Geotech report.pdf

PDF 4 MB Posted

Attached to
Kennel Building Construction
Solicitation number
12639526Q0088
Issued by

About this file

This is a Geotechnical Study Report for the Proposed Millville Kennel located at 4200 South 600 East in Millville, Utah. The report was prepared by Gordon Geotechnical Engineering, Inc. (G²) for Cushing Terrell and dated November 13, 2024 (Job No. 1342-001-24).

The study evaluated subsurface soil and groundwater conditions through two test pits excavated to depths of 7.5 to 10.5 feet below existing grade. Key findings indicate that loose, surficial soils encountered to depths of 4 to 5 inches must be completely removed from below the building footprint and exterior flatwork areas before construction. Underlying natural granular soils (primarily gravel with sand and silt) are suitable for footing support and are medium dense, slightly moist, and brown in color. No groundwater was encountered at depths explored, though seasonal fluctuations of 1 to 2 feet are anticipated. The report provides comprehensive design recommendations including: a recommended net bearing pressure of 2,500 pounds per square foot for footings on natural soils or structural fill; minimum embedment depth of 30 inches for frost protection; foundation settlements anticipated to be less than one inch; specific pavement sections for parking areas (2.5 inches asphalt over 8 inches aggregate base) and primary roadways (3.0 inches asphalt over 8 inches aggregate base); and floor slab requirements with 4 inches of free-draining fill. Geoseismic analysis recommends Site Class D soil profile with peak ground acceleration of 51.1% g for Maximum Considered Earthquake events. The report notes liquefaction potential is very low due to absence of groundwater and recommends qualified geotechnical engineer observation during foundation excavations to verify removal of unsuitable soils.

View the file

Other files

File Type Posted
12639526Q0088-0003.pdf PDF
RFIs and Responses 2.docx DOCX document
12639526Q0088-0002.pdf PDF
RFIs and Responses.docx DOCX document
Site visit attendance.pdf PDF
12639526Q0088-0001.pdf PDF
12639526Q0088.docx DOCX document
Attachment 3_Kennel Project Manual 02162026.pdf PDF
Attachment 2_Federal Construction Wage Rates_Cache County.txt TXT text file
Attachment 1_SOW for Utah Kennel Building Mar 2026.doc DOC document
Attachment 4_Kennel Drawings.pdf PDF
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

G 2 GEOTECHNICAL

GORDON

ENGINEERING, INC.

GEOTECHNICAL ENGINEERING GEOLOGICAL ENGINEERING ENVIRONMENTAL SERVICES

REPORT

GEOTECHNICAL STUDY

PROPOSED MILLVILLE KENNEL

4200 SOUTH 600 EAST

MILLVILLE, UTAH

November 13, 2024

Job No. 1342-001-24

Prepared for:

Cushing Terrell

800 West Main Street, Suite 800 Boise, Idaho 83702

Prepared by:

Gordon Geotechnical Engineering, Inc.

4426 South Century Drive, Suite 100 Salt Lake City, Utah 84123

Tel: 801-327-9600 Fax: 801-327-9601 www.gordongeotech.com

Gordon Geotechnical Engineering, Inc. Tel: 801-327-9600 4426 South Century Drive, Suite 100 Fax: 801-327-9601 Salt Lake City, Utah 84123 www.gordongeotech.com

GORDON

ENGINEERING, INC.

GEOTECHNICAL ENGINEERING GEOLOGICAL ENGINEERING ENVIRONMENTAL SERVICES

November 13, 2024 Job No. 1342-001-24

Cushing Terrell 800 West Main Street, Suite 800 Boise, Idaho 83702

Attention: Mr. Scott Roberts

Ladies and Gentlemen:

Re: Report

Geotechnical Study Proposed Millville Kennel 4200 South 600 East Millville, Utah

1. INTRODUCTION

1.1 GENERAL

This report presents the results of our geotechnical study performed at the site of the proposed Millville Kennel, which will be located at 4200 South 600 East in Millville, Utah. The general location of the site with respect to major topographic features and existing facilities, as of 1998, is presented on Figure 1, Vicinity Map. A detailed location of the site showing existing roadways and surrounding facilities, on an air photograph base, is presented on Figure 2, Area Map. The locations and alignments of photographs taken of the site during the field portion of study and the test pit locations excavated in conjunction with this study are also presented on Figure 2.

1.2 OBJECTIVES AND SCOPE

The objectives and scope of our study were planned in discussions between Mr. Scott Roberts of Cushing Terrell and Mr. Patrick Emery of Gordon Geotechnical Engineering, Inc. (G2).

In general, the objectives of this study were to:

1. Accurately define and evaluate the subsurface soil and groundwater conditions across the site.

Geotechnical Study

GORDON

ENGINEERING, INC.

