Attach4.1240LU26Q0010StRegisTechSpecsAMENDED.pdf
PDF 28 MB Posted
- Attached to
- LOLO NATIONAL FOREST - Ninemile Water & Wastewater and St. Regis Wastewater Improvements
- Solicitation number
- 1240LU26Q0010
About this file
This is a technical specifications document for the St. Regis Work Center Water and Wastewater System Improvements project managed by the USDA Forest Service, Lolo National Forest, in Mineral County, Montana. The project, numbered 1-23202, encompasses comprehensive replacement of both water distribution and wastewater collection systems, with an October 2024 preparation date.
The specifications detail extensive civil, electrical, and equipment work across 25 sheets of construction plans. Key water system components include 1,800 linear feet of 4-inch HDPE water line, 900 linear feet of 2-inch HDPE water line, nine 1-inch sanitary hydrants with backflow preventers, eight 4-inch gate valves with boxes, and two 2-inch blowoff hydrants. The wastewater system requires 1,160 linear feet of 8-inch SDR 35 PVC sewer main, 590 linear feet of HDPE force main (3-inch and 1.5-inch), 800 linear feet of 4-inch PVC service lines, seven concrete manholes, and two 120-volt grinder pump stations. The treatment system includes two 6,000-gallon septic tanks in series with a dosing pump vault, manifold distribution system, and pressure-dosed drainfield consisting of five laterals totaling 4,825 square feet. Site preparation involves clearing and grubbing, trench excavation with Type A, B, and C backfill specifications, surface restoration including seeding and sod replacement, and utility coordination with minimum 10-foot horizontal and 18-inch vertical separation between water and sewer lines. Electrical work includes grounding systems, conduit and raceway installation, equipment wiring connections, and enclosed switches per NEC standards. Testing requirements encompass hydrostatic pressure testing of water mains at 125+ PSI, leakage testing of sewer lines, television inspection of all sewer mains, and bacteriological examination following water main disinfection.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
October 2024
Technical Specifications
St. Regis Work Center Water and Wastewater System Improvements USDA Forest Service Region One
Lolo National Forest St. Regis Ranger District
Prepared by:
Set No.: ____________ Project #1-23202
TECHNICAL SPECIFICATIONS
October 2024
ST REGIS WORK CENTER
WATER AND WASTEWATER SYSTEM
IMPROVEMENTS
U.S.D.A Forest Service Region One Lolo National Forest
St. Regis Ranger District Mineral County, Montana
Prepared by:
Dan Baum
QAQC by:
Matt Mudd, PE Chad Hanson, PE
TABLE OF CONTENTS
DIVISION 1 – GENERAL REQUIREMENTS
Division Title 01010 Summary of Work 01050 Field Engineering 01275 Measurement and Payment (Water and Wastewater) 01300 Submittals 01410 Regulatory Requirements 01420 References 01430 Quality Assurance 01450 Quality Control 01500 Temporary Facilities and Controls 01660 Product Storage and Handling 01700 Contract Closeout 01730 Execution Requirements 01740 Cleaning and Waste Management
DIVISION 2 – SITE CONSTRUCTION
Section Title 02221 Trench Excavation and Backfill for Pipelines & Appurtenant Structures 02232 Site Clearing 02300 Earthwork 02536 Grinder Pumps 02650 Temporary By-Pass Pumping 02660 Water Distribution 02665 HDPE Pipe 02730 Sanitary Sewer Collection Systems 02910 Seeding
DIVISION 11 – EQUIPMENT
11600 Subsurface Treatment System
DIVISION 16 – ELECTRICAL
16000 General Electrical Requirements 16060 Grounding and Bonding for Electrical Systems 16070 Hangers and Supports for Electrical Systems 16075 Identification for Electrical Systems 16123 Low-Voltage Electrical Power Conductors and Cables 16130 Raceway and Boxes for Electrical Systems 16150 Equipment Wiring Connections 16411 Enclosed Switches
Appendix A- Soils Profiles for St Regis Work Center
DustinFarren Text Box
AMENDMENT: SPECIAL PROVISIONS
AMENDMENT: ADDED SPECIAL PROVISIONS
AMENDMENT: ADDED SPECIAL PROVISION
Stamp
DustinFarren
SECTION 00910
SPECIAL PROVISIONS
SP-07 WATER FOR CONSTRUCTION
Water for construction is the Contractor’s responsibility. The Contractor shall make all necessary arrangements as such. The Contractor is responsible for providing all required fittings, meters, hoses, backflow assemblies, valves and other appurtenances required for obtaining water for construction.
If water is acquired from metered fire hydrants, Contractor needs to know and understand proper hydrant operation procedures as they are the party ultimately responsible for improper hydrant connections or any other improper operation of a hydrant. The contractor is responsible to teach proper operation procedures to all employees using hydrants. This includes water truck drivers or any other employees of the company that operate hydrants for any reason.
Meter Hydrant Connection Procedures
1. Perform a safety check of the hydrant. Check the hydrant visually, and shake the hydrant with your hands to make sure it is rigid (do not use a movable hydrant – they are dangerous and serious injury to the operator may result). Check the hydrant to ensure the caps are tight.
2. Remove hydrant nozzle cap.
3. Attach metering device and hose and install brace support. All hydrant connections must include a RPZ backflow assembly or device acceptable to the CO at all times.
4. Open hydrant slowly. It should take more than 60 seconds to fully open to prevent surging on the water system. Open completely to shut off drip drain while hydrant is in use. Valves downstream of the hydrant shall not be used to control flow.
5. They discharge end of the hose should not be inserted under any circumstances, into a tank or container underwater or laid on the ground to make and lay in its own pool of water. There must be at all time an air gap between the end of the water hose and the container.
