Request for Pre-Qualifications | Phase 1 | MP12 B and C - 500 South Capacity Upgrades - CMGC
Solicitation number
525003195
Issued by
Salt Lake County, Salt Lake City, Utah

About this file

This is a Request for Qualifications (RFQ) Phase 1 document issued by the Salt Lake City Department of Public Utilities for Construction Manager/General Contractor (CMGC) services related to the MP12 B and C - 500 South Capacity Upgrades project. The project involves intercepting and extending existing 24-inch diameter force mains from Gladiola Street to a discharge point upstream of the 500 South Lift Station near Orange Street. Major construction challenges include crossings of the Surplus Canal, a railroad corridor (one SLG & W track and three UPRR tracks), and I-215. The scope includes construction of two of three force mains initially, with the third added as flow conditions demand, and installation of all three force mains at critical crossing points to minimize future construction and permitting efforts. Statements of Qualifications must be submitted through the Utah Public Procurement Place (U3P) website no later than 2:00 PM Mountain Standard Time on Wednesday, December 9, 2026. The CMGC contract will encompass pre-construction and procurement services, with the project milestones including CMGC procurement from October 2026 through March 2027 and 60% design completion targeted for January through April 2026.

The anticipated CMGC contract price ranges from $25 million to $35 million. The project schedule indicates ongoing design and planning phases with procurement activities occurring through early 2027. No set-asides are explicitly identified in the prequalification documents. This project represents a significant infrastructure investment by the Salt Lake City Department of Public Utilities to enhance wastewater system capacity and address flow management requirements in the 500 South corridor.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

EJCDC® CMAR-200, Request for Qualifications –Construction Manager at Risk Series.

Copyright© 2023 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

REQUEST FOR QUALIFICATIONS—

CONSTRUCTION MANAGER AT RISK SERIES

ARTICLE 1—GENERAL INFORMATION

1.01 Definitions

A. Terms used in the Proposal Documents have the meanings indicated in the General Conditions and Supplementary Conditions. Additional terms have the meanings indicated below:

1. Proposal Documents—The Advertisement of Request for Qualifications (Advertisement), Request for Qualifications, Statement of Qualifications, Request for Proposals, Proposal, Proposal Bond, and other documents so designated in Paragraph 1.04.

2. Proposer—A Construction Manager at Risk (CMAR) entity that submits a Statement of Qualifications and, if invited to do so in a two-step selection process, submits a Proposal for the CMAR Contract. The Proposer / CMAR team includes the CM/GC and Tunneling Teaming Partner.

3. Construction Manager at Risk (CMAR) & Construction Manager / General Contractor (CM/GC) – In this document, the Construction Manager at Risk (CMAR) entity is used synonymously with the term Construction Manager / General Contractor (CM/GC) entity. A CM/GC may only submit one Statement of Qualifications.

4. Tunneling Teaming Partner - In this document, the Tunneling Teaming Partner refers to a Contractor that submits a Statement of Qualifications in conjunction with the CM/GC for the CMAR Contract. A Tunneling Teaming Partner may team and submit a Statement of Qualifications with multiple CM/GC entities.

5. Subcontractor – In this document, a subcontractor refers to any subcontractor outside of the CM/GC and Tunneling Teaming Partner.

6. Request for Qualifications (RFQ)—The document issued by Owner to prospective Proposers requesting that they submit qualifications and other information to be used by the Owner in ranking Proposers and either selecting the successful Proposer in a one-step selection process or determining which Proposers in a two-step selection process will be invited to submit a Proposal for the CMAR Contract.

7. Statement of Qualifications (SOQ)—The document submitted to Owner by a Proposer in response to the RFQ, including any completed forms, attachments, and exhibits, to demonstrate experience, competence, and ability to successfully perform the CMAR Services and furnish and complete the Work.

8. Request for Proposal (RFP)—The document issued directly to the most highly ranked Proposers in a two-step selection process based on evaluations of the submitted Statements of Qualifications, asking each selected Proposer to submit a Proposal for providing CMAR Services and furnishing and completing the Work.

9. Proposal—The document submitted to Owner by a Proposer in response to the RFP, including any completed forms, attachments, and exhibits presenting the compensation

Copyright© 2023 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

(price) terms to be included in the Agreement between Owner and Construction Manager at Risk if the selected Proposer is awarded the CMAR Contract.

