10-HVCC ATEC - Schedule Update DD 3.13.2026.pdf

PDF 749 KB Posted

Attached to
ATEC Project Commissioning Services
Solicitation number
RFP 26-544
Issued by
New York

About this file

This document is a project schedule update for the ATEC (Advanced Technology and Education Center) Project at Hudson Valley Community College (HVCC) in New York, dated March 13, 2026. The schedule outlines a comprehensive construction and commissioning timeline spanning from the August 15, 2024 bid date through August 23, 2027 for owner move-in. The project encompasses multiple phases including project startup and engineering, critical submittal management for long-lead items such as transformers, chillers, air handling units, and electrical equipment, coordination drawings for structural elements across multiple floors, and extensive direct work comprising sitework and utilities, building structure and enclosure, and interior construction across multiple areas and floor levels. Key milestones include contract issuance on December 30, 2024, a stop work order issued February 26, 2025 and removed October 13, 2025, with substantial completion targeted for August 6, 2027, and certificate of occupancy scheduled for August 20, 2027. The schedule reflects detailed activity sequencing across numerous construction trades with dependencies on equipment procurement, inspection approvals, and weather impacts.

The schedule identifies significant commissioning activities commencing May 14, 2026, including fire alarm certification, MEP (mechanical, electrical, plumbing) start-up and checkout, and testing and balancing of HVAC systems, scheduled for completion by July 23, 2027. Building power infrastructure work spans from May 14, 2026 through February 9, 2027, encompassing underground conduit installation, feeder wire placement on both floors, transformer and switch installation, and permanent power connections. Critical path items include structural steel sequences, MEP rough-in work across all areas, and interior finishing trades. The project demonstrates a total float of zero days on multiple critical activities, indicating minimal scheduling flexibility for on-time delivery. Punch list activities, final cleaning, and demobilization are scheduled for completion by August 13, 2027, with owner move-in on August 23, 2027.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Activity ID Activity Name Original Duration

Remaining Duration

Start Finish Total Float

HVCC ATEC Draft Schedule 2.2.2026HVCC ATEC Draft Schedule 2.2.2026 774 372 15-Aug-24 A 23-Aug-27 0

PROJECT STARTUP / ENGINEERINGPROJECT STARTUP / ENGINEERING 465 168 15-Aug-24 A 06-Nov-26 204

PRO-1000 Bid Date 1 0 15-Aug-24 A 15-Aug-24 A

PRO-1010 Contract Issuance 1 0 30-Dec-24 A 30-Dec-24 A

PRO-1020 Submittals (will resume after stop work order) 90 0 20-Jan-25 A 27-Feb-26 A

PRO-1040 Priority Sumittal Review (Long Lead Items) 30 0 20-Jan-25 A 21-Feb-25 A

PRO-1030 Procurement (will resume after stop work order) 90 0 25-Feb-25 A 02-Mar-26 A

Constraints/Delays/Weather ImpactsConstraints/Delays/Weather Impacts 90 0 26-Feb-25 A 11-Sep-25 A

A1650 Stop Work Order Issued 90 0 26-Feb-25 A 11-Sep-25 A

Critical SubmittalsCritical Submittals 336 168 29-Jan-25 A 06-Nov-26 201

A1400 Oil Filled Transformer (EC to verify leadtime during Bid) 325 0 29-Jan-25 A 22-Jan-26 A

A1420 Chiller 190 0 07-Feb-25 A 03-Jun-25 A

A1430 AHU-1 & AHU-2 225 0 07-Feb-25 A 17-Apr-26 A

A1490 ERU-1 225 0 07-Feb-25 A 16-Apr-26 A

A1660 ERU-2 225 0 07-Feb-25 A 16-Apr-26 A

A1670 ERU-3 225 0 07-Feb-25 A 16-Apr-26 A

A1680 ERU-4 225 0 07-Feb-25 A 30-Apr-26 A

A1690 ERU-5 225 0 07-Feb-25 A 16-Apr-26 A

A1700 ERU-6 225 0 07-Feb-25 A 16-Apr-26 A

A1600 Cooling Tower 60 0 13-Feb-25 A 03-Jun-25 A

A1610 MV Switch 325 49 21-Feb-25 A 20-May-26* -8

A1410 480V Switchboard 200 168 14-May-25 A 06-Nov-26 107

Coordination DrawingsCoordination Drawings 64 0 13-Jan-25 A 07-Jul-25 A

COOR-1000 Model Creation 15 0 13-Jan-25 A 17-Jan-25 A

COOR-1010 Under Slab Coordination 30 0 17-Jan-25 A 11-Mar-25 A

COOR-1020 Overhead Coordination (1st Floor) 30 0 03-Mar-25 A 09-Apr-25 A

COOR-1030 Submit Underslab Coordination Dwgs for Design Team Review 10 0 11-Mar-25 A 28-Mar-25 A

COOR-1040 Overhead Coordination (2nd Floor) 30 0 01-Apr-25 A 09-Jun-25 A

COOR-1050 Submit 1st Floor Coordination Dwgs for Design Team Review 10 0 09-Apr-25 A 19-May-25 A

COOR-1060 Submit 2nd Floor Coordination Dwgs for Desing Team Review 10 0 10-Jun-25 A 07-Jul-25 A

