12-26-296 Bid Schedule Worksheet.xlsx

XLSX spreadsheet 17 KB Posted

Attached to
IFB - GEORGE WASHINGTON BLVD CONSTRUCTION - Virgin River Bridge to River Road
Solicitation number
26-296
Issued by
Washington County, Utah

About this file

This is a Bid Schedule Worksheet for the City of St. George, Utah, related to the IFB for George Washington Boulevard construction from the Virgin River Bridge to River Road. The worksheet serves as a detailed pricing and scheduling document that bidders must complete as part of their proposal submission. The document outlines the specific line items, quantities, and unit pricing that contractors must bid on for the various construction phases and components of this public infrastructure project. Bidders are required to provide detailed cost breakdowns for labor, materials, equipment, and other associated costs for each identified work item on the schedule.

All bids must be accompanied by a bid bond equal to 5% of the total bid amount, issued by a surety company licensed in Utah and acceptable to the City of St. George. One hundred percent payment and performance bonds will be required upon contract award. The City of St. George reserves the right to reject any or all proposals or waive any formality or technicality as deemed in the city's interest. Bidders should refer to the complete bid documents and specifications to accurately complete all pricing schedules and ensure compliance with all bonding, insurance, and contractual requirements established by the municipality.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

26-269 Bid Schedule WORKSHEET
George Washington Blvd - Virgin River Bridge to River Road

