1--3- 1.4 Section 2 Document 3.0 Schedule of Values.xlsx
XLSX spreadsheet 13 KB Posted
- Solicitation number
- SLCo PAR129713 Holladay Lions Recreation Center RTU Replacement - CONST
- Issued by
- Salt Lake County, Hildale City, Utah
About this file
This is a Schedule of Values document for a construction project under Salt Lake County, Utah, for the Holladay Lions Recreation Center RTU Replacement (Project PAR129713). The schedule establishes the breakdown of costs across various work divisions, including Payment and Performance Bond, Insurance and Builder's Risk, and Division 01-General Conditions, with provisions for a base bid and three alternate bids (Alternates 1, 2, and 3) plus additional alternates designated as B and C. The document requires bidders to specify their entire work scope and ensure that all totals submitted match those entered into the Online Solicitation System (OSS), with a dedicated field for the name of the company submitting the bid.
The project scope involves replacing air handling units (RTU) on the roof of the Holladay Lions Recreation Center, with work coordination required with a separate re-roofing project. All line items in the submitted schedule show $0 values, indicating this is a template document awaiting completion by contractors during the bidding process. Bidders must provide detailed cost allocations for each division of work and alternate scope options, ensuring alignment between the Schedule of Values submission and their OSS bid entry. The document does not specify pricing terms, contract term length, set-asides, or award dates within the template itself, as these details would be contained in the primary solicitation documents.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Section 2 - Document 3.0 | |||||||
| Schedule Of Values | |||||||
| Project: PAR129713 Holladay Lions Recreation Center RTU Replacement | |||||||
| Divisions of Work | Base Bid | Alternate 1 | Alternate 2 | Alternate 3 | |||
| (Specify entire work scope; examples are listed below) | Alternate B | Alternate C | Total | ||||
| Payment & Performance Bond | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||
| Insurance & Builder's Risk | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||
| Division 01-General Conditions | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||
| $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||
| $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||
| $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||
| $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||
| $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||
| $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||
| $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||
| $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||
| $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||
| $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||
| $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||
| $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||
| Totals (Enter in OSS) | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| The total for the base bid must be the same total that was entered into the Online Solicitation System (OSS). |
| The total for each alternate must be the same total that was entered into the Online Solicitation System (OSS) |
| Name of Company Bidding ________________________________ |