DIRECT WORKDIRECT WORK 612 339 18-Feb-25 A 07-Jul-27 22

SITEWORK / UTILITIESSITEWORK / UTILITIES 589 316 18-Feb-25 A 04-Jun-27 35

SITE-1000 GPR 2 0 18-Feb-25 A 21-Feb-25 A

SITE-1010 Mobilize 3 0 24-Feb-25 A 26-Feb-25 A

SITE-1020 Fencing 7 0 24-Feb-25 A 01-Mar-25 A

SITE-1030 Temp Road / Tree Removal 6 0 24-Feb-25 A 26-Feb-25 A

SITE-1040 Equipment Mobilize 1 0 24-Feb-25 A 24-Feb-25 A

SITE-1080 Construction Entrance 2 0 13-Oct-25 A 10-Feb-26 A

J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O

Bid Date

Contract Issuance

Submittals (will resume after stop work order)

Priority Sumittal Review (Long Lead Items)

Procurement (will resume after stop work order)

Stop Work Order Issued

Oil Filled Transformer (EC to verify leadtime during Bid)

Chiller

AHU-1 & AHU-2

ERU-1

ERU-2

ERU-3

ERU-4

ERU-5

ERU-6

Cooling Tower

MV Switch

480V Switchboard

Model Creation

Under Slab Coordination

Overhead Coordination (1st Floor)

Submit Underslab Coordination Dwgs for Design Team Review

Overhead Coordination (2nd Floor)

Submit 1st Floor Coordination Dwgs for Design Team Review

Submit 2nd Floor Coordination Dwgs for Desing Team Review

GPR

Mobilize

Fencing

Temp Road / Tree Removal

Equipment Mobilize

Construction Entrance

HVCC ATEC Draft Schedule 2.2.2026 NY-01 Current Schedule-Collapsed Print date:16-Mar-26 14:11

Data Date:13-Mar-26

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Remaining Duration

Start Finish Total Float

SITE-1070 Remobilize (Following Removal of Stop Work Order) 5 0 13-Oct-25 A 17-Oct-25 A

SITE-1090 Install lay down Area / Trailer 4 0 14-Oct-25 A 17-Oct-25 A

SITE-1110 Site clearing & demo 15 0 17-Oct-25 A 06-Nov-25 A

SITE-1050 Strip Topsoil 5 0 21-Oct-25 A 23-Oct-25 A

SITE-1100 Remove Parking Lot Asphalt 5 0 21-Oct-25 A 29-Oct-25 A

SITE-1170 Screen Topsoil 24 0 24-Oct-25 A 09-Jan-26 A

SITE-1140 Excavate for footings 15 0 31-Oct-25 A 12-Dec-25 A

SITE-1120 Undercuts 20 0 06-Nov-25 A 11-Dec-25 A

SITE-1130 Site utilities & drainage 60 60 10-Dec-25 A 05-Jun-26* -39

SITE-1150 Excavate for MPE utilities / lighting 20 20 08-Jun-26 06-Jul-26 179

SITE-1230 Concrete Equipment Pads (Transformer, Switch, Cooling Tower) 5 5 07-Jul-26 13-Jul-26 222

SITE-1160 Concrete Light Pole Bases 1 1 14-Jul-26 14-Jul-26 222

Landscaping / Site FurnishingsLandscaping / Site Furnishings 45 45 05-Apr-27 04-Jun-27 35

SITE-1180 Prep for sidewalks / paving 15 15 05-Apr-27* 23-Apr-27 35

SITE-1190 Sidewalks 10 10 26-Apr-27 07-May-27 55

SITE-1200 Paving 10 10 26-Apr-27* 07-May-27 35

SITE-1210 Bollards / signage 10 10 26-Apr-27 07-May-27 55

SITE-1220 Topsoil & seeding / plantings 20 20 10-May-27* 04-Jun-27 35

INTERIOR / BUILDING ConstructionINTERIOR / BUILDING Construction 415 339 10-Nov-25 A 07-Jul-27 22

Building Structure & EnclosureBuilding Structure & Enclosure 165 165 20-Apr-26 10-Dec-26 160

403 Steel Sequences 1 & 2 10 10 20-Apr-26* 01-May-26 0

413 Structural Steel Sequences 3, 4, 5 & 6 15 15 04-May-26 22-May-26 10

354 Metal Deck Seq. 1 & 2 5 5 04-May-26 08-May-26 0

423 Structural Steel Sequences 7 & 8 5 5 26-May-26 01-Jun-26 10

364 Metal Deck Seq. 3, 4, 5 & 6 7 7 26-May-26 03-Jun-26 78

324 Metal Deck Seq. 7 & 8 5 5 02-Jun-26 08-Jun-26 10

328 Field measure metal wall panels 5 5 02-Jun-26 08-Jun-26 65

329 MWP - Lead time 50 50 09-Jun-26 18-Aug-26 65

330 Spray Foam 5 5 25-Jun-26 01-Jul-26 98

326 Masonry Fire Wall 25 25 10-Aug-26 14-Sep-26 52

325 Elevator Shaft Masonry 25 25 02-Sep-26 07-Oct-26 175

327 Stairs & Railings 25 25 02-Nov-26 07-Dec-26 115

333 Exterior Signage 5 5 04-Dec-26* 10-Dec-26 160

AREA 1A - 1ST FLOOR / ROOFAREA 1A - 1ST FLOOR / ROOF 373 256 10-Nov-25 A 10-May-27 64

118 FOOTINGS & FOUNDATIONS 20 0 10-Nov-25 A 30-Jan-26 A

119 DAMPROOFING & INSULATION 5 0 19-Jan-26 A 24-Feb-26 A

131 FOOTING DRAIN & BACKFILL 5 0 19-Jan-26 A 13-Mar-26 A

159 UNDERSLAB EXCAVATION & ROUGH IN 30 30 11-May-26 22-Jun-26 0

369 Underslab Plumbing 35 35 14-May-26 02-Jul-26 32

J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O

Remobilize (Following Removal of Stop Work Order)