6. Upon filling the tank or upon completion of the permitted use, slowly close hydrant valve.
7. Remove hose
8. Replace nozzle cap and tighten securely.
9. No hydrant shall ever be left without the cap replaced and securely tightened.
The Contractor is required to obtain written permission for obtaining water from any public or private water system and provide documentation to the Government.
SP-08 SITE RESTORATION
Site Restoration is an important part of this project. Site Restoration is replacement or reconstruction of site improvements to rights-of-way, easements, public property, and private property that are affected or altered by construction operations, with improvements restored to a condition which is equal to, or better than, that which existed prior to construction operations. These Site Restoration items include but are not limited to; concrete curb and gutter replacement, sidewalk replacement, concrete surfaces, asphalt replacement, gravel restoration, seeding, sod, and irrigation system repair.
Initial restoration (rough grading, temporary aggregate if necessary, removal of excess excavated material and debris) shall be done each day to the extent necessary to allow the movement of local traffic and permit access to all areas for emergency vehicles. Maintenance of streets, drives, sidewalks, etc. shall be the responsibility of the Contractor (including dust control, grading, stabilization, etc.) until the
DustinFarren restoration is complete and has been accepted by the Government and CO. Restoration of each street or section of utility line shall follow the construction in a timely fashion so as to minimize inconvenience to the Government and the general public. The manner in which this restoration is done by the Contractor will be a determining factor in the approval of partial payment requests.
After utility work is completed on underground utilities and submitted on monthly estimate for payment, complete site restoration for those utility segments before next monthly estimate for payment is submitted, unless extended in writing by Government and CO. If site restoration is not completed, the Contractor’s partial payment request may be denied or additional retainage may be withheld.
SP-09 PRIVATE ACCESS
At all times during construction, afford government access to their property to the highest degree possible. Ensure that businesses will have at least one approach open at all times, if possible, and open closed-off approaches as quickly as possible.
The Contractor shall provide a minimum of 48 hour notice to residents of construction in front of their private residents and that access will be impacted.
The maximum un-backfilled open trench within the street sections during each day of construction shall not exceed 50 lineal feet.
SP-10 LANDSCAPED AREAS
Repair any landscaped or vegetated areas on private or public land that are scarred or destroyed during construction to an equal or better condition than that prior to the start of construction. This will include removing, replacing and grading topsoil. Replace all landscaped and/or grass areas disturbed during the construction process with a minimum of 6-inches of topsoil. Furnish and install sod as necessary to replace grass in areas as needed to restore to original condition.
Work to paid for under bid item “Type C Surface Restoration (Lawn)”. See Section 01275: Measurement and Payment for more information.
SP-11 REMOVAL AND REPLACEMENT OF FENCES, SIGNS, SIDEWALKS, CURBS,
GUTTERS, POSTS, BARRICADES, ETC.
Culverts, fences, signs, decorative rocks, newspaper boxes, posts, sidewalks, curbs, gutters, propane tanks, satellite dishes, barricades, etc. may be encountered during construction that may hinder construction operations. Whether on private or public property, remove and replace these objects as necessary to conduct construction operations. Replace objects removed in as good a condition as previously existed and to the satisfaction of the CO.
No additional payment will be allowed the Contractor for this work. See Section 01275: Measurement and Payment and the Drawings for more information.
SP-12 REMOVAL AND REPLACEMENT OF EXISTING FENCES
It is the responsibility of the Contractor to coordinate with Government, prior to removing existing fences, to determine procedures, length of time fence may be removed, and requirements for temporary fencing until permanent fencing is complete.
DustinFarren
All fence removed must be reassembled prior to the end of the workday. A secure fence will be required at the end of each workday. The trench under the fencing section must be backfilled at least 20’ either side of the fence at the end of each workday. Removal and replacement of fences and/or gates is considered incidental to the portion of contract work being completed for which the fence or gate removal is required and the cost is included in the bid price for the related item. No additional payment for fence and/or gate removal and replacement will be provided.
SP-13 STAGING AREA
The Contractor is required to make all arrangements for a construction staging area for material, equipment, office and related items as necessary. The Government owns areas that may be used as a location for the construction office and/or as a staging area for materials and equipment storage to the extent area is available. Make all necessary arrangements with the Government or other property Governments as needed. Take care to protect, preserve and/or replace objects and structures encountered within the confines of the staging areas and restore all disturbed areas as close as possible to original condition as possible unless otherwise dictated in these specifications.
Storage of construction materials, equipment, and other items pertinent to the construction of the project will be allowed in the staging areas. However, bulk storage of petroleum based products stored in tanks will not be allowed, unless otherwise accepted by the COR. At all times, spill kits must be available on-site for any accidental spills of petroleum.
No payment will be allowed to the Contractor for any work, including restoration, with regards to the staging areas.
SP-14 CONFLICTS WITH UTILITIES
As shown on the plans, underground utilities may be in conflict with certain areas of the project. Whether on private or public property, Contractor shall relocate, remove, replace, cross, work around, support, or other as necessary to conduct construction operations and properly construct the project. Utilities and other appurtenances may include but are not limited to the following: culverts, propane lines, TV cables, telephone lines and pedestals, electrical boxes and lines, gas mains, street lights, telephone and power poles, water mains and services, sewer mains and services and storm drain pipe and inlets.
Utility locations are based on the best available information which has been provided to or discovered by the CO. There is no guarantee as to the accuracy and completeness thereof is expressly disclaimed.
