Amendment 3.pdf

PDF 276 KB Posted

Attached to
R5 Multi-Forest Critical Water System Federal contract opportunity
Solicitation number
129JGP20R0007
Issued by
Department of Agriculture Forest Service R5-Pacific Southwest Region

About this file

This document provides information on a solicitation for construction services on four recreational sites located on the Calaveras Ranger District of the Stanislaus National Forest. The solicitation will seek a firm fixed price contract to perform work at Lake Alpine Recreation Area, Marmot Day Use Area, Big Meadows Campground, and Sourgrass Day Use Area. Services include removing and relocating waterlines, reconstructing a bike path, demolishing bathrooms and installing prefabricated vault toilets, constructing a well house, and sealing water tanks. The solicitation package will be issued on approximately March 25, 2020, with award expected within 10 days of the response date listed in the package or subsequent amendments. The purpose of the notice is to meet FAR requirements and notify contractors to monitor for amendments. The project is set aside for total small businesses with a NAICS code of 237110 and $39.5 million annual receipts size standard. Offers will only be considered from firms certified as both total small businesses and meeting the size standard.

View the file

Other files for this federal contract opportunity

Other files attached to R5 Multi-Forest Critical Water System, newest first.
File Type Posted
Amendment 7.pdf PDF
Amendment 6.pdf PDF
Amendment 5.pdf PDF
Amendment 4 with Attachments.pdf PDF
PAL Fire Plan Aug 2012.pdf PDF
R5 Multi Forest Critcal Water Systtem Repair.pdf PDF
STF Waterline Ph1 Spec.pdf PDF
DB Wage Det.pdf PDF
STF WATER SYSTEM PLANS.pdf PDF
Amendment 2 with attachments.pdf PDF
Amendment 1 R5 Multi Forest Critical Water System Repair.doc DOC document
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE PAGE OF PAGES

1 2

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable) 3 04/09/2020

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

USDA Forest Service Central California Acquisition Service Area Tahoe National Forest 631 Coyote Street Nevada City, CA 95959

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State, and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NO.

129JGP20R0007

9B. DATED (SEE ITEM 11)

02/25/2020

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended, is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS, IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED

IN ITEM 14. (TO BE FILLED OUT BY THE CONTRACTING OFFICER)

(X) A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN

THE CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.

Amendment 2 Provides response to RFI 2. See attachment.

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

OLAINE MARTINEZ

15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED

04/08/2020 (Signature of person authorized to sign) (Signature of Contracting Officer)

NSN 7540-01-152-8070

Previous edition unusable

30-105 STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

RFI #2.

RFI #14 – Site 2, Plan sheet C3 note 2, The plan notes call for the prefabricated vault toilet to have a minimum 7/12 roof pitch and a snow load rating of 350 psf. In speaking with a commonly used manufaturer of these units on USFS projects, this rating is over specified and will require new/additional engineering at the plant. This will increase cost and extend lead time. Existing vault units in production have a 6/12 roof pitch, and a snow load rating of 250 psf. According the manufacturer, these units have been installed at elevations up to 14,000ft. Will these new specifications of prefabricated units be acceptable?

Sheet C3 has been corrected to reflect a 250 psf snow load requirement and 6/12 minumum roof pitch.

RFI #15 – Site 2, Plan sheet C3, The scope of work and plans call for the new vault toilet building to be installed in the footprint of the existing toilet building to be removed. This and most of the surrounding area appear to be located on a giant granite “slab” adjacent to the lake. With subgrade excavation required for the new unit, will blasting be permitted if refusal is met, or will the location of the unit be moved?

Work Note 3 has been modified to require potholing prior to excavation and that alternative sites may be considered.

File details come from the government source that posted it. Updated .