Install lay down Area / Trailer

Site clearing & demo

Strip Topsoil

Remove Parking Lot Asphalt

Screen Topsoil

Excavate for footings

Undercuts

Site utilities & drainage

Excavate for MPE utilities / lighting

Concrete Equipment Pads (Transformer, Switch, Cooling Tower)

Concrete Light Pole Bases

Prep for sidewalks / paving

Sidewalks

Paving

Bollards / signage

Topsoil & seeding / plantings

Steel Sequences 1 & 2

Structural Steel Sequences 3, 4, 5 & 6

Metal Deck Seq. 1 & 2

Structural Steel Sequences 7 & 8

Metal Deck Seq. 3, 4, 5 & 6

Metal Deck Seq. 7 & 8

Field measure metal wall panels

MWP - Lead time

Spray Foam

Masonry Fire Wall

Elevator Shaft Masonry

Stairs & Railings

Exterior Signage

FOOTINGS & FOUNDATIONS

DAMPROOFING & INSULATION

FOOTING DRAIN & BACKFILL

UNDERSLAB EXCAVATION & ROUGH IN

Underslab Plumbing

HVCC ATEC Draft Schedule 2.2.2026 NY-01 Current Schedule-Collapsed Print date:16-Mar-26 14:11

Data Date:13-Mar-26

Actual Work

Remaining Work

Critical Remaining Work

Remaining Duration

Start Finish Total Float

134 EXTERIOR METAL WALL FRAMING 15 15 04-Jun-26 24-Jun-26 78

171 ROOFING 30 30 25-Jun-26 06-Aug-26 78

160 BACKFILL 10 10 06-Jul-26 17-Jul-26 32

161 SLAB PREP 10 10 20-Jul-26* 31-Jul-26 32

162 SLAB ON GRADE 5 5 03-Aug-26 07-Aug-26 42

174 METAL WALL PANELS 20 20 19-Aug-26 16-Sep-26 65

175 SPRAY ON FIREPROOFING 5 5 15-Sep-26 21-Sep-26 52

363 Duct Rough-in (Level 1A) 30 30 15-Sep-26 26-Oct-26 52

373 Mechanical Pipe Rough-in (Level 1A) 30 30 15-Sep-26 26-Oct-26 67

309 Sprinkler Rough-in (Level 1A) 15 15 15-Sep-26 05-Oct-26 87

172 EDGE METAL 7 7 17-Sep-26 25-Sep-26 141

191 ALUMINUM / WINDOWS 25 25 17-Sep-26 21-Oct-26 95

193 MASONRY VENEER 15 15 17-Sep-26* 07-Oct-26 125

359 Sprinkler Test (Level 1A) 1 1 06-Oct-26 06-Oct-26 151

319 Sprinkler Trim / Finishes (Level 1A) 2 2 07-Oct-26 08-Oct-26 151

341 TEMP HEAT 5 5 22-Oct-26 28-Oct-26 95

163 INTERIOR WALL FRAMING 20 20 27-Oct-26 23-Nov-26 72

353 Welding Exhaust Rough-in 25 25 27-Oct-26 01-Dec-26 52

393 Mechanical Insulation Level 1A 20 20 27-Oct-26 23-Nov-26 107

173 OH Electrical Rough-in (lighting, FA, Low Voltage etc) 20 20 27-Oct-26 23-Nov-26 57

164 HM FRAMES 5 5 03-Nov-26 09-Nov-26 102

192 OH DOORS 5 5 24-Nov-26 01-Dec-26 72

165 MPE IN-WALL ROUGH INS 20 20 02-Dec-26 30-Dec-26 52

166 GWB, TAPE, FINISH 30 30 31-Dec-26 10-Feb-27 52

168 PAINT WALLS 25 25 21-Jan-27 24-Feb-27 52

379 Ceiling MEP Trim (Lighting, FA, RGDs etc) 20 20 04-Feb-27 03-Mar-27 57

135 ACOUSTICAL CEILING GRID 15 15 11-Feb-27 03-Mar-27 52

167 PAINT CEILINGS 10 10 11-Feb-27 24-Feb-27 69

177 CERAMIC TILE AT BATHROOMS 15 15 11-Feb-27 03-Mar-27 79

182 ELEVATOR 40 40 11-Feb-27 07-Apr-27 87

169 WOOD & METAL CEILINGS 10 10 25-Feb-27 10-Mar-27 54

176 MPE WALL FINISHES/TRIM (Plumb Fixtures, Elect Devices) 15 15 25-Feb-27 17-Mar-27 69

179 WINDOW SHADES 5 5 25-Feb-27 03-Mar-27 94

189 VISUAL DISPLAY BOARDS 3 3 25-Feb-27 01-Mar-27 99

136 ACOUSTICAL CEILING TILE 5 5 04-Mar-27 10-Mar-27 52

178 TOILET ACCESSORIES & PARTITIONS 15 15 04-Mar-27 24-Mar-27 79

181 FLOOR SEALER / FLOOR POLISH 20 20 11-Mar-27 07-Apr-27 54

183 FLOOR MATS 2 2 08-Apr-27 09-Apr-27 67

184 WOOD TRIMS / ARCH CASEWORK 15 15 08-Apr-27 28-Apr-27 57

J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O

EXTERIOR METAL WALL FRAMING

ROOFING

BACKFILL

SLAB PREP

SLAB ON GRADE

METAL WALL PANELS

SPRAY ON FIREPROOFING

Duct Rough-in (Level 1A)

