This request for quotation solicits proposals for drydocking and repair services for the NOAA Ship FAIRWEATHER. The work includes inspection, maintenance, and repair of hull structures, propulsion and electrical systems, deck equipment, habitability spaces, and installed scientific instrumentation. Offerors must have experience performing drydocking and repairs for vessels of similar size and complexity to the NOAA research ship. The solicitation includes detailed specifications and drawings outlining the full scope of work. Proposals are due by March 15, 2022 and the period of performance is scheduled from June to September 2022 at the offeror's shipyard facility.

View the file

Other files

Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA DD Q&A AMENDMENT 1

Work
ItemParagraphContractor InquiryGovernment Response
3.13.1.4.23.1.4.2 requires the contractor to provide various storage (Outside, Inside, Temp Controlled, Envrio Controlled, Locked). Please provide how much storage, in approximate square feet, that will be required for each category.2ea 20 ft Connex boxes and an interior 12 x 12 sf feet of warehouse space
3.113.11.4.7Paragraph 3.11.4.7 requires the contractor to supply hotel accommodations for the ship’s crew while the grey water tank is being repaired. Please provide the number of crew hotels will be required for.See revised Item
3.143.14.4.2Please provide make,model and size for 12 port lights to be renewed.Replace in kind.
3.153.15.4.2Please provide all sizes for replacement materials for the c-02-001 vent pipe and describe the interferences for the under deck location.Piping to replace in kind; shipcheck for interferences
3.23.20.1.2The OEM needs the serial numbers for the UP6-25 Air Compressors and Air Dryer. Can you provide this information?Serial Numbers not available at the present
3.21N/APlease confirm that we are only quoting the couplings on the port main engine.Yes, only the port engine.
3.243.24.4.6This paragraph calls to "blast" the davits to an SSPC-11 profile. This description doesn't match standards under SSPC. Please determine if the davits need to be blasted and provide the appropite SSPC SP code. SSPC SP-11 is power tool cleaning and not blasting.See revised Item
3.253.25.4.10.2Please provide the existing make and model of deck light switches or the preferred unit to replace them with.Replace in kind.
3.43.4.4.4.3Paragraph 3.4.4.4.3 states to remove all loose paint that is not tightly adhered and prepare surface to an SP-12. For bidding purposes, please advise what percent of the square footage you expect to have to perform the SP-12 spot blast on?Spec states up to 20 percent
3.43.4.4.4.3Will an SP-6 commercial blast be an acceptable substitute for the SP-12 waterjetting?See revised Item
3.43.4.4.7The spec states: 3.4.4.7. Accomplish additional surface preparation to a total area not exceeding 20 percent of the 3.4.4.7.3 surfaces as follows: . There is no section 3.4.4.7.3. Please provide the surface identification and the number of square feet associated with them.See revised Item
3.43.4.4.9The spec states: 3.4.4.9. In the areas of 3.4.4.9 and 3.4.4.9.3, Apply 2 full spot coats of ablative, self- polishing, tin free, contrasting color anti-fouling (AF) conforming to INTERNATIONAL BRA 640 or equal, 4-6 mils DFT. There are no identifications of areas to coat in 3.4.4.9 and there is no section 3.4.4.9.3. Please advise.See revised Item
3.43.4.4.16The spec states: 3.4.4.16. Reinstall equipment removed and preserved in 3.4.4.6.4 installing new CRES fasteners and lockwire. 3.4.4.6.4 states Care shall be taken not to damage sonar transducers and Impressed Current Cathodic Protection anodes and references cells from damage during surface preparation and preservation by installing heavy plywood shields over these items. No items appear to be removed under 3.4.4.6.4. Please advise what equipment 3.4.4.16 is referring to.See revised Item
3.5N/APlease provide drawings with dimensions and photos of the wind breaks to determine the extend of work required for this item.Windbreak is shown on General Plans. Also, dwg FA-RA-116-S1103-8 shows locations
3.5N/AAt 3.5 Windbreak Preservation:

Please specify paint requirements for fiberglass windbreaks.

Please provide details regarding quantity and sizes of new stainless steel mounting hardware to be provided.Windbreaks are shown on General Plans and FA-RA-116-S1103-8
3.63.6.2.1Please provide referenced drawing RA S2806-2 Painting and Identification SchemeAdditionally, the requirements of this item appear to conflict with the requirements of 3.12 Weather Deck Non-Skid Renewal paragraphs 3.12.1.2.4 and 3.12.4.11.
Please clarify the preservation requirements for the top of the house.Located in FA-631 Fairweather Painting Schedule.

