This is a Measurement and Payment document for the City of St. George's Country Club Water Tank project in Utah, which involves the construction of a 2.5 million gallon concrete water tank along with site preparation, water mains, and associated infrastructure. The project encompasses multiple bid items including clearing and grubbing, tank rock excavation and site grading, erosion control, mobilization, exploratory excavation, selective demolition, water tank removal, concrete headwall construction, cast-in-place concrete vault work, roadway excavation, untreated base course installation, and various piping installations ranging from 8 inches to 18 inches in diameter for waterline and drain pipe applications. Additional items include chain link fencing, gate installations, valve installations, manhole construction, electrical conduit, and foundation drain work. Measurements are specified by unit type (e.g., by acre for clearing and grubbing, by cubic yard for excavation and base course, by linear foot for piping and conduit, and by each unit for discrete items), with some items designated as lump sum payments and others as hourly rates for specialized work such as exploratory excavation and selective demolition.

The payment structure incorporates a comprehensive basis of measurement and payment methodology detailing what is included in each bid item's scope, with specifications tied to plan quantities indicated in the Bid Schedule. The bid requirements mandate a bid bond equal to 5 percent of the total bid amount issued by a Utah-licensed surety company, and a 100 percent performance bond covering labor and materials will be required upon award. The City of St. George reserves the right to reject any or all submissions and waive any formality or technicality as deemed in the city's interest.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ITEM

NO.

SECTION

01 50 00

Basis of Measurement:

Basis of Payment:

01 71 13

Basis of Measurement:

Basis of Payment:

02 32 19

Basis of Measurement:

Basis of Payment:

02 41 19

Basis of Measurement:

Basis of Payment:

02 65 00

Basis of Measurement:

Basis of Payment:

03 30 00

Basis of Measurement:

Basis of Payment:

03 30 00

Basis of Measurement:

Basis of Payment:

31 11 00

Basis of Measurement:

Basis of Payment:

31 23 16

Basis of Measurement:

Basis of Payment:

TABLE 1 MEASUREMENT AND PAYMENT

1-1

1-2

1-3

1-4

1-5

1-6

1-7

1-8

1-9

DESCRIPTION

Includes excavation, over-excavation and rock excavation as defined in this Section, use of specialized attachments to excavation equipment, dewatering, stockpiling, scarifying subgrade for fills, filling, watering, grading, finishing, compacting, subgrade preparation, disposal of unsuitable and excess materials, spreading topsoil, and incidental work.

Includes installation, removal and materials for temporary erosion and sediment control devices required in accordance with Section 01 50 00.

Includes mobilization to and from Project Site, field office, temporary utilities, temporary facilities, traffic control, removal, restoration of site, cleanup, and incidental work.

Payments will be made in accordance with table included in Section 01 71 13.

Includes excavation, backfill, compaction, locating existing utilities by typical excavating methods, and incidental work.

Includes cutting, selective demolition indicated, loading, removal from Site, dust control and incidental work.

Includes excavation, tank and appurtenances removal, backfill, and surface restoration.

Includes excavation, over-excavation, rock excavation, forming, reinforcing steel, embedded items, concrete, placement and consolidation, finishing, curing, backfill, compaction, and incidental work. Includes items within pay lines shown on Drawings.

Includes excavation, over-excavation, rock excavation, forming, reinforcing steel, embedded items, concrete, placement and consolidation, finishing, curing, backfill, compaction, and incidental work. Includes items within pay lines shown on Drawings.

Includes clearing and grubbing site, loading and removing waste materials from site, and incidental work.

By each unit for size and type indicated.

Clearing and Grubbing (Plan Quantity):

By acre. Will be plan quantity indicated on Bid Schedule.

Tank Rock Excavation & Site Grading (Plan Quantity):

By cubic yard. Will be plan quantity indicated on Bid Schedule.

Erosion Control:

None – lump sum.

Mobilization:

None – lump sum.

Exploratory Excavation:

Hourly

Selective Demolition:

Hourly

Water Tank Removal:

By each tank.

Concrete Headwall:

By each unit.

15.5' x 13.5' Cast-in-Place Concrete Vault:

31 23 16

Basis of Measurement:

Basis of Payment:

32 11 23

Basis of Measurement:

Basis of Payment:

32 31 13

Basis of Measurement:

Basis of Payment:

32 31 13

Basis of Measurement:

Basis of Payment:

33 05 61

Basis of Measurement:

Basis of Payment:

33 14 12

Basis of Measurement:

Basis of Payment:

33 14 12

Basis of Measurement:

Basis of Payment:

33 14 12

Basis of Measurement:

Basis of Payment:

33 14 12

Basis of Measurement:

1-11

1-10

Includes excavating existing topsoil and soil to required elevations, over-excavation, rock excavation, dewatering, stockpiling, scarifying subgrade for fills, filling, watering, grading, finishing, compacting, subgrade preparation, disposal of unsuitable and excess materials, spreading topsoil, and incidental work.

Includes untreated base course material, hauling, placement, grading, watering, compaction, and incidental work.

1-12

1-13

1-14

1-15

1-16

1-17

Includes excavation, over-excavation, rock excavation, pipe, fittings, thrust restraint devices, tracer wire, bedding, backfill, compaction, cleaning, disinfection, pressure testing, bacteriological testing, trench compaction, abandonment of existing lines where applicable, and incidental work.

Includes excavation, over-excavation, rock excavation, pipe, fittings, thrust restraint devices, tracer wire, bedding, backfill, compaction, cleaning, disinfection, pressure testing, bacteriological testing, trench compaction, abandonment of existing lines where applicable, and incidental work.

Includes, valve, fittings, installation, cleaning, and incidental work.

