.pdf PDF
OT-S3801-12.pdf PDF
OT-S45-1-2 (2).pdf PDF
FY23 Oregon II Register of Lifting Appliances.pdf PDF
Engineering Report ER20200324_NO2 UPS Review.pdf PDF
R2_NONE_S38-1-14_RevNONE_Sht4_N_OT-S38-1-14-4.pdf PDF
OT-S11-0-1-1 (1).pdf PDF
MOC-573-2 Overhaul Repair of Hyd Cyls.pdf PDF
OT-S3801-11.pdf PDF
R2_NONE_S38-1-14_RevNONE_Sht5_N_OT-S38-1-14-5.pdf PDF
OR-S62-0-10 Elect One Line (MRP 1998) with Galley Update.pdf PDF
AMC-573-1C Weight Handling Gear Testing.pdf PDF
OR-S21-0-4 sheet 2 of 8.pdf PDF
ATTACHMENT D1 NOAA Ship Oregon II FY 2024 Drydock Specs.pdf PDF
s1205 Zinc Protectors.pdf PDF
OR-S21-0-4 sheet 5 of 8.pdf PDF
ATTACHMENT D5 Pricing Schedule O2 DD FY24.xlsx XLSX spreadsheet
AMC-000-1G General Requirements for Ship Repair Contract Work on NOAA Ships.pdf PDF
R2_NONE_S11-0-3_RevNONE_Sht1_N_OT-S11-0-3-1 (2) (2).pdf PDF
Show 40 more

Latest 50 of 133 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMC-581-1A

SEPTEMBER 1992

SUPERSEDING

AMC-581-1

MARCH 1988

NATIONAL OCEANIC AND ATMOSPHERIC ADMINISTRATION (NOAA)

ATLANTIC MARINE CENTER

STANDARD SPECIFICATION AMC-581-1A

INSPECTION AND PRESERVATION OF GROUND TACKLE

1. SCOPE. This specification contains the requirements for inspection, preservation, and marking of anchors and anchor chain.

2. REFERENCES.

a. Steel Structures Painting Council Surface Preparation Specification No. 10 (SSPC-SP 10-85), "Near White Blast Cleaning"

3. REQUIREMENTS.

3.1 Removal. Remove anchors and anchor chain, including

shackles, shackle pins, and detachable links, from the ship and fake the chain onto the dock. Disassemble all detachable links and shackles.

3.2 Preparation. Sandblast the chains, anchors, detachable

links, shackles, swivels, and other fittings to a near white metal in accordance with reference 2.a. and apply one coat, 2.0-

3.0 mils dry film thickness, epoxy-polymide, MIL-P-24441A, Formula 150 (green).

3.3 Tests and Inspections. After sandblasting and applying one coat of paint, conduct the following:

3.3.1 Visual Inspections. Conduct a visual inspection of

all anchors, anchor chains, detachable links, shackles, shackle pins, swivels, locking pins, and other fittings for excessive wear, corrosion, distortion, cracks, and other defects.

3.3.2 Wire Diameter Inspections. Conduct inspections of

each anchor chain link to determine the mean diameter as follows:

a. Take two wire diameter measurements at each end of each link at the bearing area. The two measurements shall be at right angles to each other. A snap gage may be used to take the measurements. If the snap gage will not fit over the link in two places at right angles to each other, the link is acceptable. If the snap gage fits over the link during either measurement, the actual dimensions shall be taken using a micrometer.

b. When micrometer measurements are taken, calculate the mean diameter by averaging the two micrometer readings taken of the link. Compare the calculated mean wire diameter to the table in paragraph 3.3.4.

c. Record the mean wire diameter, and mark the links, which are less than or equal to the 90-percent nominal wire diameter listed. Prior to proceeding with any preservation of the chain, submit to the COTR a report of all links which failed this acceptance criteria.

3.3.3 Six-Link Dimensional Inspection.

a. With a load applied to the chain equal to 10 percent of the proof load, perform a six-link dimensional inspection, measured from every third link, of the entire chain.

The table in paragraph 3.3.4 provides the 10-percent proof load and the maximum six-link dimension for standard anchor chain sizes.

b. A bar gage shall be used to check the six-link dimension. When the bar gage will not fit over the ends of the links, the chain has been stretched and is not suitable for further use. Mark all chain sections which have been stretched beyond that specified. Prior to proceeding with any preservation of the chain, submit to the COTR a report of the sections which failed the acceptance criteria.

