1. Statement of Work.pdf

PDF 430 KB Posted

Attached to
127EAW23R0002 - Hirz Mountain Lookout Restoration
Solicitation number
127EAW23R0002
Issued by

View the file

Other files

File Type Posted
P00003 - RFIs Round 2.pdf PDF
A00002 - RFIs and Lead Report.pdf PDF
RFI Official Responses - 1.pdf PDF
Lead Based Paint Report_4-28-2021.pdf PDF
Amendment A00001 - Revised Solicitation.pdf PDF
Amendment A00001 - Revised Solicitation.pdf PDF
127EAW23R0002 - Revised 21 Nov.pdf PDF
3. Fire Plan.pdf PDF
7. Davis-Bacon Act WD # CA20220007.pdf PDF
127EAW23R0002.pdf PDF
2. Schedule.docx DOCX document
8. RFI Form.docx DOCX document
6. NEPA Report.pdf PDF
4. Project Plans.pdf PDF
5. Location Plan.pdf PDF
Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

US Department of Agriculture (USDA)

Statement of Work

Great American Outdoor Act

Hirz Mountain Lookout Restoration

Shasta-Trinity National Forest

Contents Project

General Information

1.0 Scope of Work

2.0 Background and Location

Contractor Requirements

3.0 Technical Requirements / Tasks

3.1 Lead-Based Paint Material Abatement and Disposal

3.1 Roof, Outriggers, and Upper Siding

3.2 Siding

3.3 Window Replacement, Repairs, and Improvements

3.4 Finishing

3.5 Shutter & Door Cover Assembly

3.6 Stair Tread and Landing Replacement

3.7 Deck & Stairway Railing Fence

4.0 Government Furnished

5.0 Deliverables / Schedule

5.1 Mobilization

5.2 Submittals

5.3 Protection of Existing Improvements

5.4 Disposal

5.5 Time of Completion

6.0 Travel

7.0 Attachments

Project Great American Outdoor Act – Hirz Mountain Lookout Restoration

General Information

1.0 Scope of Work

The purpose of this project is to restore the historic Hirz Mountain Lookout to be safe and preserve the structural integrity. The scope of work for the Base Projects will include, but not necessarily limited to: upper siding and outrigger lead-based paint material abatement and disposal; removing the roof shingles, water-resistive barrier, and sheathing to expose the roof framing; removing the upper trim, siding, shutter ledger, and sheathing to expose the wall framing;

replacing the structural components of the shutter outrigger assembly (some rafters and ties); replacing the roofing materials; replacing the upper siding materials; priming and painting new work and repairs. The scope of work for the

Options will include, but not necessarily limited to: constructing and installing new shutters; replacing deck railing fence & installing railing fence on stairway; replacing the steps and landing boards on the stairs; window replacement, repairs, and improvements; replacing some exterior trim; lower siding lead-based paint abatement and disposal; installing sash zone trim; installing a door threshold; priming and painting new work and repairs.

The Contractor shall furnish all material, labor, equipment, documentation, communication, notifications, and transportation as required to furnish and install the improvements described herein, as shown on the Project Plans, and as otherwise required by the Contract. All demolition, disposal, construction, and improvements described herein and as shown on the Project Plans are the responsibility of the Contractor. Only items Awarded by the Contracting Officer shall be removed, replaced, painted and/or installed to receive payment for those items.

2.0 Background and Location

This project is to be funded by the Great American Outdoor Act. The Hirz Mountain Lookout is a historic fire lookout tower and will be used as a Recreation Rental upon completion. It is currently closed to the public because of its need for restoration. The lookout does not have power or water available.

Hirz Mountain Lookout is located on the west side of the McCloud arm of Shasta Lake. From Redding, CA, take I-5 North for 20 miles to Exit 698 for Gilman Rd. Go east on Gilman Rd for 4.5 miles and turn left onto Hirz Mountain Rd. Follow Hirz Mountain Rd for 5.3 miles (about 30 minutes) until you reach the gated entrance leading up to the lookout. From the gate, the lookout is ¼ mile uphill. Four-wheel drive is recommended to reach the lookout staging area before the entry gate. Due to steep grade, abrupt switchbacks and loose rock, the Contractor shall consider the use of alternative four-wheel drive transport such as ATVs and/or UTVs for transport to the lookout from the staging area/gated entrance.

In any event, the contractor is responsible for understanding the access conditions and appropriate modes of transport to the work site. The slope is estimated at 17.5% from the staging area to the lookout.

Contractor Requirements

3.0 Technical Requirements / Tasks

Refer to the Technical Tasks and Specifications herein for installation instructions and requirements. The Contractor shall be aware that the Project Plans including existing drawings with notes and revisions in red. The font is much different and larger than the existing drawings. It may be beneficial to print the drawings in color. Everything described in the Construction Notes in the Project Plans and herein is the scope of work. Only the Awarded Items shall be demolished/abated/disposed/constructed/painted. The work is almost entirely exterior except for some minor repairs and improvements to some windows. The Contractor shall be responsible for repairing or replacing any damage to other lookout features during demolition and construction during the duration of this project.

