10-HVCC ATEC - Schedule Update DD 3.13.2026.pdf
PDF 749 KB Posted
- Attached to
- ATEC Project Commissioning Services
- Solicitation number
- RFP 26-544
- Issued by
- New York
About this file
This document is a project schedule update for the ATEC (Advanced Technology and Education Center) Project at Hudson Valley Community College (HVCC) in New York, dated March 13, 2026. The schedule outlines a comprehensive construction and commissioning timeline spanning from the August 15, 2024 bid date through August 23, 2027 for owner move-in. The project encompasses multiple phases including project startup and engineering, critical submittal management for long-lead items such as transformers, chillers, air handling units, and electrical equipment, coordination drawings for structural elements across multiple floors, and extensive direct work comprising sitework and utilities, building structure and enclosure, and interior construction across multiple areas and floor levels. Key milestones include contract issuance on December 30, 2024, a stop work order issued February 26, 2025 and removed October 13, 2025, with substantial completion targeted for August 6, 2027, and certificate of occupancy scheduled for August 20, 2027. The schedule reflects detailed activity sequencing across numerous construction trades with dependencies on equipment procurement, inspection approvals, and weather impacts.
The schedule identifies significant commissioning activities commencing May 14, 2026, including fire alarm certification, MEP (mechanical, electrical, plumbing) start-up and checkout, and testing and balancing of HVAC systems, scheduled for completion by July 23, 2027. Building power infrastructure work spans from May 14, 2026 through February 9, 2027, encompassing underground conduit installation, feeder wire placement on both floors, transformer and switch installation, and permanent power connections. Critical path items include structural steel sequences, MEP rough-in work across all areas, and interior finishing trades. The project demonstrates a total float of zero days on multiple critical activities, indicating minimal scheduling flexibility for on-time delivery. Punch list activities, final cleaning, and demobilization are scheduled for completion by August 13, 2027, with owner move-in on August 23, 2027.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Activity ID Activity Name Original Duration
Remaining Duration
Start Finish Total Float
HVCC ATEC Draft Schedule 2.2.2026HVCC ATEC Draft Schedule 2.2.2026 774 372 15-Aug-24 A 23-Aug-27 0
PROJECT STARTUP / ENGINEERINGPROJECT STARTUP / ENGINEERING 465 168 15-Aug-24 A 06-Nov-26 204
PRO-1000 Bid Date 1 0 15-Aug-24 A 15-Aug-24 A
PRO-1010 Contract Issuance 1 0 30-Dec-24 A 30-Dec-24 A
PRO-1020 Submittals (will resume after stop work order) 90 0 20-Jan-25 A 27-Feb-26 A
PRO-1040 Priority Sumittal Review (Long Lead Items) 30 0 20-Jan-25 A 21-Feb-25 A
PRO-1030 Procurement (will resume after stop work order) 90 0 25-Feb-25 A 02-Mar-26 A
Constraints/Delays/Weather ImpactsConstraints/Delays/Weather Impacts 90 0 26-Feb-25 A 11-Sep-25 A
A1650 Stop Work Order Issued 90 0 26-Feb-25 A 11-Sep-25 A
Critical SubmittalsCritical Submittals 336 168 29-Jan-25 A 06-Nov-26 201
A1400 Oil Filled Transformer (EC to verify leadtime during Bid) 325 0 29-Jan-25 A 22-Jan-26 A
A1420 Chiller 190 0 07-Feb-25 A 03-Jun-25 A
A1430 AHU-1 & AHU-2 225 0 07-Feb-25 A 17-Apr-26 A
A1490 ERU-1 225 0 07-Feb-25 A 16-Apr-26 A
A1660 ERU-2 225 0 07-Feb-25 A 16-Apr-26 A
A1670 ERU-3 225 0 07-Feb-25 A 16-Apr-26 A
A1680 ERU-4 225 0 07-Feb-25 A 30-Apr-26 A