3.3.4 Anchor Chain Table.

Chain Size 90 Percent Six-Link 10-Percent Nom. Wire Dia. Nom. Wire Dia. Dimension Proof Load (Inches) (Inches) (Inches) (Pounds)

3/4 0.675 20-1/16 4,800 7/8 0.788 23-13/32 6,400 1 0.900 26-3/4 8,400 1-1/16 0.956 28-7/16 9,400 1-1/8 1.013 30-3/32 10,600 1-3/16 1.069 31-49/64 11,700 1-1/4 1.125 33-7/16 13,000 1-3/8 1.238 36-25/32 15,700 1-7/16 1.294 38-15/32 17,000 1-1/2 1.350 40-1/8 18,500 1-9/16 1.406 41-13/16 20,000 1-5/8 1.463 43-15/32 21,600 1-11/16 1.519 45-1/16 23,200 1-3/4 1.575 46-13/16 24,900 1-13/16 1.631 48-31/64 26,700 1-7/8 1.688 50-5/32 28,500 2 1.800 53-1/2 32,200

3.3.5 In the event the chain is a size not listed in the

above table, the COTR shall provide the required information.

3.4 Reassembly. After all tests and inspections, reassemble

the chain shots, detachable links, swivels, and other fittings.

Renew all locking wire with new stainless steel 304 wire. Pack detachable links during reassembly with molybdenum disulfide grease. During reassembly, the COTR may direct shots of chain be arranged in different order and locations than when disassembled.

The COTR may also elect to provide new shots of chain to be used in lieu of existing shots.

3.5 Preservation. After completion of inspections, continue

with preservation of the chains, anchors, detachable links, shackles, swivels, and other fittings by applying the following coating system:

3.5.1 One coat, 2.0-3.0 mils dry film thickness, epoxy-

polymide, MIL-P-24441A, Formula 150 (green). This coat is in addition to the coat applied prior to inspections.

3.5.2 One coat, 2.0-3.0 mils dry film thickness, epoxy-

polymide, MIL-P-24441A, Formula 153 (black).

3.5.3 To the anchor only, apply one coat, 2.0-3.0 mils dry

film thickness, black silicone alkyd marine grade paint while the last coat of epoxy-polymide is still tacky.

3.6 Markings.

3.6.1 Mark each shot of chain with turns of wire on the

studs of certain links as follows:

a. Locate the detachable link between the first and the second 15-fathom shots from the anchor. Mark the first link on each side (total of 2 links) of this detachable link with one turn of wire on the studs of the links.

b. Locate the detachable link between the second and third 15-fathom shots from the anchor. Mark the second link on each side (total of 2 links) of this detachable link with two turns of wire on the studs of the links.

c. Continue to mark all the chain in the same manner, each time counting an additional link from the detachable link in each direction and marking each of the two links with one more turn of wire than the preceding two links.

d. The anchor chains on each side of the ship shall be marked in the same manner.

e. In the event no detachable links are installed, a similar marking system shall be used to mark the chain at 15-fathom locations.

3.6.2 Using 2.0-3.0 mils dry film thickness of silicone

alkyd marine grade paint, mark the anchor chains as follows:

a. Paint red all detachable links. T

b. Paint white one link on each side (total of two) * of the detachable link between the first and second 15-fathom * shots from the anchor. *

c. Paint white two links on each side (total of four) * of the detachable link between the second and third 15-fathom * shots from the anchor. *

d. Paint white three links on each side (total of * six) of the detachable link between the third and fourth 15- * fathom shots from the anchor. *

e. Continue the sequence of painting white the links * on each side of the detachable links, increasing by one link on * each side of each successive detachable link, until the entire * length of chain (excluding the last two inboard shots on each * side) has been marked. *

f. In lieu of marking the last two inboard links as * specified above, paint red all links in the last inboard 15- * fathom shot and paint yellow all links in the next-to-last * inboard 15-fathom shot. R

g. The chains shall be painted the same on each side of the ship.

h. In the event the chains do not have detachable links, they shall be painted in a similar manner at 15-fathom locations.

3.7 Reinstallation. After completion of all other work, reinstall the anchors and chains on the ship, connected and stowed in their normal place.

END OF SPECIFICATION