Mechanical Pipe Rough-in (Level 1A)

Sprinkler Rough-in (Level 1A)

EDGE METAL

ALUMINUM / WINDOWS

MASONRY VENEER

Sprinkler Test (Level 1A)

Sprinkler Trim / Finishes (Level 1A)

TEMP HEAT

INTERIOR WALL FRAMING

Welding Exhaust Rough-in

Mechanical Insulation Level 1A

OH Electrical Rough-in (lighting, FA, Low Voltage etc)

HM FRAMES

OH DOORS

MPE IN-WALL ROUGH INS

GWB, TAPE, FINISH

PAINT WALLS

Ceiling MEP Trim (Lighting, FA, RGDs etc)

ACOUSTICAL CEILING GRID

PAINT CEILINGS

CERAMIC TILE AT BATHROOMS

ELEVATOR

WOOD & METAL CEILINGS

MPE WALL FINISHES/TRIM (Plumb Fixtures, Elect Devices)

WINDOW SHADES

VISUAL DISPLAY BOARDS

ACOUSTICAL CEILING TILE

TOILET ACCESSORIES & PARTITIONS

FLOOR SEALER / FLOOR POLISH

FLOOR MATS

WOOD TRIMS / ARCH CASEWORK

HVCC ATEC Draft Schedule 2.2.2026 NY-01 Current Schedule-Collapsed Print date:16-Mar-26 14:11

Data Date:13-Mar-26

Actual Work

Remaining Work

Critical Remaining Work

Remaining Duration

Start Finish Total Float

185 LOCKERS 2 2 08-Apr-27 09-Apr-27 67

186 FABRICATION CRANE 5 5 08-Apr-27 14-Apr-27 64

188 DOORS & HARDWARE 10 10 08-Apr-27 21-Apr-27 59

335 MISC EQUIPMENT & FINISHES 15 15 08-Apr-27 28-Apr-27 54

121 Construction Clean 3 3 29-Apr-27 03-May-27 54

190 PUNCH LIST - Level 1A 5 5 04-May-27 10-May-27 54

AREA 1 - 1ST FLOOR AREA 1 - 1ST FLOOR 368 302 19-Jan-26 A 17-May-27 59

123 FOOTINGS & FOUNDATIONS 20 10 19-Jan-26 A 26-Mar-26 -19

138 RIGID INSULATION 5 5 19-Jan-26 A 02-Apr-26* -19

139 FOOTING DRAIN & BACKFILL 10 10 02-Mar-26 A 16-Apr-26* -19

153 EXTERIOR METAL WALL FRAMING 20 20 18-Jun-26 16-Jul-26 128

199 UNDERSLAB EXCAVATION & ROUGH IN 20 20 23-Jun-26 21-Jul-26 0

200 BACKFILL UNDERSLAB UTILITIES 10 10 22-Jul-26 04-Aug-26 30

202 SLAB PREP 15 15 05-Aug-26 25-Aug-26 30

261 Mechanical Pipe Rough-in (Level 1 Area 1) 35 35 19-Aug-26 07-Oct-26 100

205 Sprinkler Rough-in (Level 1 Area 1) 20 20 19-Aug-26 16-Sep-26 140

203 SLAB ON GRADE 5 5 26-Aug-26 01-Sep-26 30

231 Duct Rough-in (Level 1 Area 1) 35 35 02-Sep-26 21-Oct-26 75

195 METAL WALL PANELS 30 30 17-Sep-26 28-Oct-26 65

235 Sprinkler Test (Level 1 Area 1) 1 1 17-Sep-26 17-Sep-26 166

210 PAINT CEILINGS 10 10 18-Sep-26 01-Oct-26 169

285 Sprinkler Finish/Trim (Level 1 Area 1) 3 3 18-Sep-26 22-Sep-26 166

197 MASONRY VENEER 20 20 08-Oct-26* 04-Nov-26 125

206 INTERIOR WALL FRAMING 20 20 22-Oct-26 18-Nov-26 90

321 Mechanical Insulation (Level 1 Area 1) 8 8 22-Oct-26 02-Nov-26 127

305 OH Electrical Rough-in (Lighting, FA, Low Voltage) 20 20 22-Oct-26 18-Nov-26 75

196 ALUMINUM / WINDOWS 30 30 29-Oct-26 10-Dec-26 75

198 EDGE METAL 10 10 29-Oct-26 11-Nov-26 118

207 HM FRAMES 5 5 29-Oct-26 04-Nov-26 110

204 OH DOORS 5 5 19-Nov-26 25-Nov-26 90

208 MPE IN-WALL ROUGH INS 20 20 19-Nov-26 17-Dec-26 75

342 TEMP HEAT 5 5 28-Dec-26 01-Jan-27 65

209 GWB, TAPE, FINISH 20 20 04-Jan-27 29-Jan-27 65

211 PAINT WALLS 15 15 11-Jan-27 29-Jan-27 65

389 Ceiling MEP Trim (Lights, FA, RGDs) 20 20 25-Jan-27 19-Feb-27 65

212 WOOD & METAL CEILINGS 10 10 01-Feb-27 12-Feb-27 85

213 ACOUSTICAL CEILING GRID 5 5 01-Feb-27 05-Feb-27 65

216 CERAMIC TILE AT BATHROOMS 10 10 01-Feb-27 12-Feb-27 117

225 WINDOW SHADES 5 5 01-Feb-27 05-Feb-27 115

J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O

LOCKERS

FABRICATION CRANE

DOORS & HARDWARE

MISC EQUIPMENT & FINISHES

Construction Clean

PUNCH LIST - Level 1A

FOOTINGS & FOUNDATIONS

RIGID INSULATION

FOOTING DRAIN & BACKFILL

EXTERIOR METAL WALL FRAMING

UNDERSLAB EXCAVATION & ROUGH IN

BACKFILL UNDERSLAB UTILITIES

SLAB PREP

Mechanical Pipe Rough-in (Level 1 Area 1)