The Contractor shall coordinate his work with all utility companies or private entities that may be affected by the project. The Contractor will also coordinate with the appropriate utility companies to relocate, remove, replace, cross, work around, support, or other as necessary to conduct construction operations and properly construct the project. The Contractor will pay for any charges associated to relocate, remove, replace, cross, work around, support, or other as necessary to conduct construction operations and properly construct the project. The Contractor shall be solely responsible for any damage to these utilities due to his operations. The Contractor shall work closely with the utilities to ensure their criteria are met and no problems result. No separate payment will be made for this work and the Contractor shall figure the cost of such work into other applicable bid items. The Contractor shall also check with the Utilities Underground Location Center (1-800-424-5555) at least 48 hours in advance so that all utilities are located prior to digging.
DustinFarren
SP-15 DEWATERING
The Contractor will be responsible for any dewatering operations which may be necessary to adequately remove water such that construction activities can be completed as specified. The Contractor will be responsible for conveyance and disposal of water to surface watercourses. Make all necessary arrangements for infringements across private property and obtain and adhere to any necessary discharge permits.
The Contractor shall not discharge to the sanitary sewer or the existing storm drain pipe located along Ninemile Road to discharge groundwater during construction.
All temporary above ground piping used for dewatering shall not impede travel in the public right-or-way or existing access for private residents without prior approval.
SP-16 TESTING
Complete testing of all components of the project will be required to the satisfaction of the Government and the CO. Remedy all defects and performance problems revealed by the testing to the satisfaction of the CO by the Contractor at no additional expense to the Government.
The CO will conduct the following tests at no cost to the Contractor:
1. On-site moisture and density testing of trench backfill, embankments, engineered fill placement, crushed base course, and asphalt pavement.
Should the materials fail to meet the test specified, the Contractor will pay the costs of all retests conducted by the CO, or the Contractor may elect to have an approved testing laboratory conduct retests at the Contractor’s expense.
The Contractor will be responsible for conducting and paying for the following tests:
1. Laboratory analysis of concrete aggregate.
2. Slump and Air Entrainment tests for concrete.
3. Taking and breaking of concrete test cylinders.
4. Gradations for gravels, bedding, and base materials as specified.
1. Gradations for seal coat aggregate as specified.
5. Proctors for different materials and gravels used for backfill.
6. Leak testing the sewer mains and manholes.
7. Alignment testing the piping.
8. Pressure testing of mains. (Force mains)
9. TV inspection of all sewer mains.
10. Run tests of all pumps.
11. Marshall and core testing for bituminous asphalt concrete.
12. Re-testing of failed tests that were conducted by the CO.
13. Other tests as outlined in the Technical Specifications.
All tests which are the responsibility of the Contractor must be conducted by an approved, certified testing laboratory or individual. Acceptance or rejection of materials will generally be determined from tests made in-place in the field.
The following is frequency testing table for soils and concrete:
DustinFarren
Quality Control Frequency Table
SECTION ITEM DESCRIPTION TEST OR SUBMITTAL FREQUENCY
GENERAL
Varies All Materials Sieve Analysis Every New Material Varies All Materials Atterburg Limits Every New Material Varies All Materials Lab. Max Density Every New Material 02221 Type 'A' Trench Backfill Field Density/Moisture Content 1 test / 200 LF / lift 02221 Type 'B' Trench Backfill Field Density/Moisture Content 1 test / 300 LF / lift 02221 Type 'C' Trench Backfill Field Density/Moisture Content 1 test / 400 LF / lift 02300 Select Fill/Structural Fill Field Density/Moisture Content 1 test / 1,000 SF / lift 02320 Lagoon Embankment Field Density/Moisture Content 1 test / 5,000 SF / lift
GENERAL - ROADWAY
Varies All Materials Sieve Analysis Every New Material Varies All Materials Lab. Max Density Every New Material 02230 Borrow / Embankment Fill Field Density/Moisture Content 1 test / 5,000 SF / lift 02230 Original Ground / Native Subgrade Field Density/Moisture Content 1 test / 5,000 SF / lift 02234 Sub-Base Course(s) Field Density/Moisture Content 1 test / 2,500 SF / lift 02235 Base Course(s) Field Density 1 test / 2,000 SF / lift
STRUCTURES
Varies All Materials Sieve Analysis Every New Material Varies All Materials Lab. Max Density Every New Material
03310 Structural Concrete Mill Certificates With Every Mix Design
Mix Design Every Concrete Class Air Content 1 test / 75CY / Day Slump 1 test / 75CY / Day Compressive Strength 1 test / 75CY / Day Temperature 1 test / 75CY / Day
Original Ground and Base of Cuts (Native Subgrade) Field Density/Moisture Content 1 test / 1,500 SF
SP-17 CONSTRUCTION STAKING
The CO/COR will provide horizontal control for the project consisting of stakes along the project baseline. Vertical control will be provided by benchmarks throughout the project site. All offset staking is the Contractors responsibility. The Contractor is required to provide a qualified surveyor to provide construction staking.
The COR shall provide the following staking consisting of stakes or hubs.
DustinFarren
• Vertical Control - Vertical control will be provided by benchmarks throughout the project site.
• Piping - Horizontal control will be given at each change in horizontal alignment, pipe termination, structure, valve and each fitting. Intermediate staking will be placed on centerline a minimum of every 200 feet.
• Structures and Manholes - Horizontal control will be given at the centerline of each new structure and manhole.
• Fence Corners and Gates.
Actual new main locations may vary from either side of the centerline of pipe as shown on the Drawings if it is required to avoid utilities, obstructions, pavement, etc. Since this will be to the benefit of the Contractor, no additional cost will be allowed the Contractor. COR will determine the actual locations of the new mains in the field.
SP-18 CONTRACT PERIOD SHUTDOWN
A shutdown due to inclement weather during the winter months may be requested by the Contractor.