The Contractor shall carry out regulatory compliance requirements, abatement, demolition and disposal of the associated items as shown on the project plans for the Hirz Mountain Lookout Restoration, as described elsewhere in these specifications, and in the “Lead-Based Paint Report” prepared by Guzi-West, dated April 28, 2021, as it relates to Lead-

Based Paints/Lead Containing Surface Coatings. The samples were taken from various locations and all painted surfaces shall be considered to contain lead-based paint and shall be treated as such.

The Contractor shall choose to reuse or replace any flashing and fasteners at no extra cost to the Government.

The Contractor shall relinquish all specialized security drill bits to the Government upon completion of the project.

3.1 Lead-Based Paint Material Abatement and Disposal

Any paint or painted material removed shall be abated and disposed by certified personnel. Any surface to be disturbed during this contract shall be evaluated by the Contractor and the Lead-Based Paint Abatement Contractor to determine whether the paint shall be removed and disposed or the entire painted board shall be removed and disposed. The workers must use proper personal protective equipment and be properly certified per California Department of Public Health laws and regulations and the US EPA. Refer to Table 1 for approximate areas to be abated and disposed—refer to

Sheet 5 of the Project Plans for a visual.

• Contractors must abide by Title 8 California Code of Regulations Section 1532.1 (or most recent version) o Contractors shall establish and implement a compliance program for Section 1532.1, and they shall provide a written Pre-Job Notification to the nearest Division of Occupational Safety and Health Cal/OSHA office 24 hours before the start of the project o Cal/OSHA District Office – Region 2 – Redding (530) 224-4743

• All painted materials described for replacement in the contract shall be abated and disposed by a proper Lead- Based Paint Abatement Contractor o A Certified Supervisor shall prepare and provide a Lead Abatement Plan o Certified Workers and/or the Certified Supervisor shall perform the Lead Abatement Activities o The Certifications and the Lead Abatement Plan shall be given to the Contracting Officer’s Representative prior to any work being done on the lookout o The Contracting Officer’s Representative shall be notified 7 days in advance and required to be on-site each day while the lead-based paint abatement contractors are on-site o The Forest Service shall be provided the Hazardous Waste Manifest prior to payment for the Lead-Based Paint activities and closure of the contract—the Forest Service shall provide the EPA ID number.

Table 1. Approximate areas to be abated and disposed for Lead-Based Paint

Description Approximate Area (SF) Base Project 1: Upper Siding & Outriggers Lead-Based Paint Material Abatement and Disposal 180 Option 1: Lower Siding Lead-Based Paint Material Abatement and Disposal 120 Option 2: Sash Zone Lead-Based Paint Abatement and Disposal 280

3.1 Roof, Outriggers, and Upper Siding

The existing roof caps, shingles, underlayment, and sheathing shall be removed to expose the rafters used to support the shutters. The siding and sheathing above the windows shall be removed to replace the outrigger ties.

• Remove and dispose of roof shingles, underlayment, and sheathing.

o Protect lightning rod assembly

▪ Disassemble and reinstall properly when appropriate

• Replace outrigger rafters, rafter fascia, and outrigger assembly one side at a time to maintain structural integrity of the roof system o Protect all existing framing to remain, included, but not limited to rafter hips, hip ties, ceiling, joists, blocking, header, and rafters not used to support the outrigger assembly o Remove and dispose of the siding, vent trim, shutter ledger, and sheathing above the windows

▪ Protect the louvres

▪ Protect the flashing around the outrigger ties

▪ Protect the flashing for the shutter ledger o Install the shutter ledger as a continuous board on each side

▪ Install shutter ledger flashing o Remove, dispose, and replace only the rafters used in the outrigger assembly, rafter facia, and construct the outrigger assembly as shown in the Project Plans

▪ It is suggested to attach the outrigger ties to the wall framing as shown in the Project Plans, then to install the siding (Siding is described in Section 3.2) before installing the rafters to have adequate space for the siding

• Reuse outrigger tie bolts if possible

▪ The outrigger assembly shall be constructed using continuous boards

• The 4 in. x 4 in. x 6 in. blocks shall be cut, drilled, attached by fasteners to prevent swiveling, and placed for shutter bolt support as shown in the Project Plans o 4 in. x 4 in. x 12 in. center blocks as shown in the Project Plans

• Install roof sheathing, underlayment, flashing, and wood shingles as shown in the Project Plans o Roof sheathing shall be installed on-center and attached to each rafter

▪ Stagger splicing o The fascia boards shall be cut to fit between the rafters and attached to the sheathing and adjacent rafters at the same angle of the roof sheathing and flush against the siding o The flashing shall be installed along the eave edge (cut to fit around outrigger rafters) and overlapped around the corners of the building.

o The underlayment shall be installed from the eave edge to cover the flashing and overlap the ridges o The wood shingles shall be attached per the recommendations of the manufacturer and as described herein and per the Project Plans

• Install the metal roof caps to protect the ridges and peak from weather o Attach with corrosion-resistant roofing screws with rubber seals o Install hip caps first

▪ Apply caulking along the edge of the hip cap to seal o Cut and bend metal ridge cap to construct a cap for the peak

