S01 12FPC120Q0039 Att8QAP58_25ThirdAveExt.pdf

PDF 333 KB Posted

Attached to
Residential Parcel Demolition and Site Finishing for the State of Connecticut, USDA NRCS.
Solicitation number
12FPC120Q0039
Issued by

View the file

Other files

File Type Posted
S01 12FPC120Q0039 Amend1 Att2-2CS1Clearing58_25ThirdAveExt_REVISED 7_16_2020.pdf PDF
S01 12FPC120Q0039 Amend1 Att1 SOWDemoPrelimRest58_25ThirdAveExt6.2020_REVISED07142020.pdf PDF
S01 12FPC120Q0039 Amend1 SF 30.pdf PDF
S01 12FPC120Q0039 Amend1_Price Schedule_TermsConditionsClauseProvisions_REVISED_07.20.2020.pdf PDF
S01 12FPC120Q0039 Amend1 Att2-11CS426Topsoiling58_25ThirdAveExt_REVISED 7_14_2020.docx.pdf PDF
S01 12FPC120Q0039 Price Schedule_TermsConditionsClauseProvisions.pdf PDF
S01 12FPC120Q0039 Att4CPS342CritAreaPlantImpReq58_25DemoRest.pdf PDF
S01 12FPC120Q0039 Att2-9CS421 Excavation58_25ThirdAveExt.pdf PDF
S01 12FPC120Q0039 Att2-5CS406SeedSprigMulching58_25ThirdAveExt.pdf PDF
S01 12FPC120Q0039 Att3CPS342CritAreaPlant58_25ThirdAveExt.pdf PDF
S01 12FPC120Q0039 Att5-225ThirdAveExtBoundarySurveyMap.pdf PDF
S01 12FPC120Q0039 Att2-12CS494ContrQualCont58_25ThirdAveExt.pdf PDF
S01 12FPC120Q0039 Att2-1CS8MobDemo58_25ThirdAveExt.pdf PDF
S01 12FPC120Q0039 Att9DavisBaconActWDCT20200010NewHavenCtyCT.pdf PDF
S01 12FPC120Q0039 Att2-3CS403StructureRemoval58_25ThirdAveExt.pdf PDF
S01 12FPC120Q0039 Att2-4CS405PollutionControl58_25ThirdAveExt.pdf PDF
S01 12FPC120Q0039 Att2-2CS1Clearing58_25ThirdAveExt.pdf PDF
S01 12FPC120Q0039 Att7-2HazardBuildMatInvRpt58ThirdAveExt.pdf PDF
S01 12FPC120Q0039 Att2-11CS426Topsoiling58_25ThirdAveExt.pdf PDF
S01 12FPC120Q0039 Att7-1HazardBuildMatInvRpt25ThirdAveExt.pdf PDF
S01 12FPC120Q0039 Att1 SOWDemoPrelimRest58_25ThirdAveExt6.2020.pdf PDF
S01 12FPC120Q0039 Att5-158ThirdAveExtBoundarySurveyMap.pdf PDF
S01 12FPC120Q0039 Att2-6CS409TrafficControl58_25ThirdAveExt.pdf PDF
S01 12FPC120Q0039 Att6SEC22a133k3GrdWaterRemediationStds.pdf PDF
S01 12FPC120Q0039 Att2-8CS411 RemovalWater58_25ThirdAveExt.pdf PDF
S01 12FPC120Q0039 Att2-7CS410WaterforConst58_25ThirdAveExt.pdf PDF
S01 12FPC120Q0039 SF 1442.pdf PDF
S01 12FPC120Q0039 Att2-10CS423Earthfill58_25ThirdAveExt.pdf PDF
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Emergency Watershed Protection Program—Floodplain Easements

Abatement, Demolition and Preliminary

Restoration of 25 and 58 Third Avenue Extension, West Haven CT

New Haven County, Connecticut

QUALITY ASSURANCE PLAN

UNITED STATES DEPARTMENT OF AGRICULTURE

NATURAL RESOURCES CONSERVATION SERVICE

Tolland, Connecticut

July 2019

2 QUALITY ASSURANCE PLAN

EWPP-FPE West Haven, Round 2

Demo/Preliminary Restoration for Residential Properties

West Haven Round 2 Floodplain Easements Demolition and Preliminary Restoration On-Site Work

