C05 RFI Log 127EAX26Q0069_Amendment No 3 Questions 046 - 096.docx

DOCX document 30 KB Posted

Attached to
Barillas Peak & Encino Vista Lookout Tower Restoration, Santa Fe NF
Solicitation number
127EAX26Q0069
Issued by

About this file

This is an RFI Log (Request for Information Q&A document) for Solicitation No. 127EAX26Q0069, containing responses to questions 046-096 submitted by potential bidders regarding the Barillas Peak & Encino Vista Lookout Tower Restoration project. The RFI close date was October 1, 2026 (extended to October 19, 2026 per Amendment 1), and quotations were due November 6, 2026.

The Barillas Peak scope includes complete cab replacement, existing tower repairs, CMU toilet building construction, utilities installation, ANT150F2 communications system, solar and generator systems, lightning protection and grounding, and civil/site work. The Encino Vista Option A is limited to design and installation of solar/backup-generator and lightning-protection/grounding systems only. Both sites require the same 5.2 kW solar power and 48 VDC battery concept, with Barillas Peak receiving a full cabin replacement with specified amenities and Encino Vista designed to support the same systems for future use. Key requirements include: contractor-designed cab dimensions and architectural features; single-occupancy water systems designed for 6-7 months annual use; wastewater and gray-water system design by licensed professionals; a 125-gallon propane tank addition; Osborne fire finder procurement and installation at Barillas; dual-pane, low-E tempered glass windows with high-visibility screens and rolling shutters capable of withstanding 100+ mph winds; a powered mechanical lift system for loads up to 100 lbs; and TEDS grounding certification by a third-party provider. All civil and structural design work must be stamped by a New Mexico-licensed professional engineer at the 100% design phase, with all site construction performed by licensed professionals. The Government will not furnish property beyond relevant documents and will require one week advance notice for major construction inspections. Equipment must be cleaned and certified prior to entering Santa National Forest. Approximately 45 tons of 2-3" crushed gravel is estimated for access-road improvements at Barillas Peak. The contractor is responsible for all permit acquisition and compliance with applicable federal, state, and local building codes.

View the file

Other files

File Type Posted
Sol_127EAX26Q0069_Amd_0003.pdf PDF
C05 Attachment 12 Region 3-0310 Santa Fe National Forest - Encino LO.pdf PDF
C05 Attachment 15 031005L050501-20221109-Barrillas Lookout-TSIR-Combined-v-13.8_01.pdf PDF
C05 Attachment 2 Sched of Items - 127EAX26Q0069 R1.xlsx XLSX spreadsheet
C05 Attachment 11 Encino LO Structural Data.pdf PDF
C05 Attachment 9 127EAX26Q0069 Pre-Bid Sign In Sheet.pdf PDF
C05 Attachment 8 RFI Log 001-044.docx DOCX document
C05 Attachment 13 031001L010201-Encino Lookout-20250513-C-TSIR-V16_01.pdf PDF
C05 Attachment 14 031001L010201-Encino Lookout-20250513-SAR-LO-Data V1.1.pdf PDF
C05 127EAX26Q0069 0002.pdf PDF
C05 Attachment 17 031005L050501-Barillas Lookout-20230906-SAR-V9.pdf PDF
C05 Attachment 16 031005L050501-Barillas Lookout-20230906-SAR-DATA-V9.pdf PDF
C05 Attachment 7 WD NM20260011.pdf PDF
C05 Attachment 10 CL-100_Plans.pdf PDF
127EAX26Q0069 Amendment 00001.pdf PDF
127EAX26Q0069 Amendment 00001 Provisions and Clauses.docx DOCX document
C04 Attachment 5 WD NM20260028.pdf PDF
C04 Attachment 4 Fire Plan and Guidelines.docx DOCX document
C04 Attachment 2 Sched of Items.xlsx XLSX spreadsheet
C04 Attachment 3 Specifications.pdf PDF
C04 127EAX26Q0069.pdf PDF
C04 Attachment 1 Statement of Work.pdf PDF
C04 Attachment 6 WD NM20260026.pdf PDF
Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFI LOG

Project Name: Barrillas Peak & Encino Vista Lookout Tower Restoration

Solicitation No.127EAX26Q0069
Solicitation Date 11 September 2026RFI Close Date 01 October 2026
RFI #
DESCRIPTION
RESPONSE
046
Please confirm that Barillas Peak includes the complete cab replacement, existing tower repairs, CMU toilet

building, utilities, ANT150F2 communications system, solar and generator system, lightning protection, grounding, and civil/site work.