3.12.1.2.4 deleted and preservation of house is in accordance with 3.6

3.103.10.2.3Please provide reference drawing # FA-S4803-2 Rev 11 Arrangement Firemain System.The reference has been provided
4.14.1.4.26.1Please provide detailed point of contact info (name, company name, address, phone and email) for required APC engineering support.Contractor should contact the vendor as prescribed in the work

spec:Suggested source for APC Engineer support:

APC-Schneider Electric (800-555-7927)

4.14.1.5.2.2.Please provide photos of area as well as all the intereference in way of this work item that will need to be removed.Contractor should determine amount and sizes of hardware from existing
4.2N/APart of this work item, 6ea state rooms & the steering gear flat (2nd Deck "E", FR76-88 & 112-116, port & stbd) were identified as affected areas inway of chock & bulwark redesign. Please provide photos of area as well as all the intereference in way of this work item that will need to be removed.Shipcheck will outline intereferences
4.3N/APlease provide photos of area as well as all the intereference in way of this work item that will need to be removed.Shipcheck will outline intereferences
4.4N/APlease provide photos of area as well as all the intereference in way of this work item that will need to be removed.Shipcheck will outline intereferences
7.1N/APlease provide applicable drawings and photos for the Shaft Alley deck, includding all drip pans, bilge pockets, equipment supports, structural memebers, pipes, sidewalls and bulkheads.FA-RA-61-S1101 included in references
7.1N/AWhat is the estimated percentage of spot prep for bidding purpose?Will be determined upon joint walkthrough at the start of the availability
7.27.2.4.3.Please provide photos of area as well as all the intereference in way of this work item that will need to be removed.Shipcheck will outline intereferences
7.37.3.4.4.Please provide photos of area as well as all the intereference in way of this work item that will need to be removed.Shipcheck will outline intereferences
7.47.4.4.2.Please provide photos of area as well as all the intereference in way of this work item that will need to be removed.Shipcheck will outline intereferences
7.4N/AAdvise/provide any NOAA-preferred published vibration standards. Note that CPM's analysis is more thorough than "meets standard

/does not meet standard," but these can be included if desired.

Vibration sensor mounting as close as possible to bearing housing is preferred. Please advise if there are access restrictions to equipment or measurement locations requiring more than basic tools to access, reinstall, or replace. (Assistance may be requested.)

Machinery information:

o Bow Thruster Gearbox (high priority) § # of gear teeth § bearing numbers if available § drawings if available o Bow Thruster Engine § minimum engine info (e.g. 1500 rpm 4-stroke V-12) o Generator Engines: 1, 2, & 3 § minimum engine info (e.g. 1500 rpm 4-stroke V-12) o Generators: 1, 2, & 3 § kW § bearing numbers if available o Equipment descriptions (low priority) § Aft Capstan Motor § Launch Davit 4 & 6 Motor § Launch Davit 3 & 5 Motor § FRB Davit Motor § Ambar Davit Motor § ^Are these HPUs? Winches? Any constraints on continuous operation for testing?

o Basic machinery info (HP, configuration, model, etc) and bearing numbers are very useful (and less time on-site) if the data is already available in a spreadsheet or similar, but not necessary. Essential info will be gathered during initial database setup.

Bow thruster gearbox:

No information available Bow thruster engine:

Detroit 8V71, 2 Stroke, 1800 RPM, 200HP, 5000lb Thrust Generators:

1: Detroit Series 60, 4 Stroke, 1800 RPM, 321kW, Magnaplus Model 433PSL6216 2: Detroit Series 60, 4 Stroke, 1800 RPM, 321kW, Magnaplus Model 433PSL6216 3: Volvo Penta D13, 4 Stroke, 1800 RPM, 340kW, Stamford Mode lHCM534C1

8.2 8.2.4.9.2. Please provide photos of the overhead CO Stateroom. Focus shall be on interference that is in way of work that requires removal. Shipcheck will show interference but it's a wireway and insulation

