Amendment 01- SF 30.pdf
PDF 97 KB Posted
- Attached to
- USDA Forest Service Puerto Rico- Aviary Roofing Replacement and Photovoltaic System Installation
- Solicitation number
- 12445221R0010
- Issued by
-
Department of Agriculture Forest Service
About this file
This document provides an amendment to a solicitation for roof replacement and photovoltaic system installation services. The USDA Forest Service is seeking to replace roofs and install a 26kW photovoltaic system with 24kW battery backup at the Jimenez Aviary in Puerto Rico. The amendment provides clarification questions and answers from a pre-bid meeting, including confirmation that wind load design must withstand category 5 hurricanes, battery backup will charge from the generator during a power outage, and that Buy American requirements apply. The solicitation is set aside for small businesses and offers are due by April 29th for a firm fixed price construction contract between $250,000 to $500,000. The selected contractor must meet all bonding and documentation requirements specified.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment 02.pdf | ||
| SF 30 Amendment 01.pdf | ||
| 1Bldg3 Membrane reference.jpg | JPG image | |
| PV PREBID ATTENDEES 040721.xlsx | XLSX spreadsheet | |
| A_B2_Roof.zip | ZIP file | |
| Amendment 01 Updated Attachment 05 DBC AVIARY PV SYSTEM.docx | DOCX document | |
| 2Bldg3 Membrane reference.jpg | JPG image | |
| Attachment 04 PV BESS Technical Specifications PSL 05 22.docx | DOCX document | |
| Attachment 00- Schedule of Items.xlsx | XLSX spreadsheet | |
| Attachment 01 Davis Bacon Wages.docx | DOCX document | |
| Attachment 02 STATEMENT OF WORK ROOFS AND PV SYSTEM.docx | DOCX document | |
| SF -1442 12445221R0010.pdf | ||
| Attachment 03 Aviary TPO Spec.docx | DOCX document | |
| Attachment 06 Aviary Bid Set.pdf | ||
| Solicitation Body 12445221R0010.docx | DOCX document | |
| Attachment 08 Experience Questionnaire.docx | DOCX document | |
| Attachment 05 DBC AVIARY PV SYSTEM.docx | DOCX document | |
| Attachment 07 Proposed solar array1.pdf |
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
12445221R0010 x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
ATLANTA GA 30309-2449
STE 876S
1720 PEACHTREE ST NW
USDA-FS CSA EAST 12
04/09/20210001
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
03/30/2021
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Aviary Replace Roofs and Install Photovoltaic (PV) System on Jimenez, Rio Grande
Amendment 01 Incorporates the following in text below or included as attachment. Potential offerors are required to confirm receipt by submitting the SF-30 along with the proposal.
The response date has not been extended. All other solicitation terms and conditions remain unchanged.
1. Clarifications: Bid Bond is required at 100% of proposal response.
2. Attachment 05- Clarification of Magnitude: $250000 and $500000 is accurate.
3. Roof Photos have been uploaded to BETA-Sam. As a reference two additional photos labeled "Roof Membrane Reference" have been uploaded to BETA-Sam
Continued ...
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
TAKELE WOLDU
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 4
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
12445221R0010/0001
4. A list of attendees present at the Pre-Bid
Meeting have been uploaded to the solicitation in the solicitation announcement in BETA-Sam.
Questions and Answers:
Question 1: Do you want a 26kW or 24kW system?
Answer 2: Per Attachment 04 PHOTO VOLTAIC AND
BATTERY ENERGY STORAGE SYSTEM
(PV + BESS) DESIGN SPECIFICATIONS, Page 6 Design and build a minimum 26 kW roof mounted photovoltaic system and 24 kW, 100 kWh
Lithium-ion Battery Energy Storage Systems (PV +
BESS).
Provide a 26 kW system, with a 24kW battery.
Question 2: What wind load should the system be designed to?
Answer 2: Per Attachment 04 PHOTO VOLTAIC AND
BATTERY ENERGY STORAGE SYSTEM
(PV + BESS) DESIGN SPECIFICATIONS, Page 6: The PV system shall be designed to withstand category 5 hurricane winds.
The structure and BESS will survive up to a Cat 5 hurricane, but the panels will be expected to be a loss.
Question 3: During a power grid outage, what is the order of powering up the facility?
Answer 3: Per Attachment 04 PHOTO VOLTAIC AND
BATTERY ENERGY STORAGE SYSTEM
(PV + BESS) DESIGN SPECIFICATIONS, Page 6:
Grid outage scenario: Integrate the PV + BESS with the existing 60 kW Generac emergency generator and automatic transfer switch (ATS).
Install a microgrid control system and modify the existing ATS as necessary to provide electricity to the building upon grid failure as follows:
Provide electricity from the PV + BESS until the
BESS is drained to 20% (20 kWh) remaining.
When the BESS is at 20% start the emergency generator to power the building and recharge the
BESS. When the BESS is 80% charged turn off the emergency generator and power building with the
PV + BESS until BESS is at 20%, then start the emergency generator again. Repeat this cycle
Continued ...
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
3 4
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
12445221R0010/0001 until grid power is returned.
Question 4: Has the designer completed a solar study of the roof? If so, does the Contractor need to do one?
Answer 4: Per Attachment 04 PHOTO VOLTAIC AND
BATTERY ENERGY STORAGE SYSTEM
(PV + BESS) DESIGN SPECIFICATIONS, Page 6, Existing Feasibility Studies and Engineering
Studies Done by Others¿
The Contractor is responsible for ascertaining relevant site conditions to determine project feasibility and final PV + BESS design and installation according to the terms of this solicitation. If any existing engineering studies or facility conditions reports are provided through this solicitation from the site information package or agency representative, the bidder and Contractor shall independently verify all information provided.
Question 5: Attachment 04 PHOTO VOLTAIC AND
BATTERY ENERGY STORAGE SYSTEM (PV + BESS) DESIGN
SPECIFICATIONS, Page 9 requires one person be
NABCEP certified. Puerto Rico doesn't typically require this certification. Do you want to keep this requirement?
Answer 5: Yes.
Question 6: Is the complex power system entirely
120/240V, single phase power?
Answer 6 Yes.
Question 7: How many emergency generators (and what size) are on site?
Answer 7: There are two generators on site. Each was originally rated at 100 kW. Both have been modified to provide 120/240 V power and now each is capable of 60 kW. There is a manual switch to operate one at a time, to provide a rest period for each generator.
Question 8: Is there an existing underground conduit from the emergency generators to Building
1 and 2 that this project can use?
Continued ...
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
4 4
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
12445221R0010/0001
Answer 8: An existing underground conduit is in place; however, it is full. This project should not require a new conduit from the emergency generator building to the BESS in Bldg 2.
Question 9: Can we climb up the ladders to inspect the existing roof conditions?
Answer 9: Unfortunately, it was raining during the pre-bid conference. The government determined the ladders were too slick to allow contractors to safely climb at that time. The government will provide photographs showing the existing Building 1 and 2 roofs. In addition, the government will provide photographs of the
Bldg 3 roof. Although Building 3 is not in the project scope, it has the specified roof in place. (PICTURES HAVE BEEN UPLOADED AS ATTACHMENTS
Question 10: Can we provide foreign manufactured components to reduce the project cost?
Answer 10: No. The Buy American Act will be strictly enforced.
End.