About this file
This document is a contract amendment for a federal solicitation to remodel Building 24 at the Lolo National Forest Headquarters. The key details are:
The amendment extends the due dates for questions (from July 22 to August 15) and proposal submissions (from August 6 to September 5). It incorporates a list of vendors who attended the mandatory site visit on July 15. A forthcoming amendment will respond to vendor questions. All other terms and conditions remain unchanged. Questions and proposals should be emailed to the Contract Specialist and Contracting Officer.
The original solicitation is for the remodeling of specified areas of Building 24, including the south wing on the upper floor to accommodate the Missoula Dispatch, the front desk area, a single private office in the north wing, minor exterior work, and installing access control. The government agency is the Department of Agriculture Forest Service.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| A0004_Building 24 Dispatch Remodel.pdf | ||
| A0003_Building 24 Dispatch Remodel.pdf | ||
| Attach 10_Demo Plan West Wing Sheets 1-11.pdf | ||
| A0002_Building 24 Dispatch Remodel.pdf | ||
| Attach 7_ADDENDUM 2 _Updates to Plans_Drawings_07242024.pdf | ||
| Attach 9_Demo Plan South Wing Sheets 2 and 6 of 11.pdf | ||
| Attach 14_Reception Area Remodel Sheets 1 - 3.pdf | ||
| Attach 12_E Sheets E1 - E8.pdf | ||
| Attach 13_M Demo Sheets M1 - M3.pdf | ||
| Attach 8_Asbestos Report-Building 24.pdf | ||
| Attach 11_Demolition Plan Sheets 1-5.pdf | ||
| Attch 1 SOW.pdf | ||
| Attch 2 -Schedule of Items -SOI.xlsx | XLSX spreadsheet | |
| Attch 3- Plans_Drawings.pdf | ||
| Attch 4 - 100 Percent Construction Documents Volume 1 Specification.pdf | ||
| Attch 6 - Wage Determination.pdf | ||
| 1282B124R0054_BUILDING 24.pdf | ||
| Attch 5 - 100 Percent Construction Documents Volume 2 Specification.pdf |
Show all 18
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SUMMARY OF CHANGES
Building 24 Dispatch Remodel
SOLICITATION 1282B124R0054
Amendment 0001
The Purpose of Amendment One is as follows:
1. To extend the response due dates for Questions and Proposals as follows: Extend the due date for Questions from July 22, 2024, at 11:00 a.m. Central Time to August 15, 2024, at 11:00 a.m. Central Time.
Extend the due date for Proposals from August 6, 2024, at 11:00 a.m. Central Time to September 5, 2024, at 11:00 a.m. Central Time.
2. To incorporate the list of vendors attending the Site Visit held on July 15, 2024, at 11:00 a.m. Central Time.
3. See Summary of Changes. A forthcoming Amendment will respond to questions that have been submitted by vendors.
4. All other terms and conditions remain unchanged.
Questions and Proposals shall be sent via email to the following POC's:
Janice King, Contract Specialist, at janice.king@usda.gov and
Lucas Dahlman, Contracting Officer, at lucas.dahlman@usda.gov mailto:janice.king@usda.gov mailto:lucas.dahlman@usda.gov
Attendee’s List for Site Visit held on July 15, 2024
Systems NW
Paulson Electric Inc.
Northwest Interior Contracting
Anchor Electric
Sierra Pacific Windows
Quality Construction
Valley Electric
Snow Mountain Elec
Communicator Resources
Touchstone
Peter Electric
Bryon Obleness Construction
Sirius Construction
Talco Electric
| A0001_Draft |
| v3_SUMMARY OF CHANGES |
| 2024-07-25T13:31:04-0500 | |
| LUCAS DAHLMAN |
File details come from the government source that posted it. Updated .