Sprinkler Rough-in (Level 1 Area 1)

SLAB ON GRADE

Duct Rough-in (Level 1 Area 1)

METAL WALL PANELS

Sprinkler Test (Level 1 Area 1)

PAINT CEILINGS

Sprinkler Finish/Trim (Level 1 Area 1)

MASONRY VENEER

INTERIOR WALL FRAMING

Mechanical Insulation (Level 1 Area 1)

OH Electrical Rough-in (Lighting, FA, Low Voltage)

ALUMINUM / WINDOWS

EDGE METAL

HM FRAMES

OH DOORS

MPE IN-WALL ROUGH INS

TEMP HEAT

GWB, TAPE, FINISH

PAINT WALLS

Ceiling MEP Trim (Lights, FA, RGDs)

WOOD & METAL CEILINGS

ACOUSTICAL CEILING GRID

CERAMIC TILE AT BATHROOMS

WINDOW SHADES

HVCC ATEC Draft Schedule 2.2.2026 NY-01 Current Schedule-Collapsed Print date:16-Mar-26 14:11

Data Date:13-Mar-26

Actual Work

Remaining Work

Critical Remaining Work

Remaining Duration

Start Finish Total Float

228 VISUAL DISPLAY BOARDS 5 5 01-Feb-27 05-Feb-27 95

214 ACOUSTICAL CEILING TILE 5 5 08-Feb-27 12-Feb-27 70

215 MPE WALL FINISHES/TRIM (Plumb Fixtures, Elect Devices) 15 15 15-Feb-27 05-Mar-27 75

217 TOILET ACCESSORIES & PARTITIONS 5 5 15-Feb-27 19-Feb-27 117

219 FLOOR SEALER / FLOOR POLISH 15 15 15-Feb-27 05-Mar-27 85

218 RESILENT FLOORING 7 7 08-Mar-27 16-Mar-27 85

221 FLOOR MATS 3 3 08-Mar-27 10-Mar-27 104

227 DOORS & HARDWARE 7 7 08-Mar-27 16-Mar-27 100

336 MISC EQUIPMENT & FINISHES 20 20 08-Mar-27 02-Apr-27 75

222 WOOD TRIMS / ARCH CASEWORK 15 15 17-Mar-27 06-Apr-27 85

229 PUNCH LIST - Level 1 (Area 1) 5 5 06-May-27 12-May-27 52

230 Construction Clean (Level 1 Area 1) 3 3 13-May-27 17-May-27 59

AREA 2 - 1ST FLOOR AREA 2 - 1ST FLOOR 350 294 24-Nov-25 A 12-May-27 52

126 FOOTINGS & FOUNDATIONS 20 0 24-Nov-25 A 13-Mar-26 A

140 RIGID INSULATION 5 0 19-Jan-26 A 20-Mar-26* -2

141 FOOTING DRAIN & BACKFILL 10 10 19-Jan-26 A 02-Apr-26* -2

127 EXTERIOR METAL WALL FRAMING 15 15 10-Jul-26 30-Jul-26 128

236 UNDERSLAB EXCAVATION & ROUGH IN 30 30 22-Jul-26 01-Sep-26 0

306 Underslab Duct Rough-in (Dyno) 5 5 22-Jul-26 28-Jul-26 25

237 BACKFILL 10 10 02-Sep-26 16-Sep-26 0

239 SLAB PREP 15 15 17-Sep-26 07-Oct-26 0

240 SLAB ON GRADE 5 5 08-Oct-26 14-Oct-26 5

288 Duct Rough-in (Level 1 Area 2) 35 35 15-Oct-26 03-Dec-26 30

308 Mechanical Pipe Rough-in (Level 1 Area 2) 35 35 22-Oct-26 10-Dec-26 40

358 Sprinkler Rough-in (Level 1 Area 2) 20 20 22-Oct-26 18-Nov-26 99

232 METAL WALL PANELS 25 25 29-Oct-26 03-Dec-26 65

234 MASONRY VENEER 15 15 05-Nov-26 25-Nov-26 125

233 ALUMINUM / WINDOWS 25 25 19-Nov-26 24-Dec-26 65

368 Sprinkler Test (Level 1 Area 2) 1 1 19-Nov-26 19-Nov-26 99

378 Sprinkler Finishes / Trim (Level 1 Area 2) 3 3 20-Nov-26 24-Nov-26 118

244 HM FRAMES 5 5 04-Dec-26 10-Dec-26 75

331 OH Electrical Rough-in (Power, FA, Low Voltage) 20 20 04-Dec-26 01-Jan-27 30

243 INTERIOR WALL FRAMING 15 15 11-Dec-26 01-Jan-27 40

348 Mechanical Insulation 8 8 11-Dec-26 22-Dec-26 82

241 OH DOORS 5 5 04-Jan-27 08-Jan-27 45

245 MPE IN-WALL ROUGH INS 20 20 04-Jan-27 29-Jan-27 30

246 GWB, TAPE, FINISH 20 20 01-Feb-27 26-Feb-27 30

248 PAINT WALLS 15 15 08-Feb-27 26-Feb-27 35

312 Ceiling MEP Trim (Lights, FA, RGDs etc) 20 20 22-Feb-27 19-Mar-27 45

J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O

VISUAL DISPLAY BOARDS

ACOUSTICAL CEILING TILE

MPE WALL FINISHES/TRIM (Plumb Fixtures, Elect Devices)