2. Provide appropriate foundation, earthwork, geoseismic, and pavement recommendations to be utilized in the design and construction of the proposed structure.

In accomplishing these objectives, our scope has included the following:

1. A field program consisting of the excavating, logging, and sampling of 2 test pits which extended to depths of 7.5 to 10.5 feet below the existing grade.

2. A laboratory testing program.

3. An office program consisting of the correlation of available data, engineering analyses, and the preparation of this summary report.

1.3 AUTHORIZATION

Authorization was provided by returning a signed copy of our Professional Services Agreement No. 24-0814 dated August 14, 2024 and executed on September 30, 2024.

1.4 PROFESSIONAL STATEMENTS

Supporting data upon which our recommendations are based are presented in subsequent sections of this report. Recommendations presented herein are governed by the physical properties of the soils encountered in the exploration test pits for this study, measured and projected groundwater conditions, and the layout and design data discussed in Section 2., Proposed Construction, of this report. If subsurface conditions other than those described in this report are encountered and/or if design and layout changes are implemented, G2 must be informed so that our recommendations can be reviewed and amended, if necessary.

Our professional services have been performed, our findings developed, and our recommendations prepared in accordance with generally accepted engineering principles and practices in this area at this time.

2. PROPOSED CONSTRUCTION

A kennel structure covering a footprint of 6,000 square feet is planned for the site. The proposed structure is anticipated to be one level above grade, and of light gauge steel-frame construction established slab-on-grade.

It is anticipated that the maximum column loads will be in the range of 60 to 90 kips. There may also be some internal bearing walls with loads in the range of 2 to 3 kips per lineal foot.

GORDON

ENGINEERING, INC.

We estimate that maximum cuts and fills to achieve design grades will be minimal, on the order of two to three feet.

Paved entryways and at-grade parking surrounding the proposed building will also be a part of the overall development. Traffic over the entryway pavement surface will consist of a moderate volume of automobiles and light trucks, and a light volume of medium- and heavy-weight trucks.

Traffic in the parking areas will be lighter.

3. INVESTIGATIONS

3.1 FIELD PROGRAM

In order to define and evaluate the subsurface soil and groundwater conditions across the site, 2 test pits were excavated to depths of 7.5 to 10.5 feet below existing grade. Locations of the test pits are presented on Figure 2.

The field portion of our study was under the direct control and continual supervision of an experienced member of our geotechnical staff. During the course of the excavation operations, a continuous log of the subsurface conditions encountered was maintained. In addition, relatively undisturbed and small disturbed samples of the typical soils encountered were obtained for subsequent laboratory testing and examination. The soils were classified in the field based upon visual and textural examination. These classifications have been supplemented by subsequent inspection and testing in our laboratory. Detailed graphical representation of the subsurface conditions encountered is presented on Figures 3A and 3B, Log of Test Pits. Soils were classified in accordance with the nomenclature described on Figure 4, Unified Soil Classification System.

Disturbed bag samples were collected from the soils brought up by the backhoe bucket.

Following completion of excavating and logging, each test pit was backfilled. Although an effort was made to compact the backfill with the backhoe, backfill was not placed in uniform lifts and compacted to a specific density. Consequently, settlement of the backfill with time is likely to occur.

Following completion of excavating operations, one and one-quarter-inch diameter slotted PVC pipe was installed in Test Pits TP-1 and TP-2 in order to provide a means of monitoring the groundwater fluctuations.

GORDON

ENGINEERING, INC.

3.2 LABORATORY TESTING

3.2.1 General

In order to provide data necessary for our engineering analyses, a laboratory testing program was performed. The program includes moisture and partial gradation tests. The following paragraphs describe the tests and summarize the test data.

3.2.2 Moisture Tests

To aid in classifying the soils and to help correlate other test data, moisture tests were performed on selected undisturbed samples. The results of these tests are presented on the test pit logs, Figures 3A and 3B.

3.2.3 Partial Gradation Tests

To aid in classifying the soils and to provide general index parameters, a partial gradation test was performed upon three representative samples of the soils encountered in the exploration test pits. The test results are tabulated below:

Test Pit No.

Depth (feet)

Percent Passing No. 4 Sieve

Percent Passing No. 200 Sieve

Soil Classification

TP-1 4.0 17.2 6.2 GP/GM

TP-1 7.0 28.4 2.2 SP

TP-2 4.0 49.0 4.7 GP/SP

4. SITE CONDITIONS

4.1 SURFACE

At the time of the site visit, the site was mostly vacant and undeveloped. The overall site is part of the Millville Predator Research Facility. Vegetation consists of a light growth of grasses and weeds. Earthwork operations have previously occurred at the site.