A1690 ERU-5 225 0 07-Feb-25 A 16-Apr-26 A
A1700 ERU-6 225 0 07-Feb-25 A 16-Apr-26 A
A1600 Cooling Tower 60 0 13-Feb-25 A 03-Jun-25 A
A1610 MV Switch 325 49 21-Feb-25 A 20-May-26* -8
A1410 480V Switchboard 200 168 14-May-25 A 06-Nov-26 107
Coordination DrawingsCoordination Drawings 64 0 13-Jan-25 A 07-Jul-25 A
COOR-1000 Model Creation 15 0 13-Jan-25 A 17-Jan-25 A
COOR-1010 Under Slab Coordination 30 0 17-Jan-25 A 11-Mar-25 A
COOR-1020 Overhead Coordination (1st Floor) 30 0 03-Mar-25 A 09-Apr-25 A
COOR-1030 Submit Underslab Coordination Dwgs for Design Team Review 10 0 11-Mar-25 A 28-Mar-25 A
COOR-1040 Overhead Coordination (2nd Floor) 30 0 01-Apr-25 A 09-Jun-25 A
COOR-1050 Submit 1st Floor Coordination Dwgs for Design Team Review 10 0 09-Apr-25 A 19-May-25 A
COOR-1060 Submit 2nd Floor Coordination Dwgs for Desing Team Review 10 0 10-Jun-25 A 07-Jul-25 A
DIRECT WORKDIRECT WORK 612 339 18-Feb-25 A 07-Jul-27 22
SITEWORK / UTILITIESSITEWORK / UTILITIES 589 316 18-Feb-25 A 04-Jun-27 35
SITE-1000 GPR 2 0 18-Feb-25 A 21-Feb-25 A
SITE-1010 Mobilize 3 0 24-Feb-25 A 26-Feb-25 A
SITE-1020 Fencing 7 0 24-Feb-25 A 01-Mar-25 A
SITE-1030 Temp Road / Tree Removal 6 0 24-Feb-25 A 26-Feb-25 A
SITE-1040 Equipment Mobilize 1 0 24-Feb-25 A 24-Feb-25 A
SITE-1080 Construction Entrance 2 0 13-Oct-25 A 10-Feb-26 A
J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O
Bid Date
Contract Issuance
Submittals (will resume after stop work order)
Priority Sumittal Review (Long Lead Items)
Procurement (will resume after stop work order)
Stop Work Order Issued
Oil Filled Transformer (EC to verify leadtime during Bid)
Chiller
AHU-1 & AHU-2
ERU-1
ERU-2
ERU-3
ERU-4
ERU-5
ERU-6
Cooling Tower
MV Switch
480V Switchboard
Model Creation
Under Slab Coordination
Overhead Coordination (1st Floor)
Submit Underslab Coordination Dwgs for Design Team Review
Overhead Coordination (2nd Floor)
Submit 1st Floor Coordination Dwgs for Design Team Review
Submit 2nd Floor Coordination Dwgs for Desing Team Review
GPR
Mobilize
Fencing
Temp Road / Tree Removal
Equipment Mobilize
Construction Entrance
HVCC ATEC Draft Schedule 2.2.2026 NY-01 Current Schedule-Collapsed Print date:16-Mar-26 14:11
Data Date:13-Mar-26
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Remaining Duration
Start Finish Total Float
SITE-1070 Remobilize (Following Removal of Stop Work Order) 5 0 13-Oct-25 A 17-Oct-25 A
SITE-1090 Install lay down Area / Trailer 4 0 14-Oct-25 A 17-Oct-25 A
SITE-1110 Site clearing & demo 15 0 17-Oct-25 A 06-Nov-25 A
SITE-1050 Strip Topsoil 5 0 21-Oct-25 A 23-Oct-25 A
SITE-1100 Remove Parking Lot Asphalt 5 0 21-Oct-25 A 29-Oct-25 A
SITE-1170 Screen Topsoil 24 0 24-Oct-25 A 09-Jan-26 A
SITE-1140 Excavate for footings 15 0 31-Oct-25 A 12-Dec-25 A
SITE-1120 Undercuts 20 0 06-Nov-25 A 11-Dec-25 A
SITE-1130 Site utilities & drainage 60 60 10-Dec-25 A 05-Jun-26* -39
SITE-1150 Excavate for MPE utilities / lighting 20 20 08-Jun-26 06-Jul-26 179
SITE-1230 Concrete Equipment Pads (Transformer, Switch, Cooling Tower) 5 5 07-Jul-26 13-Jul-26 222
SITE-1160 Concrete Light Pole Bases 1 1 14-Jul-26 14-Jul-26 222
Landscaping / Site FurnishingsLandscaping / Site Furnishings 45 45 05-Apr-27 04-Jun-27 35
SITE-1180 Prep for sidewalks / paving 15 15 05-Apr-27* 23-Apr-27 35
SITE-1190 Sidewalks 10 10 26-Apr-27 07-May-27 55
SITE-1200 Paving 10 10 26-Apr-27* 07-May-27 35
SITE-1210 Bollards / signage 10 10 26-Apr-27 07-May-27 55
SITE-1220 Topsoil & seeding / plantings 20 20 10-May-27* 04-Jun-27 35
INTERIOR / BUILDING ConstructionINTERIOR / BUILDING Construction 415 339 10-Nov-25 A 07-Jul-27 22
