11-2025-08-27 Pine Island Strux Pre-Bid Presentation printfriendly.pdf
PDF 5 MB Posted
- Attached to
- Pine Island Breakwater Project
- Solicitation number
- 2025-23
- Issued by
- Barnwell County, South Carolina
About this file
The document is a Pre-Bid Conference presentation for the Pine Island Breakwater Project, solicitation IFB #2025-23, issued by the Town of Hilton Head Island, South Carolina. The project involves constructing a series of six breakwater structures (S1-S6) along Pine Island's shoreline in Port Royal Sound, with a pre-bid conference scheduled for August 26, 2025. The planned work includes excavation, foundational treatments, stone placement, and installation of marine mattresses and geogrid/fabric composites. The total estimated quantities include 9,870 tons of armor stone, 1,740 tons of chinking stone, 32,032 square feet of Size 1 marine mattresses, 7,722 square feet of Size 2 marine mattresses, and 14,800 square feet of geogrid/fabric composite. The project will be completed in stages, starting with establishing a staging area at the Dolphin Head Recreation Area, working from the furthest structure (S6) back to the nearest (S1), and concluding with site restoration.
The project has a 10% retainage requirement, and rock quantities will be certified by truck load weigh tickets and verified by survey. Work is limited to Monday through Saturday, with specific hours (7 AM to sunset on weekdays, 8 AM to 5 PM on Saturdays) and no work permitted on Sundays or holidays. Material deliveries are allowed Monday through Friday from 7 AM to 6 PM. The contract will be awarded to the lowest most responsible and responsive bidder, with consideration given to proposed construction schedules, mobilization methods, personnel and equipment commitment, and contractor qualifications. Marine mattresses will be assembled and filled offsite, and all stone must be clean, free of debris, and separated into similar-sized piles at the staging area. The project involves detailed environmental considerations, including vibration monitoring and careful excavation and foundation preparation.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Town of Hilton Head Island, SC
PINE ISLAND BREAKWATER
PROJECT
IFB #: 2025-23
Pre-Bid Conference
Town of Hilton Head Island, SC
Hilton Head Plantation
August 26, 2025, 11:00am
Project Overview & Purpose
Gated
Access
Port Royal
Sound
Skull Creek
PINE ISLAND
Marshlands Dolphin
Head Rec
Area
Erosional
Beach
Accretional
Spit
Direction of Sand Transport
Site Overview
Tidal
Range
8-10 FT
Beach Fill to be Completed by
Others Prior to Construction
(Fall 2025)
SOFT SOIL
CONDITIONS
Contract Schedule
Date Event
1.) August 12, 2025 Bid Advertised
2.) August 26, 2025 at 11:00 a.m. Mandatory Pre-bid Conference
3.) September 3, 2025 at 5:00 p.m. Deadline to submit questions
4.) September 11, 2025 at 5:00 p.m. Bid Submittal
5.) September 12, 2025 at 9:30 a.m. Virtual Bid Opening
6.) Within 7 Days of Bid Opening (Goal) Owner issues Notice-of-Award
7.) Within 10 Days of Notice of Award Contractor provides signed Contract, Insurance Documentation and Bonds
8.) Within 30 Days of Receipt of Signed Owner executes Contract and issues
Contract and Bonds Notice-to-Proceed (NTP)
Bid Schedule of Quantities
Estimated
Quantity Units Unit Cost Cost
1 Town Business License 1 allowance 25,000$ 25,000$
2 Mobilization/Demobilization 1 lump sum $ $
3 Armor Stone 9,870 ton $ $
4 Chinking Stone 1,740 ton $ $
5 Stone-Filled Marine Mattresses - Size 1 (22'x6.5'x0.5') 32,032 sqft $ $
6 Stone-Filled Marine Mattresses - Size 2 (18'x6.5'x0.5') 7,722 sqft $ $
7 Geogrid / Fabric Composite 14,800 sqft $ $
8 Structure Inspection and Vibration Monitoring 1 lump sum $ $
9 Signage 1 lump sum $ $
* Actual quantities to be placed and accepted may vary from Base Bid by +/- 20 percent (%) or less.
IFB# 2025-23
TOTAL
Item
BID
Discussion on Stone at End of Presentation
General
• Basis for Award
• Lowest most responsible, responsive bidder
• Proposed construction schedule
• Methods of mobilization/demob
• Personnel and equipment committed
• Qualifications and experience
• Contract Schedule/Town Council Approval-
Execution Process
General
• Permits included with bid documents
• Retainage 10%
• Rock quantities for payment to be certified by truck load weigh tickets
• Rock placement to be verified by survey
• Conduct vibration monitoring and control throughout project
Order of Work
• Establish staging/access area
• Complete furthest structure from access back to nearest (S6 to S1)
• Excavation
• Foundational treatments
• Stone placement
• Backfilling/washing sand into voids
• Install warning sign
• Site Restoration
Operations
• Staging/access: Dolphin Head Rec Area
• Works Days/hours
• M-F: 7 AM to sunset; Sat: 8 AM to 5 PM
• Material/equipment deliveries: M-F: 7 AM to 6 PM
• No work Sundays and Holidays
• Mattresses to be assembled & filled offsite
• Stone clean & free of debris
• Separated into piles of similar size at staging area
Materials
• Armor Stone (discussion at end)
• Marine Mattresses (Tensar BX 1500, or equivalent)
• Size 1: 22’ x 6.5’ x 0.5’
• Size 2: 18’ x 6.5’ x 0.5’
• Geotextile Fabric (US Fabrics US1540, or equivalent)
• Geogrid/Fabric Composite (Tensar GC654050, or equivalent)
• Timber pile warning sign
• Location to be coordinated with Town
Staging/Access
Limits to be field verified
Structure Layout
Size 1
Mattresses
Size 2
Mattresses
Geogrid/Fabric
Composite
Structure Layout
Size 1
Mattresses
Size 2
Mattresses
Geogrid/Fabric
Composite
Warning
Sign
Structure Cross-Sections
Excavation
Limit
Excavation
Limit
All side slopes 2H:1V
Structure Cross-Sections
Marine Mattresses
2’ Extension for
Overlapping
Questions/Discussion
| Slide 1 |
| Slide 2 |
| Slide 3 |
| Slide 4 |
| Slide 5 |
| Slide 6 |
| Slide 7 |
| Slide 8 |
| Slide 9 |
| Slide 10 |
| Slide 11 |
| Slide 12 |
| Slide 13 |
| Slide 14 |
| Slide 15 |
| Slide 16 |
| Slide 17 |
| Slide 18 |
| Slide 19 |
| Slide 20 |
| Slide 21 |
| Slide 22 |
| Slide 23 |
| Slide 24 |
| Slide 25 |
File details come from the government source that posted it. Updated .