Reference Document RequestGovernment Response
3.16.2.8. NOAA Ship Fairweather – Lifting Appliance Test Report FY22Included table in work item
3.18.2.4. FA-S6700-23 Rev 2, Modifications for New Transducers, Hull Penetrations & Multibeam Sonar InstallationsDwg changed to FA-461-S6700-23
3.23.2.7. FA-812-001 Rev 0 (Generator Installation Fan Rooms Arrangement )Dwg changed to FA-RA-512-S3801 Vent & AC Arrgt Fan Room
3.25.2.4. PPI NBR 63421-006H (Rev 04), Preservation Process Instruction (PPI) for Cosmetic Polymeric Deck Coverings Type
II, Classes 1 & 2 for Wet and Dry Interior SpacesDeleted reference
4.2.2.1.6. FA-S1103-4: After Peak Framing & TransomDwg changed to FA-RA-117-S1103-4
4.2.2.1.7. FA-S1201-1: Mooring Arrg’t, Fdns, & Dets of Bitts, Chocks, and FairleadsDwg changed to FA-RA-183-S1201-1
7.5.2.1. Drawing FA-S3801-2, Diagram Ventilation & Air Condition .Changed dwg to FA-3801-114 HVAC System
7.5.2.2. Drawing FA-S3801-22, Vent arrgt-C.P.O. Pantry & Main galley, Main DK FRS 52-74-1/2(P) & ward room galley, Main DK FRS 43-49 (S)Deleted reference
7.5.2.3. Drawing FA-S3801-23, Vent & AC Arrgt. Superstructure DK-frs 48-72 & NAV. Bridge DK-AFT FR 52Deleted reference
8.1.2.1. List: MACS Updates required by the CME and/or the Chief EngineerWill be provided within 5 days at the start of the availability
3.16.2.10. 29 CFR §1919.1, Gear Certification – Purpose and Scope

3.16.2.11. 29 CFR §1919 Subpart C, Duties of Persons Accredited

3.16.2.12. Gear 29 CFR §1919 Subpart D, Certification of Vessels CargoHN-9002 Service Manual- FA 583-01-320 Rev 1 Winch Type A-320-D

4.1.2.12. ROXTEC Cable & Pipe Transits for Marine Applications

8.6.2.2. ASTM F-1321 (Standard for Conducting Stability Tests )

These documents may be obtained via internet search
3.20. Air Compressor Servicing Ingersoll-Rand UP6-25 Operation and Maintenance Manual

FA DD Q&A AMENDMENT 2

Work
ItemParagraphContractor InquiryGovernment Response
3.5The wind break is constructed of fiberglass which could potentially be damaged by an SP-10 sandblast. May the contractor substitute SP-11 mechanical preparation for sandblasting.

Lacking the opportunity to inspect the wind break, can NOAA specify what percentage of the surface area needs to be mechanically prepared (5%, 10%, 20%...)

SP-11 can be substituted Shipcheck available, around 20%.

3.7 Are all the fittings on the hydraulic hoses to be steel or stainless steel?

How many internal flexible hoses are there to each HN-9001 HPU?

Can NOAA provide photos of each davit, crane, A Frame, control stations and HPUs showing hoses to replace to show location, interferences, ability to access locations because of not being able to ship check the vessel for bidding purposes?

Can NOAA supply drawings and Technical Publications on each davit, crane, A Frame, control station and HPUs showing hydraulic hoses that are to be replaced for bidding purposes? Inside the HPU the fittings can be steel but fiitings on the exterior should be stainless.

4 in total.

Once the cover is removed, the number can be verified.

Shipcheck will be granted and contractor can note interferences at that time.

Manuals were provided.

3.8 3.8.4 “Crop out and renew approximately 5 x 5 square feet of the heavy pitting that was found in the hull plating on the outboard longitudinal bulkhead of DB D/O Tank A-07-102 between Frames 70 and 71 in accordance with 3.8.2.5. Assume plate thickness is 1/2 inch however it must be verified by the contractor”

Please confirm the area to be renew is 5 FT X 5 Ft for a total of 25 sq ft. Square footage is provided in an effort to give the contractor an idea of the wastage area. Report 49702 previously provided shows the pitted areas identified for repairs.

3.83.8.4.5Is the intent of this paragraph to crop out and renew a 10' x 10' hull plating, specifications suggest that the repair area is bounded by frames 70-71 (2 frames), but wouldn't a 10' x 10' insert would affect at least 5 frames?
Is the attached photo of a double bottom tank top rather than hull plate of bulkhead plating?Report 49702 was provided to show the pitted areas in need of replacement. 25 sq ft was provided to give contractor an estimate for bidding but item will require shipchecking for actual footage.