This statement is valid for the Barillas Peak Lookout Tower Site.

047
Please confirm that Encino Vista Option A is limited to design and installation of the solar/backup-generator system and lightning-protection/grounding system, including inspection and testing, and does not include cab replacement, plumbing, CMU construction, antenna work, mechanized lift, or road improvements unless specifically identified by amendment.
This statement is valid for the Encino Vista Lookout Tower Site.
048
Attachment 3 contains general provisions for tower delivery, installation, air-lift operations, existing tower removal, and foundation removal. Please identify which, if any, of these provisions apply to Barillas Peak or

Encino Vista.

These are general provisions and generally do not apply to either site in this contract. Air-lift operations for delivering materials is not required as both sites are accessible by high clearance vehicles. If an offeror wants to pursue this method of delivery, then the air lift operation requirements will be enforced.

049
Please confirm whether helicopter air-lift service is required or anticipated for removal of the existing Barillas cab, delivery of the new cab, tower materials, solar equipment, or other construction materials. If required, please provide anticipated lift locations, load limits, staging areas, flight restrictions, and Government coordination responsibilities.
As mentioned in other responses this is not a required method. Both sites are accessible by vehicle. Please acknowledge the maintenance level of access roads as provided in the contract documents.
050
Please identify any Government-furnished property, materials, equipment, drawings, engineering data, staging areas, or logistical assistance that bidders may rely upon.
The USFS has provided all relevant documents pertaining to the existing sites that we have. At this time the USFS does not anticipate providing any additional GFP.
051
Please provide all available original tower drawings, foundation drawings, prior structural analyses, FAA or Forest Service inspection reports, fire-damage assessments, material information, antenna inventories, and repair history for both towers.
The extent of what the USFS has to provide has been provided.
052
Please clarify whether repair or reinforcement of the existing Barillas tower is included within the lump-sum bid regardless of existing conditions, or whether structural deficiencies that cannot be determined before award will

be handled as differing site conditions or contract modifications.

Structural deficiencies not determined before award will be considered an unforeseen condition. The SA report at the 90% design phase shall be furnished and stamped by a PE licensed in the state of NM, and that is where any deficiencies and/or strengthening requirements shall be properly documented as stated in a previous RFI.

053
Please identify the known extent and location of fire damage to the Barillas cab, tower steel, coatings, bolts, stairs, platform, foundation, utilities, and communications equipment.
The extent of what the USFS has regarding this can be located in the applicable FAA report.
054
Attachment 3 states that tower legs are to be hot-dip galvanized and describes tower delivery and installation.

Please confirm that no new primary tower structure is required and that these provisions apply only to replacement or reinforcement steel.

No new tower is to be procured/constructed, delivered and installed.

055
Please confirm the required New Mexico professional licenses and design disciplines. Must the 30%, 60%, 90%, 100%, structural analysis, civil, electrical, plumbing, solar, lightning-protection, and architectural documents each be stamped by the applicable New Mexico-licensed professional?
All Civil/Structural design work shall be stamped at the 100% design phase. Stamps are not needed for the 30%-90% phases. Once work begins on site, all work shall be carried out by licensed professionals with licensure in the State of NM, in accordance with any/all design documents that were stamped by the PE at the 100% design phase.
056
Please provide the required cab dimensions, floor plan, architectural appearance, window sizes, material requirements, existing platform dimensions, and connection elevations, or confirm that these are entirely

contractor-designed.

These are contractor designed components. The USFS will work with the contractor throughout the design process to ensure basic requirements are met.

057
Please confirm whether the small electric water heater identified as “currently not priced” is a contract requirement and, if so, provide the required capacity and location.
Refer to RFI 017
058
Please clarify the clean-water system requirements, including required storage capacity, container type, fill method, freeze protection, pump requirements, piping, and whether potable-water treatment is required.
This is to be designed by the contractor based on single person occupancy for 6-7 months a year.
059
Please clarify the gray-water and wastewater design. Attachment 3 references both a gray-water cistern and connection to the existing septic tank. Please identify which fixtures connect to each system and the intended

final configuration.