Indicate the number of calendar days being requested in the original shutdown request. This initial request may be extended during the shutdown period as long as such extension is justifiable and requested at least 14 calendar days prior to the date the original extension was to elapse. Any extension of shutdown will require the Contractor to demonstrate that adequate operations can be maintained throughout the extended period. Shutdown extensions may require operation modifications and approval of the Montana DEQ. Only one winter shutdown will be granted during the project.
The Government reserves the right to approve or disapprove any shutdown or extension requests. As a condition of approval of a shutdown, close all open excavations, provide for maintaining traffic, and provide for protection of public property at the work site. The Contractor will not be allowed to perform any work during the shutdown period unless prior approval is granted by the Government.
SP-19 PERMITS
The Contractor is responsible for obtaining all necessary permits, licenses, agreements, insurance, and approvals required by any government authority or agency for the performance of this work at his own expense. Government will allow Contractor access, as appropriate and necessary, for obtaining data in regard to permits and, at its own discretion, may assist Contractor, when necessary, in obtaining such permits. These Permits may include but are not limited to the following:
1. Storm Water Discharge Permit. The work requires a General Permit for Storm Water
Discharges Associated with Construction Activities, and all discharges must be in accordance with the submitted Storm Water Pollution Prevention Plan (SWPPP). The` Contractor is required to develop a construction SWPPP and Erosion Control Plan for the project including submitting a complete Notice of Intent (NOI) package to the Montana Department of Environmental Quality. The Contractor will be responsible for all fees associated with the permit application. Any costs associated with a SWPPP will be part of the mobilization bid item.
2. Missoula County Excavation Permit. The Contractor must complete an excavation permit for the sewer force main to be placed in Munger Road. The permit application must be
DustinFarren Line
DustinFarren Line
DustinFarren submitted and approved prior to construction. The permit application can be obtained by calling the Missoula permit coordinator at (406) 258-3701. Submit approved permit to COR prior to beginning work.
3. Building Permit – As required for state, county and local agencies.
4. Electrical Permit – As required for state, local agencies.
SP-20 TEMPORARY PROJECT SIGNS
Construct and install a project sign in accordance with Section 00900: Funding Agency Special Provisions. The sign must acknowledge the Government and any others the CO deems necessary. Submit a proposed sign design in accordance with the referenced conditions, and the CO will fill in the applicable dollar amounts on the submittal and make any other comments or corrections at that time.
No separate payment will be made for this work. The cost of furnishing and installing the signs will be included in the mobilization Bid Item for the base bid.
SP-21 EASEMENTS, CONSTRUCTION LIMITS, AND RIGHT-OF-WAY
Conduct construction operations within the easement, construction limits, and right-of-way limits. Obtain written permission from the adjoining private landowner prior to conducting any operations off the allowed easement. Take care to protect, preserve and/or replace objects and structures encountered within the confines of the easements and restore all disturbed areas restored to the original condition unless otherwise dictated in these specifications.
Contractor is required to submit a haul route plan to the CO for review and approval prior to proceeding with construction. The limitations are specified to limit disturbances to the site to only those areas necessary to complete the work.
SP-22 WORKING HOURS
Regular working hours are defined as an eight-hour period (plus 1 hour lunch allotment) within the bounds of 7:00 AM and 7:00 PM. Work during other hours may be permitted following written approval of the Government. Contractor shall provide the CO a request at least three (3) working days prior to working other hours, or in excess of 8 hours per day. CO shall provide a response to the request within 24 hours of receipt. Emergency work may be done without prior permission.
SP-23 CONTRACTOR EMERGENCY CONTACT
Provide a primary and secondary 24-hour, 7-day a week emergency contact.
SP-24 SEEDING
Furnish a dry land pasture seed mixture below, to be placed around pasture in all disturbed areas (not including landscaped areas in community), and up the transmission main route.
The necessary bulk seed can be calculated by:
DustinFarren Line
DustinFarren Line
DustinFarren Line
DustinFarren Line
DustinFarren
DustinFarren
DustinFarren
DustinFarren Text Box
AMENDMENT: ADDED SPECIAL PROVISION
DustinFarren Line
DustinFarren Line
Line
DustinFarren
DIVISION 1
GENERAL REQUIREMENTS
SECTION 01010
SUMMARY OF WORK
SECTION 01010
SUMMARY OF WORK
PART 1 - GENERAL
1.1 DESCRIPTION
A. The Invitation to Bid contains a general description of the project work to be performed under this Contract. The Supplemental Conditions and Special Provisions and other documents contain additional information necessary to perform the work.
B. Replacement of the water distribution system serving the St Regis Work Center. The project includes new water main, and all associated valves, fittings, and blowoff hydrants to sanitary hydrants.
C. Replacement of the wastewater system serving the St Regis Work Center. The project includes new sewer collection mains, manholes, and service connections. The project also includes a new wastewater treatment system consisting of a new septic tank, a new main and a new pressure dosed drainfield. Abandonment of the existing septic tanks and lift station is also part of the project.
1.2 CONTRACT DOCUMENTS
A. Portions of the Contract Documents are written in the imperative mode. Except where specifically intended otherwise, the subject of all imperative statements is the Contractor.
For example, “Furnish...” means “Contractor shall furnish...”, “Provide” means Contractor shall provide...”. For imperatives specifically addressing the CO/Government, see paragraph 1.02, General Conditions.
B. Contract Documents are defined in Article 1, paragraph 1.01.A.13, General Conditions, as modified by Montana Public Works Standard Specifications, and any supplemental conditions.
C. The Contract Documents are intended to provide the basis for proper completion of the work suitable for the intended use of the Government. Comply with Article 3, General Conditions. Specifications and Drawings included in these contract documents establish the performance, quality requirements, location and general arrangement of materials and equipment, and establish the minimum standards for quality of workmanship and appearance. Anything not expressly set forth but which is reasonably implied or necessary for proper performance of the project shall be included.
