Attach 4_C06 SOW_Stove Prairie Campground gate Amended.pdf

PDF 749 KB Posted

Attached to
Stove Prairie Campground Gate Replacement
Solicitation number
117346
Issued by

About this file

This is a Statement of Work (SOW) for the Stove Prairie Campground Gate Replacement project issued by the US Department of Agriculture (USDA) Forest Service.

The project scope involves disposal and replacement of a broken 32-foot double-lane closure gate at Stove Prairie Landing in the Arapaho & Roosevelt National Forests and Pawnee National Grassland. The existing gate serves as a seasonal closure device spanning the entire width of a double-lane roadway using two individual gates with a center locking mechanism. The contractor must furnish all management, labor, equipment, supervision, tools, materials, transportation, and supplies necessary to complete the work. The project comprises two base line items: (1) Mobilization (lump sum), and (2) Replacement of 32-foot double-lane gate (lump sum). Gate installation requirements include site preparation, removal of existing gate and posts, disposal of removed materials at state-approved facilities, surveying for level installation, excavation, concrete bedding and pouring for holding and support posts, gate installation, backfill, and site restoration. The gate must measure 32 feet center-to-center of structural tubing support with specific dimensional requirements and must be primed and painted Forest Service Brown (FS 30059). Foundation specifications call for 24-inch Sono Tube diameter and 3 feet 6 inches tall with minimum 4 feet of structural tubing support above road surface. The contractor must submit a schedule, materials submittals (gate drawings, concrete information, object markers), staging area plan, traffic control plan, and accident prevention plan at least 14 days before construction begins. The government furnishes Yale locks and seed. Invoices must be submitted via the Department of Treasury's Invoice Processing Platform (IPP) with payment due within 30 days of receipt. The Contracting Officers Representative is Juan Londono (juan.londono@usda.gov). The project site is located at 16500 Poudre Canyon Road, Bellvue, Colorado.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

US Department of Agriculture (USDA)

Statement of Work

Stove Prairie Campground Gate Replacement

Contents Project

General Information

1.0 Scope of Work

2.0 Background

Contractor Requirements

3.0 Technical Requirements / Tasks

4.0 Government Furnished

5.0 Deliverables / Schedule

6.0 Travel

7.0 Contractor’s Key Personnel

8.0 Security Requirements

9.0 Data Rights

10.0 Section 508 – Electronic and Information Technology Standards

Attachment

Project

General Information

1.0 Scope of Work

The purpose is for disposal and replacement of an existing broken 32’ double lane closure gate at Stove Prairie Landing.

2.0 Background

The existing double lane closure gate at Stove Prairie Landing serves as the closure device for seasonal restrictions at this site, prohibiting traffic from accessing the site. This gate totals 32’, spanning the entire width of the double lane by using two individual gates on either side with a locking mechanism securing the end of both gates in the middle of the roadway. There are two posts on either side of the road that hold the gate and provide the hinging mechanism and there are two other posts on both sides that provide support for the end of both gates when the road is open.

Contractor Requirements

3.0 Technical Requirements / Tasks

SCHEDULE OF ITEMS (SOI)

ARAPAHO & ROOSEVELT NATIONAL FORESTS AND PAWNEE NATIONAL GRASSLAND

Base Items

Description Method of Measure

Unit Quantity Unit Price TOTAL

1 Mobilization L.S.Q Lump Sum

Job

Replacement of 32’ double lane gate

L.S.Q Lump Sum

Job

TOTAL BASE ITEMS

Electronic version of the SOI has also been provided to the contractor.

The Contractor shall furnish all management, labor, equipment, supervision, tools, materials, transportation, operating supplies, supervision, workman’s compensation, unemployment insurance and incidentals necessary to perform the work in accordance with the specification and provisions of the contract. All work shall be in accordance with the attached “Forest Service Supplemental Specifications” and FP-24 Standard Specifications for Construction of Roads & Bridges on Federal Highway Projects.

This project includes the following items:

1. Mobilization

a. This base item consists of all preparatory work and operations necessary for the movement of personnel, equipment, supplies, and incidentals to the project site, and for all other work and operations that must be performed or that cause costs to be incurred prior to beginning work on the various items on the project site. This base item applies to work included in the base items only.

b. Payment shall be made at the contract lump-sum price.