GENERAL

PRE-CONSTRUCTION CONFERENCE

INSPECTION REQUIREMENTS

QUALITY CONTROL PROGRAM ..................................................................................................................... 5-6

QUALITY ASSURANCE (QA) PROGRAM ....................................................................................................... 7-8

ITEMS OF WORK ADVANCE NOTICE REQUIREMENTS

TESTING EQUIPMENT AND FACILITIES NEEDED

STAFFING NEEDED TO PERFORM INSPECTION ....................................................................................... 9-10

SKILLS NEEDED TO PERFORM THE INSPECTION REQUIRED

NAMES & QUALIFICATIONS OF STAFF HAVING REQUIRED SKILLS ................................................ 12-13

Contracting Officer’s Technical Representative – Kristin Walker

Civil Engineering Technician (Inspector) – Mario Sapia ............................................................................. 12-13

APPROVALS

STATEMENT OF QUALIFICATION AND AVAILABILITY

TABLE OF CONTENTS

3 QUALITY ASSURANCE PLAN

GENERAL

This project is for the hazardous abatement, demolition and preliminary site restoration of 5 easement properties in West Haven, Connecticut. The site(s) are located at the following addresses:

1. 58 Third Avenue Extension, Single Family Residence on 0.08 ac

2. 25 Third Avenue Extension, Two-Family Residence with outbuildings on 0.126 ac

Major work items include:

1) Hazardous Material abatement potentially including lead paint abatement, and proper disposal for residences with known hazardous materials as identified in Haz-Mat Assessment Report(s) (to be provided to awarded bidder)

2) Demolition and proper disposal of all structures on property including outbuildings

3) Disconnecting and properly sealing sewer and water lines and/or pumping and removal of septic tanks (where applicable). Decommissioning of private water wells, if applicable.

4) Removal and earth fill of structure foundations including basements

5) Site grading, finishing, seeding and installation of erosion control blanket as specified.

Pre-Construction Conference

Include a discussion of the following items in addition to the standard pre-construction agenda items.

(1) Go over specifications package and answer questions about technical documents

(2) Discuss tidal influence on basement removal and filling operations and discuss de-watering plan.

(3) Identify and discuss staging areas and portable bathroom location. Discuss signage and posting requirements. Identify stockpile area for removed refuse.

(4) Discuss need to secure clean backfill and topsoil source and related laboratory tests early in the process to ensure filling and top soiling operations can occur uninterrupted.

(5) Go over safety fencing and pollution and erosion control plan(s)

(6) Discuss manifest tracking and need to submit paperwork to Inspector/COTR as waste is hauled off-site

(7) Discuss inspection requirements for sewer and water works decommissioning operations.

(8) Discuss inspection requirements for basement removal and filling operations

(9) Discuss water source for construction

(10) Discuss utility disconnections and demolition permits needed prior to commencement of demo

4 QUALITY ASSURANCE PLAN

INSPECTION REQUIREMENTS

At a minimum, all work shall be periodically observed for compliance with the construction documents.

The following are specific items of work to be inspected during the performance of this contract:

Description

Inspection

Frequency

Mobilization/Demobilization Periodic

Safety signage, fencing, barriers, and other safety measures Periodic

Pollution control work, including erosion & sediment control measures Periodic

Abandoning/sealing wells, sewer lines and septic systems Continuous

Mobilization efforts and access roads Periodic

Hazardous Material disposal—check facility acceptance agreements/manifests Continuous (as available)

Demolition of Structure(s) and use of dust control measures Continuous

Verify Earthfill/Topsoil sources meet DEEP and NRCS requirements Periodic (as available)

Earthfill and Compaction of basement(s) Continuous

Clearing & Grading/Earthfill of site Periodic

Seeding & Mulching Periodic

Contractor Quality Control Periodic

5 QUALITY ASSURANCE PLAN

Demo/Preliminary Restoration for Residential Properties

July 2019

QUALITY CONTROL PROGRAM

1. Mobilization/Demobilization: Contractor shall mobilize heavy equipment to areas designated for parking and staging. Inspector will ensure equipment traffic over parcels not owned by City of

West Haven is minimized if not eliminated altogether. Any damage caused to neighboring parcels shall be identified by the Inspector and Contractor shall repair the same day the damage was caused.