• Reinstall lightning rod assembly o Attach using existing connectors and clips

▪ The shutter doors shall not be impeded by the grounding cable o Ensure grounding continuity and connections and splices are secured and maintained

3.1.1 Wood Shingles

Wood Shingles shall be installed to comply with section and table 1507.8 of the IBC. The wood shingles shall be cedar, 18 inches in length, grade No. 2, 4.5 inch exposure, and fire-retardant treated in accordance with AWPA C1 or approved equivalent. The weather exposure shall not exceed that set in Table 1507.8.6. There shall be 2 fasteners per shingle and comply with section 1507.8.5 for a minimum penetration of .75 inch into the sheathing and be corrosion resistant. The starter course shall be a double layer. Spacing between shingles shall be .25 to .375 inches. Install as explained or per the manufacturer’s installation instructions.

3.1.2 Water-Resistive Barrier and Eave Flashing

The water-resistive barrier shall be Grace Ice & Water Shield roofing underlayment or approved equivalent meet ASTM standards for thickness, strength, temperature flexibility, adhesion to plywood, and permeance. It shall be installed per the recommendations of the manufacturer or at a minimum of 2 inch overlap with a single, continuous layer starting from the eave edge and lapping the upper courses horizontally. The underlayment shall be run at a minimum of 6 inches over the ridges from each direction. No. 26 galvanized sheet gage corrosion resistant metal flashing shall be installed per

1507.8.7 on the eave edge.

3.1.3 Roof Sheathing

Roof sheathing shall be used in accordance with sections 1507.8.1.1, 2303.1.8, and 2304.7.2. The roof sheathing shall be a minimum of 23/32 in. x 4 ft. x 8 ft. Fir Sheathing Plywood or approved equivalent and conform to the applicable APWA

Standard U1 and M4. The roof sheathing shall be installed with 1/8 inch gaps between the adjacent panels. Use sheathing clips between rafters to provide the necessary clearance to prevent buckling. The sheathing clips shall be ¾ inch 20 gauge galvanized steel to resist corrosion.

3.1.4 Rafters, Shutter Ledger, Fascia, and Outrigger Assembly

The rafters, ties, shutter ledger, fascia, and outrigger assembly shall all be constructed of continuous 2 in. x 4 in. douglas fir boards. The 4 in. x 4 in. x 6 in. & 4 in. x 4 in. x 12 in. blocks shall be from untreated kiln-dried douglas fir.

3.1.5 Steel Roof Panel Ridge Caps

The existing metal caps shall be reused if possible. Otherwise, replace with same materials. 29-gauge 14 in. x 126 in

Steel Roof Panel Ridge Cap (painted brown to match the wood shingle color) or approved equivalent.

3.1.6 Fasteners and Outrigger Shutter Bolts

Fasteners used shall comply to section 2303.6 and conform to requirements of ASTM F 1667. Refer to the fastening schedule on Table 2304.9.1, unless otherwise noted on the Project Plans. Weather boarding and wall coverings shall be securely fastened with aluminum, copper, zinc, zinc-coated or other approved corrosion-resistant fasteners in accordance with the nailing schedule in Table 2304.9.1 or approved manufacturer’s installation instructions. Sheathing fasteners shall be driven so that the head is flush per section 2304.9.2.

The Outrigger Shutter Bolts shall be ½ in-13 x 14 in. galvanized steel hex bolts with galvanized steel washers and nuts, and wing nuts as shown in the Project Plans.

3.2 Siding

The siding, trim, baseboard, underlayment, and wall sheathing will all be replaced as shown on the Project Plans and described herein. All exposed trim edges shall be sanded to provide a softer, rounded edge.

• Remove and install the upper siding as described in Section 3.1 and herein o The wall sheathing shall be cut to fit around the outrigger ties and louvres

▪ Cover the wall from the corner of the building until the edge of the louvre is covered

▪ Attach the wall sheathing to each framing member o Install the underlayment per the recommendations of the manufacturer

▪ The underlayment shall overlap the corners of the building and shall be cut around each tie and louvre to cover the entire wall sheathing o Cut the v-rustic shiplap siding to fit continuously over the outrigger ties to meet at the edge of the louvre o The louvre trim shall be installed on top of the siding and around the louvre on top and on both sides o Install the corner moulding

• Remove and install the lower siding, baseboard, flashing, underlayment, and wall sheathing o Protect the windowsill o Protect the baseboard flashing o Install the wall sheathing and attach to each frame member on-center o Install the baseboard as a continuous board

▪ Replace the baseboard below the doorway

▪ Install the flashing o Install the underlayment per the manufacturer’s installation guide

▪ Cover the flashing and wrap around the corners o Install the v-rustic siding and cut to fit

▪ The siding will butt against each other flush on the corner and flush against the doorframe o Install the corner moulding over the shiplap siding

• Remove and replace all corner trim in the sash zone o Install per the Project Plans

• Remove the trim between the window sashes that are not flush and do not match (such as cut plywood) and replace as necessary o Protect the window casing and frame o At least 1 piece of trim is missing and 1 is not flush

▪ Not all trim was able to be assessed—Up to 5 pieces of trim between the windows shall be considered to be replaced

• Contractor is to confirm with COR which trim shall be replaced on site o Replace trim between window sashes per the Project Plans

3.2.1 V-Rustic Shiplap and Trim

Shiplap v-rustic wood siding must be attached to the sheathing or framing in accordance with Table 2304.9.1 or the approved manufacturer’s installation instructions. The method of nailing is illustrated in Figure 1405.16. 1 in. x 8 in. x 16

ft. V-rustic shiplap siding to be used or approved equivalent. The boards are to be installed continuously and horizontally.