10. Proposal Bond—The surety bond provided by Proposer at the time the Proposal is submitted and held by Owner until the Agreement is executed and the evidence of insurance and bonds required by the Contract Documents are provided.

B. In addition to terms specifically defined, terms with initial capital letters in the Proposal Documents include references to identified articles and paragraphs, and the titles of other documents or forms.

1.02 Project Description

A. The Project is identified as:

Owner: Salt Lake City Department of Public Utilities Project Name: MP12B and C - 500 South Capacity Upgrades Project Number: 525003195

B. The scope of the CMAR Contract is summarized as follows:

The project will be located in the northwest quadrant of Salt Lake City, Utah. An overall project exhibit is attached to this RFQ depicting the project location and major components of the project. The previous phase of this project installed a new sewer pump station and two 24-inch force mains discharging to the 500 South Sewer at Gladiola Street (3400 W). This project will intercept the existing 24-inch diameter 700 South force mains on the north side of the railroad tracks at Gladiola Street and will extend them from that location to a discharge point upstream of the 500 South Lift Station near Orange Street. The project includes construction of two of the three force mains with the third being added as flow conditions demand. Each tunnel/crossing or other critical points will include installation of all three force mains to avoid multiple construction and permitting efforts in the future. Major crossings include the Surplus Canal, a railroad corridor (one SLG&W track and three UPRR tracks), and I-215.

C. OWNER'S RIGHTS RESERVED:

The OWNER reserves the right to prequalify any or all contractors, request additional information, and/or to modify the schedule and scope of this project.

1.03 Selection Process

A. The Owner is issuing this Request for Qualifications as the first step in a two-step process for selecting a CMAR. First step: Owner will receive and evaluate SOQs based on the prescribed selection criteria (which will not include price) to determine which of the responding Proposers the Owner deems qualified to propose on the Project.

1. In the second step, Owner will issue a Request for Proposals to the Proposers deemed qualified to propose on the Project, inviting each thus identified to submit proposed prices for CMAR Services, Construction Support Costs, the CMAR Fee on the Cost of the Work, and an Estimated Preliminary Guaranteed Maximum Price based on the Estimated Cost of the Work.

1.04 Proposal Documents

A. Instructions for obtaining the Proposal Documents are set forth in the Advertisement.

Copyright© 2023 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

B. Proposers must obtain a complete set of the Proposal Documents indicated below for use in preparation of the Statement of Qualifications. Proposers are responsible for ensuring that a complete set of documents is obtained and used and assume sole responsibility for errors or misinterpretations resulting from the use of incomplete Proposal Documents. For those Proposers that qualify for the Proposal step, the Owner will provide additional Proposal Documents as attachments to the Request for Proposals.

The Proposal Documents available for the Statement of Qualifications step consist of the following:

1. Advertisement;

2. Request for Qualifications;

3. Statement of Qualifications Certification and Attachments;

4. Informational Documents including:

a. Project Exhibit

b. GEI Documents

C. For those Proposers that are invited to submit a Proposal, the Owner will issue the following additional Proposal Documents:

1. Request for Proposals;

2. Proposal Certification and Attachments;

3. 60% Design Drawings;

4. Homeland Security Request Form

5. Interim drafts of Contract Documents (including draft Front End Contract Documents), to be determined.

D. Owner makes copies of the Proposal Documents, including any Addenda and related supplemental data, available for the sole purpose of obtaining Statements of Qualifications or, subsequently, as to Proposal Documents issued to short-listed Proposers only, to obtain Proposals, and does not confer a license or grant permission or authorization for any other use. Authorization to download documents includes the right for Proposers to print documents for their use. Electronic or printed documents may not be re-sold under any circumstances.

1.05 Information Conference

A. Owner does not presently plan to conduct an Information Conference regarding the CMAR Contract and CMAR selection process.

1.06 Examination of Proposal Documents

A. Examine the Proposal Documents before submitting a Statement of Qualifications.

1. Carefully study the Proposal Documents, including any draft or supplemental information made available to the Proposer.

2. Become familiar with all federal, state, and local Laws and Regulations that may affect cost, progress, or the completion of Work.

