About this file

The document is a scope of work for the installation of resilient tile flooring as part of the Chicopee Armory Rehabilitation project in Chicopee, Massachusetts. The project requires the installation of vinyl composition floor tile, including product submittals, qualification data for the installer, and closeout documentation. The scope specifies requirements for product standards, installation methods, substrate preparation, and project conditions. The project is being bid by the Massachusetts state government, with bids due on 05/20/11.

The scope requires the contractor to furnish extra materials, maintain appropriate temperature and humidity levels during installation, and comply with FloorScore and low-VOC requirements. Pricing information is not provided, nor are any details on set-asides, incumbent contractors, funding sources, or other commercial terms. The scope focuses exclusively on the technical specifications and execution requirements for the resilient tile flooring portion of the larger Chicopee Armory Rehabilitation project.

View the file

Other files

File Type Posted
AE121-10090.pdf PDF
ED101-10090.pdf PDF
Sub_Bid_Result_Chicopee_2011.xls XLS spreadsheet
AE102-10090.pdf PDF
Business_Reference_Form_GC_Chicopee2011.doc DOC document
230719_hvac_pipe_ins.pdf PDF
EP651-10090.pdf PDF
Ch_149_FORM_FOR_SUB_BID_MIL_Chicopee2011_Electrical.doc DOC document
Ch_149_FORM_FOR_SUB_BID_MIL_Chicopee2011_Metal_Windows.doc DOC document
013200_FL-CONSTRUCTION_PROGRESS_DOCUMENTATION.pdf PDF
014000_FL-QUALITY_REQUIREMENTS.pdf PDF
236313_air_cooled_condensers.pdf PDF
AE311-10090.pdf PDF
020800_Asbestos_Technical_Specifications.pdf PDF
E-601-10090.pdf PDF
230001-HVAC_FSB.pdf PDF
Ch_149_FORM_FOR_SUB_BID_MIL_Chicopee2011_Resilient_Floors.doc DOC document
017900_FL-DEMONSTRATION_AND_TRAINING.pdf PDF
Ch_149_FORM_FOR_SUB_BID_MIL_Chicopee2011_Masonry.doc DOC document
AE401-10090.pdf PDF
SF502-10090.pdf PDF
070002-ROOFING_AND_FLASHING_FSB.pdf PDF
265100_Lighting_Fixtures.pdf PDF
030130_FL-MAINTENANCE_OF_CAST-IN-PLACE_CONCRETE.pdf PDF
220001-PLUMBING-FSB.pdf PDF
013100_FL-PROJECT_MANAGEMENT_AND_COORDINATION.pdf PDF
238900_Louvers_and_Vents.pdf PDF
SF101-10090.pdf PDF
016000_FL-PRODUCT_REQUIREMENTS.pdf PDF
M-651-10090.pdf PDF
GI001-10090.pdf PDF
Ch_149_FORM_FOR_GENERAL_BID_MIL_Chicopee2011.doc DOC document
093000_FL-TILING_v1.pdf PDF
088000_FL-GLAZING_v1.pdf PDF
081113_FL-HOLLOW_METAL_DOORS_AND_FRAMES_v1.pdf PDF
231123_fuel_gas_piping.pdf PDF
PL101-10090.pdf PDF
230900_hvac_instrumentation_controls.pdf PDF
224000_plumbing_fixtures_JPB.pdf PDF
061600_FL-SHEATHING_v1.pdf PDF
220100_plumbing_requirements_JPB.pdf PDF
232113_hydronic_piping.pdf PDF
EL101-10090.pdf PDF
232300_refrigerant_piping.pdf PDF
General_Bid_Tabulation_Chicopee_2011.xls XLS spreadsheet
220500_plumbing_materials_JPB.pdf PDF
262413_Switchboards.pdf PDF
092216_FL-NON-STRUCTURAL_META_FRAMING_v1.pdf PDF
X-100_SURVEY_CONTROL_PLAN.pdf PDF
AE611-10090.pdf PDF
Show 40 more

Latest 50 of 185 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CHICOPEE ARMORY REHABILITATION MMD PROJECT NO. 985101

CHICOPEE, MASSACHUSETTS ISSUED FOR BID - 05/20/11

10090 RESILIENT TILE FLOORING 096519 - 1

SECTION 096519

RESILIENT TILE FLOORING

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary

Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Vinyl composition floor tile.

B. Related Sections:

1. Section 096513 "Resilient Base and Accessories" for resilient base, reducer strips, and other accessories installed with resilient floor coverings.