Building Structure & EnclosureBuilding Structure & Enclosure 165 165 20-Apr-26 10-Dec-26 160
403 Steel Sequences 1 & 2 10 10 20-Apr-26* 01-May-26 0
413 Structural Steel Sequences 3, 4, 5 & 6 15 15 04-May-26 22-May-26 10
354 Metal Deck Seq. 1 & 2 5 5 04-May-26 08-May-26 0
423 Structural Steel Sequences 7 & 8 5 5 26-May-26 01-Jun-26 10
364 Metal Deck Seq. 3, 4, 5 & 6 7 7 26-May-26 03-Jun-26 78
324 Metal Deck Seq. 7 & 8 5 5 02-Jun-26 08-Jun-26 10
328 Field measure metal wall panels 5 5 02-Jun-26 08-Jun-26 65
329 MWP - Lead time 50 50 09-Jun-26 18-Aug-26 65
330 Spray Foam 5 5 25-Jun-26 01-Jul-26 98
326 Masonry Fire Wall 25 25 10-Aug-26 14-Sep-26 52
325 Elevator Shaft Masonry 25 25 02-Sep-26 07-Oct-26 175
327 Stairs & Railings 25 25 02-Nov-26 07-Dec-26 115
333 Exterior Signage 5 5 04-Dec-26* 10-Dec-26 160
AREA 1A - 1ST FLOOR / ROOFAREA 1A - 1ST FLOOR / ROOF 373 256 10-Nov-25 A 10-May-27 64
118 FOOTINGS & FOUNDATIONS 20 0 10-Nov-25 A 30-Jan-26 A
119 DAMPROOFING & INSULATION 5 0 19-Jan-26 A 24-Feb-26 A
131 FOOTING DRAIN & BACKFILL 5 0 19-Jan-26 A 13-Mar-26 A
159 UNDERSLAB EXCAVATION & ROUGH IN 30 30 11-May-26 22-Jun-26 0
369 Underslab Plumbing 35 35 14-May-26 02-Jul-26 32
J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O
Remobilize (Following Removal of Stop Work Order)
Install lay down Area / Trailer
Site clearing & demo
Strip Topsoil
Remove Parking Lot Asphalt
Screen Topsoil
Excavate for footings
Undercuts
Site utilities & drainage
Excavate for MPE utilities / lighting
Concrete Equipment Pads (Transformer, Switch, Cooling Tower)
Concrete Light Pole Bases
Prep for sidewalks / paving
Sidewalks
Paving
Bollards / signage
Topsoil & seeding / plantings
Steel Sequences 1 & 2
Structural Steel Sequences 3, 4, 5 & 6
Metal Deck Seq. 1 & 2
Structural Steel Sequences 7 & 8
Metal Deck Seq. 3, 4, 5 & 6
Metal Deck Seq. 7 & 8
Field measure metal wall panels
MWP - Lead time
Spray Foam
Masonry Fire Wall
Elevator Shaft Masonry
Stairs & Railings
Exterior Signage
FOOTINGS & FOUNDATIONS
DAMPROOFING & INSULATION
FOOTING DRAIN & BACKFILL
UNDERSLAB EXCAVATION & ROUGH IN
Underslab Plumbing
HVCC ATEC Draft Schedule 2.2.2026 NY-01 Current Schedule-Collapsed Print date:16-Mar-26 14:11
Data Date:13-Mar-26
Actual Work
Remaining Work
Critical Remaining Work
Remaining Duration
Start Finish Total Float
134 EXTERIOR METAL WALL FRAMING 15 15 04-Jun-26 24-Jun-26 78
171 ROOFING 30 30 25-Jun-26 06-Aug-26 78
160 BACKFILL 10 10 06-Jul-26 17-Jul-26 32
161 SLAB PREP 10 10 20-Jul-26* 31-Jul-26 32
162 SLAB ON GRADE 5 5 03-Aug-26 07-Aug-26 42
174 METAL WALL PANELS 20 20 19-Aug-26 16-Sep-26 65
175 SPRAY ON FIREPROOFING 5 5 15-Sep-26 21-Sep-26 52
363 Duct Rough-in (Level 1A) 30 30 15-Sep-26 26-Oct-26 52
373 Mechanical Pipe Rough-in (Level 1A) 30 30 15-Sep-26 26-Oct-26 67
309 Sprinkler Rough-in (Level 1A) 15 15 15-Sep-26 05-Oct-26 87
172 EDGE METAL 7 7 17-Sep-26 25-Sep-26 141
191 ALUMINUM / WINDOWS 25 25 17-Sep-26 21-Oct-26 95
193 MASONRY VENEER 15 15 17-Sep-26* 07-Oct-26 125
359 Sprinkler Test (Level 1A) 1 1 06-Oct-26 06-Oct-26 151
319 Sprinkler Trim / Finishes (Level 1A) 2 2 07-Oct-26 08-Oct-26 151
341 TEMP HEAT 5 5 22-Oct-26 28-Oct-26 95
163 INTERIOR WALL FRAMING 20 20 27-Oct-26 23-Nov-26 72
353 Welding Exhaust Rough-in 25 25 27-Oct-26 01-Dec-26 52
393 Mechanical Insulation Level 1A 20 20 27-Oct-26 23-Nov-26 107
173 OH Electrical Rough-in (lighting, FA, Low Voltage etc) 20 20 27-Oct-26 23-Nov-26 57
164 HM FRAMES 5 5 03-Nov-26 09-Nov-26 102
192 OH DOORS 5 5 24-Nov-26 01-Dec-26 72
165 MPE IN-WALL ROUGH INS 20 20 02-Dec-26 30-Dec-26 52
166 GWB, TAPE, FINISH 30 30 31-Dec-26 10-Feb-27 52