2. Signage and Safety Measures: Contractor shall have required safety signage (e.g. overhead power lines, open trench, etc.) in place at all times during the construction period. Temporary fencing, traffic barriers or temporary signage shall also be in place when trenches are open for sealing of sewer lines, open basements, septic removal, etc.. Hardhats are to be worn at all times on the construction site, including heavy machinery operators. Inspector will verify that necessary signage is in place before the beginning of each day and will verify throughout construction that appropriate exclusionary fencing/safety barriers are in place as needed for open trench work. Inspector will also ensure hardhats are worn on a continuous basis.

3. Pollution Control: The Contractor shall maintain silt fence and other erosion and sediment control measures when necessary to provide effective sediment retention for the duration of the contract.

Inspector will provide periodic inspection of measures in place and will notify the COR if measures are not effective, need repair, or were installed improperly. Contractor will work with CO/COR to rectify any identified deficiencies before proceeding with construction/demo.

4. Abandoning and Sealing of Wells, Sewage Lines and Septic Systems: The Contractor shall inform the COR/Inspector 1 business day in advance of sealing sewer connections and/or pumping/removing existing septic tanks. Contractor is to conduct all well and sewer/septic abandoning activities in accordance with the Statement of Work, referenced specifications and

NRCS Standard 351—Well Decommissioning. Well abandonment procedures (if applicable) shall be performed or directed only by a Connecticut registered well driller. The registered well drilling contractor who performs the work shall notify the local health authority of the abandonment of the well. The work shall be done in strict compliance with the Connecticut Well Drilling Code unless a special exemption from one or more of the applicable regulations has been granted by the

Department of Energy and Environmental Protection (CT-DEEP).

Permit Requirements: Before commencing work on the abandonment of any well, a registered contractor shall complete an application for a permit in a format acceptable to the Commissioner of Consumer Protection, and such application shall be filed with the authority having jurisdiction for the issuance of a permit as provided by section 25-130 of the General Statutes found in the

State of Connecticut Regulation of the Department of Consumer Protection Concerning Well

Drilling and Geoexchange Systems. Permit shall be sent to COR prior to commencing abandonment procedures.

Inspector will verify that sealing of sewer connections and removal of septic tanks has been done in accordance with the aforementioned guidance documents and will give the clearance to backfill the trench or pit. Inspector will also verify septic systems have been pumped out by an appropriate waste handling service and that all below ground septic structures have been removed to the extent practicable prior to granting clearance to backfill septic pits and trenches. Inspector will verify abandonment procedures were done by a registered CT well driller and performed in accordance with the terms and conditions of the abandonment permit.

5. Hazardous Material Disposal: Contractor shall provide documentation to COR/Inspector from hazardous material disposal facility agreeing to accept the types and quantities of hazardous waste for disposal identified within the haz-mat assessment reports prior to commencing haz-mat

6 QUALITY ASSURANCE PLAN

Demo/Preliminary Restoration for Residential Properties

July 2019 abatement activities. Contractor shall provide tracking manifests to COR/Inspector of types and quantities of materials disposed of at facility.

6. Demolition of Structures: The Contractor shall inform the Inspector/COR 1 business day in advance of commencing demolition activities. The Contractor is responsible for administering dust control measures continuously throughout demolition activities. Inspector will continuously monitor dust activities, and if necessary, may require additional measures taken to control dust if Contractor’s methods are found insufficient. Demolition shall be done in such a way to minimize impacts to surrounding neighbors and shall be performed within hours outside of local noise ordinances. Inspector shall verify that all structures, including basement walls and foundations, outbuildings, etc. have been removed. If necessary, safety fencing or barriers will need to be installed around open basement holes. Inspector will verify fencing or other safety precautions are taken. Inspector is not to be inside the working project limits during demolition of structures.