TOILET ACCESSORIES & PARTITIONS

FLOOR SEALER / FLOOR POLISH

RESILENT FLOORING

FLOOR MATS

DOORS & HARDWARE

MISC EQUIPMENT & FINISHES

WOOD TRIMS / ARCH CASEWORK

PUNCH LIST - Level 1 (Area 1)

Construction Clean (Level 1 Area 1)

FOOTINGS & FOUNDATIONS

RIGID INSULATION

FOOTING DRAIN & BACKFILL

EXTERIOR METAL WALL FRAMING

UNDERSLAB EXCAVATION & ROUGH IN

Underslab Duct Rough-in (Dyno)

BACKFILL

SLAB PREP

SLAB ON GRADE

Duct Rough-in (Level 1 Area 2)

Mechanical Pipe Rough-in (Level 1 Area 2)

Sprinkler Rough-in (Level 1 Area 2)

METAL WALL PANELS

MASONRY VENEER

ALUMINUM / WINDOWS

Sprinkler Test (Level 1 Area 2)

Sprinkler Finishes / Trim (Level 1 Area 2)

HM FRAMES

OH Electrical Rough-in (Power, FA, Low Voltage)

INTERIOR WALL FRAMING

Mechanical Insulation

OH DOORS

MPE IN-WALL ROUGH INS

GWB, TAPE, FINISH

PAINT WALLS

Ceiling MEP Trim (Lights, FA, RGDs etc)

HVCC ATEC Draft Schedule 2.2.2026 NY-01 Current Schedule-Collapsed Print date:16-Mar-26 14:11

Data Date:13-Mar-26

Actual Work

Remaining Work

Critical Remaining Work

Remaining Duration

Start Finish Total Float

247 PAINT CEILINGS 10 10 01-Mar-27 12-Mar-27 30

249 WOOD & METAL CEILINGS 15 15 01-Mar-27 19-Mar-27 52

250 ACOUSTICAL CEILING GRID 5 5 01-Mar-27 05-Mar-27 35

253 CERAMIC TILE AT BATHROOMS 10 10 01-Mar-27 12-Mar-27 85

262 WINDOW SHADES 5 5 01-Mar-27 05-Mar-27 92

265 VISUAL DISPLAY BOARDS 3 3 01-Mar-27 03-Mar-27 74

337 MISC EQUIPMENT & FINISHES 20 20 04-Mar-27 31-Mar-27 74

252 MPE WALL FINISHES/TRIM (Plumb Fixtures, Elect Devices) 15 15 15-Mar-27 02-Apr-27 30

254 TOILET ACCESSORIES & PARTITIONS 5 5 15-Mar-27 19-Mar-27 85

256 FLOOR SEALER / FLOOR POLISH 15 15 22-Mar-27 09-Apr-27 52

251 ACOUSTICAL CEILING TILE 5 5 05-Apr-27 09-Apr-27 30

255 RESILENT FLOORING 5 5 12-Apr-27 16-Apr-27 52

258 FLOOR MATS 3 3 12-Apr-27 14-Apr-27 64

264 DOORS & HARDWARE 7 7 12-Apr-27 20-Apr-27 60

322 LAB METAL CASEWORK & EQ 15 15 12-Apr-27 30-Apr-27 52

259 WOOD TRIMS / ARCH CASEWORK 10 10 19-Apr-27 30-Apr-27 52

267 Construction Clean 3 3 03-May-27 05-May-27 52

266 PUNCH LIST - Level 1 (Area 2) 5 5 06-May-27 12-May-27 52

AREA 1 - 2ND FLOOR / ROOFAREA 1 - 2ND FLOOR / ROOF 236 236 07-Aug-26 07-Jul-27 12

143 ROOFING 30 30 07-Aug-26 18-Sep-26 118

268 SOD PREP 10 10 08-Oct-26 21-Oct-26 0

269 SLAB ON DECK 5 5 22-Oct-26 28-Oct-26 0

287 Duct Rough-in (Level 2) 60 60 29-Oct-26 22-Jan-27 0

297 Mechanical Pipe Rough-in (Level 2) 60 60 12-Nov-26 05-Feb-27 0

304 Sprinkler Rough-in (Level 2) 25 25 12-Nov-26 17-Dec-26 100

144 EDGE METAL 10 10 04-Dec-26 17-Dec-26 103

314 Sprinkler Test (Level 2) 1 1 18-Dec-26 18-Dec-26 100

344 Sprinkler Finishes / Trim (Level 2) 2 2 21-Dec-26 22-Dec-26 100

334 Classroom Folding Partitions 5 5 13-Jan-27 19-Jan-27 125

271 INTERIOR WALL FRAMING 15 15 25-Jan-27 12-Feb-27 25

272 HM FRAMES 5 5 01-Feb-27 05-Feb-27 40

557 Mechanical Insulation 30 30 08-Feb-27 19-Mar-27 25

356 OH Electrical Rough-in (Power, FA, Low Voltage) 20 20 08-Feb-27 05-Mar-27 0

273 MPE IN-WALL ROUGH INS 20 20 08-Mar-27 02-Apr-27 0

274 GWB, TAPE, FINISH 15 15 05-Apr-27 23-Apr-27 0

276 PAINT WALLS 15 15 05-Apr-27 23-Apr-27 0

275 PAINT CEILINGS 10 10 26-Apr-27 07-May-27 12

277 WOOD & METAL CEILINGS 15 15 26-Apr-27 14-May-27 13

278 ACOUSTICAL CEILING GRID 10 10 26-Apr-27 07-May-27 0

J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O

PAINT CEILINGS

WOOD & METAL CEILINGS

ACOUSTICAL CEILING GRID

CERAMIC TILE AT BATHROOMS

WINDOW SHADES

VISUAL DISPLAY BOARDS

MISC EQUIPMENT & FINISHES

MPE WALL FINISHES/TRIM (Plumb Fixtures, Elect Devices)