Corner trim above and below the sash zone to cover the shiplap v-rustic should 1.25 in. x 1.25 in. x 96 in. Mixed Grain

Hemlock Outside Corner Moulding or approved equivalent.

Exterior trim for use between the sashes and around the louvres are to be 1 in. x 4 in. x 8 ft. S1S2E Cedar Board or approved equivalent. Attach on face with 2 nails on either side every 6 inches and 2 inches from the cut ends. Install trim between sashes as shown in Project Plans.

Exterior trim for use as corner boards are to be 1 in. x 6 in. x 8 ft. S1S2E Cedar Board or approved equivalent. Attach on face with 2 nails on either side every 6 inches and 2 inches from the cut ends. Install trim around the corners in the sash zone as shown in Project Plans.

3.2.2 Water-Resistive Barrier

The water-resistive barrier shall be Grace Ice & Water Shield roofing underlayment or approved equivalent meet ASTM standards for thickness, strength, temperature flexibility, adhesion to plywood, and permeance. It shall be installed per the recommendations of the manufacturer and be a single, continuous layer starting from the sheathing bottom edge to the windowsill or roof eave. The underlayment shall be run at a minimum of 6 inches around the corners from each direction. Flashing shall be installed to comply with Section 1405 with a drip edge on top of the exterior baseboard.

3.2.3 Wall Sheathing

The wall sheathing shall minimum of 23/32 in. x 4 ft. x 8 ft. Fir Sheathing Plywood or approved equivalent and comply with section 2304.6 and Table 2308.9.3(2). The wall sheathing shall be installed with 1/8 inch gaps between the adjacent panels. Use sheathing clips between rafters to provide the necessary clearance to prevent buckling. The sheathing clips shall be ¾ inch 20 gauge galvanized steel to resist corrosion.

3.2.4 Fasteners

Fasteners used shall comply to section 2303.6 and conform to requirements of ASTM F 1667. Refer to the fastening schedule on Table 2304.9.1, unless otherwise noted on the Project Plans. Weather boarding and wall coverings shall be securely fastened with aluminum, copper, zinc, zinc-coated or other approved corrosion-resistant fasteners in accordance with the nailing schedule in Table 2304.9.1 or approved manufacturer’s installation instructions. Sheathing fasteners shall be driven so that the head is flush per section 2304.9.2.

3.3 Window Replacement, Repairs, and Improvements

One window on the south elevation above the stairway hatch is broken and shall be replaced. All windows have paint smudged around the moulding on the glass (interior and exterior) from the previous paint job—this paint shall be removed. There are 3 hinged single sashes—1 on the S elevation, 1 one the W elevation, and 1 on the N elevation. The N elevation hinged sash needs its weather stripping replaced and to strengthen the existing struts as the screws are loose.

The W elevation needs its loose hinges strengthened, it only has 1 strut (this strut shall be replaced for 2 new similar struts), and needs its weather stripping replaced. The S elevation hinged sash is missing its struts (2 new struts shall be installed), it is boarded shut (remove boards and make operable), and replace the weatherstripping. All 3 windows have screens and they do not need to be replaced—protect the screens. All 3 hinged sashes shall be prepped for priming and painting for the areas that were replaced and any area that was missing or damaged.

• Remove broken glass & Install new tempered glass windowpane o Protect the sash, casing, and frame o Protect the moulding o Contractor shall confirm window sizing on site (approx. 25” x 48”) o Reuse existing moulding

▪ If the moulding shall break, replace it in kind

• Remove smudged paint o Protect the windows o Remove paint from the glass (interior and exterior)

• Repair and Improve hinged sashes o Protect the frame and casing o Protect the glass o Protect existing interior paint

▪ Repair as necessary o Protect the screen o N elevation hinged sash

▪ Repair the existing strut holes

• Remove struts and repair fastener holes o Fill with wood filler or wood putty as deemed appropriate by the contractor

• Prep, prime, and paint the struts to match existing

▪ Repair/Replace existing weatherstripping

• The existing weatherstripping has fallen

• Clean the weatherstripping area

• Repair the existing weatherstripping as it has fallen or replace and install new to provide a weatherproof seal around the entire window o W elevation hinged sash

▪ Repair the existing hinge and strut holes

• Remove struts and repair fastener holes o Fill with wood filler or wood putty as deemed appropriate by the contractor

• Remove hinge and repair fastener holes o Only remove what is necessary to make the repair

▪ Not all hinge components are loose o Fill with wood filler or wood putty as deemed appropriate by the contractor

▪ Replace the 1 existing strut with 2 new matching struts

• The new struts shall be similar in length and/or installed in such a way as the match the opening distance of the existing struts on the N elevation