Copyright© 2023 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

3. Make observations and investigations, correlate knowledge and observations with the requirements of the Proposal Documents and consider these in preparation of a Statement of Qualifications.

4. Determine that the Proposal Documents, Addenda, and supplemental data are adequate to indicate and convey understanding of all terms and conditions for preparing a Statement of Qualifications.

5. Promptly notify the Owner’s Advisor of all conflicts, errors, ambiguities, or discrepancies that the Proposer discovers in the Proposal Documents, Addenda, or supplemental information.

B. The submission of a Statement of Qualifications will constitute an incontrovertible representation by the Proposer that it has complied with every requirement of the RFQ and other Proposal Documents, that the Proposer has given the Owner’s Advisor written notice of all conflicts, errors, ambiguities, and discrepancies that the Proposer has discovered in the Proposal Documents, and that the Proposal Documents indicate and convey understanding of all terms and conditions required for preparation of the Proposal.

1.07 Site Visit

A. Owner will subsequently provide Site visit instructions to short-listed Proposers in the Request for Proposals.

1.08 Questions regarding the Statement of Qualifications

A. Submit questions about the meaning or intent of the Proposal Documents, Addenda, and the related supplemental data to U3P. All inquiries must be received no later than 7 days prior to the date for submittal of SOQs. Responses deemed materially relevant to the RFQ/SOQ will be issued by Addenda posted to U3P to all contractors who have recorded receipt of the

RFQ.

B. Responses to questions will be posted on the designated website for the benefit of all Proposers. Responses to questions do not modify or supplement the Proposal Documents, including any draft Contract Documents, unless set forth in an Addendum that expressly modifies or supplements such Documents. Any response that requires a modification or supplementation of the Proposal Documents, including any draft Contract Documents, will be made by Addendum posted on the designated website. Owner will not be responsible for any explanations or interpretations other than those posted.

1.09 Addenda

A. The Owner reserves the right to issue Addenda to the Proposal Documents. Proposer is responsible for being aware of all Addenda issued by the Owner.

1.10 Confidentiality of Submitted Information

A. To the fullest extent permitted by Laws and Regulations:

1. Trade secrets and confidential information in Statements of Qualifications, and subsequently in Proposals, are not open for public inspection;

2. Statements of Qualifications and Proposals will be opened in a manner that avoids disclosure of confidential information to competing Proposers and keeps the

Copyright© 2023 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Statements of Qualifications and Proposals from the public until a CMAR Contract is awarded; and

3. If it is necessary to make Statements of Qualifications or Proposals open for public inspection after the CMAR Contract is awarded, trade secrets and confidential information in Statements of Qualifications or Proposals will be shielded from public inspection.

B. Each Proposer must clearly indicate in its SOQ submittal, and subsequently in a Proposal, which specific documents are considered to be trade secrets or confidential information by stamping or watermarking all such documents with the word “confidential” prominently on each page or sheet or on the cover of bound Documents. Place “confidential” stamps or watermarks so that they do not obscure any of the required information on the document, either in the original or in a way that would obscure any of the required information in a photocopy of the document. Submit all confidential information in a distinct binder or electronic file so this confidential material is separate from the rest of the SOQ or Proposal.

C. The Owner is a governmental body subject to the limitations of Laws and Regulations and has limited authority to withhold confidential information submitted by Proposers when presented with an open records request. The Owner, upon receiving an application or other request for the disclosure of confidential information, will promptly notify Proposer of the request as required by Laws and Regulations. Proposer may request a ruling by the agency having jurisdiction as to whether any such information may be withheld.

D. Proposer acknowledges and agrees that it will be solely responsible for submitting any arguments, authorities, or other information to the agency having jurisdiction regarding release of the information marked as confidential as provided by Laws and regulations, and that if disclosure is required by the agency having jurisdiction, the Owner has no liability for releasing this information and Proposer will not be entitled to exercise any remedy for a disclosure made pursuant to the Laws and Regulations.

