This is a Government Response document to contractor questions regarding bonding requirements for solicitation 12C0BA26Q0011, a Request for Quotation (RFQ) issued by the Department of Agriculture for the USDA-ARS Tifton Roofing Remodel project. The solicitation seeks to replace aging roofing materials with 26-gauge standing seam metal roofs on multiple buildings at the Tifton, Georgia facility. The project value is estimated between $250,000 and $500,000, is set-aside for small business concerns in NAICS code 238160 (Roofing Contractors) with a $19M size standard, and requires bid, performance, and payment bonds.

The Government's response clarifies bonding submission requirements: an executed SF 24 (Bid Bond) is required with the quotation if the contract amount exceeds $150,000, while executed SF 25 (Performance Bond) and SF 25A (Payment Bond) are due within five calendar days after contract award. The response addresses contractor concerns regarding the timing conflict between the requirement for fully executed bonds (which require a contract date and number) and the five-day post-award deadline, confirming that only the bid bond accompanies the initial quote submission, with performance and payment bonds deliverable post-award within the specified timeframe.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

QuestionAnswer
The newly posted SF 1442, Item 12, indicates that performance and payment bonds must be furnished within five calendar days after award. In addition, SF 25 and SF 25A require a contract date and number and state that the bond execution date must be the same as or later than the contract date. Those forms therefore cannot be fully executed before award. Please confirm whether an executed SF 24 is required with the quotation and the executed SF 25 and SF 25A are due within five calendar days after award. If you require something concerning performance and payment bonding with the quote, please identify the specific document or evidence the Government will accept before a contract date and number exist.SF24 bid bond is due with quote if over amount is over $150k. Performance and payment bonds are due within 5 calendars days of the award from the awardee.