This is to be designed by the contractor, in conjunction with licensed professional subject matter experts.

060
Please provide available inspection information, capacity, condition, and location of the existing septic tank and confirm responsibility if it is unsuitable for reuse.
The USFS does not have the requested data on the existing septic tank, however there is no anticipation that they existing tank is unsuitable for use. There is a requirement in the Phase I design stage to investigate the existing septic tank for capacity, condition and connection points. The USFS will require a 1 week notice from the contractor as to when this will occur so a representative is on site.
061
Please provide foundation, architectural, plumbing, electrical, finish, door, roof, ventilation, and freeze-protection requirements for the approximately 8-foot by 8-foot by 9-foot CMU toilet/storage building.
The design and construction of the CMU toilet building is the responsibility of the contractor. The USFS will participate in review/design process along the way.
062
Please provide the design loads, required daily energy consumption, autonomy period, battery chemistry,

minimum battery capacity, inverter output, panel count, preferred manufacturers, and cold-weather design criteria for each site.

All known design loads are not available as some aspects are included as design items for the contractor to submit on and design for. Encino Vista will have a 50-watt 30-amp BK radio wired to two LiFeP04 Lithium Battery 140 amp hours batteries. Barillas will have a 50-watt 30-amp BK radio with a 25-amp power supply AC-DC. It will need two 150-174 MHz 6 dB Omni Exposed Dipole Antennas on top of the lookout.

063
Please confirm whether the approximate 5.2 kW PV and 48 VDC battery concept applies to Barillas Peak only or to both sites.
The Solar Power and backup power systems shall be the same at both sites. Though Barillas is the only getting a full cabin replacement with specified amenities, Encino shall be designed to support the same amenities for future use.
064
Please provide the required propane generator capacity, voltage, fuel consumption or run-time requirement, enclosure, cold-weather package, transfer controls, and auto-start/stop sequence for each site.
These are all to be designed by the contractor. Technical proposal shall be constructed to show bidders competence as pricing will not be the only thing bidders are evaluated on for potential award.
065
Please confirm whether propane tanks currently exist at either site. If new or replacement tanks are required, provide the required capacity, location, ownership, initial fill requirement, and permitting responsibility.
There is a propane tank on site, however please include a new 125 gallon propane tank on the Base Bid within line item 7 and for the option bid within line item 4.
066
Please clarify the requirement for “Certification of NEC and State approved commercial electric skills and expertise.” Identify the specific New Mexico electrical license or certification that must be submitted with the quotation.
Refer to RFI 055 for professional licensure requirements. Bidders are responsible to ensure all parties working on this are properly licensed. Any/all relevant certificates from licensing authorities shall be provided upon request by the USFS.
067
Please confirm whether the contractor must furnish the ANT150F2 antenna, LDF4-50 coax, connectors, mounting hardware, entry panels, Polyphaser, grounding kits, and all associated materials, or whether any items are Government-furnished.
There will be no government furnished property other than relevant documents that we can provide.
068
Please provide the intended ANT150F2 mounting height, tower face or leg, frequency, cable length, radio termination location, and any required coordination with the Government radio technician.
These are items for the contractor to include as a part of the design, during design phases. The Government Radio Technician will be available for consultation during the project.
069
Please define “TEDS,” identify the required third-party grounding certification provider or qualification, and provide the referenced TEDS design report.
TEDS is a grounding method standard to the USFS for this type of work. It is the contractors responsibility to find a third party provider to perform this.
070
Please confirm whether the baseline lightning-protection configuration of four 15-foot Schedule 80 extensions, four air terminals, 2/0 downleads, fourteen ground rods, ground-enhancement material, test wells, and bus bars applies independently at both sites.
Lightning protection systems shall comply to any/all Federal State and/or local regulations applicable. Contractor is responsible for the final design of the LP systems in conjunction with USFS reviews at milestone completion percentages. For bidding purposes contractor shall assume the same baseline system at each site.
071
Please confirm whether the 10-ohm maximum is required at each individual grounding electrode, each site-wide system, or both, and state the required test procedure and acceptable test conditions.
Contractors shall follow any/all standard codes for electrical/grounding and Lightning protections systems. Site relevant regulations that support bidders choice of method in bid package.
072
Please clarify whether the Government will witness grounding, concrete, compaction, rebar, RF sweep, solar, generator, and final commissioning tests, and state the required advance notice for each inspection.
The Government will have multiple representatives available to monitor this project in addition to the COR. A 1 week notice ahead of time for major construction features such as but limited to those mentioned in this question will be required.
073
Please provide the limits, width, depth, aggregate gradation, estimated quantities, and compaction requirements for access-road, turnaround, and parking-area improvements at Barillas Peak.
We are simply requesting new gravel surfacing. Estimated quantity of material is 45 tons of 2-3” crushed, washed gravel surfacing.
074
Please identify approved staging, crane, helicopter, equipment-parking, material-storage, and waste-container areas at each site.
There is currently no designated area(s). This is information that will be discussed with the awardee at the time of the pre-construction.
075
Please confirm whether crane access is feasible at Barillas Peak and provide any known roadway width, grade, turn-radius, bridge, culvert, weight, or overhead-clearance restrictions.
This is not a question that can be directly answered by the USFS. Site visits were held to field verify these types of items, though they were not mandatory they were highly recommended for these reasons. Other potential bidders did seem to think crane access was feasible. The USFS does have a road reconstruction project for this road in place, and we will coordinate internally so that the road is prepped for this project.
076
Please identify all known seasonal wildlife restrictions, Mexican Spotted Owl restrictions, fire restrictions, road closures, and construction blackout periods that should be included in the 548-day schedule.
Fire restrictions and road closures are not typically predictable situations. Contractors shall be familiar with the Forest Fire plan and are expected to remain in compliance with that at all times and during all stages of fire restrictions. Similarly, road closures are only anticipated during unforeseen events such as flooding and/or wildfires.