E. The obligations of the Owner, as recipient of information indicated to be confidential in a Statement of Qualifications or Proposal, are subject to the following exceptions:

1. If confidential information becomes a part of the public domain through publication or otherwise but through no fault of the Owner;

2. If Owner can demonstrate through suitable documentation that the confidential information was already in the Owner’s possession or otherwise publicly available prior to the date of disclosure;

3. If the confidential information is subsequently disclosed to Owner by a third party who has a lawful right to disclose such information; or

4. If Owner is required to disclose the confidential information by court order or by applicable law.

F. If the Owner is requested or becomes legally compelled, by oral questions, interrogatories, requests for information or documents, subpoena, civil or criminal investigative demand, public information requests, including requests under Laws and Regulations, or similar process, or is required by a regulatory body to make any disclosure that is prohibited or otherwise constrained by this RFQ, the Owner will provide Proposer with prompt notice of

Copyright© 2023 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

this request so that Proposer may seek an appropriate protective order or other appropriate remedy.

G. By submitting a Statement of Qualifications or Proposal, the Proposer consents to the procedure outlined in this section of the RFQ as its sole remedy and waives any claim against the Owner because of actions taken under this procedure.

1. Notwithstanding any other provision of the RFQ, it is stipulated and agreed that by accepting a Statement of Qualifications or Proposal, the Owner has not and does not waive its sovereign immunity from suit and/or liability.

2. To the extent that the Owner withholds from disclosure all or any portion of Proposer’s documents at Proposer’s request, Proposer, by submitting a Statement of Qualifications or Proposal in response to this RFQ or a RFP agrees to fully indemnify, defend, and hold harmless the Owner from all damages, penalties, attorneys’ fees and costs the Owner incurs related to withholding information from public disclosure.

ARTICLE 2—EVALUATION CRITERIA

2.01 Evaluation Categories

A. The table in this paragraph lists the rating categories (1 through 6) by which Owner will score the SOQs. Rating categories 1 through 6 will be applied to the evaluation of the Statements of Qualifications. The maximum point value for each category is indicated in the final column of the table:

Rating Category

Description Point Value

Minimum Qualifications / Experience

1.a Project Experience 1.b CM/GC Experience

Pass/Fail Pass/Fail

2 Business Office in the state of Utah & Utah Contractor’s License Pass/Fail 3 Bonding and Insurance Requirements Pass/Fail

Legal 4.a Pending litigation?

4.b Litigation against company in last 3 years?

4.c E-Verify program

Yes/No Yes/No

Pass/Fail 5 Safety Record EMR Rating < 1.1 Pass/Fail 6 Confidentiality and Ethics Clause Pass/Fail

2.02 Evaluation for Rating Categories

A. Rating Category 1.a—Experience/Past Performance of Proposer (Pass/Fail)

1. Owner will consider the experience and past performance of the Proposer as a company, including, but not limited to:

a. Proposer’s current experience and performance on similar projects; The CM/GC shall demonstrate successful experience managing specialty contractors on projects of similar size, complexity, and risk.

1) Demonstrates ability to complete quality projects on time and within budget as demonstrated by SOQ information.

Copyright© 2023 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

b. Qualifications of the offered management team;

c. Contractors shall submit qualifications/experience shown as projects on the forms provided in Attachment A or use the Contractor’s forms that include all the information shown in Attachment A.

2. Companies that cannot meet the requirements for similar projects defined in the Statement of Qualifications may be disqualified.

B. Rating Category 1.b—CM/GC Experience of Proposer (Pass/Fail)

1. Submit a list of the five (5) most recent CM/GC Projects completed by the Proposer using Attachment B.

C. Rating Category 2—Business Office in the state of Utah & Utah Contractor’s License (Pass/Fail)

1. Note the location of the Contractor’s office.

2. Submit a current copy of the Utah Contractor’s License. The Contractor’s License must be current on the date the SOQs are due. License shall be for classification appropriate to the project. Having a current Utah Contractor’s license is required for passing the license criteria.

D. Rating Category 3—Bonding and Insurance Requirements (Pass/Fail)

1. General Contractors shall submit a signed letter from a surety that the General Contractor has available unused bonding capacity equal to the estimated contract value of $25-35M USD. The surety companies providing the letters shall be named in the list of “Companies Holding Certificates of Authority as Acceptable Sureties on Federal Bonds and as Acceptable Reinsuring Companies” as published in Circular 570 (amended) by the Financial Management Service, Surety Bond Branch, U.S. Department of the Treasury.