1.3 ACTION SUBMITTALS

A. Product Data: For each type of product indicated.

B. Samples for Initial Selection: For each type of floor tile indicated.

C. Samples for Verification: Full-size units of each color and pattern of floor tile required.

D. Product Schedule: For floor tile.

1.4 INFORMATIONAL SUBMITTALS

A. Qualification Data: For qualified Installer.

1.5 CLOSEOUT SUBMITTALS

A. Maintenance Data: For each type of floor tile to include in maintenance manuals.

1.6 MATERIALS MAINTENANCE SUBMITTALS

A. Furnish extra materials that match products installed and that are packaged with protective covering for storage and identified with labels describing contents.

10090 RESILIENT TILE FLOORING 096519 - 2

1. Floor Tile: Furnish 1 box for every 50] boxes or fraction thereof, of each type, color, and pattern of floor tile installed.

1.7 QUALITY ASSURANCE

A. Installer Qualifications: A qualified installer who employs workers for this Project who are competent in techniques required by manufacturer for floor tile installation indicated.

1. Engage an installer who employs workers for this Project who are trained or certified by manufacturer for installation techniques required.

B. Fire-Test-Response Characteristics: As determined by testing identical products according to

ASTM E 648 or NFPA 253 by a qualified testing agency.

1. Critical Radiant Flux Classification: Class I, not less than 0.45 W/sq. cm.

1.8 DELIVERY, STORAGE, AND HANDLING

A. Store floor tile and installation materials in dry spaces protected from the weather, with ambient temperatures maintained within range recommended by manufacturer, but not less than 50 deg F or more than 90 deg F. Store floor tiles on flat surfaces.

1.9 PROJECT CONDITIONS

A. Maintain ambient temperatures within range recommended by manufacturer, but not less than

70 deg F or more than 95 deg F , in spaces to receive floor tile during the following time periods:

1. 48 hours before installation.

2. During installation.

3. 48 hours after installation.

B. Until Substantial Completion, maintain ambient temperatures within range recommended by manufacturer, but not less than 55 deg F] or more than 95 deg F .

C. Close spaces to traffic during floor tile installation.

D. Close spaces to traffic for 48 hours after floor tile installation.

E. Install floor tile after other finishing operations, including painting, have been completed.

PART 2 - PRODUCTS

2.1 PERFORMANCE REQUIREMENTS

A. FloorScore Compliance: Resilient tile flooring shall comply with requirements of FloorScore

Standard.

10090 RESILIENT TILE FLOORING 096519 - 3

B. Low-Emitting Materials: Flooring system shall comply with the testing and product requirements of the California Department of Health Services' "Standard Practice for the

Testing of Volatile Organic Emissions from Various Sources Using Small-Scale Environmental

Chambers."

2.2 VINYL COMPOSITION FLOOR TILE <Insert drawing designation>

A. Products: Subject to compliance with requirements available products that may be incorporated into the Work include, but are not limited to, the following:

1. Armstrong World Industries, Inc.; .

2. Congoleum Corporation; .

3. Mannington Mills, Inc.; Tarkett, Inc.; .

B. Tile Standard: ASTM F 1066, Class 2, through-pattern tile .

C. Wearing Surface: Smooth .

D. Thickness: [0.125 inch] .

E. Size: 12 by 12 inches.

F. Colors and Patterns: As selected by Architect from full range of industry colors.

2.3 INSTALLATION MATERIALS

A. Trowelable Leveling and Patching Compounds: Latex-modified, portland cement based or blended hydraulic-cement-based formulation provided or approved by manufacturer for applications indicated.

B. Adhesives: Water-resistant type recommended by manufacturer to suit floor tile and substrate conditions indicated.

1. Adhesives shall comply with the following limits for VOC content when calculated according to 40 CFR 59, Subpart D (EPA Method 24):

a. VCT and Asphalt Tile Adhesives: Not more than 50 g/L.

2. Adhesives shall comply with the testing and product requirements of the California

Department of Health Services' "Standard Practice for the Testing of Volatile Organic

Emissions from Various Sources Using Small-Scale Environmental Chambers."

C. Floor Polish: Provide protective liquid floor polish products as recommended by manufacturer.

http://www.specagent.com/LookUp/?ulid=484&mf=04&src=wd http://www.specagent.com/LookUp/?uid=123456789500&mf=04&src=wd http://www.specagent.com/LookUp/?uid=123456789503&mf=04&src=wd http://www.specagent.com/LookUp/?uid=123456789505&mf=04&src=wd http://www.specagent.com/LookUp/?uid=123456793038&mf=04&src=wd

10090 RESILIENT TILE FLOORING 096519 - 4

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine substrates, with Installer present, for compliance with requirements for maximum moisture content and other conditions affecting performance of the Work.