For Encino Vista the only wildlife guidance is to try and avoid disturbing any birds nesting from Mid-April to Mid-August. This is more geared towards no major clearing and grubbing. There are no seasonal wildlife restriction for Barillas.

077
Please clarify the SOW statement that erosion-control measures must be performed at no additional cost and “shall not be included in contractor’s bid.” Should bidders include these incidental costs within other line-item prices without a separate pay item?
Refer to RFI 025
078
Please confirm whether contractor equipment must be cleaned and certified only before initial entry to Forest Service land or also between Barillas Peak and Encino Vista.
Equipment shall be cleaned prior to entering the Santa National Forest, therefore additional cleaning between site mobilization is not required.
079
Please clarify the specification requiring quality audits “at a minimum of two intervals per shelter” and references to shelter handoff and communications-tower manufacture. Do these provisions apply to this lookout-tower

project?

Yes, the contractor is required to take quality assurance precautions throughout. The shelter refers to the cabin at Barillas. As a part of this statement, it is required that the contractor provide documentation validating compliance with either forest service specifications and/or design requirements set forth by the design firm, ultimately to ensure NEC compliance. Examples are things like compaction reports, concrete/rebar inspection reports etc. Additionally, the contractor is required to provide a step-by-step directions for proper winterization of the cab.