The photo only shows the access to the Shaft Alley to give the contractor a picture of where the work will be located

3.9 3.9.5.5.1 For estimating purposes, How many 2"x2" clad welds are there?

What are the frame numbers?

Please provide pictures of each area to be clad welded.See the UT report that was provided
3.93.9.5.7.1Are we to replace the existing manhole with a new manhole assembly?This manhole requirement will be revisited during the next shipcheck period
3.93.9.5.8How thick is the concrete?See the shell plating drawings previously provided
3.93.9.5.9Please provide pictures of the two areas that need to be cropped and inserted along with the frame numbers.

Need Pictures of all interferences

Need a detailed list of all interferencesSee then UT report that was provided
3.93.9.7.43.9.7.4 encourages the contractor to perform a field inspection prior to submitting a bid proposal. How can the Contractor be held responsible for inspecting the vessel and identifying and providing an allowance for any and all interferences when the Government is not able to provide the Contractor access to the vessel?Shipcheck will be granted and contractor can get a clearer picture of interferences
3.13The following paragraphs seem to reference one anode, which paragraph is contractor to follow?

3.13.4.3.2. Anode P Frame 33.5 to P Frame 100

3.13.4.3.3. The Port anode at Frame 33.5 will remain in the same location

Contractor would like photos of location and interferences around where new materials to be installed

Please provide Pictures, a Rip out Drawing for current system and a Lay out Installation Drawing for the refitAfter 3.13.4.2.1 is accomplished, any ambiguity should be cleared up at that time. MD20017 drawing was provided to the contractor
3.143.14.4.4What type of floor covering in present?Poured terrazzo as stated in 3.14.4.8.1
3.143.14.4.64 square feet or 4 lineal feet?Linear feet
3.143.14.4.6Are we correct in assuming the repair area starts at the horizontal weld seam contained within the yellow circle?Circle identifies the area in question
3.143.14.4.4.8Are the boundaries of the plate replacement going to be within the galley?See The General Plans and the contractor can see what boundaries are impacted
3.143.14.4.2The government's response to the request for make and model of port light ("Replace In Kind") does not provide any detail to what port lights to purchase. Other NOAA vessels have a drawing identifying all of the port lights including manufacturer, model and size. Does the Fairweather have a similar drawing for the port lights.Drawing for Portlights on the Fairweather is not available, however Cornell Carr is the manufacturer. Portlights should be around 16" diameter with dead light covers and they come hinged or fixed. After shipcheck, the contractor can verify actual diameter.

Port lights are not GFM.

3.143.14.4.2.23.14.4.2.2 says to Renew in kind but 3.14.4.2.5 states to fit Refurbished port lights. Please clarify.
What are the frame numbers of each port light?Replace in kind
3.143.14.4.13Without knowing where the 10ea kickpipes are located, the contractor cannot account for interferences therefore, will all interferences, coverup and staging will be subject to a change order?

What size insert is to be estimated for each kick pipe?

What pound plate is to be used when inserting the 10ea kick pipes?Kickpipes will be identified during the first week of the availability.
3.143.14.4.11How many studs are to be removed?

How many brackets are to be removed?

How many fwd deck light switches need to be removed?

Is staging required to safely access these repairs?

Are there through hull penetrations that need inserted? If so, please provide pictures and a list of all the interferences.

Proved pictures of each item to be removed along with pictures of any interferences in the interior side.

If steel is required to be replace, will that be subject to a change order.Pictures were provide of projected repairs needed; shipcheck will be granted and contractor can interferences will be clearer. Contractor can determine, based on their capabilities, if staging will be required.
3.153.15.4.3.Can NOAA provide a fittings list and a list of hull and bulkhead penetrations for the pipe replacements?Contractor can compile list upon completion of shipcheck which has been granted
3.18Specifications refer to "inspections" of the rudder and shaft bearings, but do not instruct the contractor to remove shaft rope guards and fairwaters to accomplish inspections. Could NOAA elaborate that "shaft rope guards and fairwaters are to be removed, and shaft bearing clearances are to be taken and recorded in accordance with NAVSEA 9997-1, following NOAA and ABS acceptance, rope guards and fairwaters are to be reinstalled".Please be specific in what you are proposing to fulfill your requirements to the government.
3.183.18.6.1The specification requires the drydock to be certified by a Naval Architect within twelve months of the drydocking evolution.
The USCG's program for certifying drydocks operates on a two year inspection cycle. If the contractor's facility proposes using a drydock that meets or exceeds the USCG's requirements for drydocking a vessel (SFLC Std Spec 8634, 2020) would that satisfy the requirements?Yes, using the USCG's requirement should satisfy
3.223.22.4.4.3Without knowing where the two inserts are located, the contractor cannot account for interferences therefore, will all interferences, coverup and staging will be subject to a change order?