7. Verify Earthfill/Topsoil Sources: The Contractor shall provide lab results for all earthfill/topsoil sources to the COR/Inspector at least 7 days in advance of obtaining/mobilizing fill to site.

Contractor must receive clearance from COR prior to using source of fill material.

8. Earthfill/Compaction of Basements: The Contractor shall notify the COR/Inspector at least 1 business day in advance of filling in basement(s). Contractor shall follow NRCS Construction

Specification 407—Removal of Water (if applicable) and Construction Specifications 409—

Earthfill, to fill voids remaining from basements. Inspection shall be continuous for this phase of construction and will require the inspector to monitor and note moisture content (by touch and feel methods) as well as lift thickness and type of compaction equipment used.

9. Clearing and Grading/Earthfill of Site: The Contractor shall follow NRCS Construction

Specifications 409—Earthfill and Construction Specification 1—Clearing. Prior to clearing, trees to remain will be flagged. Any invasive or dead vegetation shall be removed and disposed of at a green waste or other appropriate facility. Inspector will help to identify invasive species for removal and will ensure that roots or other propagating parts of the plant are completely removed or otherwise eradicated from the site. Inspection will be periodic for this phase of the project, including earthfill and grading activities.

10. Seeding and Mulching: Contractor shall provide seed tag information including PLS rate and species type to COR/Inspector prior to obtaining seed. Seeding and mulching shall follow NRCS

Implementation Reqeuirement 342—Critical Area Planting and NRCS Conservation Practice

Standard 342—Critical Area Planting. Inspector will verify monitor seed application rate and ensure it meets aforementioned guidance documents.

7 QUALITY ASSURANCE PLAN

QUALITY ASSURANCE (QA) PROGRAM

The Natural Resources Conservation Service (NRCS) Quality Assurance Program will be conducted to assure that the specified contract quality of materials and workmanship is attained. The primary responsibility of the QA personnel is to observe the operations of the Contractor to assure compliance with the construction contract. This includes the physical examination of materials brought on to the site;

observation of the placement of materials; observation of the construction techniques; observation of quality control and construction management operations by the Contractor; periodic and continuous observation of construction work and ensuring proper safety measures are taken on-site.

The intensity of the examination is set forth in the WORK TO BE INSPECTED section of this plan.

Periodic quality assurance observations and checks of the Contractor's Quality Control work will be conducted to verify that measurable qualities of the work meet the contract requirements. Should quality assurance inspections indicate decreased quality of work; the quality assurance effort will be intensified until the Contractor's quality control program is performing in full compliance with the contract.

The following is considered the minimum amount of quality assurance inspection required:

1. An initial site walk-thru will be conducted to identify heavy equipment staging areas, safety signage locations and areas where pollution control measures will need to be in place. Periodic spot checking will be performed to ensure safety signage, heavy equipment traffic and parking are meeting requirements.

a) Pollution control facilities will be inspected for compliance to Construction Specification

402—Pollution Control, and for effectiveness to minimize sediment leaving the site. If water surfaces and streams are becoming muddy, identify the source and inform the

Contractor to make necessary corrections. Ensure that pollution control measures are in place before areas are disturbed.

2. Ensure the correct addresses have been marked and identified for demolition. Ensure trees to remain have been flagged prior to commencing clearing or demo activities.

3. Ensure OSHA safety measures are in place and Contractor is wearing hardhat at all times while in the construction work limits.

4. Observe excavation operations and all earthfill construction for compliance with the plans, the applicable specifications, and the safety requirements. Witness contractor’s fill placement measures to ensure proper compactions are being achieved. Observe dewatering of pits or basements if applicable.

5. Observe sealing of sewer mains and ensure methods follow City of West Haven requirements. Ensure

Contractor allows for proper sealant set time before backfilling trenches.