The site grade generally slopes gently downward to the west with an overall relief of approximately three to five feet.

The site is bordered by existing structures to the north and south, similar undeveloped land to the east, and 600 East Street to the west.

GORDON

ENGINEERING, INC.

Representative photographs of the site area are shown on Figure 5, Photographs.

4.2 SUBSURFACE SOIL

In order to define and evaluate the subsurface soil and groundwater conditions at the site, 2 test pits were excavated to depths of 7.5 to 10.5 feet below existing grade. Subsurface conditions encountered at the test pit locations were relatively consistent. At each of the test pit locations, loose/disturbed surficial soil was encountered to depths ranging from four to five inches. The surficial soil appeared to have been disturbed by past site grading/earthwork activity.

In general, underlying the loose/disturbed surficial soil in each of the test pits and extending to depths explored of 7.5 to 10.5 feet, natural soils were encountered. The natural soils consist primarily of gravel with varying amounts of sand and silt. The natural granular soils are medium dense, slightly moist, and brown and will exhibit high strength and low compressibility characteristics under the anticipated loading range.

The lines designating the interface between soil types on the test pit logs generally represent approximate boundaries. In-situ, the transition between soil types may be gradual.

4.3 GROUNDWATER

Groundwater was not encountered in the test pits to the depths explored, 7.5 to 10.5 feet, during excavating operations. Groundwater is anticipated to be at a depth greater than 20 feet at the site.

Seasonal and longer-term groundwater fluctuations of one to two feet should be anticipated.

The highest seasonal levels will generally occur during the late spring and summer months.

5. DISCUSSIONS AND RECOMMENDATIONS

5.1 SUMMARY OF FINDINGS

Based on the results of our investigation, the proposed structure may be supported upon conventional shallow spread and wall foundations established on suitable natural soils.

The most significant geotechnical aspect of the site is the loose, surficial soils encountered to depths of four to five inches at each of the test pit locations. Loose, surficial soils must be completely removed from below the building footprint and exterior flatwork areas. The natural granular soils encountered at four to five inches are suitable for footing support.

Although not encountered at the test pit locations, non-engineered fills associated with the previous earthwork are likely to be encountered.

GORDON

ENGINEERING, INC.

Due to the loose, surficial soils encountered and potential for encountering non-engineered fills, a qualified geotechnical engineer from our staff must aid in verifying that suitable natural granular soils have been encountered prior to the placement of structural site grading fills, floor slabs, footings, or foundations.

Detailed discussions pertaining to earthwork, foundations, floor slabs, lateral resistance, and the geoseismic setting of the site are discussed in the following sections.

5.2 EARTHWORK

5.2.1 Site Preparation

Initial preparation of the site must consist of the removal of the existing structures and pavements, debris, and any associated non-engineered fills. In proposed flexible pavement areas, the existing asphalt concrete and fills may remain provided that they do not interfere with the final grade. The asphalt concrete should be perforated to facilitate drainage and proofrolled.

Further preparation of the site must consist of the removal of all non-engineered fills, loose surficial soils, topsoil, debris, and other deleterious materials from beneath an area extending at least three feet beyond the perimeter of the proposed building, rigid pavement, and exterior flatwork areas.

The loose/disturbed surficial soil/non-engineered fills may remain in flexible pavement areas as long as they are properly prepared. Proper preparation will consist of scarifying and moisture conditioning the upper 9 to 12 inches and recompacting to the requirements of structural fill.

However, it should be noted that compaction of fine-grained soils (clays and silts) as structural site grading fill will be very difficult, if not impossible, during wet and cold periods of the year. As an option for proper preparation and recompaction, the upper eight inches may be removed and replaced with granular subbase over proofrolled subgrade. Even with proper preparation, flexible pavements established on non-engineered fills may experience some long-term movements.

Subsequent to the above operations and prior to the placement of footings, structural site grading fill, floor slabs, or pavements, the exposed natural subgrade must be proofrolled by passing moderate-weight rubber tire-mounted construction equipment over the surface at least twice. If any loose, soft, or disturbed zones are encountered, they must be completely removed in footing and floor slab areas and replaced with granular structural fill. If removal depth required is greater than two feet, G2 must be notified to provide further recommendations. In pavement areas, unsuitable soils encountered during recompaction and proofrolling must be removed to a maximum depth of two feet and replaced with compacted granular structural fill.

GORDON

ENGINEERING, INC.

Surface vegetation and other deleterious materials should generally be removed from the site.

Topsoil if encountered, although unsuitable for re-utilization as structural fill, may be stockpiled for subsequent landscaping purposes.

