Site tour_Questions1-2_Answers.pdf

PDF 231 KB Posted

Attached to
Flathead National Forest - Condon Bunkhouse Maintenance Repairs
Solicitation number
1240LU26Q0007
Issued by

About this file

This is a Site Inspection Tour/Prebid Conference Record dated January 22, 2026, for Solicitation No. 1240LU26Q0007 regarding Condon Bunkhouse Maintenance Repairs. The meeting was conducted at the Condon Work Center by Patrick Siers (COR) and was attended by 18 total prospective bidders representing companies including Big Sky Health, Retail, Semper Fi, Copper Creek, Mr. Remodel, Red Bear, and Bold Construction, among others. The bidders represent diverse locations including Warnock, Dalco, Blackhawk, Bernardo, and MasterStream, with various construction and maintenance entities listed.

The conference record documents two preliminary questions and answers relevant to contract scope. Q1 addressed whether contractors are responsible for repairing imperfections in existing drywall, with affirmative confirmation that painting preparation includes repairing drywall damage. Q2 addressed whether bunkhouse door jambs with damaged mortises must be repaired, with the answer clarifying that door jambs will not be replaced or the modified door trim will not be modified. The document indicates that additional questions were continued on the next page. A complete site inspection tour was conducted, and the record was signed by Patrick K Siers on January 22, 2026.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SITE INSPECTION lOUR/PREBtD CONFERENCE RECORD

L /,QliC1tnion No: 1-;2.40LU;2.1oQ0007•

4. �e�in/; Place: CovtdOVt Wovk Cevttev

2. :i1lc:

CoVldOVl 13UVlkhouse MaiV<teVlaVlCe Repairs 5. Cc,nfo,�•� O} Na!lt., /',. Til\t: Patrick Sievs

3. Dote & ·nmo: JaVtUtWy ;2.;2., ;2.O;2.io 1-1-aW\

7. At'cnded By: IArtach Stpora•· S»etr. if 1/e,·c,,,_,r)/

N.smc and finu Addn::.s� .f·ncrudc: lip <:ode} Phone No.

5ndud, =• ,,..,/,)

Big Sk9 Health, Redtai/, , War"'ock, Daleo, BlackJ.tawk, Ber"'ardo, MasterStreal'I

406 Mai"'te"'a"'ce, 1-MT CustoW\ Co"'structio,,, SeW1per Fi, Copper Creek, Mr. ReW1odel, Red Bear, HoW1e 1-ow"', A(/ied CiSD, Rustic Mo"'ta"'a Co;,,.stn,ctio ", Bold co ... structio"', Mo"'ta"'a Builders

1-8 Total Pevs,:,ectiv 13iddevs

Q1:ts a Covttvactov vespovtsible to vepaiv i1Mpev-Fectiovts ivt existivtg Dvfi wall? ANs: Yes, Paivttivtg pvepavatiovt ivtcludes vepaivivtg tltle DV"!::J wall da1Mage.

Q2: 13uvtk!tlouse door- ja1Mbs ltlave da1Maged Mortises W\uSt tltle.y be vepaived? Avts: No, dovt't plavt to veplace door- jalMbS OV" tltle W\Odifiel'doov tV"iW\.

See questiovts covttivtued Ovt vtext page.

By {Nam:)

-p�vic/4 K ��

I Tille

COR

co

01/22/2026