168 PAINT WALLS 25 25 21-Jan-27 24-Feb-27 52
379 Ceiling MEP Trim (Lighting, FA, RGDs etc) 20 20 04-Feb-27 03-Mar-27 57
135 ACOUSTICAL CEILING GRID 15 15 11-Feb-27 03-Mar-27 52
167 PAINT CEILINGS 10 10 11-Feb-27 24-Feb-27 69
177 CERAMIC TILE AT BATHROOMS 15 15 11-Feb-27 03-Mar-27 79
182 ELEVATOR 40 40 11-Feb-27 07-Apr-27 87
169 WOOD & METAL CEILINGS 10 10 25-Feb-27 10-Mar-27 54
176 MPE WALL FINISHES/TRIM (Plumb Fixtures, Elect Devices) 15 15 25-Feb-27 17-Mar-27 69
179 WINDOW SHADES 5 5 25-Feb-27 03-Mar-27 94
189 VISUAL DISPLAY BOARDS 3 3 25-Feb-27 01-Mar-27 99
136 ACOUSTICAL CEILING TILE 5 5 04-Mar-27 10-Mar-27 52
178 TOILET ACCESSORIES & PARTITIONS 15 15 04-Mar-27 24-Mar-27 79
181 FLOOR SEALER / FLOOR POLISH 20 20 11-Mar-27 07-Apr-27 54
183 FLOOR MATS 2 2 08-Apr-27 09-Apr-27 67
184 WOOD TRIMS / ARCH CASEWORK 15 15 08-Apr-27 28-Apr-27 57
J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O
EXTERIOR METAL WALL FRAMING
ROOFING
BACKFILL
SLAB PREP
SLAB ON GRADE
METAL WALL PANELS
SPRAY ON FIREPROOFING
Duct Rough-in (Level 1A)
Mechanical Pipe Rough-in (Level 1A)
Sprinkler Rough-in (Level 1A)
EDGE METAL
ALUMINUM / WINDOWS
MASONRY VENEER
Sprinkler Test (Level 1A)
Sprinkler Trim / Finishes (Level 1A)
TEMP HEAT
INTERIOR WALL FRAMING
Welding Exhaust Rough-in
Mechanical Insulation Level 1A
OH Electrical Rough-in (lighting, FA, Low Voltage etc)
HM FRAMES
OH DOORS
MPE IN-WALL ROUGH INS
GWB, TAPE, FINISH
PAINT WALLS
Ceiling MEP Trim (Lighting, FA, RGDs etc)
ACOUSTICAL CEILING GRID
PAINT CEILINGS
CERAMIC TILE AT BATHROOMS
ELEVATOR
WOOD & METAL CEILINGS
MPE WALL FINISHES/TRIM (Plumb Fixtures, Elect Devices)
WINDOW SHADES
VISUAL DISPLAY BOARDS
ACOUSTICAL CEILING TILE
TOILET ACCESSORIES & PARTITIONS
FLOOR SEALER / FLOOR POLISH
FLOOR MATS
WOOD TRIMS / ARCH CASEWORK
HVCC ATEC Draft Schedule 2.2.2026 NY-01 Current Schedule-Collapsed Print date:16-Mar-26 14:11
Data Date:13-Mar-26
Actual Work
Remaining Work
Critical Remaining Work
Remaining Duration
Start Finish Total Float
185 LOCKERS 2 2 08-Apr-27 09-Apr-27 67
186 FABRICATION CRANE 5 5 08-Apr-27 14-Apr-27 64
188 DOORS & HARDWARE 10 10 08-Apr-27 21-Apr-27 59
335 MISC EQUIPMENT & FINISHES 15 15 08-Apr-27 28-Apr-27 54
121 Construction Clean 3 3 29-Apr-27 03-May-27 54
190 PUNCH LIST - Level 1A 5 5 04-May-27 10-May-27 54
AREA 1 - 1ST FLOOR AREA 1 - 1ST FLOOR 368 302 19-Jan-26 A 17-May-27 59
123 FOOTINGS & FOUNDATIONS 20 10 19-Jan-26 A 26-Mar-26 -19
138 RIGID INSULATION 5 5 19-Jan-26 A 02-Apr-26* -19
139 FOOTING DRAIN & BACKFILL 10 10 02-Mar-26 A 16-Apr-26* -19
153 EXTERIOR METAL WALL FRAMING 20 20 18-Jun-26 16-Jul-26 128
199 UNDERSLAB EXCAVATION & ROUGH IN 20 20 23-Jun-26 21-Jul-26 0
200 BACKFILL UNDERSLAB UTILITIES 10 10 22-Jul-26 04-Aug-26 30
202 SLAB PREP 15 15 05-Aug-26 25-Aug-26 30
261 Mechanical Pipe Rough-in (Level 1 Area 1) 35 35 19-Aug-26 07-Oct-26 100
205 Sprinkler Rough-in (Level 1 Area 1) 20 20 19-Aug-26 16-Sep-26 140
203 SLAB ON GRADE 5 5 26-Aug-26 01-Sep-26 30
231 Duct Rough-in (Level 1 Area 1) 35 35 02-Sep-26 21-Oct-26 75
195 METAL WALL PANELS 30 30 17-Sep-26 28-Oct-26 65
235 Sprinkler Test (Level 1 Area 1) 1 1 17-Sep-26 17-Sep-26 166
210 PAINT CEILINGS 10 10 18-Sep-26 01-Oct-26 169
285 Sprinkler Finish/Trim (Level 1 Area 1) 3 3 18-Sep-26 22-Sep-26 166
197 MASONRY VENEER 20 20 08-Oct-26* 04-Nov-26 125
206 INTERIOR WALL FRAMING 20 20 22-Oct-26 18-Nov-26 90
321 Mechanical Insulation (Level 1 Area 1) 8 8 22-Oct-26 02-Nov-26 127
305 OH Electrical Rough-in (Lighting, FA, Low Voltage) 20 20 22-Oct-26 18-Nov-26 75
196 ALUMINUM / WINDOWS 30 30 29-Oct-26 10-Dec-26 75