D. The various portions of the Contract Documents, of which these specifications are a part, are essential parts of the Agreement, and a requirement occurring in any portion or part is binding as though occurring in all. All portions are intended to be complementary and to describe and provide for a complete work as referenced in Article 3, General Conditions.
Unless specifically noted otherwise, in the case of discrepancy the following hierarchy shall be observed:
1. Permits from County Departments and other agencies as may be required by law, which will govern over;
2. Change Orders, which will govern over;
3. Executed Agreement, which will govern over;
4. Addenda, which will govern over;
5. Special Provisions, which will govern over;
6. Divisions 1 through Division 16 Technical Specifications, which will govern over;
7. Standard Modifications to the Montana Public Works Standard Specifications, which will govern over;
8. Supplementary Conditions to the General Conditions, which will govern over;
9. General Conditions, which will govern over;
10. Drawings, which will govern over;
11. Contractor’s Bid, which will govern over;
12. Montana Public Works Standard Specifications Seventh Edition, April 2021, which will govern over;
13. Montana Department of Transportation Standard Specifications for Road and
Bridge Construction, which will govern over;
14. Reference Specifications, which will govern over;
With reference to Drawings, the order of precedence is as follows:
1. Addenda/Change Order Drawings govern over any other Drawings.
2. Figures govern over scaled dimensions.
3. Contract Detail Drawings govern over Contract General Drawings.
4. Contract Drawings govern over Standard Drawings
E. The bound copy of the Montana Public Works Standard Specifications, as distributed by the Montana Contractor’s Association, Inc., will govern as the legal set of these specifications over any unbound copy, or any CD-ROM or floppy disk versions
F. A requirement mentioned in one part/section of the Contract Documents shall be considered as having been mentioned in all parts/sections.
1.3 WORK SEQUENCE
A. Comply with paragraph 2.03, 2.05 and 4.04 of the General Conditions and Milestones specified in the Contract Documents.
B. Submit detail schedules as specified in the Contract Documents.
C. Field verify dimensions indicated on drawings before fabricating or ordering materials.
Do not scale drawings.
D. Notify Engineer/Government of existing conditions differing from those indicated on the drawings. Comply with paragraph 5.04, of the General Conditions and any Supplementary Conditions. Verify the existence and location of underground utilities along the route of the proposed work. Omission of an existing or previous abandoned utility location on the Drawings is not to be considered as its nonexistence. Inclusion of existing utility locations on the Drawings is not to be considered as its definite location.
Do not remove or alter existing utilities without prior written approval.
1.4 CONTRACTOR USE OF PREMISES
A. Comply with paragraph 5.02, General Conditions, and as specified in the Contract Documents.
B. Do not park vehicles or equipment or store materials on private property without written permission from the Government. Provide Engineer/Government with copy of authorization.
1.5 GOVERNMENTFURNISHED ITEMS
A. Government-furnished items are listed in the Contract Documents.
PART 2 - PRODUCT – NOT USED
PART 3 - EXECUTION – NOT USED
PART 4 - MEASUREMENT AND PAYMENT
4.1 PAYMENT
A. Unless specifically noted otherwise, the work of Division 1 shall be incidental to the work, and no separate payment shall be made.
END OF SECTION
SECTION 01050
FIELD ENGINEERING
SECTION 01050
FIELD ENGINEERING
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and Special Provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification Sections, apply to this Section.
1.2 SUMMARY
A. This Section includes general procedural requirements governing execution of the Work including, but not limited to, the following:
1. Construction layout.
2. Field engineering.
B. Related Sections include the following:
1. Division 1 Section "Submittals" for submitting surveys.
2. Division 1 Section "Contract Closeout" for submitting final property survey with
Project Record Documents, recording of Government -accepted deviations from indicated lines and levels, and final cleaning.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 CONSTRUCTION LAYOUT
A. Verification: Before proceeding to lay out the Work, verify layout information shown on Drawings, in relation to the property survey and existing benchmarks. If discrepancies are discovered, notify CO promptly.
B. General: Engage a land surveyor to lay out the Work using accepted surveying practices.
1. Establish benchmarks and control points to set lines and levels.
2. Establish dimensions within tolerances indicated. Do not scale Drawings to obtain required dimensions.
3. Inform installers of lines and levels to which they must comply.
4. Check the location, level and plumb, of every major element as the Work progresses.
5. Notify CO when deviations from required lines and levels exceed allowable tolerances.
6. Close site surveys with an error of closure equal to or less than the standard established by authorities having jurisdiction.
SECTION 01050
FIELD ENGINEERING
C. Site Improvements: Locate and lay out site improvements, including pavements, grading, fill and topsoil placement, utility slopes, and invert elevations.
D. Record Log: Maintain a log of layout control work. Record deviations from required lines and levels. Include beginning and ending dates and times of surveys, weather conditions, name and duty of each survey party member, and types of instruments and tapes used. Make the log available for reference by CO.
3.2 FIELD ENGINEERING
A. Identification: Government and CO will identify existing benchmarks, control points, and property corners to the best of his knowledge. The Contractor will have the ultimate responsibility to locate, recognize and preserve all of these that are encountered.
B. Retain a licensed land surveyor, at the Contractor’s expense, to replace any survey corners, property pins, or highway right-of-way monuments removed or damaged during construction.
C. Reference Points: Locate existing permanent benchmarks, control points, and similar reference points before beginning the Work. Preserve and protect permanent benchmarks and control points during construction operations.
1. Do not change or relocate existing benchmarks or control points without prior written approval of CO. Report lost or destroyed permanent benchmarks or control points promptly. Report the need to relocate permanent benchmarks or control points to CO before proceeding.