B. Verify that finishes of substrates comply with tolerances and other requirements specified in other Sections and that substrates are free of cracks, ridges, depressions, scale, and foreign deposits that might interfere with adhesion of floor tile.

C. Proceed with installation only after unsatisfactory conditions have been corrected.

3.2 PREPARATION

A. Prepare substrates according to manufacturer's written instructions to ensure adhesion of resilient products.

B. Concrete Substrates: Prepare according to ASTM F 710.

1. Verify that substrates are dry and free of curing compounds, sealers, and hardeners.

2. Remove substrate coatings and other substances that are incompatible with adhesives and that contain soap, wax, oil, or silicone, using mechanical methods recommended by manufacturer. Do not use solvents.

3. Alkalinity and Adhesion Testing: Perform tests recommended by manufacturer. Proceed with installation only after substrates pass testing.

4. Moisture Testing: Perform tests recommended by manufacturer. Proceed with installation only after substrates pass testing.

a. Perform anhydrous calcium chloride test, ASTM F 1869. Proceed with installation only after substrates have maximum moisture-vapor-emission rate of [3 lb of water/1000 sq. ft.] <Insert emission> in 24 hours.

b. Perform relative humidity test using in situ probes, ASTM F 2170. Proceed with installation only after substrates have a maximum [75%] relative humidity level measurement.

C. Access Flooring Panels: Remove protective film of oil or other coating using method recommended by access flooring manufacturer.

D. Fill cracks, holes, and depressions in substrates with trowelable leveling and patching compound and remove bumps and ridges to produce a uniform and smooth substrate.

E. Do not install floor tiles until they are same temperature as space where they are to be installed.

1. Move resilient products and installation materials into spaces where they will be installed at least 48 hours in advance of installation.

F. Sweep and vacuum clean substrates to be covered by resilient products immediately before installation.

10090 RESILIENT TILE FLOORING 096519 - 5

3.3 FLOOR TILE INSTALLATION

A. Comply with manufacturer's written instructions for installing floor tile.

B. Lay out floor tiles from center marks established with principal walls, discounting minor offsets, so tiles at opposite edges of room are of equal width. Adjust as necessary to avoid using cut widths that equal less than one-half tile at perimeter.

1. Lay tiles square with room axis] .

C. Match floor tiles for color and pattern by selecting tiles from cartons in the same sequence as manufactured and packaged, if so numbered. Discard broken, cracked, chipped, or deformed tiles.

1. Lay tiles with grain direction alternating in adjacent tiles (basket-weave pattern) .

D. Scribe, cut, and fit floor tiles to butt neatly and tightly to vertical surfaces and permanent fixtures including built-in furniture, cabinets, pipes, outlets, and door frames.

E. Extend floor tiles into toe spaces, door reveals, closets, and similar openings. Extend floor tiles to center of door openings.

F. Maintain reference markers, holes, and openings that are in place or marked for future cutting by repeating on floor tiles as marked on substrates. Use chalk or other nonpermanent, nonstaining marking device.

G. Install floor tiles on covers for telephone and electrical ducts, building expansion-joint covers, and similar items in finished floor areas. Maintain overall continuity of color and pattern between pieces of tile installed on covers and adjoining tiles. Tightly adhere tile edges to substrates that abut covers and to cover perimeters.

H. Adhere floor tiles to flooring substrates using a full spread of adhesive applied to substrate to produce a completed installation without open cracks, voids, raising and puckering at joints, telegraphing of adhesive spreader marks, and other surface imperfections.

3.4 CLEANING AND PROTECTION

A. Comply with manufacturer's written instructions for cleaning and protection of floor tile.

B. Perform the following operations immediately after completing floor tile installation:

1. Remove adhesive and other blemishes from exposed surfaces.

2. Sweep and vacuum surfaces thoroughly.

3. Damp-mop surfaces to remove marks and soil.

C. Protect floor tile products from mars, marks, indentations, and other damage from construction operations and placement of equipment and fixtures during remainder of construction period.

D. Floor Polish: Remove soil, visible adhesive, and surface blemishes from floor tile surfaces before applying liquid floor polish.

10090 RESILIENT TILE FLOORING 096519 - 6

1. Apply [two] [three] coat(s).

E. Cover floor tile until Substantial Completion.

END OF SECTION 096519