Provide addional pictures of the area.

Work item calls for a UT inspection to be performed to identify areas needing replacement. Pictures provided are proposed areas requiring replacement
3.223.22.6.3What are the frame numbers relating to the location of the deck inserts?Work item calls for a UT inspection to be performed to identify areas needing replacement. Pictures provided are proposed areas requiring replacement
3.241. In paragraph 3.24.1.2.2.1. Welin Lambin Type TWPIV 9.0A Davit (2port/2 stbd), Is NOAA referencing to the (4) four Vest Davits and not Welin Lambin?Vestdavit davits are installed on the ship
3.24Is there only going to be (2) two boats to be dealt with and not (6) six boats for each of the (6) six davits called out for in the specifications?The assumption is that all of the boats will be stored prior to drydocking
3.24On paragraph 3.24.4.6, it states to blast davits to an SSPC-11 profile. SSPC-11 is a mechanical power tool to bare metal. SSPC-6 is a commercial sand blast and a SSPC-10 is a sand blast to near white metal. Can NOAA clarify the intent of the preparation?SSPC-11 is recommended; If any other method is suggested for use, how does the contractor intend to contain the grit/sand?
3.24Normally when sandblasting of davits is accomplished, disassembly of the davits is required to protect sensitive areas and be able to prepare and paint all areas of the davit needed to prevent rusting of areas not able to reach when davits are assembled. IF NOAA is not requiring the davits to be disassembled for sandblasting and painting, you must know 100% of the areas on the davit won’t be able to be properly prepped and painted. Is this NOAAs intention?For those areas that are hard to reach, the assumption is that the contractor will dissamble in that area and accomplish preservation and reassemble.
3.24Missing Reference PPI NBR 63421-006H (Rev 04), Please ProvideDeleted
3.24Is it NOAA's intention to repair the patched area around the existing protruding pipes in the picture only? Or remove and install all new decking in the entire Fwd Oceanographic Lab (D-07-102)
The installation material identified in 3.25.4.1 thru 3.25.4.9 is not Mil-D-3134J as 3.25.2.8 identifies.Only the area in question
3.253.25.4.10.2The government's response to the request for make and model of deck light switch ("Replace In Kind") does not provide any detail to what switch to purchase. With the ship check only allowing one day before the bid is due, this does not allow enough time to source a suitable replacement. Please provide a detailed description of the switch or a close up photo of the switch including any label plates to help identify what to source.ROTARY SWITCH, 20 AMP, 120/240V AC, 2-POLE, WATERTIGHT, BRASS, PAULUHN / COOPER CROUSE HINDS / EATON, 862B
4.1Reference in 4.1.2.11 pre commissioning check list is not available. Contractor cannot start work item until list is complete and reviewed by the owner per 4.1.4.26. Please provide Pre commissioning check list.Statement is somewhat incorrect but the Pre-Commissioning checklist will be provided hopefully prior to the start of the availability
4.24.2.4.1.drawing shows us to reroute a drain pipe in way of work, can we please get clarity on material grade of pipe that is required.Shipcheck will be granted and drawings provided previously for contractor to determine material grade
4.24.2.4.10Provide pictures and a detailed list of all interferences for each insert, frame stiffener, deck drain mods, bulwark mod, and mooring chocks relocation.Shipcheck will be granted and contractor will gain a clearer picture of interferences
4.24.2.3.1.Who is the manufacturer/supplier of the NOAA specified Panama Chocks ?Called out in the drawing provided, FA-582-001 Bulwark Renewal and Chock Installation
4.24.2.6.2The spec in multiple sections references 4.2.2.1.2, but 4.2.6.2 states that 4.2.2.1.2 does not represent the as-found location of all the chocks nor the number of chocks. Is the Contractor to bid reference 4.2.2.1.2? If the quantity of chocks and location of chocks are not represented correctly on ref. 4.2.2.1.2 will that be subject to a change order?No; the contractor should shipcheck this item for actual condition found
4.43. Can NOAA supply Photos of the new Oily Water Separator and the new Water Heating Unit?See N2451BM200_9913_LAY020A is provided
4.44. Can NOAA supply the manuals for the new oily water separator and the new water heating unit to show dimensions, weights, hook up points for electrical, mounting, piping, electrical requirements for each of the components?Manuals will be supplied with the equipment. However, N2451BM200_9913_LAY020A is provided
4.45. Can NOAA supply photos of where the new oily water separator and the new water heater is to be hooked up to the switchboard and the power panel 421?N145BM200_9913_PID020A is provided