2. Replace lost or destroyed permanent benchmarks and control points promptly.
Base replacements on the original survey control points.
D. Benchmarks: Establish and maintain a minimum of two permanent benchmarks on Project site, referenced to data established by survey control points. Comply with authorities having jurisdiction for type and size of benchmark.
1. Record benchmark locations, with horizontal and vertical data, on Project Record
Documents.
2. Where the actual location or elevation of layout points cannot be marked, provide temporary reference points sufficient to locate the Work.
3. Remove temporary reference points when no longer needed. Restore marked construction to its original condition.
PART 4 - MEASUREMENT AND PAYMENT (Not Used)
SECTION 01275
MEASUREMENT AND PAYMENT
SECTION 01275
MEASUREMENT AND PAYMENT
PART 1- GENERAL
1.1 MEASUREMENT AND PAYMENT
A. Measurement and payment for contract work will be made only for and under those pay items included in the SCHEDULE OF ITEMS. All other work and materials will be considered as included in the payment for items shown.
1.2 QUANTITY MEASUREMENT
A. The Contractor shall make all measurements for computation of quantities for all work items except those specified for payment by Actual Quantity (AQ) or Lump Sum Quantity (LSQ).
B. The contractor shall compute the quantities for periodic progress payments; the Contracting Officer shall compute the quantities for the final payment based on measurements taken by the Contractor.
C. All Contractor measurements are subject to verification.
D. The Contractor shall submit all field notes, calculation sheets, and other data used to determine quantities.
E. The Contractor shall certify in writing as to the accuracy of the measurements and computations submitted.
1.3 METHODS OF MEASURE AND UNITS OF MEASUREMENT
A. One of the following methods for measurement for determining final payment is DESIGNATED on the SCHEDULE OF ITEMS for each pay item;
1. Actual Quantities (AQ): Estimated quantities which are determined from actual measurements of completed work.
2. Linear Feet (LF): Linear feet measured horizontally.
3. Lump Sum Quantity (LSQ) – These quantities denote one complete unit of work as required by or described in the contract including necessary materials, equipment, and labor to complete the job. They will not be measured.
4. Each: One complete unit, which may consist of one or more parts.
1.4 BID ITEMS
A. Bid Item No. 01010-1 - MOBILIZATION
1. Description: This item is intended to compensate the Contractor for operations including, but not limited to, those necessary for the movement of personnel, equipment, supplies, and incidentals to the project site; for payment of premiums for bonds and insurance for the project; and for any other work and operations which must be performed or costs that must be incurred incident to the initiation of meaningful work at the site and for which payment is not otherwise provided for under the contract.
2. Work Required: Work required under this section includes but is not limited to the following.
a. The movement of personnel, equipment, supplies and incidentals to the project site;
b. The establishment of all facilities necessary for the work on the project;
c. The costs of obtaining the required permits, bonds, and insurance; and
d. All other work and operations which must be performed, or costs incurred prior to beginning work on the various items of the project.
3. Unit of Measurement: Lump Sum
4. Measurement: Measurement for MOBILIZATION will be made as a percentage completed of the lump sum. The total amount of premiums paid by the Contractor to obtain performance and payment bonds will be paid at one time together with the first progress payment otherwise due. When 5 percent of the total original contract amount is earned from other schedule items, 50 percent of the amount bid for mobilization will be paid, exclusive of any amount already paid the Contractor for performance and payment bond premiums. When 10 percent of the total original contract amount is earned from other schedule items, the balance of the amount bid for mobilization will be paid.
5. Payment: Payment for MOBILIZATION will be made at the contract unit price bid as a lump sum.
B. Bid Item No. 01172-1 – CONSTRUCTION SURVEY AND STAKING
1. Description: This item includes providing construction survey and staking necessary for construction of the project as shown in the Contract Documents.
2. Work Required: Work required under this section includes but is not limited to the following.
a. Provide personnel, equipment and supplies required for construction layout and reference staking necessary for the proper control and satisfactory completion of all structures, pipelines and other appurtenances required for the completion of the work and acceptance of the project; and
b. All incidental materials, tools, equipment, and labor for the completion of this item.
3. Unit of Measurement: Lump Sum
4. Measurement: Measurement for CONSTRUCTION SURVEY AND STAKING will be made as a percentage completed of the lump sum. 50% of the lump sum will be credited to the first progress payment, with the second 50% being credited to subsequent progress payments in proportion to total construction completed as a percentage of the contract unit price.
5. Payment: Payment for CONSTRUCTION SURVEY AND STAKING will be made at the contract unit price bid as a lump sum.
C. Bid Item No. 02050-(1-2) – ABANDON EXISTING SEPTIC TANK AND LIFT
STATION
1. Description: This item includes abandonment of the existing septic tank and lift station once the new treatment system is in operation. The existing structures shall be pumped out, filled with pea gravel, and then covered with fill, seeded and restored to the natural contours. The existing lids and risers shall be removed and disposed of by the Contractor.
2. Work Required: Work required under this section includes but is not limited to the following.
a. Removal and disposal of the existing lids and risers;
b. Pumping out the existing septic tank and lift station;
c. Filling the structures with pea gravel;
d. Placing fill over the tank footprints, seeding and grading to restore natural contours; and
e. All labor, tools, equipment, materials, royalties, and incidentals necessary to complete the work as specified.
3. Unit of Measurement: Lump Sum
4. Measurement for ABANDON EXISTING SEPTIC TANK AND LIFT
STATION will be by lump sum.
5. Payment: Payment for ABANDON EXISTING SEPTIC TANK AND LIFT
STATION will be made at the contract unit price bid per lump sum as indicated in the Bid Form.