The letters from the surety shall list the GC; joint ventures or listing of multiple companies to achieve the bonding capacity is not acceptable. Providing a surety letter that meets these requirements is required for passing the bonding criteria. Provide the maximum bonding capacity and the ratio of available bonding capacity.

2. The insurance requirements for the Contractor are those described in EJCDC C-700 General Conditions and Supplementary Conditions for insurance to be purchased and maintained by the Contractor and any renewals thereof for the duration of the project.

See Attachment C for full description.

E. Rating Category 4—Legal (Pass/Fail)

1. General Contractors shall submit a signed letter from a surety that the General Contractor has available unused bonding capacity equal to the estimated contract value of $25-35M.

2. Submit a list of any legal judgments awarded against the GC in favor of owners or subcontractors during the period of 2016 to 2026 or a statement that there are no judgments. The Owner reserves the right to further investigate the conditions and context of any legal judgments to determine GC’s ability to execute the project and to determine whether or not to assign a pass or fail designation.

Copyright© 2023 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

3. Also, submit a list of any pending litigation and any litigation that was settled prior to judgment during the period 2016 to 2026.

4. Contractor shall sign Certificate of Compliance with E-Verification Program. See Attachment D.

F. Rating Category 5—Safety Record EMR Rating < 1.1 (Pass/Fail)

1. Provide a one page summary of the firm’s safety record utilizing EMR methodologies, Include a 5 year record. EMR shall be less than 1.1.

G. Rating Category 6—Confidentiality and Ethics Clauses (Pass/Fail)

1. Sign (Attachment E) and attach to SOQ.

2.03 The Statement of Qualifications (SOQ) as submitted must include the information described in this RFQ, as a minimum, to allow the Owner (a) to assess the qualifications of each Proposer to successfully perform CMAR Services and complete the Work, and (b) to rank the Proposer’s qualifications objectively and as compared to the qualifications of other prospective Proposers.

The information requested in the RFQ must be provided completely and in detail.

2.04 The SOQ as furnished to Proposers is set up to require that certain information be provided in forms included in the SOQ. The information in these forms will be used to make direct comparisons with the information provided by other Proposers in response to this RFQ. Failure to submit the required information in the Statement of Qualifications may result in the Owner considering the Proposer as non-responsive. Failure to provide the information completely and clearly may result in lower scores in the evaluations which could result in the Proposer not being invited to submit a Proposal. Proposers may be required to provide supplemental information, if so requested by the Owner, to clarify, enhance, or supplement the information provided in the Statement of Qualifications.

2.05 Information requested in the forms that cannot be totally incorporated in the forms may be included as an appendix to the form. This appendix must be clearly referenced by appendix number on the form, and the appended material must include the appendix number on every sheet of the appendix. The appendix must include only the information that responds to the question or item number to which the appendix applies.

2.06 The information requested is used to address each of the selection categories presented in the RFQ (not including any price category) and should be presented in that order and be keyed specifically for each selection category. Proposers may provide supplemental information to the Statement of Qualifications such as organizational brochures or other marketing information to help demonstrate their qualifications to the Owner. This supplemental information may not be submitted as a substitute for the information specifically requested in this document. The reference must include the specific selection category to demonstrate strengths for each criterion.

2.07 Proposal Format and Presentation

A. Provide an electronic copy of the SOQ. Individual files may not exceed 100 MB. Provide confidential information in a separate file. Divide files into parts if necessary.

B. Submit confidential information in accordance with the requirements in this RFQ.

Information marked confidential, but not placed in a separate binder or electronic file as

Copyright© 2023 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

required will not be considered confidential and will be treated as other non-confidential information in the SOQ.

ARTICLE 3—INSTRUCTIONS FOR PREPARING THE STATEMENT OF QUALIFICATIONS

3.01 The following Tables, provided in the Statement of Qualifications, are to be used in preparing the Statement of Qualifications:

Table/Attachment Document Title A Contractor: Qualifications, Experience and References B CM/GC Project Experience and References C Required Contractor’s Liability Insurance and Bonds D Certification of Compliance with E-Verify Program or Equivalent E Confidentiality and Ethics Clauses F RFQ Criteria (for information only)

3.02 Project Experience

A. Provide a list of projects completed by the Proposer in the last 10 years.

B. Provide information on at least three (3) projects which demonstrate the experience of the Proposer’s team with construction of similar projects using copies of Attachment A.