5.2.2 Temporary Excavations

Temporary construction excavations through fine-grained cohesive soils, not exceeding four feet in depth, above or below the groundwater table, may be constructed with near-vertical sideslopes. Temporary excavations up to eight feet deep in fine-grained cohesive soils and above or below the water table may be constructed with sideslopes no steeper than one-half horizontal to one vertical (0.5H:1.0V). Temporary excavations up to eight feet deep in granular soils above or below the water table may be constructed with sideslopes no steeper than one horizontal to one vertical (1.0H:1.0V).

Utility trench excavations must conform within Occupational Safety and Health (OSHA) guidelines for trench safety.

To minimize disturbance to the underlying soils, it is our recommendation that footings be excavated with a backhoe equipped with a smooth-lip bucket.

All excavations must be inspected periodically by qualified personnel. If any signs of instability or excessive sloughing are noted, immediate remedial action must be initiated.

5.2.3 Structural Fill

Structural fill is defined as all fill which will ultimately be subjected to structural loadings, such as imposed by footings, floor slabs, pavements, etc. Structural fill will be required as backfill over foundations and utilities, as site grading fill, and in some areas, as replacement fill below footings. It is recommended that all structural fill must be free of sod, rubbish, topsoil, frozen soil, and other deleterious materials. Structural site grading fill is defined as fill placed over fairly large open areas to raise the overall site grade. For structural site grading fill, the maximum particle size should generally not exceed four inches; although, occasional larger particles, not exceeding six inches in diameter may be incorporated if placed randomly in a manner such that “honeycombing” does not occur and the desired degree of compaction can be achieved. The maximum particle size within structural fill placed within confined areas should generally be restricted to two inches.

The on-site natural soils may be utilized as structural site grading fill. It should be noted that unless moisture control is maintained, utilization of fine-grained soils (if encountered) as structural site grading fill will be very difficult, if not impossible, during wet and cold periods of the year. Only granular soils are recommended as structural fill in confined areas, such as around foundations and within utility trenches.

GORDON

ENGINEERING, INC.

To stabilize soft subgrade conditions a mixture of coarse gravels and cobbles and/or one and one-half- to two-inch gravel (stabilizing fill) should be utilized.

Non-structural site grading fill is defined as all fill material not designated as structural fill and may consist of any cohesive or granular soils not containing excessive amounts of degradable material.

5.2.4 Fill Placement and Compaction

Coarse gravel and cobble mixtures (stabilizing fill), if utilized, shall be end-dumped, spread to a maximum loose lift thickness of 15 inches, and compacted by dropping a backhoe bucket onto the surface continuously at least twice. As an alternative, the fill may be compacted by passing moderately heavy construction equipment or large self-propelled compaction equipment at least twice. Subsequent fill material placed over the coarse gravels and cobbles shall be adequately placed so that the “fines” are “worked into” the voids in the underlying coarser gravels and cobbles.

Structural fill shall be placed in lifts not exceeding eight inches in loose thickness. Structural fills shall be compacted in accordance with the percent of the maximum dry density as determined by the AASHTO1 T-180 (ASTM2 D-1557) compaction criteria in accordance with the following table:

Location

Total Fill Thickness

(feet) Minimum Percentage of Maximum Dry Density

Beneath an area extending at least 3 feet beyond the perimeter of the structure 0 to 8 95

Outside area defined above 0 to 5 90

Outside area defined above 5 to 8 92

Road base - 96

Structural fills greater than eight feet thick are not anticipated at the site.

Subsequent to stripping and prior to the placement of structural site grading fill, the subgrade must be prepared as discussed in Section 5.2.1, Site Preparation, of this report. In confined areas, subgrade preparation should consist of the removal of all loose or disturbed soils.

1 American Association of State Highway and Transportation Officials 2 American Society for Testing and Materials

GORDON

ENGINEERING, INC.

Non-structural fill may be placed in lifts not exceeding 12 inches in loose thickness and compacted by passing construction, spreading, or hauling equipment over the surface at least twice.

5.2.5 Utility Trenches

All utility trench backfill material below structurally loaded facilities (flatwork, floor slabs, roads, etc.) should be placed at the same density requirements established for structural fill. If the surface of the backfill becomes disturbed during the course of construction, the backfill should be proofrolled and/or properly compacted prior to the construction of any exterior flatwork over a backfilled trench. Proofrolling may be performed by passing moderately loaded rubber tire-mounted construction equipment uniformly over the surface at least twice. If excessively loose or soft areas are encountered during proofrolling, they should be removed to a maximum depth of two feet below design finish grade and replaced with structural fill.