D. Bid Item No. 02221-1 – TYPE B SURFACE RESTORATION
1. Description: This item includes the surface restoration for trench excavations in graveled areas.
2. Work Required: Work required under this section includes but is not limited to the following.
a. Furnishing and installing aggregate surface course (as detailed); and
b. All labor, tools, equipment, materials, royalties, and incidentals necessary to complete the work as specified.
3. Unit of Measurement: Lineal Foot.
4. Measurement: Measurement for TYPE B SURFACE RESTORATION will be made per lineal foot measured along the centerline of the trench excavation.
5. Payment: Payment for TYPE B SURFACE RESTORATION will be made at the contract unit price bid per lineal foot. The limits for payment extend 6 feet either side of the trench excavation centerline. Areas disturbed outside of the payment limits must be restored at the Contractor’s expense.
E. Bid Item No. 02221-2 – TYPE C SURFACE RESTORATION
1. Description: This item includes the surface restoration for trench excavations, sod will be required in lawn areas and reseeding is acceptable in native grass areas.
2. Work Required: Work required under this section includes but is not limited to the following.
a. Restoring, reseeding, and fertilizing any disturbed areas;
b. All labor, tools, equipment, materials, royalties, and incidentals necessary to complete the work as specified.
3. Unit of Measurement: Lineal Foot.
4. Measurement: Measurement for TYPE C SURFACE RESTORATION will be made per lineal foot measured along the centerline of the trench excavation.
5. Payment: Payment for TYPE C SURFACE RESTORATION will be made at the contract unit price bid per lineal foot. The limits for payment extend 8 feet either side of the trench excavation centerline. Areas disturbed outside of the payment limits must be restored at the Contractor’s expense.
F. Bid Item No. 02232-1 – CLEARING AND GRUBBING
1. Description: This item includes removing and disposing of the trees and scrubs as indicated on the Drawings and in the Contract Documents.
2. Work Required: Work required under this section includes but is not limited to the following.
a. Traffic control;
b. Removing all trees and shrubs called out on the Drawings;
c. Disposing of all removed trees and resultant debris; and
d. All labor, tools, equipment, materials, royalties, and incidentals necessary to complete the work as specified.
3. Unit of Measurement: Lump Sum
4. Measurement: Measurement for CLEARING AND GRUBBING will be made as a percentage completed of the lump sum.
5. Payment: Payment for CLEARING AND GRUBBING will be made at the contract unit price bid as a lump sum.
G. Bid Item No. 02536-1 – 120 VOLT GRINDER PUMP
1. Description: This item includes furnishing and installing sanitary sewer grinder pump service units as indicated on the Drawings and in the Contract Documents.
Each unit will consist of a grinder pump station complete with anchor, controls, electrical service to operate the pump and alarms, breakers or fuses as needed to connect to the residential power supply, conduit, control panel, valving and appurtenances.
2. Work Required: Work required under this section includes but is not limited to the following.
a. Excavation, backfill, and compaction;
b. Dewatering, sheeting, and shoring required for installation;
c. Providing submittals for materials;
d. Furnishing and installing all fittings and pipe necessary to provide a fully operational grinder pump unit;
e. Furnishing the packaged Grinder Pump Service Unit;
f. Furnishing all spare parts required;
g. Furnishing manufacturer factory trained technician(s) for startup and testing services;
h. Furnishing and installing all electrical components for operation and connections;
i. Installing per manufactures recommendations
j. Furnish and install connection for pressure pipe;
k. Furnish and install anti-floatation collar;
l. Furnish all required installation hardware;
m. Furnishing and installing grinder pump housing;
n. Furnishing and installing pipe bedding;
o. Performance testing;
p. Electrical subcontractor services and electrical permits; and
q. All labor, tools, equipment, materials, royalties, and incidentals necessary to complete the work as specified.
3. Unit of Measurement: Each
4. Measurement: Measurement for 120 VOLT GRINDER PUMP will be made by numerical count.
5. Payment: Payment for 120 VOLT GRINDER PUMP will be made at the contract unit price bid per each.
H. Bid Items No. 02665-(1-2) –HDPE WATER LINE
1. Description: HDPE water line in sizes and classes indicated on the drawings and in the contract documents.
2. Work Required: Work required under this section shall include but not be limited to the following:
a. Excavation and backfill;
b. Dewatering, sheeting, and shoring required for installation;
c. Furnishing and installing pipe and fused joints;
d. Furnishing and installing appropriate detection wire;
e. Testing, cleaning and disinfecting;
f. All labor, tools, equipment, materials, royalties, and incidentals necessary to complete the work as specified.
3. Unit of Measurement: Lineal Foot.
4. Measurement: HDPE WATER LINE will be measured per lineal foot along the centerline of the pipe through all valves, fittings, and appurtenances as indicated in the Bid Form.
5. Payment: Payment will be made at the contract price bid per lineal foot of the various sizes and classes of HDPE WATER LINE indicated in the Bid Form and shall include the cost of trench excavation, pipe bedding and backfill.
I. Bid Item No. 02660-1 – 1” POLYETHYLENE (PE) WATER SERVICE LINE:
1. Description: PE water service line in sizes and classes indicated on the drawings and in the contract documents. Service line installation shall be by: 1) Removing pavement and/or gravel, trench excavation, line installation, trench backfill, and pavement and/or gravel restoration; or 2) Pushing or pulling the service line (method to be approved by Engineer) without destruction to surfacing; or 3) Combination of 1 and 2 or other method approved by the Engineer.
2. Work Required: Work required under this section shall include but not be limited to the following:
a. Traffic control;
b. Excavation and backfill;
c. Dewatering, sheeting, and shoring required for installation;
d. Furnishing and installing bedding;
e. Testing, cleaning and disinfecting;
f. Pushing or pulling service lines if applicable;
g. Furnishing and installing polyethylene service line;
h. Surface restoration (pavement and/or gravel)
i. All labor, tools, equipment, materials, royalties, and incidentals necessary to complete the work as specified.