TOILET ACCESSORIES & PARTITIONS

FLOOR SEALER / FLOOR POLISH

ACOUSTICAL CEILING TILE

RESILENT FLOORING

FLOOR MATS

DOORS & HARDWARE

LAB METAL CASEWORK & EQ

WOOD TRIMS / ARCH CASEWORK

Construction Clean

PUNCH LIST - Level 1 (Area 2)

ROOFING

SOD PREP

SLAB ON DECK

Duct Rough-in (Level 2)

Mechanical Pipe Rough-in (Level 2)

Sprinkler Rough-in (Level 2)

EDGE METAL

Sprinkler Test (Level 2)

Sprinkler Finishes / Trim (Level 2)

Classroom Folding Partitions

INTERIOR WALL FRAMING

HM FRAMES

Mechanical Insulation

OH Electrical Rough-in (Power, FA, Low Voltage)

MPE IN-WALL ROUGH INS

GWB, TAPE, FINISH

PAINT WALLS

PAINT CEILINGS

WOOD & METAL CEILINGS

ACOUSTICAL CEILING GRID

HVCC ATEC Draft Schedule 2.2.2026 NY-01 Current Schedule-Collapsed Print date:16-Mar-26 14:11

Data Date:13-Mar-26

Actual Work

Remaining Work

Critical Remaining Work

Remaining Duration

Start Finish Total Float

281 CERAMIC TILE AT BATHROOMS 10 10 26-Apr-27 07-May-27 42

289 WINDOW SHADES 5 5 26-Apr-27 30-Apr-27 52

292 VISUAL DISPLAY BOARDS 3 3 26-Apr-27 28-Apr-27 54

290 Ceiling MEP Trim (Lights, FA, RGDs etc) 20 20 26-Apr-27 21-May-27 0

279 ACOUSTICAL CEILING TILE 5 5 10-May-27 14-May-27 5

280 MPE WALL FINISHES (Plumb Fixtures, Elect Devices) 15 15 10-May-27 28-May-27 12

282 TOILET ACCESSORIES & PARTITIONS 5 5 10-May-27 14-May-27 42

284 FLOOR SEALER / FLOOR POLISH 15 15 17-May-27 04-Jun-27 13

338 MISC EQUIPMENT & FINISHES 20 20 31-May-27 25-Jun-27 12

283 RESILENT FLOORING / CARPET 7 7 07-Jun-27 15-Jun-27 13

291 DOORS & HARDWARE 7 7 07-Jun-27 15-Jun-27 20

286 WOOD TRIMS / ARCH CASEWORK 7 7 16-Jun-27 24-Jun-27 13

294 Construction Clean (Level 2) 3 3 28-Jun-27 30-Jun-27 12

293 PUNCH LIST - Level 2 (Area 1) 5 5 01-Jul-27 07-Jul-27 12

AREA 2 - MECH ROOM /ROOFAREA 2 - MECH ROOM /ROOF 198 198 21-Sep-26 25-Jun-27 20

148 ROOFING 30 30 21-Sep-26 30-Oct-26 118

295 SLAB PREP 5 5 22-Oct-26 28-Oct-26 58

296 SLAB ON DECK 2 2 29-Oct-26 30-Oct-26 58

298 INTERIOR WALL FRAMING 7 7 02-Nov-26 10-Nov-26 71

316 Duct & Mechanical Pipe (Mech Room) 60 60 02-Nov-26 26-Jan-27 78

366 Electrical Rough-in 45 45 02-Nov-26 05-Jan-27 58

299 HM FRAMES 3 3 09-Nov-26 11-Nov-26 95

300 MPE WALL ROUGH INS 20 20 09-Nov-26 07-Dec-26 71

301 GWB, TAPE, FINISH 7 7 08-Dec-26 16-Dec-26 71

302 PAINT CEILINGS 5 5 17-Dec-26 23-Dec-26 71

149 EDGE METAL 7 7 18-Dec-26 29-Dec-26 103

303 PAINT WALLS 5 5 06-Jan-27 12-Jan-27 58

Electrical Trim (Lights, FA, Security) 15 15 13-Jan-27 02-Feb-27 58

346 Mechanical Insulation 20 20 27-Jan-27 23-Feb-27 78

311 FLOOR SEALER / FLOOR POLISH 5 5 03-Feb-27 09-Feb-27 58

307 MPE FINISHES 15 15 10-Feb-27 02-Mar-27 58

318 DOORS & HARDWARE 7 7 10-Feb-27 18-Feb-27 81

339 MISC EQUIPMENT & FINISHES 20 20 24-Feb-27 23-Mar-27 78

349 PUNCHLIST - Level 2 Mech Room/Roof 10 10 14-Jun-27 25-Jun-27 20

Mechanical EquipmentMechanical Equipment 25 25 02-Nov-26 07-Dec-26 118

313 Set Rooftop Equipment 20 20 02-Nov-26 30-Nov-26 118

383 Set Cooling Tower 5 5 02-Nov-26 06-Nov-26 138

343 Roof Top Equipment Piping Tie-ins 5 5 01-Dec-26 07-Dec-26 118

J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O

CERAMIC TILE AT BATHROOMS

WINDOW SHADES

VISUAL DISPLAY BOARDS

Ceiling MEP Trim (Lights, FA, RGDs etc)