Most utility companies and City-County governments are now requiring that Type A-1 or A-1-a (AASHTO Designation – basically granular soils with limited fines) soils be used as backfill over utilities. These organizations are also requiring that in public roadways the backfill over major utilities be compacted over the full depth of fill to at least 96 percent of the maximum dry density as determined by the AASHTO T-180 (ASTM D-1557) method of compaction. We recommend that as the major utilities continue onto the site that these compaction specifications are followed.

The natural fine-grained cohesive soils (if encountered) are not recommended for use as trench backfill.

5.2.6 Areal Settlements

Areal settlements resulting from site grading fills as much as three feet should be less than one inch. These settlements are in addition to settlements induced by foundation and floor slab loads. To reduce the total settlement that the structure will realize, site grading fill must be placed as far in advance of other construction as possible. The majority of this settlement will occur during placement.

5.3 SPREAD AND CONTINUOUS WALL FOUNDATIONS

5.3.1 Design Data

The proposed structure may be supported upon conventional spread and continuous wall foundations. The footings may be established on suitable, undisturbed natural soils and/or structural fills extending to suitable undisturbed natural soils.

GORDON

For design, the following parameters are provided:

Minimum Recommended Depth of Embedment for Frost Protection - 30 inches

Minimum Recommended Depth of Embedment for

Non-frost Conditions - 15 inches

Recommended Minimum Width for Continuous Wall Footings - 18 inches

Minimum Recommended Width for Isolated Spread

Footings - 24 inches

Recommended Net Bearing Pressures for Real Load Conditions

For footings on suitable natural soils and/or structural fill extending to suitable natural soils 2,500 pounds per square foot

Bearing Pressure Increase for Seismic Loading - 50 percent*

* Not applicable for edge bearing pressure when the footings are established upon granular soil.

The term “net bearing pressure” refers to the pressure imposed by the portion of the structure located above lowest adjacent final grade. Therefore, the weight of the footing and backfill to lowest adjacent final grade need not be considered. Real loads are defined as the total of all dead plus frequently applied live loads. Total load includes all dead and live loads, including seismic and wind.

5.3.2 Installation

Under no circumstances should the footings be installed overlying non-engineered fills, upon soft or disturbed soils, loose surficial soils, construction debris, frozen soil, or within ponded water.

If the natural soils upon which the footings are to be established become loose or disturbed, they must be removed and replaced with granular structural fill. If granular structural fill upon which the footings are to be established becomes disturbed, they should be recompacted to the requirements for structural fill or be removed and replaced with structural fill.

GORDON

ENGINEERING, INC.

The width of structural replacement fill, as required below more heavily loaded footings, should be extended laterally at least one foot beyond the edges of the footings in all directions for each foot of fill thickness beneath the footings.

5.3.3 Settlements

Settlements of foundations designed and installed in accordance with above recommendations and supporting maximum projected structural loads are anticipated to be less than one inch.

Settlements are expected to occur rapidly with approximately 60 to 70 percent of the settlements occurring during construction.

5.4 LATERAL RESISTANCE

Lateral loads imposed upon foundations due to wind or seismic forces may be resisted by the development of passive earth pressures and friction between the base of the footings and the supporting soils. In determining frictional resistance, a coefficient of 0.40 should be utilized for the natural fine-grained soils. In determining frictional resistance, a coefficient of 0.45 should be utilized for the natural granular soils. Passive resistance provided by properly placed and compacted granular structural fill above the water table may be considered equivalent to a fluid with a density of 300 pounds per cubic foot. Below the water table, this granular soil should be considered equivalent to a fluid with a density of 150 pounds per cubic foot.

A combination of passive earth resistance and friction may be utilized provided that the friction component of the total is divided by 1.5.

5.5 LATERAL PRESSURES

The lateral pressure parameters as presented within this section, assume that the backfill will consist of a drained granular soil placed and compacted in accordance with the recommendations presented herein. The lateral pressures imposed upon subgrade facilities will, therefore, be basically dependent upon the relative rigidity and movement of the backfilled structure. For active walls, such as retaining walls which can move outward (away from the backfill), granular backfill may be considered equivalent to a fluid with a density of 35 pounds per cubic foot in computing lateral pressures. For more rigid basement walls that are not more than 10 inches thick and 12 feet or less in height, granular backfill may be considered equivalent to a fluid with a density of 45 pounds per cubic foot. For very rigid non-yielding walls, granular backfill should be considered equivalent to a fluid with a density of at least 60 pounds per cubic foot. The above values assume that the surface of the soils slope behind the wall is horizontal, that the granular fill has been placed and lightly compacted, not as a structural fill. If the fill is placed as a structural fill, the values should be increased to 45 pounds per cubic foot, 60 pounds per cubic foot, and 120 pounds per cubic foot, respectively. If the slope behind the wall is two horizontal to one vertical the values for purely active walls and basement walls should increase to 57 pounds per cubic foot and 67 pounds per cubic foot, respectively.