198 EDGE METAL 10 10 29-Oct-26 11-Nov-26 118
207 HM FRAMES 5 5 29-Oct-26 04-Nov-26 110
204 OH DOORS 5 5 19-Nov-26 25-Nov-26 90
208 MPE IN-WALL ROUGH INS 20 20 19-Nov-26 17-Dec-26 75
342 TEMP HEAT 5 5 28-Dec-26 01-Jan-27 65
209 GWB, TAPE, FINISH 20 20 04-Jan-27 29-Jan-27 65
211 PAINT WALLS 15 15 11-Jan-27 29-Jan-27 65
389 Ceiling MEP Trim (Lights, FA, RGDs) 20 20 25-Jan-27 19-Feb-27 65
212 WOOD & METAL CEILINGS 10 10 01-Feb-27 12-Feb-27 85
213 ACOUSTICAL CEILING GRID 5 5 01-Feb-27 05-Feb-27 65
216 CERAMIC TILE AT BATHROOMS 10 10 01-Feb-27 12-Feb-27 117
225 WINDOW SHADES 5 5 01-Feb-27 05-Feb-27 115
J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O
LOCKERS
FABRICATION CRANE
DOORS & HARDWARE
MISC EQUIPMENT & FINISHES
Construction Clean
PUNCH LIST - Level 1A
FOOTINGS & FOUNDATIONS
RIGID INSULATION
FOOTING DRAIN & BACKFILL
EXTERIOR METAL WALL FRAMING
UNDERSLAB EXCAVATION & ROUGH IN
BACKFILL UNDERSLAB UTILITIES
SLAB PREP
Mechanical Pipe Rough-in (Level 1 Area 1)
Sprinkler Rough-in (Level 1 Area 1)
SLAB ON GRADE
Duct Rough-in (Level 1 Area 1)
METAL WALL PANELS
Sprinkler Test (Level 1 Area 1)
PAINT CEILINGS
Sprinkler Finish/Trim (Level 1 Area 1)
MASONRY VENEER
INTERIOR WALL FRAMING
Mechanical Insulation (Level 1 Area 1)
OH Electrical Rough-in (Lighting, FA, Low Voltage)
ALUMINUM / WINDOWS
EDGE METAL
HM FRAMES
OH DOORS
MPE IN-WALL ROUGH INS
TEMP HEAT
GWB, TAPE, FINISH
PAINT WALLS
Ceiling MEP Trim (Lights, FA, RGDs)
WOOD & METAL CEILINGS
ACOUSTICAL CEILING GRID
CERAMIC TILE AT BATHROOMS
WINDOW SHADES
HVCC ATEC Draft Schedule 2.2.2026 NY-01 Current Schedule-Collapsed Print date:16-Mar-26 14:11
Data Date:13-Mar-26
Actual Work
Remaining Work
Critical Remaining Work
Remaining Duration
Start Finish Total Float
228 VISUAL DISPLAY BOARDS 5 5 01-Feb-27 05-Feb-27 95
214 ACOUSTICAL CEILING TILE 5 5 08-Feb-27 12-Feb-27 70
215 MPE WALL FINISHES/TRIM (Plumb Fixtures, Elect Devices) 15 15 15-Feb-27 05-Mar-27 75
217 TOILET ACCESSORIES & PARTITIONS 5 5 15-Feb-27 19-Feb-27 117
219 FLOOR SEALER / FLOOR POLISH 15 15 15-Feb-27 05-Mar-27 85
218 RESILENT FLOORING 7 7 08-Mar-27 16-Mar-27 85
221 FLOOR MATS 3 3 08-Mar-27 10-Mar-27 104
227 DOORS & HARDWARE 7 7 08-Mar-27 16-Mar-27 100
336 MISC EQUIPMENT & FINISHES 20 20 08-Mar-27 02-Apr-27 75
222 WOOD TRIMS / ARCH CASEWORK 15 15 17-Mar-27 06-Apr-27 85
229 PUNCH LIST - Level 1 (Area 1) 5 5 06-May-27 12-May-27 52
230 Construction Clean (Level 1 Area 1) 3 3 13-May-27 17-May-27 59
AREA 2 - 1ST FLOOR AREA 2 - 1ST FLOOR 350 294 24-Nov-25 A 12-May-27 52
126 FOOTINGS & FOUNDATIONS 20 0 24-Nov-25 A 13-Mar-26 A
140 RIGID INSULATION 5 0 19-Jan-26 A 20-Mar-26* -2
141 FOOTING DRAIN & BACKFILL 10 10 19-Jan-26 A 02-Apr-26* -2
127 EXTERIOR METAL WALL FRAMING 15 15 10-Jul-26 30-Jul-26 128
236 UNDERSLAB EXCAVATION & ROUGH IN 30 30 22-Jul-26 01-Sep-26 0
306 Underslab Duct Rough-in (Dyno) 5 5 22-Jul-26 28-Jul-26 25
237 BACKFILL 10 10 02-Sep-26 16-Sep-26 0
239 SLAB PREP 15 15 17-Sep-26 07-Oct-26 0
240 SLAB ON GRADE 5 5 08-Oct-26 14-Oct-26 5
288 Duct Rough-in (Level 1 Area 2) 35 35 15-Oct-26 03-Dec-26 30
308 Mechanical Pipe Rough-in (Level 1 Area 2) 35 35 22-Oct-26 10-Dec-26 40
358 Sprinkler Rough-in (Level 1 Area 2) 20 20 22-Oct-26 18-Nov-26 99
232 METAL WALL PANELS 25 25 29-Oct-26 03-Dec-26 65
234 MASONRY VENEER 15 15 05-Nov-26 25-Nov-26 125
233 ALUMINUM / WINDOWS 25 25 19-Nov-26 24-Dec-26 65
368 Sprinkler Test (Level 1 Area 2) 1 1 19-Nov-26 19-Nov-26 99
378 Sprinkler Finishes / Trim (Level 1 Area 2) 3 3 20-Nov-26 24-Nov-26 118
244 HM FRAMES 5 5 04-Dec-26 10-Dec-26 75
331 OH Electrical Rough-in (Power, FA, Low Voltage) 20 20 04-Dec-26 01-Jan-27 30