• Prep, prime, and paint the struts to match existing

▪ Repair/Replace existing weatherstripping

• The existing weatherstripping condition is unknown—make repairs or replace as necessary to provide a complete weatherproof seal around the window o S elevation hinged sash

▪ Remove and dispose of wood impeding the window from opening

• Protect the frame and casing

▪ Repair the existing hinge and strut holes

• Repair fastener holes from previous struts o This window is missing its struts o Fill with wood filler or wood putty as deemed appropriate by the contractor

• Remove hinge and repair fastener holes if necessary o Only remove what is necessary to make the repair

▪ Not all hinge components are loose o Fill with wood filler or wood putty as deemed appropriate by the contractor

▪ Install 2 new matching struts

• The new struts shall be similar in length and/or installed in such a way as the match the opening distance of the existing struts on the N elevation

• Prep, prime, and paint the struts to match existing

▪ Repair/Replace existing weatherstripping

• The existing weatherstripping condition is unknown—make repairs or replace as necessary to provide a complete weatherproof seal around the window o Prep, prime, and paint

▪ Any repairs made shall be painted to match the existing color

▪ As described in section 3.4 Finishing—the exterior windows shall be prepped for priming and painting to match existing colors

3.3.1 Tempered Glass

The windowpane shall be tempered and conform to Chapter 24 in the IBC. The glazing shall meet the standard CPSC 16

CFR 1201 and tested and labeled as conforming to AAMA/WDMA/CSA 101/I.S.2/A440. The window shall be installed in accordance with approved manufacturer’s instructions. Fastener size and spacing shall be provided in such instructions and shall be calculated based on maximum loads and spacing used in the tests.

3.3.2 Wood Moulding

The wood moulding around the glass shall be reinstalled or replaced in kind. It shall be attached using brad nails.

Caulking shall be placed where the moulding meets the frame and the glass. Repaint as described in section 3.4 Finishing.

3.3.3 Wood Filler/Putty

The fastener holes for repair shall be filled with wood filler or wood putty as deemed appropriate by the contractor. The product shall be used as described in the manufacturer’s installation instructions. Follow appropriate drying times and finish as necessary to provide a clean surface before priming, painting, and installing/reinstalling the hinge and/or strut.

3.3.4 Weatherstripping

The weatherstripping used for the N elevation hinged sash shall be matched and used as the replacement for any necessary weatherstripping replacements. It shall be installed per the manufacturer’s installation instructions.

3.3.5 Hinged Sash Struts

The existing struts on the N elevation shall be used as the struts to match. They were measured at a fully-extended, open length of 14 inches. The new struts for the W and S elevations shall match as closely as possible or be installed in such a way that the openings are the same distance for all 3 windows to have a unified appearance. The struts shall be rated to safely hold the weight of the window.

3.4 Finishing

All exterior joints shall be caulked, including what remained in place. The sash zone (including the door framing and trim and the windowsill), siding, trim, baseboard, shutter ledger, outrigger assembly, and railing boards shall be prepped, primed, and painted as described herein. The Contractor is to match the existing colors. Remove smudged paint from interior and exterior of window glass.

• Abate all loose paint in the sash zone (exterior only) and what was described in section 3.3 for the window repairs o The sash zone includes, but not limited to the windowsill, window framing, and trim o Damaged or deteriorated paint shall be removed to the next sound layer

▪ Abrasive methods, such as sandblasting, water blasting, chemical removal, burning, and scraping are prohibited o Protect the door as it was recently installed and painted o Remove existing paint on interior and exterior of window glass

• Fill any existing holes in the sash zone, including, but not limited to holes along the windowsills o Fill as described in section 3.3.3

• Prime all exterior surfaces below the roof’s eave, including but not limited to siding, trim, flashing, outrigger assembly, window framing, and door framing with a premium exterior latex primer, such as Kilz o All surfaces must be clean, free of dust, chalk, oil, grease, wax, polish, mold and mildew, loose peeling paint, rust, and all other foreign substances o Protect decking, window glass, and door from primer o 1 coat of primer o Allow primer to completely dry before applying paint

• Paint all exterior surfaces below the eave, including but not limited to siding, trim, flashing, outrigger assembly, window framing, and door framing with a premium exterior latex paint, such as Kilz o Protect decking, window glass, and door from paint o 2 coats of paint

• Prime and paint the shutters once constructed (see section 3.5) o The shutters shall be painted the light color that is matched at the site o Before priming, use a degreaser and thoroughly rinse the galvanized sheet metal so that the primer and paint adhere

3.4.1 Primer

The primer used shall be Kilz 3 Premium Exterior Primer or approved equivalent. Allow primer to completely dry before applying paint. Apply primer as directed by the manufacturer’s installation instructions. Do not apply primer outside of the minimum or maximum application temperatures. Do not apply primer if rain is in the forecast for the following 24 hours.

The primer used shall have low volatile organic compounds.

3.4.2 Paint

The paint used shall be a premium water-based, all acrylic binding, exterior paint. Choose a paint that is compatible with the primer. Allow paint to completely dry before applying the second coat. Apply paint as directed by the manufacturer’s installation instructions. Do not apply paint outside of the minimum or maximum application temperatures. Do not apply paint if rain is in the forecast for the following 24 hours. The primer used shall have low volatile organic compounds.

