This document is a Questions and Answers (Q&A) file for the Herman Gulch Toilet Replacement project in the Arapaho & Roosevelt National Forests & Pawnee National Grassland. The document addresses two key questions from a potential contractor: the project's start date and bonding requirements. The Forest Service indicates flexibility with the start date but prefers conducting the installation in the fall, acknowledging the 120-150 day lead time for the toilet. The agency also confirms that both a bid and performance bond will be required for the project.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1) Does the Department of Agriculture have a start date in mind? This is very relevant because

a) of the potential weather in Colorado and b) because the lead time for the toilet is 120-150 days.

A: The Forest Service is aware of the lead time for the toilet. We are flexible with the start date but would prefer to conduct the install in the fall.

2) To confirm; we need to have a bid and performance bond for this project?

A: Yes