Experience must include, as a minimum, the satisfactory completion of at least three (3) similar projects within the last 10 years. Companies not meeting this requirement for similar projects may be disqualified as being non-responsive. Similar projects must include:

a. At least three (3) pipeline projects with a value of $20M USD or greater and constructed within an urban environment.

b. Installing at least 10,000 length feet (LF) of pressurized pipeline of similar length and diameter to what is shown on Project Overview Exhibit.

c. Installing 5,000 LF of 20” or larger HDPE pipe where fusion certification requirements were met.

C. Provide information on at least two (2) projects which demonstrate the experience of the Proposer’s team with water-tight construction shafts used to install tunnels using copies of Attachment A. Experience shall include secant pile, grouted sheet pile, or other water-tight alternative with base plug and a minimum depth of 30 feet in soil conditions consisting of soft clays and/or water bearing silts and sands. For each project, provide: a general description of the project, a description of soil conditions, means and methods of ground support.

D. Provide information on at least two (2) projects which demonstrate the experience of the Proposer’s team with microtunnel installations of at least 60-inch diameter and 500 feet in length in soil conditions consisting of soft clays and/or loose sands using Attachment A. For each project, provide: a general description of the project, a description of soil conditions, means and methods of ground support.

E. Provide a list of the five (5) most recent CM/GC Projects completed by the Proposer using Attachment B.

Copyright© 2023 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

3.03 Additional Statements (Optional)

A. Provide responses to the following two (2) prompts and include them in the Statement of Qualifications. Responses are optional and will not be scored. Responses may be used by the Owner in developing the RFP documents.

1. Prompt 1: The Owner prefers that the Proposer self-perform a minimum of 50% of the work. State the Proposer’s preferred percentage of self-performed work. In 500 words or less, state how the Proposer’s preferred percentage of self-performed work benefits the Owner in respects to scope, schedule and fee.

2. Prompt 2: The Project involves a USACE 408 Permit that is currently in the review process. In 250 words or less, describe the Proposer’s experience with federal permitting agencies.

ARTICLE 4—SUBMITTING THE STATEMENT OF QUALIFICATIONS

4.01 Delivery of Statement of Qualifications

A. Deliver the SOQ no later than the date and time prescribed and at the place indicated in the Advertisement.

B. Instructions: Compile your cover sheet, qualifications responses, Statement of Qualifications Certification, and any other correspondence into one single PDF file. Upload your single file for this event using the U3P website. Responses must be uploaded and the electronic submission completed by the time and date specified. After uploading your response file, offerors MUST go to "Review and Submit" and click "SUBMIT RESPONSE" to complete the process. Responses submitted electronically through U3P require uploading of electronic attachments. U3P will accept a wide variety of document types such as Word, Excel, and PDF attachments but not all. You MAY NOT submit documents that are embedded (zip files), movies, wmp and mp3 files or password protected files, etc. Such actions may cause your SOQ to be deemed as "non-responsive". All files must be smaller than 100 MB.

1. The Cover of the SOQ must be clearly marked as follows:

MP12 B and C - 500 South Capacity Upgrades Project

525003195

Statement of Qualifications for Construction Manager / General Contractor (CM/GC)

2. Responses received after 2:00PM on Wednesday, December 9, 2026 will be rejected and will be returned to the respondent unopened. Determinations as to qualification status will be made at a later date. SLCDPU reserves the right to accept or reject any or all SOQs, with or without cause, or to accept the SOQs which, in its sole judgment, best serve the interest of the City. All decisions related to this solicitation will be final.

C. If the Advertisement permits or requires electronic delivery of the SOQ, email or upload the SOQ as indicated in the Advertisement.

D. Statements of Qualifications may be modified or withdrawn using a document executed in the same manner that a SOQ must be executed. Using a method permitted for delivery of the SOQ, deliver the modification/withdrawal document prior to the date and time for the receipt of SOQs.