2. Gate Installation

a. This base item consists of all materials, personnel, labor, equipment, and supplies to install prefabricated gates, holding posts, and support posts. This item includes site preparation, removal of existing gate and posts, disposal (or otherwise, as specified by CO) of removed material and items off Forest Service land and disposed of in a State approved landfill or recycling, surveying to ensure level gate installation, excavation, bedding, pouring concrete for holding posts and support posts, installation of gate, backfill, and final site restoration.

i. Site restoration for this project will be grading and reshaping site to existing conditions.

Compacted ground shall be raked, scarified, or ripped. Government-furnished seed can be manually spread over all disturbed areas. No added materials are required.

b. Gate must be installed according to the attached drawings and in the location marked by the

COR.

i. Gate is 32’-0” center-to-center of structural tubing support. For one side of the gate, the structural tubing width is 10”, clear space from tubing to gate is 1”, vertical plate for gate is 4”, and the rest of the gate leaf is 15’-2”. See attached drawing.

ii. Gate shall be primed and painted with the only acceptable color: Forest Service Brown

(FS 30059).

iii. Foundation dimensions are: 2’-0” diameter (i.e. 24-inch Sono Tube) and 3’-6” inches tall. Depth of the foundation will vary with topography and alignment of the gate, having a minimum of 4’-0” of structural tubing support above surface of the road.

The contractor shall be responsible for obtaining any necessary licenses and permits, and for complying with any Federal, State, and Municipal laws, codes, and regulations applicable to the performance of the work. The contractor shall be responsible for all damages to persons or property, which occur as a result of the Contractor’s performance or negligence. Contractor is responsible for utility locate before excavation.

Project Site Requirements

- Recreation site will remain open (unless seasonally closed) to the public during construction. Contractor shall install and maintain suitable barriers to ensure the protection of the public, employees, and facilities. All signs shall meet MUTCD standards.

- Contractor may be allowed to temporarily close or block off traffic, with prior approval of traffic control plan from the Contracting Officer, for the safety of the public.

A. Inspection and Acceptance

a. All work shall be conducted under the general direction of the Contracting Officer and is subject to Government inspection and testing at all places and at all reasonable times before acceptance to ensure strict compliance with the terms of the contract. See FAR Clause 52.212-4(a) contained herein. The contractor is responsible for adhering to the contract specifications and for quality control.

B. Contract Administration

a. Invoices - The following supplements the invoice terms contained within FAR 52.212-4(g) contained herein.

b. Payments will be made from the Contractor’s invoice(s). All invoices are to be submitted via the electronic Invoice Processing Platform (IPP) System. The "Submit Invoice-to" address for USDA orders is the Department of Treasury's Invoice Processing Platform (IPP). The contractor must follow the instructions on how to register and submit invoices via IPP as prescribed in previous communications from USDA and Treasury.

c. Payment for services rendered shall be made within 30 days following receipt of an invoice for the work.

The contractor shall submit invoices on a monthly basis and at the end of the month. If at any time the Contractor does not perform the services per the contract in a timely manner the Contracting Officer reserves the right to contract for the work with another party and will adjust payment accordingly.

d. This is a mandatory requirement initiated by the U.S. Department of Treasury and you can find more information at this website https://www.ipp.gov/index.htm Ensure your company has registered at https://www.ipp.gov/vendors/enrollment-vendors.htm to establish your account. Offeror must have an established account prior to commencement of work.

e. Invoice Processing Platform (IPP) does not allow for the contractor to change the description of the line items being invoiced against and therefore an itemized invoice must be uploaded as an attachment(s).

https://www.ipp.gov/index.htm https://www.ipp.gov/vendors/enrollment-vendors.htm

If the itemized invoice has not been reviewed and approved by the COR, the IPP payment request will be rejected. Please follow the minimum requirements to ensure a successful payment process.

C. Forest Service Representatives

a. The signing Contracting Officer for this contract/purchase order and will be the contact on all things concerning this contract, shall be determined at a later date. Their contact information will be provided.

b. The Contracting Officers Representative (COR) is Juan Londono, reachable at juan.londono@usda.gov

D. Contract Administration

a. Contract Award: A written award or acceptance of offer mailed or otherwise furnished to the Contractor shall result in a binding contract without further action by either party.

b. Notice to Proceed. The Contractor shall commence work upon receipt of a properly executed Notice to

Proceed.

c. Changes: The Contracting Officer is the only person authorized to approve changes in any of the requirements under this contract and notwithstanding any provisions contained elsewhere in this contract the said authority remains solely with the Contracting Officer. In the event the Contractor effects any such change at the direction of any person other than the Contracting Officer, the change will be considered to have been made without authority and no adjustment will be made in the contract price to cover any increase in costs incurred as a result thereof.