GORDON

ENGINEERING, INC.

Recommended average lateral uniform pressure for various height walls are tabulated below and assume a granular wall backfill with a horizontal grade above the wall. It should be noted that the lateral pressures as quoted assume that the backfill materials will not become saturated. If the backfill becomes saturated, the above values may be decreased by one-half;

however, full hydrostatic water pressures will have to be included.

Wall Height (feet)

Uniform Seismic Lateral Pressure* (psf)

4 56

* Maximum short-term pressures, they are not sustained loads.

Note that the pressures presented in this section do not include surcharge loadings, such as floor slabs, adjacent footings, etc.

5.6 FLOOR SLABS

Floor slabs may be established upon structural fill extending to suitable undisturbed natural soils. Loose/disturbed surficial soils, non-engineered fills and topsoil are not considered suitable. To provide a capillary break, it is recommended that floor slabs be directly underlain by at least four inches of “free-draining” fill, such as “pea” gravel or three-quarters- to one-inch minus clean gap-graded gravel. Settlements of lightly to moderately loaded floor slabs are anticipated to be minor.

5.7 PAVEMENTS

The properly prepared non-engineered fills will exhibit poor engineering characteristics when saturated or nearly saturated. Loose/disturbed surficial soil/non-engineered fills may remain in flexible pavement areas if properly prepared, as stated previously in this report. Rigid pavements shall not be placed overlying loose/disturbed surficial soil/non-engineered fills, even if properly prepared. Considering the loose/disturbed surficial soil/existing non-engineered soils as the subgrade soils and the projected traffic, the pavement sections on the following pages are recommended.

GORDON

Parking Areas

(Light Volume of Automobiles and Light Trucks, Occasional Medium-Weight Trucks, and No Heavy-Weight Trucks) [1 equivalent 18-kip axle load per day]

Flexible:

2.5 inches Asphalt concrete

8.0 inches Aggregate base

Over Properly prepared natural soils, properly prepared existing non-engineered fill, and/or structural site grading fill extending to suitable stabilized natural soils.

Rigid:

5.0 inches Portland cement concrete (non-reinforced)

4.0 inches Aggregate base

Over Properly prepared natural soils, and/or structural site grading fill extending to suitable stabilized natural soils.*

* Rigid pavements shall not be placed over non-engineered fills, even if properly prepared.

GORDON

Primary Roadway Areas

(Moderate Volume of Automobiles and Light Trucks, Light Volume of Medium-Weight Trucks, and Occasional Heavy-Weight Trucks) [5 equivalent 18-kip axle loads per day]

Flexible:

3.0 inches Asphalt concrete

8.0 inches Aggregate base

Over Properly prepared natural soils, properly prepared existing non-engineered fill, and/or structural site grading fill extending to suitable stabilized natural soils.

Rigid:

5.5 inches Portland cement concrete

(non-reinforced)

5.0 inches Aggregate base

Over Properly prepared natural soils, and/or structural site grading fill extending to suitable stabilized natural soils.*

* Rigid pavements shall not be placed over non-engineered fills, even if properly prepared.

For dumpster pads, we recommend a pavement section consisting of six and one-half inches of Portland cement concrete, four inches of aggregate base, over properly prepared natural stabilized subgrade or site grading structural fills.

These above rigid pavement sections are for non-reinforced Portland cement concrete.

Concrete should be designed in accordance with the American Concrete Institute (ACI) and joint details should conform to the Portland Cement Association (PCA) guidelines. The concrete should have a minimum 28-day unconfined compressive strength of 4,000 pounds per square inch and contain 6 percent ±1 percent air-entrainment.

GORDON

ENGINEERING, INC.

5.8 GEOSEISMIC SETTING

5.8.1 General

In July 2023, the State of Utah adopted the 2021 International Building Code (IBC). The IBC 2021 code determines the seismic hazard for a site based upon 2014 mapping of bedrock accelerations prepared by the United States Geologic Survey (USGS) and the soil site class.

The USGS values are presented on maps incorporated into the IBC code and are also available based on latitude and longitude coordinates (grid points).

The structure must be designed in accordance with the procedure presented in Section 1613, Earthquake Loads, of the IBC 2021 edition.

5.8.2 Faulting

Based on our review of available literature, no active faults pass through or immediately adjacent to the site.

5.8.3 Soil Class

Based on the soils encountered and our knowledge of the underlying geology, we recommend that Site Class D - Stiff Soil Profile as defined in Table 20.3-1, Site Classification, of ASCE 7-16 be utilized for dynamic structural analysis.

