This document package includes a solicitation for site maintenance and minor construction services across Arizona and New Mexico sites, as well as notes from a follow-up question and answer meeting.
The solicitation seeks a contractor to perform site maintenance and minor construction activities at six sites within the Coronado National Forest in Arizona and two sites within the Santa Fe and Cibola National Forests in New Mexico. Services include soil decompaction, seeding, erosion control, site grading, aggregate placement, sign and gate installation, and culvert replacement. The work must be completed by December 2022. The estimated value is between $250,000 to $500,000. The solicitation will be a 100% small business set-aside. Bids are due by June 15th, 2022. The follow-up meeting notes provide additional clarification on traffic control requirements, material specifications, and answers to contractor questions about project scopes and schedules.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
127EAX22R0015
x x copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
SPRINGERVILLE AZ 85938
30 S CHIRICAHUA DR
PO BOX 640
APACHE SITGREAVES NATIONAL FOREST
USDA FOREST SERVICE
ALBUQUERQUE NM 87102
333 BROADWAY SE
SOUTHWESTERN REGION
106409306/02/2022
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
06/02/2022
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Amendment 3 to include:
1. QUESTION AND ANSWERS FROM FOLLOW-UP INFORMATION MEETING HELD MAY 26, 2022
ALL OTHER TERMS AND CONDITIONS REMAIN THE SAME
Delivery Location Code: 8371
SOUTHWESTERN REGION
333 BROADWAY SE
ALBUQUERQUE NM 87102 US
Continued ...
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 4
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
127EAX22R0015
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
Site Maintenance and Minor Construction Solicitation Follow-Up Virtual Meeting – Q&A Session May 26, 2022; 2:00 p.m.
The USFS held a virtual follow-up to site visit meeting for the Site Maintenance and Minor Construction solicitation. The USFS staff present at this meeting included:
• Michele Bahr, Contracting Officer
• Maria McGaha, COR
• Hailey Stock, Government Technical Monitor
• Steven McDonald, Government Technical Monitor
Maria initiated the meeting and introduced the USFS staff. Several contractors were present; however, no formal introductions were made. Maria reminded attendees that the bids were due to Michelle on June 15th at 1:00 p.m.
Maria provided a summary of the project which included 6 sites within New Mexico and Arizona on the
Coronado NF, Cibola NF, and Santa Fe NF.
Questions & Answers
Question 1: Is the material specification for aggregate for trail and road the same for both?
Response 1: Yes
Question 2: What is the culvert size?
Response 2: 12-inch diameter by 10 feet in length as shown in drawings
Question 3: The individual sites are relatively short-term. Will you still require a formal Traffic Control Plan?
Response 3: Yes, however, it can be brief (one-page or less) if it contains appropriate information to address any traffic along project sites. Specifically, the Harshaw sites that are along a busy Harshaw Road. For these sites, signs are required to ensure public is aware of heavy equipment in the area. Some main roads will require a Road Closure Order. Acknowledge the need to appropriate signage on roads closed through a Forest
Road Closure Order. The Road Closure Order will be done by the Forest Service prior to mobilization, but the contractor will need to provide and appropriate signage at the project sites to ensure members of the public are aware of the closures. The Traffic Control Plan is considered incidental to other work and can be submitted with the Work Plan.
Question 4: How much grout is required for Flux site?
Response 4: Include in the bid price the cost for 10ft3 of concrete to be used for grouting the riprap.
Question 5: How deep is the well at Nacimiento?
Response 5: There are no well logs available to determine the exact depth, however, for contracting purposes, a depth of 120 feet will be assumed.
Question 6: The Amendment states that an MSO Surveyor, provided by the Forest Service, will need to be on site to ensure work does not disturb MSO populations. What happens if the MSO Surveyor cannot be on site for some reason?
Answer 6: The Forest Service will coordinate the schedule of the MSO Surveyor. Their absence will not be a reason for the contractor to stop or delay work.
Question 7: Can one bid on the individual states separately?
Answer 7: No, this is one requirement and should be bid according to the schedule.
Meeting concluded at 3:00 p.m.