d. Unauthorized Instructions from Government or Other Personnel: The Contractor shall not accept instructions issued by any person employed by the U.S. Government or otherwise other than the Contracting Officer, or the authorized representative of the Contracting Officer acting within the limits of his/her authority.

e. Designation of Contracting Officer’s Representative (COR): Designation will be made upon contract issuance of the contract and a copy of the designation letter will be furnished to the Contractor. Limits of authority are described in each designation letter.

f. Designation of Authorized Representative of the Contractor: The Contractor shall assign a member or employee who will act as Project Manager during the course of this contract or during the course of this project. The official shall be responsible for affording liaison between the contract forces and the contracting offices. This designation shall be in writing and a copy furnished to the Contracting Officer.

WASHING OF EQUIPMENT

Pollutants such as fuels, lubricants, bitumen, raw sewage, and other harmful materials shall not be discharged on the ground; into or nearby rivers, streams, or impoundments; or into natural or man-made channels. Wash water or waste from concrete or aggregate operations shall not be allowed to enter live streams prior to treatment by filtration, settling, or other means sufficient to reduce the sediment content to not more than that of the stream into which it is discharged.

The Contractor shall wash all equipment except for hauling vehicles prior to entering National Forest Land. Remove all soil which could contain noxious weed seed. Remove grease and oil from drive mechanisms which would be discharged into the stream when equipment is operating. Prior to transporting equipment to the site, assure that the equipment's hydraulic, lubrication and fuel systems are free from leaks.

IPP Invoice shall have the following areas completed at a minimum:

Invoice Number Invoice Date Bill Period Start Date Bill Period End Date Supplier Contact Name Supplier Contact Phone Contract Number

Itemized invoice shall include at a minimum:

Contractor Name & Address Contract number Invoice Number Description of Services or work completed.

Date of services or completion.

4.0 Government Furnished

- Yale locks for gates

- Government-furnished seed

5.0 Deliverables / Schedule

All Submittals mentioned below shall be submitted at least fourteen (14) days prior to beginning construction.

(Item No. 2) The only requirements from Section 601 of FP-24, Minor Concrete, shall be:

• Submittal for concrete mix, in accordance with Section 601, at least fourteen (14) days prior to beginning construction.

• Concrete delivery tickets will be reviewed onsite by COR, before pouring.

• Concrete will receive a visual inspection by COR before, during, and after pouring but before backfilling.

Key Deliverables

Item No.

Deliverable / Item Title

Description Frequency Delivery Format

Due By

1 Schedule A schedule outlining the proposed construction timeline, from mobilization to demobilization

Before construction begins

Via email to

CO/COR

14 days before construction is intended to begin

2 Materials Submittals

Submit all materials for this contract to the COR, including:

- Gate Drawings

- Concrete information for footings

- Object Markers

Before construction begins

Via email to

CO/COR

14 days before construction is intended to begin

3 Staging area Outline a proposed staging area Before construction begins

Via email to

CO/COR

14 days before construction is intended to begin

4 Traffic Control Plan

Submit a traffic control plan of the construction area, with consideration given to users of recreation site. (Required only if site is occupied/open).

Before construction begins

Via email to COR

14 days before construction is intended to begin

5 Accident Prevention Plan

Submit a site-specific safety plan to ensure contractor and public safety

Before construction begins

Via email to COR

14 days before construction is intended to begin

6.0 Travel

Stove Prairie Campground: 16500 Poudre Canyon Rd, Bellvue, CO

7.0 Contractor’s Key Personnel

Contractor shall ensure that all work is conducted by personnel fully qualified to perform the tasks and supervised by a designated Contractor’s Representative.

8.0 Security Requirements

N/A

9.0 Data Rights

10.0 Section 508 – Electronic and Information Technology Standards

Attachment

- Area Map

- Gate Details Drawing

- Concrete Specifications

Area Map

Project
General Information
1.0 Scope of Work
2.0 Background
Contractor Requirements
3.0 Technical Requirements / Tasks
4.0 Government Furnished
5.0 Deliverables / Schedule
6.0 Travel
7.0 Contractor’s Key Personnel
8.0 Security Requirements
9.0 Data Rights
10.0 Section 508 – Electronic and Information Technology Standards
Attachment