This performance work statement outlines inventory, relocation, and wrapping services for two sets of Generation 2 C-130 maintenance stands. The contractor shall unwrap and verify the contents of packages from Lot 2 of the Defense Logistics Agency storage area at Hill Air Force Base in Utah. The stands shall be relocated to the Base Operations and Readiness Area east of the runway and wrapped for long-term outdoor storage. The contractor must provide all necessary personnel, equipment, materials, and documentation to move, group, shrink wrap with vents and desiccants, and label the stands to withstand three years of weathering. The related solicitation was issued by the Air Force Sustainment Center to obtain these firm fixed price inventory, relocation, and wrapping services as specified in the performance work statement.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SPECIFICATIONS/REQUIREMENTS
DESCRIPTION OF SERVICES
The Contractor shall unwrap and verify the contents of each package of two (2) sets of Gen 2 C‐130 maintenance stands. The Contractor shall next move the two (2) sets of Gen 2 C‐130 maintenance stands from their current location in Lot 2 of Defense Logistics Agency (DLA) storage area at Hill Air
Force Base, Utah, to the Base Operations and Readiness Area, (BORTA) area east of the runway designated in figure 1 for long‐term storage. The Contractor shall group all final packages as units such that each unit can be accessed and moved without moving the other unit. Next, the Contractor shall completely shrink wrap all stand sections and associated equipment and shall include moisture vents and desiccants to protect them from corrosion, or provide equivalent equipment protection. Finally, the
Contractor shall label all final packages with the unit identifiers.
TECHNICAL REQUIREMENT
The Contractor shall provide all personnel, transportation, rigging, equipment, shrink wrap materials and equipment, supervision, and all other items necessary to move two (2) sets of Gen 2 C‐130 maintenance stands from their current location in Lot 2 to the BORTA area east of the runway, as designated in Figure 1, for long term storage. The Contractor shall wrap and label as specified in section
2 of this Performance Work Station (PWS).
Any diagrams and drawings provided with this PWS are conceptual drawings to describe the requirement. The Government reserves the right to clarify the drawings, as necessary, to ensure the requirements can be met.
Unwrapping and Removal
The Contractor shall unwrap and verify the contents of each package from the documents below in appendix B for C7 and C8 Gen 2 Stands prior to moving.
The Contractor shall work with the Government Program Manager (GPM) to inspect the sections and record any damage prior to the move.
The Contractor shall ensure all tubing ends are capped to prevent debris/contamination from entering before moving.
The Contractor shall verify and document all package contents and protect stands from damage during moving.
The Contractor shall remove two (2) sets of Gen 2 stands from lot 2 just west of the
Commissary (Bldg. 400) at Hill Air Force Base, Utah, to the Base Operations and
Readiness Area, (BORTA) area east of the runway.
Placement and Wrapping
The Contractor shall remove two (2) sets of Gen 2 stands from lot 2 just west of the
Commissary (Bldg. 400) at Hill Air Force Base, Utah, to the Base Operations and
Readiness Area, (BORTA) area east of the runway.
The Contractor shall group all final packages as a unit (namely, C7 or C8), and shall place the units in such a way that each unit can be accessed and moved without moving the other unit.
The Contractor shall completely shrink wrap all stand sections and associated equipment and shall include moisture vents and desiccants, or provide equivalent equipment protection to protect them from corrosion. Stand protection should be designed to withstand the impacts from strong canyon winds, wet weather, and the sun for at least three (3) years.
The Contractor shall label all final packages with the unit identifiers (namely, C7 or C8).
The stands shall be labeled similar to the markings designated in the log tracking documents in section 2.1.1. Changes to the contents of the packages is not recommended, but shall be noted in the final tracking log, with the exception of adding end caps; this includes any changes to the Fire Suppression system, air lines, fuel ventilation system (FVS), electrical on the stands, and existing fall arrest systems.
The Contractor shall create and maintain a log or bill of materials similar to those provided in appendix A of the PWS (Performance Work Statement) that identifies the contents and placement of each package at the BORTA location.