243 INTERIOR WALL FRAMING 15 15 11-Dec-26 01-Jan-27 40
348 Mechanical Insulation 8 8 11-Dec-26 22-Dec-26 82
241 OH DOORS 5 5 04-Jan-27 08-Jan-27 45
245 MPE IN-WALL ROUGH INS 20 20 04-Jan-27 29-Jan-27 30
246 GWB, TAPE, FINISH 20 20 01-Feb-27 26-Feb-27 30
248 PAINT WALLS 15 15 08-Feb-27 26-Feb-27 35
312 Ceiling MEP Trim (Lights, FA, RGDs etc) 20 20 22-Feb-27 19-Mar-27 45
J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O
VISUAL DISPLAY BOARDS
ACOUSTICAL CEILING TILE
MPE WALL FINISHES/TRIM (Plumb Fixtures, Elect Devices)
TOILET ACCESSORIES & PARTITIONS
FLOOR SEALER / FLOOR POLISH
RESILENT FLOORING
FLOOR MATS
DOORS & HARDWARE
MISC EQUIPMENT & FINISHES
WOOD TRIMS / ARCH CASEWORK
PUNCH LIST - Level 1 (Area 1)
Construction Clean (Level 1 Area 1)
FOOTINGS & FOUNDATIONS
RIGID INSULATION
FOOTING DRAIN & BACKFILL
EXTERIOR METAL WALL FRAMING
UNDERSLAB EXCAVATION & ROUGH IN
Underslab Duct Rough-in (Dyno)
BACKFILL
SLAB PREP
SLAB ON GRADE
Duct Rough-in (Level 1 Area 2)
Mechanical Pipe Rough-in (Level 1 Area 2)
Sprinkler Rough-in (Level 1 Area 2)
METAL WALL PANELS
MASONRY VENEER
ALUMINUM / WINDOWS
Sprinkler Test (Level 1 Area 2)
Sprinkler Finishes / Trim (Level 1 Area 2)
HM FRAMES
OH Electrical Rough-in (Power, FA, Low Voltage)
INTERIOR WALL FRAMING
Mechanical Insulation
OH DOORS
MPE IN-WALL ROUGH INS
GWB, TAPE, FINISH
PAINT WALLS
Ceiling MEP Trim (Lights, FA, RGDs etc)
HVCC ATEC Draft Schedule 2.2.2026 NY-01 Current Schedule-Collapsed Print date:16-Mar-26 14:11
Data Date:13-Mar-26
Actual Work
Remaining Work
Critical Remaining Work
Remaining Duration
Start Finish Total Float
247 PAINT CEILINGS 10 10 01-Mar-27 12-Mar-27 30
249 WOOD & METAL CEILINGS 15 15 01-Mar-27 19-Mar-27 52
250 ACOUSTICAL CEILING GRID 5 5 01-Mar-27 05-Mar-27 35
253 CERAMIC TILE AT BATHROOMS 10 10 01-Mar-27 12-Mar-27 85
262 WINDOW SHADES 5 5 01-Mar-27 05-Mar-27 92
265 VISUAL DISPLAY BOARDS 3 3 01-Mar-27 03-Mar-27 74
337 MISC EQUIPMENT & FINISHES 20 20 04-Mar-27 31-Mar-27 74
252 MPE WALL FINISHES/TRIM (Plumb Fixtures, Elect Devices) 15 15 15-Mar-27 02-Apr-27 30
254 TOILET ACCESSORIES & PARTITIONS 5 5 15-Mar-27 19-Mar-27 85
256 FLOOR SEALER / FLOOR POLISH 15 15 22-Mar-27 09-Apr-27 52
251 ACOUSTICAL CEILING TILE 5 5 05-Apr-27 09-Apr-27 30
255 RESILENT FLOORING 5 5 12-Apr-27 16-Apr-27 52
258 FLOOR MATS 3 3 12-Apr-27 14-Apr-27 64
264 DOORS & HARDWARE 7 7 12-Apr-27 20-Apr-27 60
322 LAB METAL CASEWORK & EQ 15 15 12-Apr-27 30-Apr-27 52
259 WOOD TRIMS / ARCH CASEWORK 10 10 19-Apr-27 30-Apr-27 52
267 Construction Clean 3 3 03-May-27 05-May-27 52
266 PUNCH LIST - Level 1 (Area 2) 5 5 06-May-27 12-May-27 52
AREA 1 - 2ND FLOOR / ROOFAREA 1 - 2ND FLOOR / ROOF 236 236 07-Aug-26 07-Jul-27 12
143 ROOFING 30 30 07-Aug-26 18-Sep-26 118
268 SOD PREP 10 10 08-Oct-26 21-Oct-26 0
269 SLAB ON DECK 5 5 22-Oct-26 28-Oct-26 0
287 Duct Rough-in (Level 2) 60 60 29-Oct-26 22-Jan-27 0
297 Mechanical Pipe Rough-in (Level 2) 60 60 12-Nov-26 05-Feb-27 0
304 Sprinkler Rough-in (Level 2) 25 25 12-Nov-26 17-Dec-26 100
144 EDGE METAL 10 10 04-Dec-26 17-Dec-26 103
314 Sprinkler Test (Level 2) 1 1 18-Dec-26 18-Dec-26 100
344 Sprinkler Finishes / Trim (Level 2) 2 2 21-Dec-26 22-Dec-26 100
334 Classroom Folding Partitions 5 5 13-Jan-27 19-Jan-27 125
271 INTERIOR WALL FRAMING 15 15 25-Jan-27 12-Feb-27 25
272 HM FRAMES 5 5 01-Feb-27 05-Feb-27 40
557 Mechanical Insulation 30 30 08-Feb-27 19-Mar-27 25
356 OH Electrical Rough-in (Power, FA, Low Voltage) 20 20 08-Feb-27 05-Mar-27 0
273 MPE IN-WALL ROUGH INS 20 20 08-Mar-27 02-Apr-27 0
274 GWB, TAPE, FINISH 15 15 05-Apr-27 23-Apr-27 0
276 PAINT WALLS 15 15 05-Apr-27 23-Apr-27 0
