Amendment 2 with attachments.pdf
PDF 1 MB Posted
- Attached to
- R5 Multi-Forest Critical Water System Federal contract opportunity
- Solicitation number
- 129JGP20R0007
About this file
This amendment to a solicitation and request for information document provides responses to contractor questions about a fixed price construction contract for critical water system repairs on four recreational sites within California's Stanislaus National Forest. The sites include work to replace and relocate waterlines at Lake Alpine, demolish a bathroom and sewer lift station at Marmot Day Use Area, and seal water tank interiors and relocate electrical systems at Sourgrass Day Use and Big Meadows Campground. Bids are due within ten days of final amendment with award expected shortly after. The set-aside is for total small businesses under $39.5 million in annual receipts.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment 7.pdf | ||
| Amendment 6.pdf | ||
| Amendment 5.pdf | ||
| Amendment 4 with Attachments.pdf | ||
| PAL Fire Plan Aug 2012.pdf | ||
| STF Waterline Ph1 Spec.pdf | ||
| DB Wage Det.pdf | ||
| STF WATER SYSTEM PLANS.pdf | ||
| R5 Multi Forest Critcal Water Systtem Repair.pdf | ||
| Amendment 3.pdf | ||
| Amendment 1 R5 Multi Forest Critical Water System Repair.doc | DOC document |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE PAGE OF PAGES
1 2
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)
2 04/08/2020
6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE
USDA Forest Service Central California Acquisition Service Area Tahoe National Forest 631 Coyote Street Nevada City, CA 95959
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State, and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NO.
129JGP20R0007
9B. DATED (SEE ITEM 11)
02/25/2020
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended, is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS, IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED
IN ITEM 14. (TO BE FILLED OUT BY THE CONTRACTING OFFICER)
(X) A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN
THE CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.
Amendment 2 Provides response to RFI. See attachment.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
OLAINE MARTINEZ
15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED
04/08/2020 (Signature of person authorized to sign) (Signature of Contracting Officer)
NSN 7540-01-152-8070
Previous edition unusable
30-105 STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
REQUEST FOR INFORMATION (RFI) FORM
RFI #1 – General Requirements, spec 01410-1.1, Can the Site Superintendent and Quality Control Manager be the same person for this project? YES
RFI #2 – Site 1, Plan sheet C1, Is the existing water main able to be drained prior to the new tie in? Can existing water in the pipe be drained into the lake, or must it be pumped out/removed from site? The pipe will be drained prior to the start of work. It will be recharged and tested to verify that the new main is working prior to backfilling the trench. Water from the Lake Alpine Waterline can be discharged into the lake.
RFI #3 – Site 1, Plan sheet C1, The plans do not show any isolation valves being installed on the new main line at connection points. Please confirm that this is correct. It is correct.
RFI #4 – Site 1, spec 02660-3.12, testing, The spec calls for testing of the new line at 150psi for 4 hours.
Without isolation valves being installed on the new main line, is the contractor expected to test the entire main line for leaks, to inlcude the existing line remaining in place? Please clarify that only the new main will need to be tested, and if we are to install temporary valves for this. The intent is to recharge the waterline between the Lake Alpine Boat Ramp and the Chickaree Day Use Area which will include this new segment. Isolation valves are not required. The waterline needs to be in place by September 30, 2020 which is prior to the seasonal shutdown of the Lake Alpine Water System.
RFI #5- Site 1, Plan sheet C1, The plans call for the installation of a 1” drain valve with riser and lid at station 2 +56.9. There is no detail given for this valve. Is the intent of this valve to be installed as a lateral off the new 4” main line? Yes, it will be installed as a lateral and drain into the lake.
RFI #6- Site 2, Plan sheet C3, The plans call for the removal of an existing “2 pump sewer lift station”. There are no details given in regard to this lift station on the plans or in the specifications. Is there any additional information available for this? IE: photos, size, depth, material of vault, as-builts, etc.
Due to the current office access restrictions the plans are temporarily unavailable. Assume the vault is eight feet deep, 4 foot diameter, and is steel. Contractor is responsible for pumping and disposal of all wastewater in lift station and pressure line.
Marmot Lift Station Cover
RFI #7- Site 2, Plan sheet C3 note 1, The plans call for re-routing an existing water line from the old restrooms to an existing fire hydrant. There are no details for this new connection. Is there any additional information available for this? IE: photos, size of hydrant, distance for tie in, etc.
The hydrant is a faucet within 15’ of the front of the bathroom, water enters at the back side so the total run is approximately 30’ of 1” waterline. PVC buried 24” is acceptable for underground, galvanized is required within 12” of gound and higher. Provide shutoff and drain valve in a box and at low point. The hydrant is similar to this one:
RFI #8- Sites 3 and 4, Are the existing water tanks chlorinated and considered for potable use? The tanks are potable water but are only chlorinated for seasonal opening. Disinfection is required upon completion of this project.
RFI #9- Sites 3 and 4, Are the existing water tank lids removable, and if so, can they be removed temporarily for coating and sealing operations?
Both tanks have metal lids, Big Meadow is a Manhole Cover, Sourgrass has a rectangular lid, both of which allow personnel access into the tank. They can be removed to facilitate access, contractor is responsible for re-installing lids to ensure complete seal.
Big Meadow tank access.
RFI #10- Sites 3 and 4, spec 07160-1.2, The specifaction states that the sealing and coating is based upon a “designated product and installer”. Is “certified” or “designated” installer information available so that contractors may contact them for bidding/proposal purposes?
Designated installer is defined as follows: Contractor shall place sealer per manufacturer’s recommendation and comply with confined space regulations using competent personnel or sub-contractors.
RFI #11- Sites 3 and 4, spec 07160-1.2(b), Will an alternate product be considered if it is a Certified NSF/ANSI 65 compliant tank liner, and not an applied coating?
Compliance should be to NSF/ANSI 60 for potable water systems. Alternative treatments can be considered as long as they provide a total seal and meet potability requirements.
Interior of Big Meadow water tank.
RFI #12- Site 4, Plan sheet C5, Is the existing well housing (cmp) to remain in place, or be removed for new well house construction? It is to be removed and disposed of properly.
RFI #13- General, Please provide any additional photos and/or as-built plans of the scope of work items, demo items, and work locations that may be available.
Photos have been provided as available.
(Add more RFI #’s as needed)
| Amendment 2 |
| RFI set 001 R5 Critical Water System Repair - Response 04-08-20 |
| REQUEST FOR INFORMATION (RFI) FORM |