3.5 Shutter & Door Cover Assembly

The shutter and door cover assembly shall be constructed per the Project Plans and as described herein. The Contractor is to confirm measurements on-site to ensure proper fit of the shutters and door cover with the newly constructed outrigger assembly. Several adjustments have been made to the Project Plans.

• Refer to the Project Plans for approximate dimensions and material type

• Shutter Assembly o Cut the frame members to size

▪ Ensure the middle frame board will align with the outrigger bolts o Cut the plywood to size

▪ *Note that the shutter width may be wider than the width of the plywood, as such, the contractor shall cut the plywood to cover the entire frame and join accordingly on the center of the frame or as seen fit otherwise.

o Attach the frame members to the plywood with approved fasteners

▪ Do not allow fasteners to penetrate through frame boards o Crimp and cut sheet metal to fit completely around the outside of the shutter and extend to the most inner edge of the outside frame member boards

▪ Cut sheet metal at 45-degree angles at the corner to wrap around the backside

▪ Attach with sheet metal screws on the backside into the frame member boards

• Do not attach sheet metal on the outside elevation

• Ensure sheet metal is flat and flush along the plywood face

▪ Grind cut metal to smooth finish

▪ Install rubber L-style guard along the inside edge of the frame to cover the sharp metal edge as shown in the Project Plans o Cut and attach the galvanized steel solid angle only to the short edges of the shutter

▪ Drill holes every 6 inches along the steel member

• Do not drill holes or attach the steel angle to the narrow side of the shutter, only to the outside face

• Drill pilot holes through the sheet metal, plywood, and into the frame member boards and attach with lag bolts o Do not penetrate completely through the frame member boards o Attach hinges

▪ There shall be 3 hinges per shutter

• Each hinge shall attach at a frame member using galvanized carriage bolts, locking washer, and nut

• Ensure hinge bolts do not interfere with closing the shutters flush against the sash zone

▪ Attach the hinges to the shutter ledger board

• The hinges shall be attached to the shutter ledger using security lag bolts

• The shutters shall be aligned per the Project Plans o Maintain a ¼ in. gap between adjacent shutters o Drill the bolt holes to hang the shutter from the outrigger assembly

▪ Mark and drill the bolt holes to ensure proper alignment

• Door Cover Assembly o Cut the frame members to size

▪ Ensure the middle frame board will align with the outrigger bolts o Cut the plywood to size

▪ *The contractor shall cut the plywood to cover the entire frame and join accordingly on the center of the frame or as seen fit otherwise o Crimp and cut sheet metal to fit completely around the outside of the door cover’s plywood and extend to the middle edge of the outside frame member boards

▪ The sheet metal edge’s shall be sandwiched between the plywood and the door cover frame members for safety upon handling

• Attach the frame members to the plywood with approved fasteners o Do not allow fasteners to penetrate through the sheet metal exterior face

▪ Cut sheet metal at 45 degree angles at the corner to wrap around the backside

▪ Attach with sheet metal screws on the backside into the frame member boards

• Do not attach sheet metal on the outside elevation

• Ensure sheet metal is flat and flush along the plywood face

▪ Grind cut metal to smooth finish

▪ Install rubber L-style guard along the bottom edge of the door cover to provide a cushion against the threshold o Install the eye and hook bolts as shown on the project plans

▪ Attach hooks to top corners

▪ Attach eyes to door stops in a manner that prevents the door cover from falling loose

• The door cover bottom shall rest on the threshold

3.5.1 Shutter & Door Cover Frame

The shutter frame boards shall be 1 in. x 6 in. x 8 ft. S1S2E Cedar Board or approved equivalent. The frame shall be attached by fastening 3/8 in Fir Sheathing Plywood or approved equivalent.

The door cover frame boards shall be 1 in. x 4 in. x 8 ft. S1S2E Cedar Board or approved equivalent. The frame shall be attached by fastening 3/8 in Fir Sheathing Plywood or approved equivalent.

3.5.2 Shutter & Door Cover Sheathing

The shutter and door cover sheathing shall minimum of 3/8 in. x 4 ft. x 8 ft. Fir Sheathing Plywood or approved equivalent and comply with section 2304.6 and Table 2308.9.3(2). The plywood will be cut to the dimensions needed to construct the shutter and the door cover.

3.5.3 Galvanized Sheet Metal

The galvanized sheet metal shall be sized and installed as one full sheet per shutter. It shall be 28 gauge galvanized sheet metal or approved equivalent. The approximate dimensions are 6 ft. x 8 ft. to completely cover the front of the shutter and wrap the sheet metal around to cover the outside frame members.

3.5.4 Galvanized Steel Angle

The galvanized steel angle shall be 1.5 in. x 1.5 in. and installed as a continuous strip to cover each side of the shutter width.

3.5.5 L-style Edge Guard

Trim Gard – L-Style Black Door Edge Guard #RRT32-02 1/2 in. x 5/16 in. or approved equivalent shall be used to cover the metal edge attached to the shutter’s frame edge. The same material shall be installed on the bottom edge of the door cover as shown in the Project Plans.

3.5.6 Fasteners, Security Lag Bolts, & Latches

Fasteners used shall comply to section 2303.6 and conform to requirements of ASTM F 1667. Refer to the fastening schedule on Table 2304.9.1, unless otherwise noted on the Project Plans. Weather boarding and wall coverings shall be securely fastened with aluminum, copper, zinc, zinc-coated or other approved corrosion-resistant fasteners in accordance with the nailing schedule in Table 2304.9.1 or approved manufacturer’s installation instructions. Sheathing fasteners shall

The security lag bolts shall be Bryce Security Fastener – Raptor Security – Button Head – 3/8-16 – Min 3 in. – Galvanized

Lag Thread Security Bolts or approved equivalent.

The eye and hook latches shall be made of corrosion-resistant metal or coating and shall be 2 inches in length.

3.5.7 Finishing

The shutter sheet metal, steel angle, and hinges shall be primed and painted using the same methods described in section 3.4. Degrease the galvanized sheet metal before applying primer and paint to ensure proper adhesion.

3.6 Stair Tread and Landing Replacement

Some of the existing treads on the flights and landing are succumbing to the environment. All treads shall be replaced as shown in the Project Plans and described herein.

• The dimensions of the tread width and board sizes shall be confirmed on site

• Replace each tread on the flights and on the landing o Unbolt existing board and replace in kind

▪ Cut boards to match

▪ Drill holes and attach using existing bolts

• Replace bolts if corroded

• Prime the treads o Protect the surroundings o Use the same primer as used for the lookout cab

• Paint with anti-slip paint o Protect the surroundings o Paint the treads and landing with anti-slip paint o Apply 2 coats

3.6.1 Treads

The frame boards shall be 1 in. x 6 in. x 8 ft. S1S2E Cedar Board or approved equivalent. The frame shall be attached by fastening 3/8 in Fir Sheathing Plywood or approved equivalent.

3.6.2 Primer

The primer used shall be Kilz 3 Premium Exterior Primer or approved equivalent. Allow primer to completely dry before applying paint. Apply primer as directed by the manufacturer’s installation instructions. Do not apply primer outside of the minimum or maximum application temperatures. Do not apply primer if rain is in the forecast for the following 24 hours.

The primer used shall have low volatile organic compounds.

3.6.3 Anti-Slip Paint

The paint used shall be a premium water-based, all acrylic binding, exterior paint such as INSL-X Sure Step – 100%

Acrylic, Acrylic Anti-Slip Coating or approved equivalent. Choose an anti-slip paint that is compatible with the primer.

Allow paint to completely dry before applying the second coat. Apply paint as directed by the manufacturer’s installation instructions. Do not apply paint outside of the minimum or maximum application temperatures. Do not apply paint if rain is in the forecast for the following 24 hours. The primer used shall have low volatile organic compounds.

3.6.4 Fasteners

Fasteners used shall comply to section 2303.6 and conform to requirements of ASTM F 1667. Refer to the fastening schedule on Table 2304.9.1, unless otherwise noted on the Project Plans. Weather boarding and wall coverings shall be securely fastened with aluminum, copper, zinc, zinc-coated or other approved corrosion-resistant fasteners in accordance with the nailing schedule in Table 2304.9.1 or approved manufacturer’s installation instructions. Sheathing fasteners shall

3.7 Deck & Stairway Railing Fence

The deck railing has existing 2 in. x 4 in. wire fence attached to 2 in. x 4 in. boards to the top rail and to the balusters.

The deck fencing shall be replaced in kind with either 2 in. x 4 in. or 2 in. x 2in., 15 gauge wire fence or approved equivalent. The 2 in. x 4 in. boards shall be replaced as well and attached in the same manner. The tower stairways and landing currently do not have existing fencing. The Contractor shall install fencing in the same manner as the deck fencing along each stairway and landing side from the top rail to the bottom rail. Attachments will be made as shown in the project Plans. The boards shall be primed and painted to match the existing color as described in section 3.4.

• The dimensions of the fence height and board lengths shall be confirmed on site o The deck is approximately 20 ft. x 20 ft.

• Deck Railing Fence o Remove the existing fence and boards and replace in kind o Prime and Paint the boards to match the existing color o The installation shall be as shown in the Project Plans o The top of the fence shall be wedged between the top rail and the board o The bottom of the fence shall be attached to the wedged between the board and the balusters o The boards will be attached with lag bolts o The fence shall be attached with 3/4 in. hot-dipped galvanized staples o All cut fence shall be installed in a manner to prevent anyone from getting pricked or cut o The fence shall be installed as 1 continuous section per side of the deck o Protect the gate

• Stairway and Landing Railing Fence o There is not any existing fence o Install new fence as shown in the Project Plans o The top of the fence shall be wedged between the top rail and the board o The bottom of the fence shall be attached to the wedged between the board and the balusters o The boards will be attached with lag bolts o The fence shall be attached with 3/4 in. hot-dipped galvanized staples o The fence shall be installed as 1 continuous section per side of each flight and landing side o The angled fence (from the flights) shall be attached to horizontal landing fence by cutting and wrapping the wire fence sections together

▪ All cut fence shall be installed in a manner to prevent anyone from getting pricked or cut o The short side at the landing does not have corner posts

▪ The contractor shall use a 2 in. x 4 in. board to create a corner post to install the fence

3.7.1 Fencing

The fencing be minimum 15 gauge welded wire fence with mesh 2 in. x 2 in. or 2 in. x 4 in. with corrosion-resistant coating. The dimensions are to be confirmed on site.

3.7.2 Boards

The fence attachment boards shall all be constructed of 2 in. x 4 in. douglas fir boards.

3.7.4 Fasteners

Fasteners used shall comply to section 2303.6 and conform to requirements of ASTM F 1667. Refer to the fastening schedule on Table 2304.9.1, unless otherwise noted on the Project Plans. Weather boarding and wall coverings shall be securely fastened with aluminum, copper, zinc, zinc-coated or other approved corrosion-resistant fasteners in accordance with the nailing schedule in Table 2304.9.1 or approved manufacturer’s installation instructions. Sheathing fasteners shall

1.5 in. corrosion-resistant lag bolts or approved equivalent shall be used to install the 2 in. x 4 in. boards to the angled metal railings and balusters.

The fence shall be attached to the boards with 3/4 in. hot-dipped galvanized staples or approved equivalent.

4.0 Government Furnished

The Government shall allow the Contractor to stage their equipment before the gate entrance leading to the lookout tower. This area is approximately 1,500 sq. ft. The Contractor shall also be allowed to use the area around the lookout tower as well—this area is approximately 800 sq. ft. All security aspects associated with Contractor owned equipment and materials are not the responsibility of the Government. The Government assumes no liability whatsoever for Contractor use of designated staging/laydown/overnight area. Contractor is solely responsible for the security of his/her possessions related to this project. All equipment, materials, sanitation facilities, and debris shall be removed from the Government’s land upon completion of the project.

5.0 Deliverables / Schedule

5.1 Mobilization

Mobilization shall include preparatory work and operations necessary for the movement of personnel, equipment, supplies, and incidentals to the project site; utility notification/locate activities, and for the establishment other facilities necessary for the work; for premiums on bond and insurance for the work; and for other operations performed or costs incurred before the beginning of work.

The Contractor is required to furnish sanitary services for the duration of the project. The Contractor is prohibited from using the composting toilet on-site as it is currently not maintained. The Contractor is prohibited from defecating on

Forest Service land.

Contractor shall be prepared for, and in compliance with, the project Fire Plan during the performance period of the contract. Refer to the Fire Plan attachment to the contract.

The contractor shall have access to the Hirz Mountain Lookout staging area for general construction staging for the duration of the contract. The contractor shall be responsible for the security of their equipment and materials, as well as for the general protection of the lookout infrastructure that will be exposed to the contractor’s ingress/egress activity, as well as the stockpiling and transport of materials to and from the work area and the staging area.

The contractor shall ensure the work area and staging area cleanup occurs each day and at the completion of the project.

5.2 Submittals

Submittals shall include all pertinent data required to understand the quality of components, dimensional relationships, integration with other materials, assembly techniques, structural aspects, color, finish, texture, and other such characteristics as may be necessary to fully describe the item and its intended use.

Submit one electronic copy to the Contracting Officer’s Representative (COR) of all submittals or shop drawings along with detailed submittal sheet outlining all contents and purpose of each submittal for approval prior to fabrication, installation, or order placement to allow for checking and coordination.

All rejected or returned submittals shall be resubmitted with corrections to the COR for approval.

Certifications for hazardous materials and waste removal, transportation, and disposal shall be submitted to the COR prior to beginning any demolition. The Hazardous Waste Manifest and any other disposal related documents shall be submitted to the COR prior to payment for the Lead-Based Paint Abatement Item(s).

5.3 Protection of Existing Improvements

Existing pavement, buildings, landscaping, and other existing improvements shall be protected by the Contractor. The Contractor shall be responsible for repairing any damage to existing facilities and improvements.

5.4 Disposal

All excess construction waste material and existing removed material shall be properly and legally disposed of off Government land. All painted materials are considered to be hazardous materials because they contain lead-based paint—these materials shall be disposed of as such. As stated in the Lead-Based Paint Report, “Prospective contractors should have training in accordance with the requirements of Title 8, California Code of Regulations, Section 1532.1 and ensure proper worker protection is utilized during any disturbance of paint containing lead.” No hazardous materials or waste shall be stockpiled on-site—immediate removal and transportation is required.

5.5 Time of Completion

All work (including final clean-up) and the submittal of any documents shall be completed within 90 calendar days from the issuance of the Notice to Proceed.

6.0 Travel

The Contractor shall be aware that the site location is approximately 45 minutes from Exit 698 for Gilman Rd on I-5. It is

4.5 miles on Gilman Rd (paved) and another 5.3 miles on Hirz Mountain Rd (unpaved). The last ¼ mile is uphill and rocky and requires four-wheel drive.

7.0 Attachments

Attachments include:

- Fire Plan

- Lead-Based Paint Report