4.46. Is the contractor to supply and install new circuit breakers in the switchboard and power panel 421?All GFM material was identified on work item; any additional material is the responsibility of the contractor
4.44.4.2.3.Drawing specified does not show type & grade of pipe that are being renewed as part of the OWS upgrade. Also, please advise if any of the piping is insulated.This item will require the contractor to shipcheck
4.44.4.7.3This paragraph has the contractor supplyine 1 year of sapre parts and maintenance items. The manufacturer has informed us that 1 year of spare parts and maintenance items was included with their contract when NOAA purchased the Oily Water Separator. Do you want us to include the spare parts as indicated in the specification?No; if the manufacturer is providing this service, there's no need to replicate
4.4Please provide a as built drawing for the oily water seperator.RA-593-002 shows existing installation
4.54.5.4.11How many linear feet of normally submerged conduit piping and how many feet of conduit in dry area will need to be inspected?
What is the inside diameter of the conduit?This item will require shipchecking once ship is in drydock
4.54.5.4.30Please see the attached email from the OEM Kongsberg regarding the SAT plan and provide detail on how to advise the OEM for bid preparation.Email wasn't provided.
7.2Does NOAA have a contact that has performed specified repairs previously.No historical information could be found or obtained from prior repairs
7.2Please provide the module number & manufactoror of each sliding water tight door, as well as any drawings.No drawings are available on this door; Will provide model after the shipcheck
7.37.3.1.1.Item specifies replacing of gaskets & blankets to the areas that are worn. Can we please get clarity on which ones are worn and any additional relevant information for estimating purposes? Also, please include drawings of the exhaust and cooler.NOAA will try to provide pictures as they become available or until shipcheck is performed; whichever comes first.
8.28.2.4.5.Paragraph states to clean back to bare metal along frame 23 to aft corner. Please provide clarity on the verbiage of what the aft corner would be. Also, general arrangement shows a line of consoles way of this work area, please provide the list of equipment that requires removal.Equipment requiring removal is provided in work item. The desk and the EDICS equipment. Shipcheck will be granted for contractor to outline any other interferences
8.28.2.4.9.2.Paragraph states, crop and renew 12' of bulkhead, please verify that this is the bulkhead that is adjacent to the Data Processing Center? If so, please provide a list of equipment that will need to be removed in order to perform this work. Pictures would be extremely beneficial here as ship check is 1 month out. Equipment may require the use of subcontractors and will not allow enough time for contractors to submit their quotes.This bulkhead is adjacent to the Data Processing Center. Shipcheck will be granted for contractor to outline interferences.
8.28.2.4.1.1
8.2.4.3.1These two paragraphs state that the Contractor will assist Ship's Force in removal and reinstallation of the ECDIS equipment and other equipment. Is the contractor only providing general services and the Ship's Force having overall responsibility for ensuring the equipment is reconnected, tested and working properly, or is the contractor responsible for testing and overall functionality of installed equipment? If the contractor is responsible, can you provide a detailed list of the equipment that will be removed & reinstalled to determine if we need subcontractors for any of the operation?The pictures depict the equipment that is required for removal. The contractor will assist ship's force in removing and reinstalling the equipment with the reconnection, testing the responsibility of ship's force.
8.28.2.4.2.1Please provide a drawing detailing the drain lines for the bridge emergency escape windows.The interference will require removal to identify the drain lines. Shipcheck is granted during the next import however, this needs to accomplished during the first week of the availability to lessen interruptions on the bridge.
8.58.5.1.1.Paragraph states to template windows & frames, but the rest of the item does not mention templating frames. Do the frames require templating as well?The assumption is that the windows will be templated to fit the existing bronze frames. However, if the vendor cannot fit the windows to the frames, new frames will need to be templated. We want to keep the frames bronze but realize that this is an older ship and bronze may or may not be available.