275 PAINT CEILINGS 10 10 26-Apr-27 07-May-27 12
277 WOOD & METAL CEILINGS 15 15 26-Apr-27 14-May-27 13
278 ACOUSTICAL CEILING GRID 10 10 26-Apr-27 07-May-27 0
J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O
PAINT CEILINGS
WOOD & METAL CEILINGS
ACOUSTICAL CEILING GRID
CERAMIC TILE AT BATHROOMS
WINDOW SHADES
VISUAL DISPLAY BOARDS
MISC EQUIPMENT & FINISHES
MPE WALL FINISHES/TRIM (Plumb Fixtures, Elect Devices)
TOILET ACCESSORIES & PARTITIONS
FLOOR SEALER / FLOOR POLISH
ACOUSTICAL CEILING TILE
RESILENT FLOORING
FLOOR MATS
DOORS & HARDWARE
LAB METAL CASEWORK & EQ
WOOD TRIMS / ARCH CASEWORK
Construction Clean
PUNCH LIST - Level 1 (Area 2)
ROOFING
SOD PREP
SLAB ON DECK
Duct Rough-in (Level 2)
Mechanical Pipe Rough-in (Level 2)
Sprinkler Rough-in (Level 2)
EDGE METAL
Sprinkler Test (Level 2)
Sprinkler Finishes / Trim (Level 2)
Classroom Folding Partitions
INTERIOR WALL FRAMING
HM FRAMES
Mechanical Insulation
OH Electrical Rough-in (Power, FA, Low Voltage)
MPE IN-WALL ROUGH INS
GWB, TAPE, FINISH
PAINT WALLS
PAINT CEILINGS
WOOD & METAL CEILINGS
ACOUSTICAL CEILING GRID
HVCC ATEC Draft Schedule 2.2.2026 NY-01 Current Schedule-Collapsed Print date:16-Mar-26 14:11
Data Date:13-Mar-26
Actual Work
Remaining Work
Critical Remaining Work
Remaining Duration
Start Finish Total Float
281 CERAMIC TILE AT BATHROOMS 10 10 26-Apr-27 07-May-27 42
289 WINDOW SHADES 5 5 26-Apr-27 30-Apr-27 52
292 VISUAL DISPLAY BOARDS 3 3 26-Apr-27 28-Apr-27 54
290 Ceiling MEP Trim (Lights, FA, RGDs etc) 20 20 26-Apr-27 21-May-27 0
279 ACOUSTICAL CEILING TILE 5 5 10-May-27 14-May-27 5
280 MPE WALL FINISHES (Plumb Fixtures, Elect Devices) 15 15 10-May-27 28-May-27 12
282 TOILET ACCESSORIES & PARTITIONS 5 5 10-May-27 14-May-27 42
284 FLOOR SEALER / FLOOR POLISH 15 15 17-May-27 04-Jun-27 13
338 MISC EQUIPMENT & FINISHES 20 20 31-May-27 25-Jun-27 12
283 RESILENT FLOORING / CARPET 7 7 07-Jun-27 15-Jun-27 13
291 DOORS & HARDWARE 7 7 07-Jun-27 15-Jun-27 20
286 WOOD TRIMS / ARCH CASEWORK 7 7 16-Jun-27 24-Jun-27 13
294 Construction Clean (Level 2) 3 3 28-Jun-27 30-Jun-27 12
293 PUNCH LIST - Level 2 (Area 1) 5 5 01-Jul-27 07-Jul-27 12
AREA 2 - MECH ROOM /ROOFAREA 2 - MECH ROOM /ROOF 198 198 21-Sep-26 25-Jun-27 20
148 ROOFING 30 30 21-Sep-26 30-Oct-26 118
295 SLAB PREP 5 5 22-Oct-26 28-Oct-26 58
296 SLAB ON DECK 2 2 29-Oct-26 30-Oct-26 58
298 INTERIOR WALL FRAMING 7 7 02-Nov-26 10-Nov-26 71
316 Duct & Mechanical Pipe (Mech Room) 60 60 02-Nov-26 26-Jan-27 78
366 Electrical Rough-in 45 45 02-Nov-26 05-Jan-27 58
299 HM FRAMES 3 3 09-Nov-26 11-Nov-26 95
300 MPE WALL ROUGH INS 20 20 09-Nov-26 07-Dec-26 71
301 GWB, TAPE, FINISH 7 7 08-Dec-26 16-Dec-26 71
302 PAINT CEILINGS 5 5 17-Dec-26 23-Dec-26 71
149 EDGE METAL 7 7 18-Dec-26 29-Dec-26 103
303 PAINT WALLS 5 5 06-Jan-27 12-Jan-27 58
Electrical Trim (Lights, FA, Security) 15 15 13-Jan-27 02-Feb-27 58
346 Mechanical Insulation 20 20 27-Jan-27 23-Feb-27 78
311 FLOOR SEALER / FLOOR POLISH 5 5 03-Feb-27 09-Feb-27 58
307 MPE FINISHES 15 15 10-Feb-27 02-Mar-27 58
318 DOORS & HARDWARE 7 7 10-Feb-27 18-Feb-27 81
339 MISC EQUIPMENT & FINISHES 20 20 24-Feb-27 23-Mar-27 78
349 PUNCHLIST - Level 2 Mech Room/Roof 10 10 14-Jun-27 25-Jun-27 20
Mechanical EquipmentMechanical Equipment 25 25 02-Nov-26 07-Dec-26 118
313 Set Rooftop Equipment 20 20 02-Nov-26 30-Nov-26 118
383 Set Cooling Tower 5 5 02-Nov-26 06-Nov-26 138
343 Roof Top Equipment Piping Tie-ins 5 5 01-Dec-26 07-Dec-26 118
J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O
CERAMIC TILE AT BATHROOMS
WINDOW SHADES
VISUAL DISPLAY BOARDS
Ceiling MEP Trim (Lights, FA, RGDs etc)