ACOUSTICAL CEILING TILE

MPE WALL FINISHES (Plumb Fixtures, Elect Devices)

TOILET ACCESSORIES & PARTITIONS

FLOOR SEALER / FLOOR POLISH

MISC EQUIPMENT & FINISHES

RESILENT FLOORING / CARPET

DOORS & HARDWARE

WOOD TRIMS / ARCH CASEWORK

Construction Clean (Level 2)

PUNCH LIST - Level 2 (Area 1)

ROOFING

SLAB PREP

SLAB ON DECK

INTERIOR WALL FRAMING

Duct & Mechanical Pipe (Mech Room)

Electrical Rough-in

HM FRAMES

MPE WALL ROUGH INS

GWB, TAPE, FINISH

PAINT CEILINGS

EDGE METAL

PAINT WALLS

Electrical Trim (Lights, FA, Security)

Mechanical Insulation

FLOOR SEALER / FLOOR POLISH

MPE FINISHES

DOORS & HARDWARE

MISC EQUIPMENT & FINISHES

PUNCHLIST - Level 2 Mech Room/Roof

Set Rooftop Equipment

Set Cooling Tower

Roof Top Equipment Piping Tie-ins

HVCC ATEC Draft Schedule 2.2.2026 NY-01 Current Schedule-Collapsed Print date:16-Mar-26 14:11

Data Date:13-Mar-26

Actual Work

Remaining Work

Critical Remaining Work

Remaining Duration

Start Finish Total Float

COMMISSIONING, STARTUP & TESTINGCOMMISSIONING, STARTUP & TESTING 307 307 14-May-26 23-Jul-27 10

487 Fire Alarm Certification 10 10 25-Mar-27 07-Apr-27 87

317 MEP START-UP & CHECKOUT 15 15 24-May-27 11-Jun-27 0

357 Testing and Balancing of HVAC Systems 30 30 14-Jun-27 23-Jul-27 0

Building PowerBuilding Power 189 189 14-May-26 09-Feb-27 88

467 Underslab Conduits & Floor Boxes 31 31 14-May-26 26-Jun-26 46

507 Feeder Wire - 1st Floor 30 30 29-Jun-26 10-Aug-26 171

367 Main Underground Conduits 5 5 07-Jul-26 13-Jul-26 179

407 Install New Elect Manhole 2 2 07-Jul-26 08-Jul-26 184

427 Site Lighting Conduit 8 8 07-Jul-26 16-Jul-26 220

497 Grounding 15 15 07-Jul-26 27-Jul-26 186

417 High Voltage Conduit 3 3 09-Jul-26 13-Jul-26 184

377 Equipment Pads / Conduit 2 2 14-Jul-26 15-Jul-26 179

477 Equipment Pad Grounding 5 5 14-Jul-26 20-Jul-26 179

457 Wire Pull (Site) & Set Poles 13 13 17-Jul-26 04-Aug-26 220

387 Set Transformer 2 2 21-Jul-26 22-Jul-26 179

397 Set 4 Way Switch 2 2 21-Jul-26 22-Jul-26 179

437 Temporary Generator 10 10 23-Jul-26 05-Aug-26 179

447 SHUTDOWN - High Voltage Wire Pull 10 10 06-Aug-26 19-Aug-26 179

547 Final Connections and Testing at Switch 5 5 20-Aug-26 26-Aug-26 179

517 Feeder Conduits - 2nd Floor 20 20 02-Nov-26 30-Nov-26 68

527 Feeder Wire - 2nd Floor 20 20 01-Dec-26 29-Dec-26 73

537 Gear Install 20 20 30-Dec-26 26-Jan-27 73

347 Permanent Power 10 10 27-Jan-27 09-Feb-27 73

PUNCHLIST / SUBSTANTIAL COMPLETION / CLOSEOUTPUNCHLIST / SUBSTANTIAL COMPLETION / CLOSEOUT 21 21 26-Jul-27 23-Aug-27 0

320 Final Punch List & Cleaning 10 10 26-Jul-27 06-Aug-27 0

86 Substantial Completion 0 0 06-Aug-27 0

84 Demobilization 5 5 09-Aug-27 13-Aug-27 6

340 CERTIFICATE OF OCCUPANCY 10 10 09-Aug-27 20-Aug-27 0

85 Owner move in 1 1 23-Aug-27 23-Aug-27 0

J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O

Fire Alarm Certification

MEP START-UP & CHECKOUT

Testing and Balancing of HVAC Systems

Underslab Conduits & Floor Boxes

Feeder Wire - 1st Floor

Main Underground Conduits

Install New Elect Manhole

Site Lighting Conduit

Grounding

High Voltage Conduit

Equipment Pads / Conduit

Equipment Pad Grounding

Wire Pull (Site) & Set Poles

Set Transformer

Set 4 Way Switch

Temporary Generator

SHUTDOWN - High Voltage Wire Pull

Final Connections and Testing at Switch

Feeder Conduits - 2nd Floor

Feeder Wire - 2nd Floor

Gear Install

Permanent Power

Final Punch List & Cleaning

Substantial Completion

Demobilization

CERTIFICATE OF OCCUPANCY

Owner move in

HVCC ATEC Draft Schedule 2.2.2026 NY-01 Current Schedule-Collapsed Print date:16-Mar-26 14:11

Data Date:13-Mar-26

Actual Work

Remaining Work

Critical Remaining Work