080
Do we have structural drawings and architectural drawings of existing lookout tower? + Existing plans of canopy and cab. Specifically, the drawing of existing CAB on top.
The extent of drawings and/or information on the existing structures that the USFS has to offer have since been provided via Amendment 002 posted on 11/5/2026.
081
How existing cab is anchored-attached to existing main lookout tower?
A site visit was held in order for contractors to verify these conditions.
082
Once new Cab is installed, do we need to provide a SA report of main lookout tower? If yes, to above then we need original Foundation design of tower and Geo report.
A final structural analysis report is to be provided at the 90% design phase to validate the capacity of the existing tower.
083
Need more info on “CMU Toilet Building” – is this a separate unit somewhere near lookout tower on ground?
Yes, the CMU toilet building is a stand-alone structure at ground level.
084
Required permits: Please confirm that all Federal land-use authorizations, environmental clearances, and permits required for work at Barillas Peak and Encino Vista have been obtained by the Government and that no local building permits are required to be obtained by the contractor.
Any internal permitting/authorizations pertaining to clearances needed for this project are handled internally by the USFS. As this project has design elements that require licensed PE designs and stamps followed by construction by licensed professionals, it will be the responsibility of the contractor to obtain a design in accordance with applicable local State & Federal building codes, as well as to adhere to this requirements and the design by hiring licensed professionals to construct required elements. Along the way in this process the contractor will be responsible for researching the required permits associated with the work, acquiring them and following through with the requirements of the permitting authority.
085
Solicitation Clause FAR 52.236-7, Permits and Responsibilities: Please confirm that all Federal land-use authorizations, environmental clearances, cultural resource clearances, and access approvals required for construction have been obtained by the Government and identify any site-specific permits expected to be obtained by the Contractor.
Any internal permitting/authorizations pertaining to clearances needed for this project are handled internally by the USFS. As this project has design elements that require licensed PE designs and stamps followed by construction by licensed professionals, it will be the responsibility of the contractor to obtain a design in accordance with applicable local State & Federal building codes, as well as to adhere to this requirements and the design by hiring licensed professionals to construct required elements. Along the way, in this process the contractor will be responsible for researching the required permits associated with the work, acquiring them and following through with the requirements of the permitting authority.
087
Questions Related to Barillas Lookout Site, Specs: Do we need to supply and install a small electric water heater?
Refer to RFI 017
088
Questions Related to Barillas Lookout Site, Specs: Please confirm whether the Contractor is required to furnish and install a fire finder and associated mounting equipment within the lookout cab. If required, please identify the preferred manufacturer, model, or approved equal.
The contractor is responsible for the procurement and installation of an Osborne fire finder. The contractor is to include the specifics of the fire finder as a part of their bid package and the USFS will review and approve.
089
Questions Related to Barillas Lookout Site, Specs: How many of the windows need to be capable of opening or fixed. Can they be double hung windows, or crank out style window. Do the windows need to be tempered glass or a laminated glass for the safety of the occupant? Are there any specifications for the glass replacement or just able to replace the entire window?
The basic requirement for windows opening is that all four walls shall have on operable window (via sliders) for ventilation purposes. Windows should be mounted vertically not sloping and shall be fully sealed. Wind speeds are historically known to exceed 100 mph so this should be considered when sizing the windows. Windows shall have “high visibility” screens. They shall be double-paned low E, tempered glass windows. Window shutter should be of the type that roll up and down.
090
Questions Related to Barillas Lookout Site, Specs: Please identify the required location of the proposed CMU building at the Barillas Peak site and provide any available site layout drawings showing the intended placement of the structure.
Site Layout is at the discretion of the contractor in conjunction with USFS review during the design phase. Site visits were held and highly recommended for these types of items. No such guidance and/or documents exist and will not be provided.
091
Questions Related to Barillas Lookout Site, Specs: Mechnaized Lift System - Please provide the minimum performance requirements and indicate whether a manual or powered lift system is acceptable.
Minimum requirements are that the lift shall be capable of securely and safely lifting items up to 100 lbs. It shall be powered.
092
Questions Related to Barillas Lookout Site, Specs: Does the USFS have a preferred propane vendor for the area?
No particular vendor is required, however the vendor shall be informed that they are expected to drive up and refill the new tank.
093
Questions Related to Barillas Lookout Site, Specs: The specifications require a lightning protection and grounding system. Please clarify whether the lookout cab is intended to be electrically bonded to the tower structure or isolated from the tower as part of the lightning protection design.
The cab shall be protected from lighting in such a way that is compliant with any/all Federal, State, and local regulations including NFPA 70 & 780. The Contractor is responsible for ensuring a safe end product is delivered through Licensed designs and construction by licensed professionals.
094
Questions Related to Encino Vista Lookout Site: Are existing tower drawings, prior as-built drawings available for Encino Vista? If so, will they be made available to offerors?
The documents that the Forest has available have been provided via amendment 002 posted on 11/5/2026
095
Questions Related to Encino Vista Lookout Site: Please confirm whether the intended solar, battery storage, inverter, and backup generator design criteria for Encino Vista are the same as those identified for Barillas Peak, or whether separate design criteria are required for Encino Vista.
The scope/objectives and therefore end product functionality for said components are the same. Contractor will be expected to verify site conditions at each site to ensure a safe functional design is established at each site followed by the construction of a safe and functional system.
096
Questions Related to Encino Vista Lookout Site: If the new solar power system is installed at Encino Vista, please identify which existing appliances and electrical loads are to remain and which appliances, if any, are required to be replaced as part of the project scope.
The Solar powered system at Encino need to meet the minimum requirements of the system at Barillas for future use.