Schedule A

Item No.Item DescriptionQuantityUnitUnit PriceTotal
1Mobilization1Lump
2SWPPP, Traffic Control, and Site Access1Lump
3Maintain Existing Trail Access1Lump
4Construction Limits Fence14,000Ln Ft
5Clear and Grub21.0Acre
6Earthwork - General59,392Cu Yd
7Earthwork - Structural Fill for MSE Wall1,616Cu Yd
8Settlement Monuments4Each
9Remove Existing Roadway Asphalt17,478Sq Ft
10Remove Existing Curb and Gutter527Ln Ft
11Remove Existing Concrete Sidewalk2,878Sq Ft
12Remove Existing Trail Asphalt15,637Sq Ft
13Remove Existing Landscaping8,254Sq Ft
14Remove Existing Rock Rip-Rap1Lump
15Remove Existing Sewer Manhole1Each
16Remove Existing Curb Inlet Catch Basin4Each
17Remove Existing 24" Poly Storm Drain Pipe28Ln Ft
18Remove Existing 15" Poly Storm Drain Pipe61Ln Ft
19Remove Existing Roadway Striping1Lump
20Remove and Replace Pedestrian Signal1Each
21Asphalt - 6 1/2" Depth311,536Sq Ft
22Asphalt and Base Within Existing 1450 S - Match Existing Section22,879Sq Ft
23Trail Asphalt - 2 1/2" Depth28,774Sq Ft
24Asphalt Seal Coat28,774Sq Ft
25Type II Road Base - 10" Depth311,536Sq Ft
26Type II Road Base - 6" Depth43,332Sq Ft
27Type I Sub-Base - 12" Depth311,536Sq Ft
282" Angular Washed Rock189Cu Yd
29Tensar NX650 Geogrid567Sq Yd
3030" HB Curb & Gutter10,503Ln Ft
31Concrete Sidewalk - 4" Depth25,103Sq Ft
32Driveway Approach6Each
33ADA Accessible Ramp8Each
34Roadway Striping31,940Ln Ft
35Roadway Stop Bars, Cross Walks, and Turn Arrow Markings1Lump
36Trail Striping2,867Ln Ft
37Steel Fence - 5' Height3,544Ln Ft
3816' Steel Gate - 5' Height3Each
3912' Steel Gate - 5' Height2Each
404-Strand Barbed Wire Fence1,369Ln Ft
41Precast Block Retaining Wall - 28" Depth3,074Sq Ft
42Bridge Abutments2Each
43Concrete Wingwalls4Each
4414 X 102 HP-Piles450Ln Ft
45Install 95' Pedstrian Bridge (Furnished by Owner)1Lump
4642" Safety Rail - Baseplate Bolted to Concrete56Ln Ft
4742" Safety Rail - In-Ground Concrete Footings164Ln Ft
48Rock Rip-Rap (D50 = 30")8,670Cu Yd
49Gabion Basket Erosion Protection3,586Cu Yd
50Temporary Diversion Channel681Ln Ft
5124" Poly Storm Drain Pipe462Ln Ft
5218" Poly Storm Drain Pipe941Ln Ft
5315" Poly Storm Drain Pipe81Ln Ft
54Single Curb Inlet Catch Basin11Each
5560" Storm Drain Manhole4Each
56Connect to Existing 24" Poly Storm Drain Pipe1Each
57Connect to Existing 18" Poly Storm Drain Pipe2Each
58Connect to Existing 15" Poly Storm Drain Pipe1Each
59Connect to Existing Curb Inlet Catch Basin1Each
60Connect to Existing Storm Drain Manhole1Each
614' X 4' Catch Basin1Each
6230" PVC Sanitary Sewer Line - Within New Roadway3,908Ln Ft
6330" PVC Sanitary Sewer Line - Within Existing 1450 S.958Ln Ft
6424" PVC Sanitary Sewer Line37Ln Ft
658" PVC Sanitary Sewer Line70Ln Ft
6672" Polymer Sanitary Sewer Manhole1Each
6760" Polymer Sanitary Sewer Manhole20Each
68Connect to Existing Sanitary Sewer Manhole1Each
69Raise/Lower and Collar Existing Sanitary Sewer Manhole1Each
70Joint Utility Trench5,415Ln Ft
711D Fiber Optic 4-Conduit Bundle5,835Ln Ft
72Street Lights16Each
73Locate Irrigation Line and Protect in Place1Lump
74Locate 3 Phase Direct Bury Power Line and Protect in Place1Lump
7512" C900 Conduit - Future Utility130Ln Ft
768" C900 Conduit - Future Utility260Ln Ft
776" C900 Conduit - Future Utility94Ln Ft
7824" C905 Water Line4,996Ln Ft
798" C900 Water Line1,705Ln Ft
8012" C900 Irrigation Line1,016Ln Ft
8124" Butterfy Valve6Each
828" Gate Valve5Each
8312" Irrigation Butterfly Valve1Each
848" Water Line Tee1Each
858" Water Line Cross1Each
868" Water Line 90° Bend1Each
8712" Irrigation Line 90° Bend1Each
88Relocate Water Meter2Each
89Fire Hydrant Assembly6Each
90Connect to Existing 24" Water Line1Each
91Connect to Existing 8" Water Line1Each
92Connect to Existing 12" Irrigation Line1Each
93Add UDOT Type III Signal Head to Existing Signal Mast Arm1Each
94Trail Signage20Each
95Install Trail Bollards (Furnished by Owner)4Each
96Relocate Stop Sign1Each
97End of Road Markers3Each
Schedule A Total

Schedule B

Item No.Item DescriptionQuantityUnitUnit PriceTotal
101SWPPP, Traffic Control, and Site Access for Sewer Within River Rd.1Lump
102Remove and Replace Asphalt and Base for Sewer Within River Rd.2,755Sq Ft
10330" PVC Sanitary Sewer Line - Within River Rd.237Ln Ft
Schedule B Total

Schedule C

Item No.Item DescriptionQuantityUnitUnit PriceTotal
201SWPPP, Traffic Control, and Site Access for Water Line Within Existing Roadway1Lump
202Remove and Replace Asphalt and Base for Water Line Within Existing 1450 S.4,248Sq Ft
203Remove and Replace Asphalt and Base for Water Line Within River Rd.4,128Sq Ft
20424" C905 Water Line - Within Existing Roadway863Ln Ft
20524" Butterfly Valve - Within Exisitng Roadway1Each
20618" Butterfly Valve1Each
207Connect to Existing 18" Water Line1Each
20818" Water Line Tee with 18" x 24" Reducer1Each
20924" Water Line 90° Bend2Each
Schedule C Total
Project Total