6. Observe and verify that any septic pumping or well decommissioning activities are performed by a qualified professional.

7. Obtain soil laboratory analysis from Contractor for approval by COR prior to obtaining sources of earthfill or topsoil. Verify source of topsoil on-site meets source approved by COR.

Verify seed tags on-site match seed mix approved by COR prior to seeding. Observe seed application follows prescribed application rate outlined in Conservation Practice Implementation

8 QUALITY ASSURANCE PLAN

Demo/Preliminary Restoration for Residential Properties

July 2019

Requirement—Critical Area Planting.

8. Observe any land clearing activities, ensure trees to remain are not damaged, and verify that invasive species have been adequately eradicated from construction limits.

9. Obtain any tracking manifests for Haz-Mat demo materials or other construction materials.

10. The implementation of the Contractor’s quality control program will be observed for adequacy to deliver the specified quality of completed work.

The below Table 1-1: Notification Time Line for Various Items of Work lists the project “Items of Work” and their needed advance notification timelines. The COR/Inspector shall be informed of these work items and their projected timelines as soon as they are confirmed by the Contractor.

Table 1-1: Notification Time Line for Various Items of Work

Items of Work Notification Time Line Completed

1) Preconstruction meeting with

NRCS, Sponsor, Project

Inspector and Contractor

Agreed upon time before construction

2) Project Progress Reporting Each morning prior to start of a work day —or—

As Requested by Inspector/COR

3) Capping of Sewer Lines

1 Business Day in Advance

4) 1st house demolition 1 Business Day in Advance of Demolition Activities

5) Provide Documentation of

Fill Source / Topsoil

7 Days Prior to

Fill Being Placed

6) Earthfill of Basements/

Foundations or other

Significant* Earthfill operations

1 Business Day in Advance of Fill Placement

7) Encountering bones, artifacts

Or other potential cultural resources

Immediately Upon Discovery

8) Grading, seeding and final site inspection

No advance notice required

9 QUALITY ASSURANCE PLAN

TESTING EQUIPMENT AND FACILITIES NEEDED

The Contractor is not required to furnish a field office. Any required testing may be completed by the appropriate certified laboratory or at the nearest Field Office or other suitable facility.

Other Facilities Needed Include:

1. Staging/Parking area for heavy equipment mobilization

2. Demolition material dumpster or appropriate receptacle

3. On-site Restroom facilities

Testing Equipment may include (but is not limited to):

4. Measuring tape

5. Stakes, flags, ribbon, etc.

6. Marking paint

Recording Equipment may include (but is not limited to):

7. Digital camera

8. Video camera

9. Construction Inspection Notebook

STAFFING NEEDED TO PERFORM INSPECTION

The construction performance time is estimated to be 30 calendar days.

The staffing needs summary that follows shows the estimated staffing requirements. This summary is based on the Engineers’ estimated performance time. The actual staffing requirements will be determined by the Contractor’s performance and management of the work.

Estimated staffing hour requirements are shown in Table 1-2: Quality Assurance Plan—Estimate of QA

Staff Hours below.

10 QUALITY ASSURANCE PLAN

Table 1-2: Quality Assurance Plan—Estimate of QA Staff Hours

Inspection Item Personnel Hours

COR Inspector SCE

Prepare for Job Showing 16 8 8

Job Showing 8 8 8

Pre-Construction Prep 24 8 4

Construction inspection

Mob/Demob 0 4 0

Full Time Inspection days (hrs) 2 32 0

Part Time Inspection days (hrs) 40 120 8

Verification of Materials 8 2 0

Reviewing Invoices 8 0 0

Post-Construction close-out 8 8 0

As-built Survey/Documentation 16 16 0

Progress Site Visits 16 0 8

Misc. Assistance 16 8 8

Total Hours: 162 214 44

Total Contract Calendar Days: 15 (3 weeks, no weekends)

Contract Months 0.75

11 QUALITY ASSURANCE PLAN

SKILLS NEEDED TO PERFORM THE INSPECTION REQUIRED

Contracting Officer’s Representative (COR)

The COR will be the Contracting Officer’s representative and will be responsible for contract administration duties as determined by the Contracting Officer. The COR will coordinate with the

EWPP-FPE program manager and State Conservation Engineer on compliance with the technical requirements of the contract.