14" C-900 PVC Waterline:

By linear foot for each size and type indicated. Pipe included in lump sum items will not be measured.

16" C-900 PVC Waterline:

By linear foot for each size and type indicated. Pipe included in lump sum items will not be measured.

10" Electronically Actuated Valve and Meter:

By each unit for size and type indicated.

8" C-900 PVC Drain Pipe:

By linear foot for each size and type indicated. Pipe included in lump sum items will not be measured.

Includes excavation, posts, concrete footings, rails, tension wire, fabric, ties, and accessories.

Includes excavation, posts, concrete footings, rails, tension wire, fabric, ties, and accessories.

Includes excavation, over-excavation, rock excavation, bedding, precast concrete manhole sections, gaskets or mastic, steps, grade rings, frame and cover, rubber boot couplers, pipe inlets and outlets, connections to pipes, backfill, compaction, and accessories.

By linear foot for height indicated. Gate openings will not be measured.

Double Chain Link Gate:

By linear foot for each type indicated.

72" Straight Wall Manhole with Slotted Grate:

By each unit for size and type indicated.

Roadway Excavation:

By cubic yard.

Untreated Base Course:

By cubic yard, neat line in place.

Chain Link Fence:

Basis of Payment:

33 14 12

Basis of Measurement:

Basis of Payment:

33 14 12

Basis of Measurement:

Basis of Payment:

33 14 12

Basis of Measurement:

Basis of Payment:

33 14 12

Basis of Measurement:

Basis of Payment:

33 14 12

Basis of Measurement:

Basis of Payment:

33 14 12

Basis of Measurement:

Basis of Payment:

33 14 12

Basis of Measurement:

Basis of Payment:

33 14 19.19

Basis of Measurement:

Basis of Payment:

33 16 62

Basis of Measurement:

1-19

1-20

1-21

1-22

1-24

1-25

1-26

1-23

1-18

By linear foot for each size and type indicated. Pipe included in lump sum items will not be measured.

8" Gate Valve:

Includes excavation, fittings, tracer wire, bedding, backfill, compaction, cleaning, trench compaction, coring existing box, grouting, abandonment of existing lines where applicable, and incidental work.

Includes air valve, tapping main line, connecting pipe, ball valve, fittings, and incidental work. Includes items shown on Drawings.

Includes excavation, over-excavation, rock excavation, pipe, fittings, thrust restraint devices, tracer wire, bedding, backfill, compaction, cleaning, disinfection, pressure testing, bacteriological testing, trench compaction, abandonment of existing lines where applicable, and incidental work.

Includes excavation, over-excavation, rock excavation, pipe, fittings, thrust restraint devices, tracer wire, bedding, backfill, compaction, cleaning, disinfection, pressure testing, bacteriological testing, trench compaction, abandonment of existing lines where applicable, and incidental work.

Includes excavation, gate valve, fittings, valve box, collar, installation, cleaning, bedding, backfill, compaction, and incidental work.

Includes excavation, gate valve, fittings, valve box, collar, installation, cleaning, bedding, backfill, compaction, and incidental work.

Includes excavation, valve, fittings, valve box, collar, installation, cleaning, bedding, backfill, compaction, and incidental work.

Includes excavation, valve, fittings, valve box, collar, installation, cleaning, bedding, backfill, compaction, and incidental work.

Includes excavation, over-excavation, rock excavation, fittings, thrust restraint devices, tracer wire, bedding, backfill, compaction, cleaning, disinfection, pressure testing, bacteriological testing, trench compaction, abandonment of existing lines where applicable, and incidental work.

By each unit for size and type indicated.

10" Gate Valve:

By each unit for size and type indicated.

14" Butterfly Valve:

18" C-900 PVC Drain Pipe:

Connection to Existing Storm Drain Box:

By each unit for size and type indicated.

2" Air/Vac Combination Valve:

By each unit for each size and type indicated.

2.5 Million Gallon Concrete Tank:

By each unit for size and type indicated.

16" Butterfly Valve:

By each unit for size and type indicated.

Connection to existing 14" AC Pipe:

By each unit for size and type indicated.

None – lump sum.

Basis of Payment:

33 40 03

Basis of Measurement:

Basis of Payment:

33 40 03

Basis of Measurement:

Basis of Payment:

26 00 00

Basis of Measurement:

Basis of Payment:

26 00 00

Basis of Measurement:

Basis of Payment:

1-30

1-31

1-27

1-28

1-29 Includes excavation, over-excavation, rock excavation, pipe, fittings, fusing where applicable, bedding, backfill, compaction, trench compaction, and incidental work.

Includes excavation, over-excavation, rock excavation, conduit, fittings, accessories, bedding, backfill, compaction, and incidental work.

Includes excavation, unistrut pedestals, concrete bedding, backfill, panels, conduit, fittings, conductors (incl. conductors for bid item 1-30), connections, fixtures, accessories, and incidental work.

2" PVC Conduit:

By linear foot for each size indicated.

Site Electrical:

None – lump sum.

4" Single Wall HDPE Foundation Drain :

By linear foot for each size and type indicated. Pipe included in lump sum items will not be measured.

4" HDPE Drain Pipe:

By linear foot for each size and type indicated. Pipe included in lump sum items will not be measured.

Includes base, flowable fill, concrete, reinforcing steel, structural fill, form work, concrete finishing and curing, water stop, metal piping, overflow piping, fittings, connections, penetrations, vents, ladder, access hatch, sleeve and enclosure, repairs, disinfection, backfill, compaction, impervious barrier, and incidental work. Includes items within pay line 5' outside tank footprint.

Includes excavation, over-excavation, rock excavation, pipe, fittings, fusing where applicable, bedding, backfill, compaction , trench compaction, geotextile, drain rock, and incidental work.