ACOUSTICAL CEILING TILE
MPE WALL FINISHES (Plumb Fixtures, Elect Devices)
TOILET ACCESSORIES & PARTITIONS
FLOOR SEALER / FLOOR POLISH
MISC EQUIPMENT & FINISHES
RESILENT FLOORING / CARPET
DOORS & HARDWARE
WOOD TRIMS / ARCH CASEWORK
Construction Clean (Level 2)
PUNCH LIST - Level 2 (Area 1)
ROOFING
SLAB PREP
SLAB ON DECK
INTERIOR WALL FRAMING
Duct & Mechanical Pipe (Mech Room)
Electrical Rough-in
HM FRAMES
MPE WALL ROUGH INS
GWB, TAPE, FINISH
PAINT CEILINGS
EDGE METAL
PAINT WALLS
Electrical Trim (Lights, FA, Security)
Mechanical Insulation
FLOOR SEALER / FLOOR POLISH
MPE FINISHES
DOORS & HARDWARE
MISC EQUIPMENT & FINISHES
PUNCHLIST - Level 2 Mech Room/Roof
Set Rooftop Equipment
Set Cooling Tower
Roof Top Equipment Piping Tie-ins
HVCC ATEC Draft Schedule 2.2.2026 NY-01 Current Schedule-Collapsed Print date:16-Mar-26 14:11
Data Date:13-Mar-26
Actual Work
Remaining Work
Critical Remaining Work
Remaining Duration
Start Finish Total Float
COMMISSIONING, STARTUP & TESTINGCOMMISSIONING, STARTUP & TESTING 307 307 14-May-26 23-Jul-27 10
487 Fire Alarm Certification 10 10 25-Mar-27 07-Apr-27 87
317 MEP START-UP & CHECKOUT 15 15 24-May-27 11-Jun-27 0
357 Testing and Balancing of HVAC Systems 30 30 14-Jun-27 23-Jul-27 0
Building PowerBuilding Power 189 189 14-May-26 09-Feb-27 88
467 Underslab Conduits & Floor Boxes 31 31 14-May-26 26-Jun-26 46
507 Feeder Wire - 1st Floor 30 30 29-Jun-26 10-Aug-26 171
367 Main Underground Conduits 5 5 07-Jul-26 13-Jul-26 179
407 Install New Elect Manhole 2 2 07-Jul-26 08-Jul-26 184
427 Site Lighting Conduit 8 8 07-Jul-26 16-Jul-26 220
497 Grounding 15 15 07-Jul-26 27-Jul-26 186
417 High Voltage Conduit 3 3 09-Jul-26 13-Jul-26 184
377 Equipment Pads / Conduit 2 2 14-Jul-26 15-Jul-26 179
477 Equipment Pad Grounding 5 5 14-Jul-26 20-Jul-26 179
457 Wire Pull (Site) & Set Poles 13 13 17-Jul-26 04-Aug-26 220
387 Set Transformer 2 2 21-Jul-26 22-Jul-26 179
397 Set 4 Way Switch 2 2 21-Jul-26 22-Jul-26 179
437 Temporary Generator 10 10 23-Jul-26 05-Aug-26 179
447 SHUTDOWN - High Voltage Wire Pull 10 10 06-Aug-26 19-Aug-26 179
547 Final Connections and Testing at Switch 5 5 20-Aug-26 26-Aug-26 179
517 Feeder Conduits - 2nd Floor 20 20 02-Nov-26 30-Nov-26 68
527 Feeder Wire - 2nd Floor 20 20 01-Dec-26 29-Dec-26 73
537 Gear Install 20 20 30-Dec-26 26-Jan-27 73
347 Permanent Power 10 10 27-Jan-27 09-Feb-27 73
PUNCHLIST / SUBSTANTIAL COMPLETION / CLOSEOUTPUNCHLIST / SUBSTANTIAL COMPLETION / CLOSEOUT 21 21 26-Jul-27 23-Aug-27 0
320 Final Punch List & Cleaning 10 10 26-Jul-27 06-Aug-27 0
86 Substantial Completion 0 0 06-Aug-27 0
84 Demobilization 5 5 09-Aug-27 13-Aug-27 6
340 CERTIFICATE OF OCCUPANCY 10 10 09-Aug-27 20-Aug-27 0
85 Owner move in 1 1 23-Aug-27 23-Aug-27 0
J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O
Fire Alarm Certification
MEP START-UP & CHECKOUT
Testing and Balancing of HVAC Systems
Underslab Conduits & Floor Boxes
Feeder Wire - 1st Floor
Main Underground Conduits
Install New Elect Manhole
Site Lighting Conduit
Grounding
High Voltage Conduit
Equipment Pads / Conduit
Equipment Pad Grounding
Wire Pull (Site) & Set Poles
Set Transformer
Set 4 Way Switch
Temporary Generator
SHUTDOWN - High Voltage Wire Pull
Final Connections and Testing at Switch
Feeder Conduits - 2nd Floor
Feeder Wire - 2nd Floor
Gear Install
Permanent Power
Final Punch List & Cleaning
Substantial Completion
Demobilization
CERTIFICATE OF OCCUPANCY
Owner move in
HVCC ATEC Draft Schedule 2.2.2026 NY-01 Current Schedule-Collapsed Print date:16-Mar-26 14:11
Data Date:13-Mar-26
Actual Work
Remaining Work
Critical Remaining Work