5.8.4 Ground Motions

The IBC 2021 code is based on 2014 USGS mapping, which provides values of short and long period accelerations for the Site Class B boundary for the Maximum Considered Earthquake (MCE). This Site Class B boundary represents a hypothetical sandstone bedrock surface and must be corrected for local soil conditions. The following table summarizes the peak ground and short and long period accelerations for a MCE event and incorporates a soil amplification factor for a Site Class D soil profile in the second column. Based on the site latitude and longitude (41.6554 degrees north and -111.8180 degrees west, respectively), the values for this site are tabulated on the following page.

GORDON

ENGINEERING, INC.

Spectral Acceleration Value, T Seconds

Site Class B-C Boundary

[mapped values] (% g)

Site Class D [adjusted for site class effects] (% g)

Peak Ground Acceleration (Geo-Mean) 44.1 51.1

0.2 Seconds (Short Period Acceleration) SS = 101.7 SMS = 111.2

1.0 Seconds (Long Period Acceleration) S1 = 34.2 SM1 = *

* See Section 11.4.8 for requirements on site-specific ground motion studies. Please contact us for a proposal, if needed.

5.8.5 Liquefaction

The site is located in an area that has been identified by the Utah Geological Survey as having “very low” liquefaction potential. Liquefaction is defined as the condition when saturated, loose, finer-grained sand-type soils lose their support capabilities because of excessive pore water pressure which develops during a seismic event.

Due to the absence of groundwater to the depths explored our analysis indicates liquefaction is not anticipated during the design seismic event.

5.9 SITE OBSERVATIONS

As previously mentioned, loose/disturbed surficial soil and potential for encountering non-engineered fills are present across the surface of the site to varying depths. Therefore, we recommend that a qualified geotechnical engineer from our staff observe the foundation excavations to identify that these soils have been removed and that suitable soils have been encountered below structure.

--------------------■ GORDON

Job No. 1342-001-24 ■■ ;I G22 GEOTECHNICAL Geotechnical Study ■ ENGINEERING, INC.

November 13, 2024

We appreciate the opportunity of providing this service for you. If you have any questions or require additional information, please do not hesitate to contact us.

Respectfully submitted, Gordon Geotechnical Engineering, Inc.

Jos ua M. Whitney, Sta e of Utah No. 6252902 Sen or Engineer \

JMW/PRE:sn

Encl. Figure 1, Vicinity Map Figure 2, Area Map Figures 3A and 3B, Log of Test Pits

Reviewed by:

Patrick R. Emery, State of Uta Senior Engineer

Figure 4, Unified Soil Classification System Figure 5, Photographs

Addressee (3 + email)

WGS84 111.80000° W

WGS84 111.80000° W

111.81667° W

111.81667° W

111.83333° W

111.83333° W

111.85000° W

111.85000° W

.6

N

.6

N

.6

N

.6

N

.6

N

.6

N

.6

N

.6

N

Map created with Map created with Map created with Map created with Map created with Map created with Map created with Map created with Map created with TOPO!®TOPO!®TOPO!®TOPO!®TOPO!®TOPO!®TOPO!®TOPO!®TOPO!® ©2010 National Geographic ©2010 National Geographic ©2010 National Geographic ©2010 National Geographic ©2010 National Geographic ©2010 National Geographic ©2010 National Geographic ©2010 National Geographic ©2010 National Geographic

TOPO! map printed on 11/11/24 from "Untitled.tpo"

11/11/24

TN MN

10½°REFERENCE:

USGS 7.5 MINUTE TOPOGRAPHIC QUADRANGLE MAP

TITLED “LOGAN, UTAH”, DATED 1998

FIGURE 1

VICINITY MAP

CUSHING TERRELL

JOB NO. 1342-001-24

1000 10000 2000

SCALE IN FEET

SITE

FIGURE 2

AREA MAP

REFERENCE:

ADAPTED FROM AERIAL PHOTOGRAPH

DOWNLOADED FROM GOOGLE EARTH

IMAGERY DATED JUNE 26, 2023

CUSHING TERRELL

JOB NO. 1342-001-24

SCALE:

## see Figure 5, Photographs

SITE

TP-1

600 EAST STREET

TP-2

#3#2

#1

TEST PIT

Page: 1 of 1

Project Name:

Location:

Excavating Method:

Elevation:

Remarks:

Project No.:

Client:

Date Excavated:

Water Level:

Gordon Geotechnical Engineering, Inc.

