This is a Questions and Answers document for a federal construction contract solicitation issued by the Lolo National Forest for water and wastewater improvements at Ninemile and St. Regis facilities (Solicitation 1240LU26Q0010, dated 02/18/2026). The document addresses ten clarifying questions submitted by potential bidders regarding contract administration, insurance, bonding, and documentation requirements.
Key contractual details include: work must commence upon contract award, receipt of bonds, and issuance of notice to proceed, with all work completed by October 1, 2027; no liquidated damages apply to the contract; no set milestone deadlines exist, but contractors must maintain functioning water and wastewater systems throughout performance except during pre-approved interruption windows requiring two days' advance notice to the Contracting Officer; insurance requirements are governed by Montana state law per FAR 52.236-7; there are no DBE participation goals; and disputes are subject to the Contract Disputes Act (41 U.S.C. Chapter 71). The contract is issued under FAR Part 12 with incorporated Montana Public Works Standard Specifications, with FAR 52.212-4(r) Order of Precedence controlling any inconsistencies. Bidders must submit five project narratives with quotations, with additional contractor and subcontractor qualifications required after award. Bid bonds must be submitted using FAR Standard Form 24. CAD files are not provided during the solicitation phase but may be supplied to the successful contractor after award.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Ninemile Water & Wastewater and St. Regis Wastewater Improvements Lolo National Forest, Solicitation: 1240LU26Q0010
02/18/2026
Submitted questions and answers:
1. Q: Insurance Requirements - Could you please confirm the required insurance limits (general liability, automobile, umbrella, workers compensation) and whether those requirements will be included in the award document? A: Per 52.236-7 Permits and Responsibilities located in the solicitation, contractor must comply with state laws which will govern insurance requirements.
2. Q: Liquidated Damages - Are liquidated damages applicable to this contract? If so, could you confirm the daily rate and whether specific milestone or substantial completion dates will be identified? A: There are no liquidated damages associated with this contract.
3. Q: Contract Performance Period - Could you please confirm the anticipated contract duration and whether milestone deadlines will be established at award? A: The contractor may begin work as soon as contract is awarded and after receipt of bonds and issuance of notice to proceed. All work shall be complete by October 1, 2027.
There are not any set milestone deadlines, but the contractor must ensure water and wastewater systems are functioning throughout the life of the contract, except for short, pre-approved windows. See 01730 – 3.1B and 02232 – 3.3C Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated: 1. Notify Contracting Officer not less than two days in advance of proposed utility interruptions. 2. Do not proceed with utility interruptions without Contracting Officer's written permission.
4. Q: Warranty Period - Will the warranty be governed by FAR 52.246-21 (Warranty of Construction), or should we follow the warranty period referenced within the incorporated Montana Public Works Standard Specifications? A: The warranties are the same but the government will follow FAR 52.212-4 (r) Order of precedence.
5. Q: DBE Requirements - Are there any DBE participation goals or reporting requirements associated with this procurement? A: No there are no DBE participation goals.
6. Q: Dispute Resolution - In the event of a dispute, should we assume the contract will be administered under the Contract Disputes Act and applicable FAR clauses, or are there additional dispute resolution provisions we should be aware of? A: Per 52.212- 4 (e) Disputes this contract is subject to 41 U.S.C. chapter 71, Contract Disputes.
7. Q: Experience and Qualification Submittals - The Ninemile Technical Specifications reference providing contractor and subcontractor qualifications within five (5) days of request under MPWSS Articles 3.1 and 6.06, while the solicitation instructions require submission of five (5) project narratives with the quotation.
To ensure we provide the appropriate documentation at the correct time, could you please confirm:
Whether only the five (5) project narratives are required with the quotation; and
Whether the additional qualification and subcontractor information would be requested after award or during responsibility review?
A: The 5 project narrative is required as part of the quotation and the additional qualifications are required after award.
8. Q: Bid Bond Form - Should the bid guarantee be submitted using the FAR Standard Form 24 (SF 24) consistent with FAR 52.228-1, or is a specific Montana Public Works bond form preferred? A: Submit bid bond on the SF24.
9. Q: Contractual Hierarchy - Since the solicitation is issued under FAR Part 12 while incorporating the Montana Public Works Standard Specifications, we would appreciate confirmation on how any potential inconsistencies between those documents should be interpreted. A: The government will follow FAR 52.212-4 (r) Order of precedence.