Copyright© 2023 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

E. Statements of Qualifications submitted in response to this RFQ will become the property of the Owner.

ARTICLE 5—EVALUATION OF STATEMENTS OF QUALIFICATIONS

5.01 The Owner will evaluate and rank each SOQ using the selection criteria within 10 days after the date SOQs are received. Each SOQ will be evaluated by the SLCDPU Selection Committee in accordance with the SLCDPU Procurement Policy. The SOQs will be scored based on the items outlined. Non-responsive SOQs (those not conforming to the RFQ requirements) may be eliminated. The Owner reserves the right to waive all informalities and request additional information. The Contractor bears sole responsibility for the items and information included, or not included, in the SOQ. The Owner reserves the right to disqualify any SOQ that includes significant deviations or exceptions to the terms, conditions and/or specifications in this RFQ. Final recommendations of the highest ranked Contractor(s) will be made by the SLCDPU Selection Committee. Qualified proposers meeting the pass/fail requirements will be invited to propose on the project.

5.02 Owner may conduct investigations as it deems necessary to establish the responsibility, qualifications, and capability of Proposers.

5.03 Owner, at its discretion, may choose to conduct interviews with Proposers to clarify any points in the SOQ to gain a better understanding of how the Proposers can provide the best value to the Owner for the CMAR Contract.

A. If the Owner chooses to conduct interviews with some or all Proposers, they will be notified of:

1. The time and place for the interview;

2. Interview format and agenda;

3. Topics to be discussed at the interview; and

4. Individuals are expected to participate in the interview.

B. Failure to participate in the interview may result in disqualification from consideration for the award of the CMAR Contract.

5.04 Submission of a Statement of Qualifications indicates the Proposer’s acceptance of the evaluation technique and methodology in this RFQ as well as the Proposer’s recognition that some subjective judgments must be made by the Owner during the evaluation and selection process.

5.05 Ranking of Proposers

A. Based on the evaluation of the Proposals and their preliminary scoring, Owner will develop a short list of Proposers and send each a Request for Proposals.

ARTICLE 6—PUBLIC RECORDS

6.01 Pursuant to Utah Code Section 63G Chapter 2, information provided to governmental agencies and their assignees, including SLCDPU, is made available to the general public. If confidential or proprietary information is contained in a proposal, respondents should request that this

Copyright© 2023 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

information be withheld from the public records. SLCDPU waives all liability with respect to the disclosure of confidential or proprietary information.

ARTICLE 7—COSTS

7.01 Contractors shall assume all costs associated with responding to this RFQ. SLCDPU (and its engineer) shall not be responsible for any direct or indirect cost incurred by applicants because of participation in this prequalification process. Each applicant shall bear its own expense in connection with the preparation and submission of materials and the provision of any supplemental information requested. SLCDPU (and its engineer) shall have no liability for cost incurred by applicants in connection with the review and evaluation of prequalification materials and any findings and determinations made thereafter. All materials and information submitted during the prequalification process will become the property of SLCDPU and will not be returned to the Applicant.

ARTICLE 8—CONTRACT AWARD

8.01 No contract will be awarded as a result of this prequalification nor does this prequalification obligate SLCDPU to enter a contract. If SLCDPU proceeds with the bidding of the project, contractors that have met the qualification requirements and are deemed prequalified will be given the opportunity to submit a proposal for the project during the CM/GC procurement phase.

8.02 Prequalification of a Contractor does not guarantee that work will be awarded to the Contractor.

The sole responsibility for selecting prequalified contractors will be made by SLCDPU and their decision will be final. SLCDPU reserves the right to reject applications that do not meet these requirements.

ARTICLE 9—ADDENDA

9.01 All requests for interpretation of the Application for Bidder Qualification must be made in writing via U3P. To be given consideration, such requests must be received by no later than seven (7) calendar days prior to the due date of this Qualification Application. Any and all such interpretations and any supplemental instructions or changes may be in the form of a written addenda which, if issued, will be issued via U3P, not later than forty-eight (48) hours prior to the date and time fixed for submitting the application. Acknowledgement of receipt of addenda must be included on the Applicant Certification.

ARTICLE 10—APPEAL PROCESS

10.01 There is no appeal for applications that have been determined to be not qualified as a result of incompleteness, lateness, or falsification of information. The closing time for submission of prequalification packages will not be changed to accommodate supplementation of incomplete or late submissions.

