Pricing Schedule Nancy Foster FY 2021-REV 2.xlsx
XLSX spreadsheet 14 KB Posted
- Attached to
- FY21 RFQ Nancy Foster Drydock Repairs
- Solicitation number
- 1305M220QNMAN0179
About this file
This pricing schedule outlines the line items and costs for drydock repair services for the vessel Nancy Foster. The solicitation number is 1305M220QNMAN0179 and was issued by the National Oceanic and Atmospheric Administration within the Department of Commerce.
The schedule includes line items for general requirements, temporary services, ABS special survey requirements, anchor chain inspection and preservation, steel and pipe repairs and modifications, sea valve overhauls, lift raft inspection, electrical and ventilation repairs, load testing, drydocking, sea trials, and fluid monitoring system installation. It also includes optional line items for HVAC, electrical, and mechanical systems work. Pricing is shown as unit costs by line item, with totals for base work, optional work, and totals including estimated growth costs. The growth worksheet requests pricing details for additional labor and materials.
View the file
Other files
Show 40 more
Latest 50 of 87 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Schedule of Prices
| Price Schedule (REV-2) |
| NANCY FOSTER DRYDOCK REPAIRS FY21 |
| SPEC WORK ITEM | SPECIFICATION WORK ITEM TITLE | UNIT | QTY | UNIT PRICE | EXTENDED PRICE |
| 1 | General Requirements | JOB | 1 | $ - 0 | $ - 0 |
| 2.1 | Temporary Services | JOB | 1 | $ - 0 | $ - 0 |
| 3.1 | ABS Special Survey Requirement | JOB | 1 | $ - 0 | $ - 0 |
| 3.3 | Anchor Chain Inspection & Preservation | JOB | 1 | $ - 0 | $ - 0 |
| 3.4 | Steel Repairs & Modifications | JOB | 1 | $ - 0 | $ - 0 |
| 3.5 | Pipe Repairs & Modifications | JOB | 1 | $ - 0 | $ - 0 |
| 3.6 | Sea Valve Overhauls | JOB | 1 | $ - 0 | $ - 0 |
| 3.7 | Lift Raft Annual Inspection | JOB | 1 | $ - 0 | $ - 0 |
| 3.8 | Miscellaneous Electrical Repairs | JOB | 1 | $ - 0 | $ - 0 |
| 3.9 | Ventilation Air flow Study and Mods | JOB | 1 | $ - 0 | $ - 0 |
| 3.10 | Firefighting System Certification | JOB | 1 | $ - 0 | $ - 0 |
| 3.11 | Load Testing of Lifting Appliances | JOB | 1 | $ - 0 | $ - 0 |
| 3.12 | Dry Docking | JOB | 1 | $ - 0 | $ - 0 |
| 3.13 | Dock & Sea Trails | JOB | 1 | $ - 0 | $ - 0 |
| 3.14 | Fluid Quality Monitoring system Install | JOB | 1 | $ - 0 | $ - 0 |
| 3.15 | General Painting and Preservation | JOB | 1 | $ - 0 | $ - 0 |
| 3.16 | Underwater Hull Complete Coat | JOB | 1 | $ - 0 | $ - 0 |
| Total Base Items | $0.00 |
| SPEC WORK ITEM | SPECIFICATION WORK ITEM TITLE | UNIT | QTY | UNIT PRICE | EXTENDED PRICE |
| 4.1 | AIRS/Growth (estimated) |
**Provide breakdown, as follows:
AIRs/Growth Labor Rate Unit Price: $________; Quantity: 6150; Unit of Issue: Hour; Extended Price: $____________
| HRS | 6150 | $ - 0 | $0.00 |
| 4.2 | AIRs/Growth Material Markup/Handling Fee |
Unit Price: $200.000.00; Quantity: 1; Unit of Issue: Percent ________%;
| Extended Price:($200.00.00)+ percentage quoted]: $______________ | % | EST $200.000.00 | 0 |
| 4.3 | Additional Temp Services |
(See CAR CLAUSE 1372.271-86)
| EST 1 | DAY | $ - 0 | $0.00 |
| 4.4 | Laydays |
(See CAR Clause 1372.271-89)
| EST 1 | DAY | $ - 0 | $0.00 | |
| Total Growth | $0.00 |
| SPEC WORK ITEM | SPECIFICATION WORK ITEM TITLE | UNIT | QTY | UNIT PRICE | EXTENDED PRICE |
| 5.1 | IVMC system Maintenance & Upgrades | JOB | 1 | $ - 0 | |
| 5.2 | SSDG Silencer Renewals | JOB | 1 | $ - 0 | |
| 5.3 | LP Air comp renewals & Piping Mods | JOB | 1 | $ - 0 | |
| 5.4 | Interior Deck Coating Repairs | JOB | 1 | $ - 0 | |
| 5.5 | Sheet Metal Repairs | JOB | 1 | $ - 0 | |
| 5.6 | MISC HVAC repairs & Modification | JOB | 1 | $ - 0 | |
| 5.7 | Electric Distribution SYS Evaluation | JOB | 1 | $ - 0 | |
| 5.8 | MCT Repairs | JOB | 1 | $ - 0 | |
| 5.9 | BOW Thruster Renewal | JOB | 1 | $ - 0 | |
| 5.10 | Knuckle Boom Crane Installtion | JOB | 1 | $ - 0 | |
| 5.11 | NETAPPS Electronic Rack Install | JOB | 1 | $ - 0 | |
| 5.12 | EK60 70kHz Transducer Installation | JOB | 1 | $ - 0 | |
| Total Option Items | $0.00 |
| BASE + OPTIONS | $0.00 |
| BASE + OPTIONS +GROWTH | $0.00 |
&KFF0000REGION 3, TORFP 002
D 6 Pricing Schedule