4426 South Century Drive, Suite 100 Salt Lake City, Utah 84123

DESCRIPTION

G R

A P

H

IC

L O

G

W A

T E

R L

E V

E L

D E

P T

H (F

T

S A

M P

L E

S Y

M B

O L

S A

M P

L E

T Y

P E

B L

O W

S /F

T

M O

IS

T

U R

E

D R

Y D

E N

S

IT

Y (P

C F

P

A S

S

IN

G

L

IQ

U

ID

L

IM

IT

P L

A S

T

IC

L

IM

IT

REMARKS

The discussion in the text under the section titled, SUBSURFACE CONDITIONS, is necessary for proper understanding of the nature of the subsurface material.

TP-1

Proposed Millville Kennel

4200 South 600 East, Millville, Utah

Case 580 Backhoe

1342-001-24

Cushing Terrell

11-01-24

No groundwater encountered.

Ground Surface

FINE AND COARSE GRAVEL

with fine to coarse sand, cobbles/boulders, and some silt; major roots (topsoil) to 4"; brown (GP/GM)

FINE AND COARSE GRAVEL

with some fine to coarse sand, cobbles, boulders, and trace silt; brown

(GP)

B

B

1.8

1.1

6.2

2.2 slightly moist

"medium dense"

Stopped excavating at 10.5'.

No groundwater encountered at time of excavating.

No significant sidewall caving.

FIGURE 3A

TEST PIT

Page: 1 of 1

Project Name:

Location:

Excavating Method:

Elevation:

Remarks:

Project No.:

Client:

Date Excavated:

Water Level:

Gordon Geotechnical Engineering, Inc.

4426 South Century Drive, Suite 100 Salt Lake City, Utah 84123

DESCRIPTION

G R

A P

H

IC

L O

G

W A

T E

R L

E V

E L

D E

P T

H (F

T

S A

M P

L E

S Y

M B

O L

S A

M P

L E

T Y

P E

B L

O W

S /F

T

M O

IS

T

U R

E

D R

Y D

E N

S

IT

Y (P

C F

P

A S

S

IN

G

L

IQ

U

ID

L

IM

IT

P L

A S

T

IC

L

IM

IT

REMARKS

The discussion in the text under the section titled, SUBSURFACE CONDITIONS, is necessary for proper understanding of the nature of the subsurface material.

TP-2

Proposed Millville Kennel

4200 South 600 East, Millville, Utah

Case 580 Backhoe

1342-001-24

Cushing Terrell

11-01-24

No groundwater encountered.

Ground Surface

FINE AND COARSE GRAVEL/FINE TO COARSE SAND

with cobbles/boulders and trace silt; major roots (topsoil) to 5"; brown

(GP/SP)

1.2

4.7 slightly moist

"medium dense"

Stopped excavating at 7.5'.

No groundwater encountered at time of excavating.

No significant sidewall caving.

FIGURE 3B

FIGURE 4

FIGURE 5

PHOTOGRAPHS

CUSHING TERRELL

JOB NO. 1342-001-24

#1 Looking southeast. #2 Looking southeast.

#3 Looking at Test Pit TP-1.

Locations and direction, see Figure 2, Area Map

1342-001-24.cov
1342-001-24.geo
1. INTRODUCTION
1.1 GENERAL
1.2 OBJECTIVES AND SCOPE
1.3 AUTHORIZATION
1.4 PROFESSIONAL STATEMENTS
2. PROPOSED CONSTRUCTION
3. INVESTIGATIONS
3.1 FIELD PROGRAM
3.2 LABORATORY TESTING
3.2.1 General
3.2.2 Moisture Tests
3.2.3 Partial Gradation Tests
4. SITE CONDITIONS
4.1 SURFACE
4.2 SUBSURFACE SOIL
4.3 GROUNDWATER
5. DISCUSSIONS AND RECOMMENDATIONS
5.1 SUMMARY OF FINDINGS
5.2 EARTHWORK
5.2.1 Site Preparation
5.2.2 Temporary Excavations
5.2.3 Structural Fill
5.2.4 Fill Placement and Compaction
5.2.5 Utility Trenches
5.2.6 Areal Settlements
5.3 SPREAD AND CONTINUOUS WALL FOUNDATIONS
5.3.1 Design Data
5.3.2 Installation
5.3.3 Settlements
5.4 LATERAL RESISTANCE
5.5 LATERAL PRESSURES
5.6 FLOOR SLABS
5.7 PAVEMENTS
5.8 GEOSEISMIC SETTING
5.8.1 General
5.8.2 Faulting
5.8.3 Soil Class
5.8.4 Ground Motions
5.8.5 Liquefaction

5.9 SITE OBSERVATIONS

MX-5071_20241113_142603
1342-001-24-FIG1
1342-001-24-FIG2
1342-001-24-logs
TP1
TP2
uscs fig4
1342-001-24-FIG5

File details come from the government source that posted it. Updated .