ARTICLE 11—NOTIFICATION OF PREQUALIFIED CONTRACTORS

11.01 All Contractors submitting prequalification statements will be notified in writing if they did or did not prequalify. Only Contractors which are prequalified will be invited to propose on the project.

The City’s decision is final.

Article 1— General Information
1.01 Definitions
1.02 Project Description
1.03 Selection Process
1.04 Proposal Documents
1.05 Information Conference
1.06 Examination of Proposal Documents
1.07 Site Visit
1.08 Questions regarding the Statement of Qualifications
1.09 Addenda
1.10 Confidentiality of Submitted Information
Article 2— Evaluation Criteria
2.01 Evaluation Categories
2.02 Evaluation for Rating Categories
2.03 The Statement of Qualifications (SOQ) as submitted must include the information described in this RFQ, as a minimum, to allow the Owner (a) to assess the qualifications of each Proposer to successfully perform CMAR Services and complete the Work,...
2.04 The SOQ as furnished to Proposers is set up to require that certain information be provided in forms included in the SOQ. The information in these forms will be used to make direct comparisons with the information provided by other Proposers in r...
2.05 Information requested in the forms that cannot be totally incorporated in the forms may be included as an appendix to the form. This appendix must be clearly referenced by appendix number on the form, and the appended material must include the ap...
2.06 The information requested is used to address each of the selection categories presented in the RFQ (not including any price category) and should be presented in that order and be keyed specifically for each selection category. Proposers may provi...
2.07 Proposal Format and Presentation
Article 3— Instructions for Preparing the Statement of Qualifications
3.01 The following Tables, provided in the Statement of Qualifications, are to be used in preparing the Statement of Qualifications:
3.02 Project Experience
3.03 Additional Statements (Optional)
Article 4— Submitting the Statement of Qualifications
4.01 Delivery of Statement of Qualifications
Article 5— Evaluation of Statements of Qualifications
5.01 The Owner will evaluate and rank each SOQ using the selection criteria within 10 days after the date SOQs are received. Each SOQ will be evaluated by the SLCDPU Selection Committee in accordance with the SLCDPU Procurement Policy. The SOQs will b...
5.02 Owner may conduct investigations as it deems necessary to establish the responsibility, qualifications, and capability of Proposers.
5.03 Owner, at its discretion, may choose to conduct interviews with Proposers to clarify any points in the SOQ to gain a better understanding of how the Proposers can provide the best value to the Owner for the CMAR Contract.
5.04 Submission of a Statement of Qualifications indicates the Proposer’s acceptance of the evaluation technique and methodology in this RFQ as well as the Proposer’s recognition that some subjective judgments must be made by the Owner during the eval...
5.05 Ranking of Proposers
Article 6— public records
6.01 Pursuant to Utah Code Section 63G Chapter 2, information provided to governmental agencies and their assignees, including SLCDPU, is made available to the general public. If confidential or proprietary information is contained in a proposal, resp...
Article 7— Costs
7.01 Contractors shall assume all costs associated with responding to this RFQ. SLCDPU (and its engineer) shall not be responsible for any direct or indirect cost incurred by applicants because of participation in this prequalification process. Each a...
Article 8— contract award
8.01 No contract will be awarded as a result of this prequalification nor does this prequalification obligate SLCDPU to enter a contract. If SLCDPU proceeds with the bidding of the project, contractors that have met the qualification requirements and ...
8.02 Prequalification of a Contractor does not guarantee that work will be awarded to the Contractor. The sole responsibility for selecting prequalified contractors will be made by SLCDPU and their decision will be final. SLCDPU reserves the right to ...
Article 9— addenda
9.01 All requests for interpretation of the Application for Bidder Qualification must be made in writing via U3P. To be given consideration, such requests must be received by no later than seven (7) calendar days prior to the due date of this Qualific...
Article 10— appeal process
10.01 There is no appeal for applications that have been determined to be not qualified as a result of incompleteness, lateness, or falsification of information. The closing time for submission of prequalification packages will not be changed to accom...
Article 11— notification of prequalified contractors
11.01 All Contractors submitting prequalification statements will be notified in writing if they did or did not prequalify. Only Contractors which are prequalified will be invited to propose on the project. The City’s decision is final.