10. Skills Needed

a. Ability to provide technical oversight to one or more inspectors.

b. Understands the contract documents.

c. Understands construction, demolition and site work requirements.

d. Can interpret soil test data and compare to CT state criteria to determine acceptability

e. Ability to maintain communications with the Contractor, landowners, and personnel of other federal, state, and local government agencies.

f. Knowledge of the Federal Acquisition Regulations (FAR).

11. Training Required

a. COR Level I and II training courses (48+ hours training of accepted coursework for certification levels)

b. 1 year of experience performing as a COR Level I

c. Five years construction experience.

Civil Engineering Technician (Inspector)

1. Skills Needed

a. Understand the plans and specifications.

b. Ability to maintain all required construction records.

c. Experienced in the inspection of soil suitability for compacted earthfill for pits and trenches, identification of common invasive species, seeding and mulching.

d. Ability to perform basic layout, staking, quantity, and “as-built” surveys.

e. Ability to maintain communications with the Contractor, City of West Haven Sponsor, and personnel of other federal, state, and local government agencies.

2. Training Required

a. Construction Inspection Training Course.

b. Two years construction inspection experience.

12 QUALITY ASSURANCE PLAN

EWPP-FPE West Haven, Round 2

Demo/Preliminary Restoration for Residential Properties

July 2019

NAMES & QUALIFICATIONS OF STAFF HAVING REQUIRED SKILLS

The following are the names and qualifications of staffing available for this project.

Contracting Officer’s Representative – Kristin Walker, Project Engineer, acting State

EWPP-FPE Program Manager, Tolland, CT

Qualifications

1. Federal Contracting Experience: COR Level II Certification with 2+ years serving as a COR for various projects including: easement restoration/construction, Phase II Environmental

Reports, Dam Assessment reports, and Dam Rehabilitation Plans. Gained familiarity with managing and understanding government contract documents and Federal Acquisition

Regulations, provided oversight to construction inspector, oversaw demolition and construction of first round of EWPP-FPE residential properties. Experienced in understanding and interpreting soil lab analysis for determination of environmental compliance and determining potential acid-sulfate soil conditions to avoid issues with site suitability of existing or imported soils.

Communicate well with contractors, engineers, construction personnel, and all Federal, State and

Local authorities to get the job completed on schedule to quality expectations.

2. Construction Experience: 14+ years of construction experience including design and construction inspection for hundreds of EQIP projects that have spanned from irrigation and drainage systems to erosion control measures to animal waste storage and management.

3. Relevant Training:

a. Construction Inspection for Projects

b. Concrete

c. Stream and channel Bio-engineering course

d. Contracting Officer Representative Level I training (6 credit hours)

e. FAC-COR Level II training (32 credit hours)

f. Contracting with a Mission Focus (8 credit hours)

g. CLC 222 training (32 CEUs for recertification, completed May 2019)

h. 8 hours COR training for recertification (Completed May 2019)

Civil Engineering Technician (Inspector) – Mario Sapia, Civil Engineering Technician, Hamden, CT

Qualifications

13 QUALITY ASSURANCE PLAN

EWPP-FPE West Haven, Round 2

Approvals

Prepared By: Date: ____

Kristin Walker, Project Engineer

Approved By: Date: ____

Arthur Ramthun, State Conservation Engineer

STATEMENT OF QUALIFICATION AND AVAILABILITY

The construction staff assigned to this project is qualified to perform the contract administration and inspection for the proposed work at this site. They will also be available during the time period necessary for construction.

Thomas L. Morgart

State Conservationist

Date:

Arthur Ramthun

State Conservation Engineer

Date:

File: QAPStaffing&PerformanceTime-EWF.xls Page 2 of 2 NRCS-ENG-523