3. Unit of Measurement: Per Lineal Foot.
4. Measurement: Measurement for POLYETHYLENE (PE) WATER SERVICE
LINE will be measured per lineal foot along the centerline of the pipe through all valves, fittings, and appurtenances as indicated in the Bid Form.
5. Payment: Payment will be made at the contract price bid per lineal foot for the various sizes and classes of POLYETHYLENE (PE) WATER SERVICE LINE as indicated in the Bid Form and shall include the cost of trench excavation, pipe bedding, backfill and surface restoration.
J. Bid Item No. 02660-4 –GATE VALVE WITH VALVE BOX
1. Description: Gate valves with valve boxes in sizes indicated on the drawings and in the contract documents.
2. Work Required: Work required under this section shall include but not be limited to the following:
a. Traffic control;
b. Additional excavation, bedding, backfill and compaction;
c. Furnishing and installing the gate valve and box;
d. Additional couplings required;
e. Dewatering, sheeting, and shoring required for installation;
f. Thrust and anchor blocking;
g. Furnishing and installing polyethylene wrap;
h. Disinfection and testing;
i. All labor, tools, equipment, materials, royalties, and incidentals necessary to complete the work as specified.
3. Unit of Measurement: Each.
4. Measurement: GATE VALVE WITH VALVE BOX will be measured per each for each size of gate valve specified. Auxiliary gate valves and boxes associated with fire hydrants will not be measured and paid for separately, but shall be included in the costs of installing six-inch fire hydrants.
5. Payment: Payment will be made at the contract unit price bid for each size and type of GATE VALVE WITH VALVE BOX as specified in the Bid Form.
K. Bid Items No. 02660-(5, 9-10) – FITTINGS
1. Description: This item shall include furnishing and installation of all appropriate tees, bends and reducers as per the Drawings and Contract Documents.
2. Work Requirement: Work required under this section shall include but not be limited to the following:
a. Additional excavation, bedding, backfill and compaction, dewatering, sheeting, and shoring required for installation;
b. Furnishing and installing each fitting;
c. All labor, tools, equipment, materials, royalties, and incidentals necessary to complete the work as specified.
3. Unit of Measurement: Each.
4. Measurement: FITTINGS will be measured per each for each size of fitting.
5. Payment: Payment will be made at the contract unit price bid per each size of
FITTINGS as specified in the Bid Form.
L. Bid Item No. 02660-6 – CURB VALVE WITH VALVE BOX
1. Description: Curb valves with valve boxes in sizes indicated on the drawings and in the contract documents.
2. Work Required: Work required under this section shall include but not be limited to the following:
a. Trench excavation, bedding, backfill, and compaction;
b. Dewatering, sheeting, and shoring;
c. Furnishing and installing curb valves and boxes;
d. Disinfection and testing;
e. Furnishing and installing fittings to connect new service lines to existing service lines; and
f. All labor, tools, equipment, materials, royalties, and incidentals necessary to complete the work as specified.
3. Unit of Measurement: Each.
4. Measurement: Measurement for CURB VALVE WITH VALVE BOX will be measured per each for the various types and sizes listed in the Bid Form.
5. Payment: Payment will be made at the contract unit price bid per each type and size of CURB VALVE WITH VALVE BOX as specified in the Bid Form.
M. Bid Item No. 02660-7 –SANITARY HYDRANT W/ BACKFLOW PREVENTER
1. Description: This section shall include new sanitary/ frost-free hydrants tied into the new mains.
2. Work Required: Work required under this section shall include but not be limited to the following:
a. Dewatering, sheeting, and shoring;
b. Excavation, bedding, backfill and compaction around the hydrant;
c. Furnishing and installing new frost-free hydrants equipped with backflow preventer;
d. All labor, tools, equipment, materials, royalties, and incidentals necessary to complete the work as specified.
3. Unit of Measurement: Per Each.
4. Measurement: SANITARY HYDRANT W/ BACKFLOW PREVENTER will be measured per each and shall include all work and materials needed for installation, including furnishing and installing all necessary couplings and fittings.
5. Payment: Payment will be made at the contract unit price bid per each for
SANITARY HYDRANT W/ BACKFLOW PREVENTER.
N. Bid Item No. 02260-8 – REMOVE EXISTING FIRE HYDRANTS
1. Description: Existing fire hydrants will be abandoned and removed as indicated on the Drawings.
2. Work Required: Work required under this section shall include, but not be limited to the following:
a. Traffic Control;
b. Stripping and replacing gravel or pavement;
c. Trench excavation, backfill and compaction;
d. Dewatering, sheeting, and shoring;
e. Removing the fire hydrant and gate valve;
f. Plugging the existing pipe;
g. All labor, tools, equipment, materials, royalties, and incidentals necessary to complete the work as specified.
3. Unit of Measurement: Each.
4. Measurement: REMOVE EXISTING FIRE HYDRANT will be measured per each regardless of size.
REMOVE EXISTING FIRE HYDRANT as indicated in the Bid Form.
O. Bid Item No. 02660-11 –BLOWOFF HYDRANT
1. Description: This section shall include new blowoff hydrants tied into the new mains.
2. Work Required: Work required under this section shall include but not be limited to the following:
a. Dewatering, sheeting, and shoring;
b. Excavation, bedding, backfill and compaction around the hydrant;
c. Furnishing and installing new blowoff hydrants and pipe;
d. Connection to water main;
e. Furnishing and installing drain gravel;
f. All labor, tools, equipment, materials, royalties, and incidentals necessary…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .