This document provides a suggested cleaning schedule for facilities at Grand Coulee Dam, Washington. The schedule details specific areas throughout the dam and surrounding facilities, proposed cleaning frequencies, and other requirements. Key areas include administration buildings, machine shops, industrial areas, control bays, power plants, visitor centers, parks, and restrooms. Services include emptying trash, cleaning and supplying restrooms, dusting, vacuuming, sweeping, mopping, washing windows and other surfaces, shampooing carpets, scrubbing floors, stripping and sealing surfaces, and refinishing restrooms. The related federal contract opportunity is solicitation number 140R1723R0002 for janitorial services at Grand Coulee Dam, issued by the Department of the Interior Bureau of Reclamation. The schedule provides a framework of requirements for the contract's statement of work.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 2__Pricing_Schedule_0008.xlsx | XLSX spreadsheet | |
| Sol_140R1723R0002_Amd_0008.pdf | ||
| Sol_140R1723R0002_Amd_0007.pdf | ||
| Sol_140R1723R0002_Amd_0006.pdf | ||
| Sol_140R1723R0002_Amd_0005.pdf | ||
| Sol_140R1723R0002_Amd_0004.pdf | ||
| Sol_140R1723R0002_Amd_0003.pdf | ||
| 2023-2028_CBA_Agreement_-_Signed_0003.pdf | ||
| Sol_140R1723R0002_Amd_0002.pdf | ||
| Attachment_-_Past_Performance_Questionnaire_0002.docx | DOCX document | |
| Sol_140R1723R0002_Amd_0001.pdf | ||
| 2__Pricing_Schedule_0001.xlsx | XLSX spreadsheet | |
| WD_2015-5541_Jul_27_2023_Rev_20.pdf | ||
| 3__Floor_Mat_Chart.xlsx | XLSX spreadsheet | |
| Sol_140R1723R0002.pdf | ||
| WD_2015-5557_Jul_27_2023_Rev_22.pdf | ||
| WD_2015-5559_Jul_27_2023_Rev_20.pdf |
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| SUGGESTED CLEANING SCHEDULE - AREA & FREQUENCY |
| 7 = 7 Days Per Week |
5 = 5 Days Per week 3 = 3 Days Per Week 2 = 2 Days Per Week W = Weekly M = Monthly Q = Quarterly S = Semiannually - Mar / Sept.
A = Annually - (April) TD = Times Daily TW = Times Weekly TY = Times Yearly ** = included on individual floors
| Also, see Section D, paragraph D.3. | Administration Building | Security Office - SRF | Warehouse A and B Office, Breakroom, Restrooms, and Entrance from counter to Stairs | Procurement/Property Office Building | Machine Shop - Includes Mezzanine Office Complex, Second Floor Breakroom and Kitchen | Mechanical Repair Building (Truck Shop) Industrial Area | Paint Shop Office and Work Area - Warehouse 3 | ||
| Carpet | Sqft | 29294 | 1500 | - | 6677 | 1301 | - | 630 | |
| Tile, Vinyl or Asphalt | Sqft | 2293 | 1335 | 1284 | - | 2243 | 470 | 120 | |
| Tile, Quarry or Ceramic | Sqft | 4375 | - | - | 308 | - | 176 | - | |
| Terrazzo | Sqft | - | - | - | - | 590 | - | - | |
| Concrete | Sqft | 2317 | 1100 | 974 | 215 | 35890 | 7529 | 1644 | |
| Asphalt Block | Sqft | - | - | - | - | 3094 | - | - | |
| Wood | Sqft | - | - | - | - | 2064 | - | - | |
| Remove Trash | 5 | 7 | 2 | 5 | 5 | 5 | 3 | ||
| Clean & Supply Restroom | 5 | 7 | 3 | 5 | 5 | 5 | 3 | ||
| Clean Showers | - | 7 | - | - | - | - | - | ||
| Clean Water Dispenser | 5 | 7 | 3 | 5 | 5 | 5 | 3 | ||
| Clean Kitchen/Kitchenette | 5 | 7 | - | 5 | 5 | 5 | - | ||
| Dusting, Routine | 5 | 7 | 3 | 5 | 5 | 5 | 3 | ||
| Vacuum Carpets | 5 | 5 | - | 5 | - | - | 3 | ||
| Sweep Floors | 5 | 7 | 3 | 5 | 5 | 5 | 3 | ||
| Clean Office Furniture | W | W | W | W | W | W | W | ||
| Wet Mop Floors | 5 | 7 | W | W | 3 | 3 | 3 | ||
| Spray Buff | - | - | - | - | W | 3 | - | ||
| Wash Interior Glass | W | W | W | W | W | 2 | - | ||
| Wash Interior/Exterior Windows | 3TY | 3TY | 3TY | 3TY | 3TY | 3TY | 3TY | ||
| Dusting, High Spaces | M | M | M | M | M | M | W | ||
| Strip & Refinish Floors | S | - | - | S | Q | Q | - | ||
| Shampoo Carpets | Q | Q | - | Q | - | - | Q | ||
| Scrub | - | - | Q | Q | - | - | - | ||
| Strip & Refinish Restroom Floors | S | S | - | S | S | S | S | ||
| Clean Solar Screen (Egg Carton) | 2TY | - | - | - | - | - | - | ||
| Clean Stair Tread and Railings | W | - | - | - | - | - | - | ||
| Wet Mop Locker room & Exercise Mats | - | 2TW | - | - | - | - | - | ||
| SUGGESTED CLEANING SCHEDULE - AREA & FREQUENCY | |||||||||
| 7 = 7 Days Per Week |
5 = 5 Days Per week 3 = 3 Days Per Week 2 = 2 Days Per Week W = Weekly M = Monthly Q = Quarterly S = Semiannually - Mar / Sept.
A = Annually - April TD = Times Daily TW = Times Weekly TY = Times Yearly ** = included on individual floors
| Also, see Section D, paragraph D.3. | Carpenter/Laborers Shop, Offices, and Breakrooms - Industrial Area | Assembly Building | |||||||
| Indusstrial Area | 115kV SwitchyardCentral Building and Stairs Down | ||||||||
| Industrial Area | 230kV Switchyard Office and Breakroom | ||||||||
| Industrial Area | 230kV Relay Building | ||||||||
| Industrial Area | 500kV Switchyard Service Building; Excluding garage and Storage Area | Pump Generation Plant Office Wing (El 1334-1212) All Stairs and Landings | |||||||
| Carpet | Sqft | 895 | - | - | - | - | - | - | |
| Tile, Vinyl or Asphalt | Sqft | 2494 | - | 2349 | 1509 | 1100 | 9425 | - | |
| Tile, Quarry or Ceramic | Sqft | - | - | - | - | - | 1873 | - | |
| Terrazzo | Sqft | - | - | - | - | - | - | - | |
| Concrete | Sqft | 6585 | 120 | 72 | - | - | - | - | |
| Asphalt Block | Sqft | - | - | - | - | - | - | - | |
| Wood | Sqft | - | - | - | - | - | - | - | |
| Remove Trash | 5 | - | 5 | 5 | 3 | 5 | - | ||
| Clean & Supply Restroom | 5 | 2 | 5 | 5 | 3 | 5 | - | ||
| Clean Showers | - | - | - | - | - | - | - | ||
| Clean Water Dispenser | 5 | W | 5 | 5 | 3 | 5 | - | ||
| Clean Kitchen/Kitchenette | 5 | - | 5 | 5 | - | 5 | - | ||
| Dusting, Routine | W | - | 5 | 5 | W | 5 | W | ||
| Vacuum Carpets | W | - | 5 | - | - | - | - | ||
| Sweep Floors | 5 | - | 5 | 5 | 3 | 5 | W | ||
| Clean Office Furniture | W | - | W | W | - | W | - | ||
| Wet Mop Floors | 3 | - | 5 | 5 | W | 5 | W | ||
| Spray Buff | - | - | M | M | - | M | - | ||
| Wash Interior Glass | - | - | 3TY | 3TY | - | 3TY | - | ||
| Wash Interior/Exterior Windows | 3TY | - | 3TY | 3TY | - | - | - | ||
| Dusting, High Spaces | W | - | M | M | - | M | - | ||
| Strip & Refinish Floors | Q | - | Q | Q | S | S | - | ||
| Shampoo Carpets | Q | - | - | - | - | - | - | ||
| Scrub | - | - | - | - | - | - | - | ||
| Strip & Refinish Restroom Floors | S | - | S | S | S | S | - | ||
| Clean Solar Screen (Egg Carton) | - | - | - | - | - | - | - | ||
| Clean Stair Tread and Railings | W | - | W | - | M | - | W | ||
| Wet Mop Locker room & Exercise Mats | - | - | - | - | - | - | - | ||
| SUGGESTED CLEANING SCHEDULE - AREA & FREQUENCY | |||||||||
| 7 = 7 Days Per Week |
5 = 5 Days Per week 3 = 3 Days Per Week 2 = 2 Days Per Week W = Weekly M = Monthly Q = Quarterly S = Semiannually - Mar / Sept.
A = Annually - April TD = Times Daily TW = Times Weekly TY = Times Yearly ** = included on individual floors
| Also, see Section D, paragraph D.3. | Pump Generation Plant Office Wing (El 1332) Breakroom | Pump Generation Plant Office Wing (El 1321) | Pump Generation Plant Office Wing (El 1311) Office & Closet | Pump Generation Plant Office Wing (El 1301) Offices | Pump Generation Plant Office Wing (El 1290) Day Room, Lunchroom, and, Sleeping Area | Pump Generation Plant Office Wing (El 1279) Offices | Pump Generation Plant Office Wing (El 1268) Office | ||
| Carpet | Sqft | 375 | 128 | 431 | 582 | 1602 | 286 | - | |
| Tile, Vinyl or Asphalt | Sqft | - | - | - | - | 540 | - | - | |
| Tile, Quarry or Ceramic | Sqft | - | - | - | - | - | - | - | |
| Terrazzo | Sqft | - | - | 96 | 96 | 474 | - | - | |
| Concrete | Sqft | - | 420 | 380 | 169 | - | - | 312 | |
| Asphalt Block | Sqft | - | - | - | - | - | - | - | |
| Wood | Sqft | - | - | - | - | - | - | - | |
| Remove Trash | 5 | 5 | 5 | 5 | 5 | 5 | 2 | ||
| Clean & Supply Restroom | - | - | 5 | 5 | 5 | - | - | ||
| Clean Showers | - | - | - | - | - | - | - | ||
| Clean Water Dispenser | 5 | 5 | 5 | - | - | 5 | - | ||
| Clean Kitchen/Kitchenette | - | - | - | 5 | - | - | - | ||
| Dusting, Routine | 5 | 5 | 5 | 5 | 5 | 5 | W | ||
| Vacuum Carpets | 5 | 5 | 5 | 5 | 5 | 5 | - | ||
| Sweep Floors | - | 5 | 5 | 5 | 2 | - | 2 | ||
| Clean Office Furniture | W | W | W | W | W | W | W | ||
| Wet Mop Floors | - | W | 5 | 5 | W | - | W | ||
| Spray Buff | - | - | - | - | - | - | - | ||
| Wash Interior Glass | 5 | - | - | - | M | 5 | - | ||
| Wash Interior/Exterior Windows | M | - | - | - | - | - | - | ||
| Dusting, High Spaces | W | W | W | W | M | M | M | ||
| Strip & Refinish Floors | - | - | - | - | - | - | - | ||
| Shampoo Carpets | Q | Q | Q | Q | Q | Q | - | ||
| Scrub | - | - | Q | - | - | - | - | ||
| Strip & Refinish Restroom Floors | - | - | S | S | S | - | - | ||
| Clean Solar Screen (Egg Carton) | - | - | - | - | - | - | - | ||
| Clean Stair Tread and Railings | - | - | - | - | - | 5 | - | ||
| Wet Mop Locker room & Exercise Mats | - | - | - | - | - | - | - | ||
| SUGGESTED CLEANING SCHEDULE - AREA & FREQUENCY | |||||||||
| 7 = 7 Days Per Week |
5 = 5 Days Per week 3 = 3 Days Per Week 2 = 2 Days Per Week W = Weekly M = Monthly Q = Quarterly S = Semiannually - Mar / Sept.
A = Annually - April TD = Times Daily TW = Times Weekly TY = Times Yearly ** = included on individual floors
| Also, see Section D, paragraph D.3. | Pump Generation Plant Office Wing (El 1256) Contractor & Janitor Storage Room & Landing | Pump Generation Plant Office Wing (El 1246) Lobby | Pump Generation Plant Office Wing (El 1236) | Pump Generation Plant Office Wing (El 1226) Lobby | Pump Generation Plant Office Wing (El 1212) Landing | Pump Generation Plant Elevators (2) | Pump Generation Plant (El 1311) Boat & Storage Area | ||
| Carpet | Sqft | - | - | - | - | - | - | - | |
| Tile, Vinyl or Asphalt | Sqft | - | - | - | - | - | 121 | - | |
| Tile, Quarry or Ceramic | Sqft | - | - | - | - | - | - | - | |
| Terrazzo | Sqft | - | - | - | 55 | - | - | - | |
| Concrete | Sqft | 312 | 312 | 312 | 282 | 183 | - | 11700 | |
| Asphalt Block | Sqft | - | - | - | - | - | - | - | |
| Wood | Sqft | - | - | - | - | - | - | - | |
| Remove Trash | - | - | - | 5 | - | - | W | ||
| Clean & Supply Restroom | - | - | - | 5 | - | - | 5 | ||
| Clean Showers | - | - | - | - | - | - | - | ||
| Clean Water Dispenser | - | - | - | - | - | - | - | ||
| Clean Kitchen/Kitchenette | - | - | - | - | - | - | - | ||
| Dusting, Routine | - | - | - | 5 | - | - | M | ||
| Vacuum Carpets | - | - | - | - | - | - | - | ||
| Sweep Floors | - | - | - | 5 | M | 2 | W | ||
| Clean Office Furniture | - | - | - | - | - | - | - | ||
| Wet Mop Floors | - | - | - | 5 | M | W | - | ||
| Spray Buff | - | - | - | - | - | - | - | ||
| Wash Interior Glass | - | - | - | - | - | - | - | ||
| Wash Interior/Exterior Windows | - | - | - | - | - | - | - | ||
| Dusting, High Spaces | - | - | - | - | - | - | - | ||
| Strip & Refinish Floors | - | - | - | - | - | - | - | ||
| Shampoo Carpets | - | - | - | - | - | - | - | ||
| Scrub | - | - | - | Q | - | - | - | ||
| Strip & Refinish Restroom Floors | - | - | - | S | - | Q | - | ||
| Clean Solar Screen (Egg Carton) | - | - | - | - | - | - | - | ||
| Clean Stair Tread and Railings | - | - | - | - | - | - | - | ||
| Wet Mop Locker room & Exercise Mats | - | - | - | - | - | - | - | ||
| SUGGESTED CLEANING SCHEDULE - AREA & FREQUENCY | |||||||||
| 7 = 7 Days Per Week |
5 = 5 Days Per week 3 = 3 Days Per Week 2 = 2 Days Per Week W = Weekly M = Monthly Q = Quarterly S = Semiannually - Mar / Sept.
A = Annually - April TD = Times Daily TW = Times Weekly TY = Times Yearly ** = included on individual floors
| Also, see Section D, paragraph D.3. | Pump Generation Plant (El 1290) | Pump Generation Plant (El 1276) | Pump Generation Plant (El 1256) | Pump Generation Plant | |
| (El 1240 TO 1245) | Pump Generation Plant (El 1245) Operator's Office | Pump Generation Plant (El 1226) | Pump Generation Plant |
(El 1212 & 1210)
| Carpet | Sqft | - | - | - | - | 100 | - | - |
| Tile, Vinyl or Asphalt | Sqft | - | - | - | - | - | - | - |
| Tile, Quarry or Ceramic | Sqft | - | - | - | - | - | - | - |
| Terrazzo | Sqft | 875 | 147 | - | 700 | - | 120 | - |
| Concrete | Sqft | 43368 | 14949 | 12470 | 8081 | - | 20055 | 11200 |
| Asphalt Block | Sqft | - | - | - | - | - | - | - |
| Wood | Sqft | - | - | - | - | - | - | - |
| Remove Trash | 5 | 3 | 3 | W | 5 | W | - | |
| Clean & Supply Restroom | 5 | 3 | - | - | - | 5 | - | |
| Clean Showers | - | - | - | - | - | - | - | |
| Clean Water Dispenser | 5 | 3 | - | W | - | 5 | - | |
| Clean Kitchen/Kitchenette | 5 | 3 | - | - | - | - | - | |
| Dusting, Routine | 5 | W | M | W | 5 | 3 | W | |
| Vacuum Carpets | - | - | - | - | 5 | - | - | |
| Sweep Floors | 5 | W | W | 3 | W | 3 | W | |
| Clean Office Furniture | W | W | - | - | W | W | - | |
| Wet Mop Floors | M | M | M | M | - | M | M | |
| Spray Buff | W | - | - | - | - | - | - | |
| Wash Interior Glass | W | M | W | W | W | - | - | |
| Wash Interior/Exterior Windows | - | - | - | - | - | - | - | |
| Dusting, High Spaces | - | - | - | - | - | - | - | |
| Strip & Refinish Floors | Q | S | - | S | - | S | A | |
| Shampoo Carpets | - | - | - | - | Q | - | - | |
| Scrub | M | - | - | Q | - | Q | S | |
| Strip & Refinish Restroom Floors | S | S | - | - | - | S | - | |
| Clean Solar Screen (Egg Carton) | - | - | - | - | - | - | - | |
| Clean Stair Tread and Railings | - | - | - | - | - | - | - | |
| Wet Mop Locker room & Exercise Mats | - | - | - | - | - | - | - | |
| SUGGESTED CLEANING SCHEDULE - AREA & FREQUENCY | ||||||||
| 7 = 7 Days Per Week |
5 = 5 Days Per week 3 = 3 Days Per Week 2 = 2 Days Per Week W = Weekly M = Monthly Q = Quarterly S = Semiannually - Mar / Sept.
A = Annually - April TD = Times Daily TW = Times Weekly TY = Times Yearly ** = included on individual floors Also, see Section D, paragraph D.3. Pump Generation Plant (El 1203, 1200, 01192, 1189, 1187) Incld Stairs & Handrails Pump Generation Plant Elevator (1) Pump Generation Plant (El 1290 to 1226) Stairs & landings Pump Generation Plant (El 1226 to 1212) Stairs & Landings Pump Generation Plant (El 1312 to 1245) Stairs (El 1318 to 1226) Left Service Bay 12th - 6th FL's Stairs & Landings, Walls & Outside Fire Escape Stairs & Landings Left Service Bay 6th to 1st FL's Stairs & Landings, Walls
| Carpet | Sqft | - | - | - | - | - | - | - |
| Tile, Vinyl or Asphalt | Sqft | - | 80 | - | - | - | - | - |
| Tile, Quarry or Ceramic | Sqft | - | - | - | - | - | - | - |
| Terrazzo | Sqft | - | - | - | - | 2750 | ** | - |
| Concrete | Sqft | 8376 | - | ** | ** | 3478 | - | ** |
| Asphalt Block | Sqft | - | - | - | - | - | - | - |
| Wood | Sqft | - | - | - | - | - | - | - |
| Remove Trash | - | - | - | - | 7 | - | - | |
| Clean & Supply Restroom | - | - | - | - | 7 | - | - | |
| Clean Showers | - | - | - | - | - | - | - | |
| Clean Water Dispenser | - | - | - | - | 7 | - | - | |
| Clean Kitchen/Kitchenette | - | - | - | - | - | - | - | |
| Dusting, Routine | M | - | W | W | 7 | 2 | W | |
| Vacuum Carpets | - | - | - | - | - | - | - | |
| Sweep Floors | W | 5 | W | W | 7 | 2 | W | |
| Clean Office Furniture | - | - | - | - | - | - | - | |
| Wet Mop Floors | - | 5 | M | M | 7 | W | M | |
| Spray Buff | - | - | - | - | 7 | - | - | |
| Wash Interior Glass | - | - | - | - | 7 | - | - | |
| Wash Interior/Exterior Windows | - | - | - | - | M | - | - | |
| Dusting, High Spaces | - | - | - | - | W | - | - | |
| Strip & Refinish Floors | - | Q | A | A | Q | S | - | |
| Shampoo Carpets | - | - | - | - | - | - | - | |
| Scrub | - | - | S | - | - | - | - | |
| Strip & Refinish Restroom Floors | - | - | - | S | S | - | - | |
| Clean Solar Screen (Egg Carton) | - | - | - | - | - | - | - | |
| Clean Stair Tread and Railings | M | - | S | S | W | W | - | |
| Wet Mop Locker room & Exercise Mats | - | - | - | - | - | - | - | |
| SUGGESTED CLEANING SCHEDULE - AREA & FREQUENCY | ||||||||
| 7 = 7 Days Per Week |
5 = 5 Days Per week 3 = 3 Days Per Week 2 = 2 Days Per Week W = Weekly M = Monthly Q = Quarterly S = Semiannually - Mar / Sept.
A = Annually - April TD = Times Daily TW = Times Weekly TY = Times Yearly ** = included on individual floors
| Also, see Section D, paragraph D.3. | Left Control Bay (El 1077) 12th Floor | Left Control Bay (El 1064) 11th Floor | Left Control Bay (El 1051) 10th Floor | Left Control Bay (El 1038) 9th Floor | Left Control Bay (El 1025) 8th Floor | Left Control Bay (El 1012) 7th Floor | Left Control Bay (El 1012) 7th FL. Main Gallery tp Block 11 | ||
| Carpet | Sqft | - | 2217 | 1100 | 4084 | 4774 | - | - | |
| Tile, Vinyl or Asphalt | Sqft | - | 3295 | 3488 | 1059 | 560 | 420 | - | |
| Tile, Quarry or Ceramic | Sqft | - | - | - | - | - | - | - | |
| Terrazzo | Sqft | - | 745 | 1037 | 1000 | 682 | 3553 | 1570 | |
| Concrete | Sqft | 2050 | - | 1533 | 530 | - | 50 | - | |
| Asphalt Block | Sqft | - | - | - | - | - | - | - | |
| Wood | Sqft | - | - | - | - | - | - | - | |
| Remove Trash | W | 5 | 5 | 5 | 5 | 5 | - | ||
| Clean & Supply Restroom | - | 5 | 5 | 5 | 5 | 5 | - | ||
| Clean Showers | - | - | - | - | - | - | - | ||
| Clean Water Dispenser | - | 5 | 5 | 5 | 5 | 5 | - | ||
| Clean Kitchen/Kitchenette | - | 5 | 5 | 5 | 5 | 3 | - | ||
| Dusting, Routine | M | 5 | 5 | 5 | 5 | 5 | - | ||
| Vacuum Carpets | - | 5 | 5 | 5 | 5 | 5 | - | ||
| Sweep Floors | W | 5 | 5 | 5 | 5 | 5 | 5 | ||
| Clean Office Furniture | - | W | W | W | W | W | - | ||
| Wet Mop Floors | M | 5 | 5 | 5 | 5 | 5 | 5 | ||
| Spray Buff | - | W | W | W | W | W | - | ||
| Wash Interior Glass | - | 5 | W | 5 | 5 | 5 | - | ||
| Wash Interior/Exterior Windows | - | 3TY | - | - | - | W | - | ||
| Dusting, High Spaces | - | M | M | M | M | M | - | ||
| Strip & Refinish Floors | - | Q | Q | Q | Q | Q | Q | ||
| Shampoo Carpets | - | Q | Q | Q | Q | Q | - | ||
| Scrub | - | - | - | - | - | - | - | ||
| Strip & Refinish Restroom Floors | - | S | S | S | S | S | - | ||
| Clean Solar Screen (Egg Carton) | - | - | - | - | - | - | - | ||
| Clean Stair Tread and Railings | - | - | - | - | - | - | - | ||
| Wet Mop Locker room & Exercise Mats | - | - | - | - | - | - | - | ||
| SUGGESTED CLEANING SCHEDULE - AREA & FREQUENCY | |||||||||
| 7 = 7 Days Per Week |
5 = 5 Days Per week 3 = 3 Days Per Week 2 = 2 Days Per Week W = Weekly M = Monthly Q = Quarterly S = Semiannually - Mar / Sept.
A = Annually - April TD = Times Daily TW = Times Weekly TY = Times Yearly ** = included on individual floors Also, see Section D, paragraph D.3. Left Service Bay (El 991) 6th Floor Left Service Bay (El 979) 5th Floor Left Service Bay (El 968) 4th Floor Left Service Bay (El 951) 3rd Floor Left Service Bay (El 934 & 943) 2nd Floor Left Service Bay (El 921) 1st Floor Left Power House(El 1012) 7th FL.
Unloading Floor, Balcony, Catwalk & Stairs
| Carpet | Sqft | 1009 | 793 | - | - | - | - | - |
| Tile, Vinyl or Asphalt | Sqft | 663 | - | - | 96 | - | - | - |
| Tile, Quarry or Ceramic | Sqft | - | - | - | - | - | - | - |
| Terrazzo | Sqft | 914 | - | 506 | 4373 | - | - | 9053 |
| Concrete | Sqft | 13581 | 10501 | 7580 | 9115 | 2954 | 2009 | 256 |
| Asphalt Block | Sqft | - | - | - | - | - | - | - |
| Wood | Sqft | - | - | - | - | - | - | - |
| Remove Trash | 5 | 5 | 5 | 5 | W | W | 5 | |
| Clean & Supply Restroom | 5 | - | - | 5 | - | - | - | |
| Clean Showers | - | - | - | - | - | - | - | |
| Clean Water Dispenser | 5 | - | 5 | 5 | - | - | - | |
| Clean Kitchen/Kitchenette | 5 | 5 | 5 | - | - | - | - | |
| Dusting, Routine | 5 | 5 | 5 | 5 | - | - | W | |
| Vacuum Carpets | 5 | - | - | - | - | - | - | |
| Sweep Floors | 5 | 5 | 5 | 5 | M | M | 5 | |
| Clean Office Furniture | W | W | W | W | - | - | - | |
| Wet Mop Floors | 5 | 5 | 5 | 5 | M | M | 5 | |
| Spray Buff | - | - | M | M | - | - | - | |
| Wash Interior Glass | W | 5 | W | W | - | - | 3 | |
| Wash Interior/Exterior Windows | - | - | - | - | - | - | 3TY | |
| Dusting, High Spaces | M | M | M | - | - | - | - | |
| Strip & Refinish Floors | Q | Q | Q | Q | - | - | Q | |
| Shampoo Carpets | Q | Q | - | Q | - | - | - | |
| Scrub | W | M | M | M | Q | Q | - | |
| Strip & Refinish Restroom Floors | S | - | - | S | - | - | - | |
| Clean Solar Screen (Egg Carton) | - | - | - | - | - | - | - | |
| Clean Stair Tread and Railings | - | - | - | - | - | - | - | |
| Wet Mop Locker room & Exercise Mats | - | - | - | - | - | - | - | |
| SUGGESTED CLEANING SCHEDULE - AREA & FREQUENCY | ||||||||
| 7 = 7 Days Per Week |
5 = 5 Days Per week 3 = 3 Days Per Week 2 = 2 Days Per Week W = Weekly M = Monthly Q = Quarterly S = Semiannually - Mar / Sept.
A = Annually - April TD = Times Daily TW = Times Weekly TY = Times Yearly ** = included on individual floors Also, see Section D, paragraph D.3. Left Power House (El 991) 6th FL. Left Power House (El 979) 5th FL. Left Power House (El 968) 4th FL. Left Power House (El 951) 3rd FL. Left Power House (El 934) 2nd FL. Left Power House (El 921) 1st FL. Left Control Bay 2 Elevators
| Carpet | Sqft | - | - | - | - | - | - | - |
| Tile, Vinyl or Asphalt | Sqft | - | - | - | - | - | - | 240 |
| Tile, Quarry or Ceramic | Sqft | - | - | - | - | - | - | - |
| Terrazzo | Sqft | 27261 | - | - | 9593 | - | - | - |
| Concrete | Sqft | 26650 | 42003 | 49545 | 29746 | 7831 | 11598 | - |
| Asphalt Block | Sqft | - | - | - | - | - | - | - |
| Wood | Sqft | - | - | - | - | - | - | - |
| Remove Trash | 2 | 2 | 2 | 5 | - | - | - | |
| Clean & Supply Restroom | 3 | - | 5 | - | - | - | - | |
| Clean Showers | - | - | - | - | - | - | - | |
| Clean Water Dispenser | 2 | - | 2 | 3 | - | - | - | |
| Clean Kitchen/Kitchenette | - | - | - | - | - | - | - | |
| Dusting, Routine | W | W | W | W | - | - | - | |
| Vacuum Carpets | - | - | - | - | - | - | - | |
| Sweep Floors | 2 | 2 | 2 | 2 | M | M | 5 | |
| Clean Office Furniture | - | - | - | - | - | - | - | |
| Wet Mop Floors | W | - | - | W | - | - | 5 | |
| Spray Buff | - | - | - | - | - | - | - | |
| Wash Interior Glass | - | - | - | - | - | - | - | |
| Wash Interior/Exterior Windows | - | - | - | - | - | - | - | |
| Dusting, High Spaces | - | - | - | - | - | - | - | |
| Strip & Refinish Floors | S | - | - | Q | - | - | Q | |
| Shampoo Carpets | - | - | - | - | - | - | - | |
| Scrub | M | M | M | M | - | - | - | |
| Strip & Refinish Restroom Floors | - | - | - | - | - | - | - | |
| Clean Solar Screen (Egg Carton) | - | - | - | - | - | - | - | |
| Clean Stair Tread and Railings | - | - | - | - | - | - | - | |
| Wet Mop Locker room & Exercise Mats | - | - | - | - | - | - | - | |
| SUGGESTED CLEANING SCHEDULE - AREA & FREQUENCY | ||||||||
| 7 = 7 Days Per Week |
5 = 5 Days Per week 3 = 3 Days Per Week 2 = 2 Days Per Week W = Weekly M = Monthly Q = Quarterly S = Semiannually - Mar / Sept.
A = Annually - April TD = Times Daily TW = Times Weekly TY = Times Yearly ** = included on individual floors
| Also, see Section D, paragraph D.3. | Left Power House (El 991 to 921) Stairs & Landings | Left Power House (El 1012) 7th FL | |||||||
| Outside Concrete Slab Between Control Bay and Power Plant | Main Dam (El 1050, 1150, 1229) Block 54 Restrooms | Right Control Bay 11th to 6th FL's Stairs & Landings, Outside Fire Escape Stairs & Landings | Right Control Bay (El 1077) 12th FL. Stairs, Floor, Training Room | Right Control Bay (El 1064) 11th FL. | Right Control Bay (El 1051) 10th FL. | ||||
| Carpet | Sqft | - | - | - | - | 1469 | 3174 | - | |
| Tile, Vinyl or Asphalt | Sqft | - | - | - | - | - | 337 | 1124 | |
| Tile, Quarry or Ceramic | Sqft | - | - | - | - | - | - | - | |
| Terrazzo | Sqft | - | - | - | ** | - | 1570 | 714 | |
| Concrete | Sqft | ** | 3813 | 81 | - | 1190 | - | 2717 | |
| Asphalt Block | Sqft | - | - | - | - | - | - | - | |
| Wood | Sqft | - | - | - | - | - | - | - | |
| Remove Trash | - | 5 | W | - | W | 5 | 5 | ||
| Clean & Supply Restroom | - | - | W | - | - | 5 | 5 | ||
| Clean Showers | - | - | - | - | - | - | 5 | ||
| Clean Water Dispenser | - | - | - | - | - | 5 | 5 | ||
| Clean Kitchen/Kitchenette | - | - | - | - | - | 5 | 5 | ||
| Dusting, Routine | W | - | - | W | W | 5 | W | ||
| Vacuum Carpets | - | - | - | - | W | 5 | 5 | ||
| Sweep Floors | W | - | - | W | 3 | 5 | 5 | ||
| Clean Office Furniture | - | - | - | - | W | W | W | ||
| Wet Mop Floors | M | - | - | M | W | 5 | W | ||
| Spray Buff | - | - | - | - | - | W | W | ||
| Wash Interior Glass | - | - | - | - | - | 5 | - | ||
| Wash Interior/Exterior Windows | - | - | - | - | - | 3TY | 3TY | ||
| Dusting, High Spaces | - | - | - | M | M | M | M | ||
| Strip & Refinish Floors | - | - | - | S | - | Q | Q | ||
| Shampoo Carpets | - | - | - | - | S | Q | Q | ||
| Scrub | S | - | - | - | - | - | - | ||
| Strip & Refinish Restroom Floors | - | - | - | S | - | S | S | ||
| * Wash Down Concrete Slab as needed | - | Mar/Sept | - | - | - | - | - | ||
| Clean Stair Tread and Railings | - | - | - | W | W | - | - | ||
| Wet Mop Locker room & Exercise Mats | - | - | - | - | - | - | - | ||
| SUGGESTED CLEANING SCHEDULE - AREA & FREQUENCY | |||||||||
| 7 = 7 Days Per Week |
5 = 5 Days Per week 3 = 3 Days Per Week 2 = 2 Days Per Week W = Weekly M = Monthly Q = Quarterly S = Semiannually - Mar / Sept.
A = Annually - April TD = Times Daily TW = Times Weekly TY = Times Yearly ** = included on individual floors
| Also, see Section D, paragraph D.3. | Right Control Bay (El 1038) 9th FL. | Right Control Bay (El 1025) 8th FL. | Right Control Bay (El 1012) 7th FL. | Right Service Bay (El 991) 6th Floor, Including Stairs & Landings down to 3rd Floor | Right Service Bay Ramp (El 979 to 968) 5th to 3rd floor TTP | Right Service Bay (El 979) 5th FL. | Right Service Bay (El 968) 4th FL. | ||
| Carpet | Sqft | 1603 | - | 475 | - | - | - | - | |
| Tile, Vinyl or Asphalt | Sqft | 1801 | - | 110 | - | - | - | - | |
| Tile, Quarry or Ceramic | Sqft | - | - | - | - | - | - | - | |
| Terrazzo | Sqft | 1148 | 1971 | 2191 | 832 | - | - | - | |
| Concrete | Sqft | 1404 | 2228 | - | 1194 | 800 | 10663 | 3104 | |
| Asphalt Block | Sqft | - | - | - | - | - | - | - | |
| Wood | Sqft | - | - | - | - | - | - | - | |
| Remove Trash | 5 | 5 | 5 | 5 | - | 5 | 5 | ||
| Clean & Supply Restroom | 5 | 5 | 5 | 5 | - | - | - | ||
| Clean Showers | - | - | - | - | - | - | - | ||
| Clean Water Dispenser | 5 | 5 | 5 | 5 | - | - | - | ||
| Clean Kitchen/Kitchenette | 5 | 5 | 5 | - | - | - | - | ||
| Dusting, Routine | 5 | 5 | 5 | 5 | W | M | M | ||
| Vacuum Carpets | 5 | 5 | 5 | - | - | - | - | ||
| Sweep Floors | 5 | 5 | 5 | 5 | 2 | 3 | 3 | ||
| Clean Office Furniture | W | W | W | W | - | - | - | ||
| Wet Mop Floors | W | W | 5 | W | - | - | - | ||
| Spray Buff | W | W | W | - | - | - | - | ||
| Wash Interior Glass | Q | Q | 5 | - | - | - | - | ||
| Wash Interior/Exterior Windows | 3TY | 3TY | 3TY | - | - | - | - | ||
| Dusting, High Spaces | M | M | - | - | - | - | - | ||
| Strip & Refinish Floors | Q | Q | Q | Q | - | - | - | ||
| Shampoo Carpets | Q | Q | Q | - | - | - | - | ||
| Scrub | - | - | - | Q | - | Q | Q | ||
| Strip & Refinish Restroom Floors | S | S | S | S | - | - | - | ||
| Clean Solar Screen (Egg Carton) | - | - | - | - | - | - | - | ||
| Clean Stair Tread and Railings | - | - | - | - | - | - | - | ||
| Wet Mop Locker room & Exercise Mats | - | - | - | - | - | - | - | ||
| SUGGESTED CLEANING SCHEDULE - AREA & FREQUENCY | |||||||||
| 7 = 7 Days Per Week |
5 = 5 Days Per week 3 = 3 Days Per Week 2 = 2 Days Per Week W = Weekly M = Monthly Q = Quarterly S = Semiannually - Mar / Sept.
A = Annually - April TD = Times Daily TW = Times Weekly TY = Times Yearly ** = included on individual floors
| Also, see Section D, paragraph D.3. | Right Service Bay (El 951) 3rd FL. | Right Service Bay (El 934) 2nd FL. | Right Service Bay (El 921) 1st FL. | Right Power House (El 1012) Outside Concrete Slab between Control Bay and Power Plant | Right Power House (El 991 to 921) FL's | ||||
| Floors, Stairs & Landings | Right Power House (El 1012) Unloading Floor | ||||||||
| Balcony, Catwalk | Right Power House (El 991) 6th Fl. | ||||||||
| Carpet | Sqft | - | - | - | - | - | - | - | |
| Tile, Vinyl or Asphalt | Sqft | 352 | - | - | - | - | - | - | |
| Tile, Quarry or Ceramic | Sqft | - | - | - | - | - | - | - | |
| Terrazzo | Sqft | 2579 | - | - | - | - | 9646 | 27900 | |
| Concrete | Sqft | - | 1062 | 1343 | 3575 | ** | 289 | 26019 | |
| Asphalt Block | Sqft | - | - | - | - | - | - | - | |
| Wood | Sqft | - | - | - | - | - | - | - | |
| Remove Trash | 5 | - | - | 5 | - | 5 | 5 | ||
| Clean & Supply Restroom | - | - | - | - | - | - | 3 | ||
| Clean Showers | - | - | - | - | - | - | - | ||
| Clean Water Dispenser | - | - | - | - | - | - | 3 | ||
| Clean Kitchen/Kitchenette | - | - | - | - | - | - | - | ||
| Dusting, Routine | 5 | - | - | - | W | 3 | - | ||
| Vacuum Carpets | - | - | - | - | - | - | - | ||
| Sweep Floors | 5 | Q | Q | - | W | 5 | 2 | ||
| Clean Office Furniture | - | - | - | - | - | - | - | ||
| Wet Mop Floors | W | - | - | - | M | 3 | 2 | ||
| Spray Buff | W | - | - | - | - | W | - | ||
| Wash Interior Glass | 5 | - | - | - | - | 5 | - | ||
| Wash Interior/Exterior Windows | - | - | - | - | - | 3TY | - | ||
| Dusting, High Spaces | - | - | - | - | - | - | - | ||
| Strip & Refinish Floors | Q | - | - | - | - | Q | Q | ||
| Shampoo Carpets | - | - | - | - | - | - | - | ||
| Scrub | M | - | - | - | S | M | M | ||
| Strip & Refinish Restroom Floors | - | - | - | - | - | - | S | ||
| Clean Solar Screen (Egg Carton) | - | - | - | - | - | - | - | ||
| Clean Stair Tread and Railings | - | - | - | - | - | - | - | ||
| * Wash Down Concrete Slab as needed | - | - | - | S | - | - | - | ||
| SUGGESTED CLEANING SCHEDULE - AREA & FREQUENCY | |||||||||
| 7 = 7 Days Per Week |
5 = 5 Days Per week 3 = 3 Days Per Week 2 = 2 Days Per Week W = Weekly M = Monthly Q = Quarterly S = Semiannually - Mar / Sept.
A = Annually - April TD = Times Daily TW = Times Weekly TY = Times Yearly ** = included on individual floors
| Also, see Section D, paragraph D.3. | Right Power House (El 979) 5th Fl. | Right Power House (El 968) 4th Fl. | Right Power House (El 951) 3rd Fl. | Right Power House (El 934) 2nd Fl. | Right Power House (El 921) 1st Fl. | Right Control Bay Elevators (2) | Third Power Plant (El 1012) 5th FL. Glass Area Over Stairwell South End | ||
| Carpet | Sqft | - | - | - | - | - | - | - | |
| Tile, Vinyl or Asphalt | Sqft | - | - | - | - | - | 240 | - | |
| Tile, Quarry or Ceramic | Sqft | - | - | - | - | - | - | - | |
| Terrazzo | Sqft | - | - | 10002 | - | - | - | - | |
| Concrete | Sqft | 42372 | 45406 | 27879 | 7831 | 11520 | - | 107000 | |
| Asphalt Block | Sqft | - | - | - | - | - | - | - | |
| Wood | Sqft | - | - | - | - | - | - | - | |
| Remove Trash | 5 | W | 3 | - | - | - | 5 | ||
| Clean & Supply Restroom | - | 3 | - | - | - | - | - | ||
| Clean Showers | - | - | - | - | - | - | - | ||
| Clean Water Dispenser | - | - | 3 | - | - | - | 5 | ||
| Clean Kitchen/Kitchenette | - | - | - | - | - | - | - | ||
| Dusting, Routine | - | - | W | - | - | - | W | ||
| Vacuum Carpets | - | - | - | - | - | - | - | ||
| Sweep Floors | 2 | 2 | 3 | M | M | 5 | 5 | ||
| Clean Office Furniture | - | - | W | - | - | - | - | ||
| Wet Mop Floors | - | - | W | - | - | 5 | W | ||
| Spray Buff | - | - | - | - | - | - | - | ||
| Wash Interior Glass | - | - | 5 | - | - | - | S | ||
| Wash Interior/Exterior Windows | - | - | - | - | - | - | - | ||
| Dusting, High Spaces | - | - | - | - | - | - | - | ||
| Strip & Refinish Floors | - | - | Q | - | - | Q | - | ||
| Shampoo Carpets | - | - | - | - | - | - | - | ||
| Scrub | M | M | M | - | - | - | W | ||
| Strip & Refinish Restroom Floors | - | - | - | - | - | - | - | ||
| Clean Solar Screen (Egg Carton) | - | - | - | - | - | - | - | ||
| Clean Stair Tread and Railings | - | - | - | - | - | - | - | ||
| Wet Mop Locker room & Exercise Mats | - | - | - | - | - | - | - | ||
| SUGGESTED CLEANING SCHEDULE - AREA & FREQUENCY | |||||||||
| 7 = 7 Days Per Week |
5 = 5 Days Per week 3 = 3 Days Per Week 2 = 2 Days Per Week W = Weekly M = Monthly Q = Quarterly S = Semiannually - Mar / Sept.
A = Annually - April TD = Times Daily TW = Times Weekly TY = Times Yearly ** = included on individual floors
| Also, see Section D, paragraph D.3. | Third Power Plant (El 990) 4th FL. | Third Power Plant (El 968) 3rd FL. Tour Stop Including Elevations 971 & 975 | Third Power Plant (El 943) 2nd FL. | Third Power Plant (El 919) 1st FL. | Third Power Plant (El 904) Gallery | Third Power Plant | |
| Stairwell S-1 thru S-64 | Third Power Plant |
Elevators North & South ends of Power Plant
| Carpet | Sqft | - | 235 | - | - | - | - | - |
| Tile, Vinyl or Asphalt | Sqft | - | 938 | 560 | - | - | - | 240 |
| Tile, Quarry or Ceramic | Sqft | 256 | - | 144 | - | - | - | - |
| Terrazzo | Sqft | - | - | - | - | - | - | - |
| Concrete | Sqft | 107000 | 107639 | 52994 | 54830 | 21894 | ** | - |
| Asphalt Block | Sqft | - | 14409 | - | - | - | - | - |
| Wood | Sqft | - | - | - | - | - | - | - |
| Remove Trash | 5 | 5 | - | 5 | - | - | - | |
| Clean & Supply Restroom | 5 | 5 | - | 5 | - | - | - | |
| Clean Showers | - | - | - | - | - | - | - | |
| Clean Water Dispenser | 5 | - | - | 5 | - | - | - | |
| Clean Kitchen/Kitchenette | 5 | 5 | - | M | - | - | - | |
| Dusting, Routine | 5 | 5 | - | W | - | M | W | |
| Vacuum Carpets | - | - | - | - | - | - | - | |
| Sweep Floors | 2 | 5 | M | W | M | M | 5 | |
| Clean Office Furniture | 5 | 5 | - | - | - | - | - | |
| Wet Mop Floors | - | 3 | - | - | - | M | 5 | |
| Spray Buff | - | - | - | - | - | - | - | |
| Wash Interior Glass | - | 3 | - | - | - | - | - | |
| Wash Interior/Exterior Windows | - | - | - | - | - | - | - | |
| Dusting, High Spaces | - | M | - | - | - | - | - | |
| Strip & Refinish Floors | S | - | - | S | - | - | - | |
| Shampoo Carpets | - | Q | - | - | - | - | - | |
| Scrub | M | W | M | - | - | - | - | |
| Strip & Refinish Restroom Floors | S | S | - | - | - | - | - | |
| Clean Solar Screen (Egg Carton) | - | - | - | - | - | - | - | |
| Clean Stair Tread and Railings | - | - | - | - | - | M | - | |
| Wet Mop Locker room & Exercise Mats | - | - | - | - | - | - | - | |
| SUGGESTED CLEANING SCHEDULE - AREA & FREQUENCY | ||||||||
| 7 = 7 Days Per Week |
5 = 5 Days Per week 3 = 3 Days Per Week 2 = 2 Days Per Week W = Weekly M = Monthly Q = Quarterly S = Semiannually - Mar / Sept.
A = Annually - April TD = Times Daily TW = Times Weekly TY = Times Yearly ** = included on individual floors
| Also, see Section D, paragraph D.3. | Third Power Plant Tourest Facilities (El 968) | ||||
| Winter Schedule | Third Power Plant Tourest Facilities (El 968) | ||||
| Summer Schedule | Third Power Plant (El 1012 to 1060) Stairwell 5th FL. up to Crane | Wing Dam Block 119 Elevator Tower (El 1290 to 1311) | Wing Dam Incline Elevator Head Station (El 1311) | Wing Dam (El 1311) Asphalt Block & Concrete Sidewalk to Main Dam Block 84, both sides | Wing Dam Inclined Elevator Magnetometer Outside Area |
Summer Schedule
| Carpet | Sqft | - | - | - | - | - | - | - |
| Tile, Vinyl or Asphalt | Sqft | - | - | - | 30 | - | - | - |
| Tile, Quarry or Ceramic | Sqft | 300 | 300 | - | 108 | - | - | - |
| Terrazzo | Sqft | - | - | - | - | 50 | - | - |
| Concrete | Sqft | - | - | ** | 206 | - | 7219 | ** |
| Asphalt Block | Sqft | 7582 | 7582 | - | - | 2304 | 30190 | 100 |
| *Rubber Cord Tile | Sqft | 426 | 426 | - | - | - | - | - |
| Remove Trash | 5 | 7 | - | W | 3 | 5 | 7 | |
| Clean & Supply Restroom | 5 | 7 | - | W | - | - | - | |
| Clean Showers | - | - | - | - | - | - | - | |
| Clean Water Dispenser | 5 | 7 | - | W | 3 | - | 7 | |
| Clean Kitchen/Kitchenette | - | - | - | - | - | - | - | |
| Dusting, Routine | 5 | 7 | - | W | 3 | - | 7 | |
| Vacuum Carpets | - | - | - | - | - | - | - | |
| Sweep Floors | 5 | 7 | Q | W | 3 | W | 7 | |
| Clean Office Furniture | - | - | - | - | - | - | - | |
| Wet Mop Floors | 5 | 7 | Q | W | 3 | - | - | |
| Spray Buff | - | - | - | - | - | - | - | |
| Wash Interior Glass | W | 7 | - | - | - | - | - | |
| Wash Interior/Exterior Windows | - | - | - | - | - | - | - | |
| Dusting, High Spaces | - | - | - | - | W | - | - | |
| Strip & Refinish Floors | - | - | - | - | - | - | - | |
| Shampoo Carpets | - | - | - | - | - | - | - | |
| Scrub | M | M | - | - | W | - | - | |
| Strip & Refinish Restroom Floors | S | S | - | S | - | - | - | |
| Clean Solar Screen (Egg Carton) | - | - | - | - | A | - | 7 | |
| Clean Stair Tread and Railings | - | - | - | - | - | - | - | |
| Wet Mop Locker room & Exercise Mats | - | - | - | - | - | - | - | |
| SUGGESTED CLEANING SCHEDULE - AREA & FREQUENCY | ||||||||
| 7 = 7 Days Per Week |
5 = 5 Days Per week 3 = 3 Days Per Week 2 = 2 Days Per Week W = Weekly M = Monthly Q = Quarterly S = Semiannually - Mar / Sept.
A = Annually - April TD = Times Daily TW = Times Weekly TY = Times Yearly ** = included on individual floors
| Also, see Section D, paragraph D.3. | Wing Dam Inclined Elevator Magnetometer Outside Area | ||||||||
| Winter Schedule | Wing Dam Inclined Elevator Magnetometer Outside Area | ||||||||
| Winter Schedule | Main Dam Elevator Tower (El 1040, 1295, 1311, 1318) Ramp, Stairs & Landing | Main Dam Block 64 Elevator Tower and Stairs (El 1311 to 1323) | Main Dam Elevator Tower (El 1040, 1295, 1311, 1318) Ramp, Stairs & Landing | Main Dam Block 64 Elevator Tower and Stairs (El 1311 to 1323) | Main Dam Block 31 Elevator Tower and Stairs(El 1311 to 1323) | ||||
| Carpet | Sqft | - | - | - | - | - | - | - | |
| Tile, Vinyl or Asphalt | Sqft | - | - | 125 | 125 | 125 | 125 | 125 | |
| Tile, Quarry or Ceramic | Sqft | - | - | - | - | - | - | - | |
| Terrazzo | Sqft | - | - | 2255 | 142 | 2255 | 142 | 81 | |
| Concrete | Sqft | ** | ** | 93 | 93 | 93 | 93 | 224 | |
| Asphalt Block | Sqft | 100 | 100 | - | - | - | - | - | |
| *Rubber Cord Tile | Sqft | - | - | - | - | - | - | - | |
| Remove Trash | 3 | 3 | 3 | W | 3 | W | W | ||
| Clean & Supply Restroom | - | - | 3 | 5 | 3 | 5 | - | ||
| Clean Showers | - | - | - | - | - | - | - | ||
| Clean Water Dispenser | 3 | 3 | 3 | - | 3 | - | - | ||
| Clean Kitchen/Kitchenette | - | - | - | - | - | - | - | ||
| Dusting, Routine | 3 | 3 | 3 | - | 3 | - | - | ||
| Vacuum Carpets | - | - | - | - | - | - | - | ||
| Sweep Floors | 3 | 3 | 3 | M | 3 | M | M | ||
| Clean Office Furniture | - | - | - | - | - | - | - | ||
| Wet Mop Floors | - | - | 3 | M | 3 | M | M | ||
| Spray Buff | - | - | M | - | M | - | - | ||
| Wash Interior Glass | - | - | 3 | M | 3 | M | M | ||
| Wash Interior/Exterior Windows | - | - | 3TY | M | 3TY | M | M | ||
| Dusting, High Spaces | - | - | - | - | - | - | - | ||
| Strip & Refinish Floors | - | - | Q | S | Q | S | S | ||
| Shampoo Carpets | - | - | - | - | - | - | - | ||
| Scrub | - | - | - | - | - | - | - | ||
| Strip & Refinish Restroom Floors | - | - | S | - | S | - | - | ||
| *Strip and Seal Terrazzo Seats | 3 | 3 | - | - | - | - | - | ||
| Clean Stair Tread and Railings | - | - | - | - | - | - | - | ||
| Wet Mop Locker room & Exercise Mats | - | - | - | - | - | - | - | ||
| SUGGESTED CLEANING SCHEDULE - AREA & FREQUENCY | |||||||||
| 7 = 7 Days Per Week |
5 = 5 Days Per week 3 = 3 Days Per Week 2 = 2 Days Per Week W = Weekly M = Monthly Q = Quarterly S = Semiannually - Mar / Sept.
A = Annually - April TD = Times Daily TW = Times Weekly TY = Times Yearly ** = included on individual floors
| Also, see Section D, paragraph D.3. | Main Dam Block 11 Elevator Tower Stairs & Landing (El 1311 to 1323, 1295) | Main Dam Elevator Gallery (El 1250) 5th FL. Left Power House to 9th FL. Pump Generation Plant Ramp (El 1245) | Visitors Center and Eevator, Stairs | |
| Winter Schedule | Visitors Center and Eevator, Stairs | |||
| Summer Schedule | Visitors Center Basement & Stairs | Visitors Center Lower Park Comfort Stations "A" | ||
| 1 May to 30 Sept | Visitors Center Lower Park Comfort Stations "A" |
1 Oct to 30 Nov
| Carpet | Sqft | - | - | 2858 | 2858 | - | - | - |
| Tile, Vinyl or Asphalt | Sqft | 125 | - | - | - | - | - | - |
| Tile, Quarry or Ceramic | Sqft | - | - | 7777 | 7777 | 271 | 700 | 700 |
| Terrazzo | Sqft | 675 | 2074 | - | - | - | - | - |
| Concrete | Sqft | 224 | - | - | 9051 | 6120 | 141 | 141 |
| Asphalt Block | Sqft | - | - | - | - | - | - | - |
| *Rubber Cord Tile | Sqft | - | - | 85 | 85 | - | - | - |
| Remove Trash | 3 | - | 7 | 3TD | 3 | 7 | 3 | |
| Clean & Supply Restroom | 3 | - | 7 | 3TD | 3 | 7 | 3 | |
| Clean Showers | - | - | - | - | - | - | - | |
| Clean Water Dispenser | 3 | - | 7 | 3TD | - | 7 | 3 | |
| Clean Kitchen/Kitchenette | - | - | 7 | 7 | - | - | - | |
| Dusting, Routine | 3 | - | 7 | 7 | - | 7 | 3 | |
| Vacuum Carpets | - | - | 7 | 7 | - | - | - | |
| Sweep Floors | 3 | 5 | 7 | 7 | W | 7 | 3 | |
| Clean Office Furniture | - | - | 7 | 7 | - | - | - | |
| Wet Mop Floors | 3 | W | 3 | 7 | M | 5 | 3 | |
| Spray Buff | - | - | - | - | - | - | - | |
| Wash Interior Glass | W | - | W | W | - | - | - | |
| Wash Interior/Exterior Windows | M | - | 3TY | 3TY | - | - | - | |
| Dusting, High Spaces | - | - | M | M | - | M | M | |
| Strip & Refinish Floors | Q | Q | S | A | - | - | - | |
| Shampoo Carpets | - | - | Q | Q | - | - | - | |
| *Clean/Disinfect Hands-On Displays | - | - | 7 | 3TD | - | - | - | |
| Strip & Refinish Restroom Floors | S | - | S | S | S | A-July | - | |
| *Sweep Entryway/Sidewalk/Bleachers | - | - | - | 7 | - | - | - | |
| Clean Stair Tread and Railings | - | - | - | 7 | - | - | - | |
| *Power Wash Bleachers | - | - | - | 7 | - | - | - | |
| SUGGESTED CLEANING SCHEDULE - AREA & FREQUENCY | ||||||||
| 7 = 7 Days Per Week |
5 = 5 Days Per week 3 = 3 Days Per Week 2 = 2 Days Per Week W = Weekly M = Monthly Q = Quarterly S = Semiannually - Mar / Sept.
A = Annually - April TD = Times Daily TW = Times Weekly TY = Times Yearly ** = included on individual floors
| Also, see Section D, paragraph D.3. | Visitors Center Lower Park Comfort Stations "A" | ||||||||
| *Closed 1 Dec to 30 Apr | Visitors Center Lower Park Comfort Stations "B" | ||||||||
| 1 May to 30 Sept | Visitors Center Lower Park Comfort Stations "B" | ||||||||
| 1 Oct to 30 Apr | North Dam Park Upper Loop Comfort Station 1 May to 30 Sept | North Dam Park Upper Loop Comfort Station *Closed 1 Nov to 30 Apr | Magnatometer Building and Vaault Toilet Tourist Season Only | Construction Building | |||||
| Carpet | Sqft | - | - | - | - | - | 240 | 4840 | |
| Tile, Vinyl or Asphalt | Sqft | - | - | - | - | - | - | 240 | |
| Tile, Quarry or Ceramic | Sqft | 700 | 542 | 542 | - | - | - | - | |
| Terrazzo | Sqft | - | - | - | - | - | - | - | |
| Concrete | Sqft | 141 | 127 | 127 | 262 | 262 | 80 | - | |
| Asphalt Block | Sqft | - | - | - | - | - | - | - | |
| *Rubber Cord Tile | Sqft | - | - | - | - | - | - | - | |
| Remove Trash | - | 7 | 3 | 7 | - | 7 | 5 | ||
| Clean & Supply Restroom | - | 7 | 3 | 7 | - | 7 | 5 | ||
| Clean Showers | - | - | - | - | - | - | - | ||
| Clean Water Dispenser | - | 7 | 3 | 7 | - | - | 5 | ||
| Clean Kitchen/Kitchenette | - | - | - | - | - | - | 5 | ||
| Dusting, Routine | - | 7 | 3 | 7 | - | 7 | 3 | ||
| Vacuum Carpets | - | - | - | - | - | 7 | 3 | ||
| Sweep Floors | - | 7 | 3 | 7 | - | 7 | 3 | ||
| Clean Office Furniture | - | - | - | - | - | 7 | 3 | ||
| Wet Mop Floors | - | 5 | 3 | 5 | - | W | 3 | ||
| Spray Buff | - | - | - | - | - | - | - | ||
| Wash Interior Glass | - | - | - | - | - | Q | Q | ||
| Wash Interior/Exterior Windows | - | - | - | - | - | Q | Q | ||
| Dusting, High Spaces | - | M | M | M | - | M | M | ||
| Strip & Refinish Floors | - | - | - | - | - | - | Q | ||
| Shampoo Carpets | - | - | - | - | - | M | Q | ||
| Scrub | - | - | - | - | - | - | - | ||
| Strip & Refinish Restroom Floors | - | A-July | - | A-July | - | - | Q | ||
| Clean Solar Screen (Egg Carton) | - | - | - | - | - | 7 | - | ||
| Clean Stair Tread and Railings | - | - | - | - | - | - | - | ||
| Wet Mop Locker room & Exercise Mats | - | - | - | - | - | - | - | ||
| SUGGESTED CLEANING SCHEDULE - AREA & FREQUENCY | ‡‡CLEANING NOT REQUIRED UNTIL RETURN TO SERVICE, See chapter D.X for dates | ||||||||
| 7 = 7 Days Per Week |
5 = 5 Days Per week 3 = 3 Days Per Week 2 = 2 Days Per Week W = Weekly M = Monthly Q = Quarterly S = Semiannually - Mar / Sept.
A = Annually - April TD = Times Daily TW = Times Weekly TY = Times Yearly ** = included on individual floors
| Also, see Section D, paragraph D.3. | Material Storage Building (MSB) | North Canal Vault Toilets (2) and Trach Cans | Guard Station 3 Vault Toilet and Trash Can | Downriver Trail Upper Vault Toilet and Trash Can | Down River Trail Vault Toilet (2) and Trash cans | Seaton's Grove Boat Ramp Vault Toilet and Trash Cans | Fire Station, First Floor | ||
| Carpet | Sqft | - | - | - | - | - | - | - | |
| Tile, Vinyl or Asphalt | Sqft | 130 | - | - | - | - | - | - | |
| Tile, Quarry or Ceramic | Sqft | 193 | - | - | - | - | - | - | |
| Terrazzo | Sqft | - | - | - | - | - | - | 3805 | |
| Concrete | Sqft | - | - | 40 | 40 | - | - | 9232 | |
| Asphalt Block | Sqft | - | - | - | - | - | - | - | |
| *Fiberglass | Sqft | - | 80 | - | - | 80 | 40 | 862 | |
| Remove Trash | 3 | 3 | 3 | 3 | 3 | 3 | 7 | ||
| Clean & Supply Restroom | 3 | 3 | 3 | 3 | 3 | 3 | 7 | ||
| Clean Showers | 3 | - | - | - | - | - | 7 | ||
| Clean Water Dispenser | 3 | - | - | - | - | - | 5 | ||
| Clean Kitchen/Kitchenette | - | - | - | - | - | - | - | ||
| Dusting, Routine | 3 | 3 | 3 | 3 | 3 | 3 | 5 | ||
| Vacuum Carpets | - | - | - | - | - | - | - | ||
| Sweep Floors | 3 | 3 | 3 | 3 | 3 | 3 | 5 | ||
| Clean Office Furniture | 3 | - | - | - | - | - | 5 | ||
| Wet Mop Floors | 3 | 3 | 3 | 3 | 3 | 3 | 5 | ||
| Spray Buff | - | - | - | - | - | - | - | ||
| Wash Interior Glass | Q | - | - | - | - | - | W | ||
| Wash Interior/Exterior Windows | Q | - | - | - | - | - | 3TY | ||
| Dusting, High Spaces | M | - | - | - | - | - | W | ||
| Strip & Refinish Floors | Q | - | - | - | - | - | Q | ||
| Shampoo Carpets | - | - | - | - | - | - | - | ||
| Scrub | - | - | - | - | - | - | - | ||
| Strip & Refinish Restroom Floors | Q | - | - | - | - | - | Q | ||
| *Sweep Entryway/Sidewalk/Bleachers | - | - | - | - | - | - | - | ||
| Clean Stair Tread and Railings | - | - | - | - | - | - | 3 | ||
| Wet Mop Locker room & Exercise Mats | - | - | - | - | - | - | 7 | ||
| SUGGESTED CLEANING SCHEDULE - AREA & FREQUENCY | ‡‡CLEANING NOT REQUIRED UNTIL RETURN TO SERVICE, See chapter D.X for option years | ||||||||
| 7 = 7 Days Per Week |
5 = 5 Days Per week 3 = 3 Days Per Week 2 = 2 Days Per Week W = Weekly M = Monthly Q = Quarterly S = Semiannually - Mar / Sept.
A = Annually - April TD = Times Daily TW = Times Weekly TY = Times Yearly ** = included on individual floors
| Also, see Section D, paragraph D.3. | Fire Station Second Floor | North Dam Park | |
| 8 - 30 gal Trash Cans | Feeder Canal Outlet Area | ||
| 2 - 30 gal Trash Cans | 115kV Switch Yard Overlook | ||
| 1 - 30 gal Trash Can | Pole Park | ||
| 4 - 30 gal Trash Cans | Model Dam Parking Lot | ||
| 2 - 30 gal Trash Cans | FDR Park |
3 - 30 gal Trash Cans
| Carpet | Sqft | - | - | - | - | - | - | - |
| Tile, Vinyl or Asphalt | Sqft | - | - | - | - | - | - | - |
| Tile, Quarry or Ceramic | Sqft | 328 | - | - | - | - | - | - |
| Terrazzo | Sqft | 4614 | - | - | - | - | - | - |
| Concrete | Sqft | - | - | - | - | - | - | - |
| Asphalt Block | Sqft | - | - | - | - | - | - | - |
| *Exersize Flooring | Sqft | - | - | - | - | - | - | - |
| Remove Trash | 5 | 5 | 5 | 5 | 5 | 5 | 5 | |
| Clean & Supply Restroom | 5 | - | - | - | - | - | - | |
| Clean Showers | 5 | - | - | - | - | - | - | |
| Clean Water Dispenser | 5 | - | - | - | - | - | - | |
| Clean Kitchen/Kitchenette | 5 | - | - | - | - | - | - | |
| Dusting, Routine | 5 | - | - | - | - | - | - | |
| Vacuum Carpets | - | - | - | - | - | - | - | |
| Sweep Floors | 5 | - | - | - | - | - | - | |
| Clean Office Furniture | 5 | - | - | - | - | - | - | |
| Wet Mop Floors | 5 | - | - | - | - | - | - | |
| Spray Buff | - | - | - | - | - | - | - | |
| Wash Interior Glass | W | - | - | - | - | - | - | |
| Wash Interior/Exterior Windows | 3TY | - | - | - | - | - | - | |
| Dusting, High Spaces | W | - | - | - | - | - | - | |
| Strip & Refinish Floors | Q | - | - | - | - | - | - | |
| Shampoo Carpets | - | - | - | - | - | - | - | |
| Scrub | - | - | - | - | - | - | - | |
| Strip & Refinish Restroom Floors | Q | - | - | - | - | - | - | |
| *Strip and Seal Terrazzo Seats | - | - | - | - | - | - | - | |
| Clean Stair Tread and Railings | 3 | - | - | - | - | - | - | |
| Wet Mop Locker room & Exercise Mats | - | - | - | - | - | - | - | |
| SUGGESTED CLEANING SCHEDULE - AREA & FREQUENCY | ||||||||
| 7 = 7 Days Per Week |
5 = 5 Days Per week 3 = 3 Days Per Week 2 = 2 Days Per Week W = Weekly M = Monthly Q = Quarterly S = Semiannually - Mar / Sept.
A = Annually - April TD = Times Daily TW = Times Weekly TY = Times Yearly ** = included on individual floors
| Also, see Section D, paragraph D.3. | Tailrace Overlook | |
| 2 - 30 gal Trash Cans | Visitor Center Parking Lot and Bleachers | |
| 14 - 30 gal Trash Cans | Pumping Plant Upper Deck and Parking Area | |
| 5 - 30 gal Trash Cans | Top of Dam Roadway | |
| 6 - 30 gal Trash Cans | Public Boat Launch Seaton's Grove | |
| 1 - 30 gal Trash Can and 1 - 60 Bear Proof Trash Receptical | Public Boat Launch North Marina Way | |
| 2 - 30 gal Trash Cans | Incline Elevator Head Station (El 1311) |
2 - 30 gal Trash Cans
| Carpet | Sqft | - | - | - | - | - | - | - |
| Tile, Vinyl or Asphalt | Sqft | - | - | - | - | - | - | - |
| Tile, Quarry or Ceramic | Sqft | - | - | - | - | - | - | - |
| Terrazzo | Sqft | - | - | - | - | - | - | - |
| Concrete | Sqft | - | - | - | - | - | - | - |
| Asphalt Block | Sqft | - | - | - | - | - | - | - |
| *Exersize Flooring | Sqft | - | - | - | - | - | - | - |
| Remove Trash | 5 | 5 | 5 | 5 | 5 | 5 | 5 | |
| Clean & Supply Restroom | - | - | - | - | - | - | - | |
| Clean Showers | - | - | - | - | - | - | - | |
| Clean Water Dispenser | - | - | - | - | - | - | - | |
| Clean Kitchen/Kitchenette | - | - | - | - | - | - | - | |
| Dusting, Routine | - | - | - | - | - | - | - | |
| Vacuum Carpets | - | - | - | - | - | - | - | |
| Sweep Floors | - | - | - | - | - | - | - | |
| Clean Office Furniture | - | - | - | - | - | - | - | |
| Wet Mop Floors | - | - | - | - | - | - | - | |
| Spray Buff | - | - | - | - | - | - | - | |
| Wash Interior Glass | - | - | - | - | - | - | - | |
| Wash Interior/Exterior Windows | - | - | - | - | - | - | - | |
| Dusting, High Spaces | - | - | - | - | - | - | - | |
| Strip & Refinish Floors | - | - | - | - | - | - | - | |
| Shampoo Carpets | - | - | - | - | - | - | - | |
| Scrub | - | - | - | - | - | - | - | |
| Strip & Refinish Restroom Floors | - | - | - | - | - | - | - | |
| *Strip and Seal Terrazzo Seats | - | - | - | - | - | - | - | |
| Clean Stair Tread and Railings | - | - | - | - | - | - | - | |
| Wet Mop Locker room & Exercise Mats | - | - | - | - | - | - | - | |
| SUGGESTED CLEANING SCHEDULE - AREA & FREQUENCY | ‡‡CLEANING NOT REQUIRED UNTIL RETURN TO SERVICE, See chapter D.X for option years | |||||||
| 7 = 7 Days Per Week |
5 = 5 Days Per week 3 = 3 Days Per Week 2 = 2 Days Per Week W = Weekly M = Monthly Q = Quarterly S = Semiannually - Mar / Sept.
A = Annually - April TD = Times Daily TW = Times Weekly TY = Times Yearly ** = included on individual floors
| Also, see Section D, paragraph D.3. | Third Power Plant Incline Elevator Cab Winter Schedule | Third Power Plant Incline Elevator Cab Summer Schedule | Third Power Plant Crossover Bridge (El 1081 to 968) Observation Decks, Balconies & walkways Winter Schedule | Third Power Plant Crossover Bridge (El 1081 to 968) Observation Decks, Balconies & walkways Summer Schedule | Third Power Plant Mid-Station Stairwell (El 1081 to 983) | |
| Summer Schedule | Third Power Plant Mid-Station Stairwell (El 1081 to 983) | |||||
| Summer Schedule | Third Power Plant Mid-Station Stairwell (El 1081) |
Winter Schedule
| Carpet | Sqft | - | - | - | - | - | - | - |
| Tile, Vinyl or Asphalt | Sqft | - | - | - | - | - | - | - |
| Tile, Quarry or Ceramic | Sqft | - | - | - | - | - | - | 615‡‡ |
| Terrazzo | Sqft | - | - | - | - | - | - | 50‡‡ |
| Concrete | Sqft | - | - | - | - | ** | - | - |
| Asphalt Block | Sqft | - | - | 20000‡‡ | 20000‡‡ | - | - | 1762‡‡ |
| *Rubber Cord Tile | Sqft | 200‡‡ | 200‡‡ | - | - | - | - | - |
| Remove Trash | 5 | 7 | 3 | 7 | - | - | 3 | |
| Clean & Supply Restroom | - | - | - | - | - | - | 3 | |
| Clean Showers | - | - | - | - | - | - | - | |
| Clean Water Dispenser | - | - | - | - | - | - | 3 | |
| Clean Kitchen/Kitchenette | - | - | - | - | - | - | - | |
| Dusting, Routine | 5 | 7 | 3 | 7 | - | - | 3 | |
| Vacuum Carpets | 5 | 7 | - | - | - | - | - | |
| Sweep Floors | - | - | 3 | 7 | M | - | 3 | |
| Clean Office Furniture | - | - | - | - | - | - | - | |
| Wet Mop Floors | - | - | - | - | - | - | - | |
| Spray Buff | - | - | - | - | - | - | - | |
| Wash Interior Glass | 5 | 7 | 3 | 7 | - | - | 3 | |
| Wash Interior/Exterior Windows | W | W | 3 | 7 | - | - | - | |
| Dusting, High Spaces | - | - | W | W | - | - | W | |
| Strip & Refinish Floors | - | - | - | - | - | - | - | |
| Shampoo Carpets | Q | Q | - | - | - | - | - | |
| Scrub | - | - | W | W | - | - | W | |
| Strip & Refinish Restroom Floors | - | - | - | - | - | - | - | |
| *Strip and Seal Terrazzo Seats | - | - | - | A | - | - | - | |
| Clean Stair Tread and Railings | - | - | - | - | M | - | - | |
| SUGGESTED CLEANING SCHEDULE - AREA & FREQUENCY | ‡‡CLEANING NOT REQUIRED UNTIL RETURN TO SERVICE, See chapter D.X for option years | |||||||
| 7 = 7 Days Per Week |
5 = 5 Days Per week 3 = 3 Days Per Week 2 = 2 Days Per Week W = Weekly M = Monthly Q = Quarterly S = Semiannually - Mar / Sept.
A = Annually - April TD = Times Daily TW = Times Weekly TY = Times Yearly ** = included on individual floors
| Also, see Section D, paragraph D.3. | Third Power Plant Mid-Station Stairwell (El 1081) | ||||||||
| Summer Schedule | Third Power Plant 5th floor | ||||||||
| Schedule | Shooting Range Three Classroom Trailers | Shooting Range Restroom/Shower Trailer April Through November | Shooting Range Restroom/Shower Trailer December through March | ||||||
| Carpet | Sqft | - | - | 1232 | - | - | - | - | |
| Tile, Vinyl or Asphalt | Sqft | - | - | 768 | 130 | 130 | - | - | |
| Tile, Quarry or Ceramic | Sqft | 615‡‡ | - | - | - | - | - | - | |
| Terrazzo | Sqft | 50‡‡ | 108000 | - | - | - | - | - | |
| Concrete | Sqft | - | - | - | - | - | - | - | |
| Asphalt Block | Sqft | 1762‡‡ | - | - | - | - | - | ||
| *Exersize Flooring | Sqft | - | - | - | - | - | - | - | |
| Remove Trash | 7 | 7 | 5 | 5 | 2 | - | - | ||
| Clean & Supply Restroom | 7 | 7 | 5 | 2 | - | - | |||
| Clean Showers | - | - | - | 5 | 2 | - | - | ||
| Clean Water Dispenser | 7 | 7 | - | - | - | - | - | ||
| Clean Kitchen/Kitchenette | - | - | - | - | - | - | - | ||
| Dusting, Routine | 7 | 7 | 5 | 5 | 2 | - | - | ||
| Vacuum Carpets | - | - | 5 | - | - | - | - | ||
| Sweep Floors | 7 | 7 | 5 | 5 | 2 | - | - | ||
| Clean Office Furniture | - | - | W | - | - | - | - | ||
| Wet Mop Floors | - | - | W | 5 | 2 | - | - | ||
| Spray Buff | - | - | - | - | - | - | - | ||
| Wash Interior Glass | 7 | - | W | - | - | - | - | ||
| Wash Interior/Exterior Windows | - | - | 3TY | - | - | - | - | ||
| Dusting, High Spaces | W | W | M | 5 | 2 | - | - | ||
| Strip & Refinish Floors | Q | Q | - | - | - | - | - | ||
| Shampoo Carpets | - | - | - | - | - | - | - | ||
| Scrub | W | W | - | - | - | - | - | ||
| Strip & Refinish Restroom Floors | A | Q | - | - | - | - | - | ||
| *Strip and Seal Terrazzo Seats | A | Q | - | - | - | ||||
| Exercise Mats | - | - | - | - | - | - | - | ||
| Clean Stair Tread and Railings | - | - | - | - | - | - | - |