This document is a product requirements specification for the Chicopee Armory Rehabilitation project (MMD Project No. 985101) located in Chicopee, Massachusetts. The specification covers administrative and procedural requirements for the selection, delivery, storage, handling, and warranties of products to be incorporated into the rehabilitation project. Key requirements include providing new, undamaged products that comply with the contract documents, as well as providing product samples and data to demonstrate compliance with specified characteristics for comparable products. The specification also includes requirements for product delivery, storage, and handling, as well as manufacturer's standard and special warranties.

The related state and local contract opportunity is for a general contractor to perform the Chicopee Armory Renovations in Chicopee, Massachusetts. The project is being managed by the state of Massachusetts. No other details about the contract opportunity, such as response due dates, funding sources, or set-asides, are provided in the given information.

View the file

Other files

File Type Posted
AE121-10090.pdf PDF
ED101-10090.pdf PDF
Sub_Bid_Result_Chicopee_2011.xls XLS spreadsheet
AE102-10090.pdf PDF
Business_Reference_Form_GC_Chicopee2011.doc DOC document
230719_hvac_pipe_ins.pdf PDF
EP651-10090.pdf PDF
Ch_149_FORM_FOR_SUB_BID_MIL_Chicopee2011_Electrical.doc DOC document
Ch_149_FORM_FOR_SUB_BID_MIL_Chicopee2011_Metal_Windows.doc DOC document
013200_FL-CONSTRUCTION_PROGRESS_DOCUMENTATION.pdf PDF
014000_FL-QUALITY_REQUIREMENTS.pdf PDF
236313_air_cooled_condensers.pdf PDF
AE311-10090.pdf PDF
020800_Asbestos_Technical_Specifications.pdf PDF
E-601-10090.pdf PDF
230001-HVAC_FSB.pdf PDF
Ch_149_FORM_FOR_SUB_BID_MIL_Chicopee2011_Resilient_Floors.doc DOC document
017900_FL-DEMONSTRATION_AND_TRAINING.pdf PDF
Ch_149_FORM_FOR_SUB_BID_MIL_Chicopee2011_Masonry.doc DOC document
AE401-10090.pdf PDF
SF502-10090.pdf PDF
070002-ROOFING_AND_FLASHING_FSB.pdf PDF
265100_Lighting_Fixtures.pdf PDF
030130_FL-MAINTENANCE_OF_CAST-IN-PLACE_CONCRETE.pdf PDF
220001-PLUMBING-FSB.pdf PDF
013100_FL-PROJECT_MANAGEMENT_AND_COORDINATION.pdf PDF
238900_Louvers_and_Vents.pdf PDF
SF101-10090.pdf PDF
M-651-10090.pdf PDF
GI001-10090.pdf PDF
Ch_149_FORM_FOR_GENERAL_BID_MIL_Chicopee2011.doc DOC document
093000_FL-TILING_v1.pdf PDF
088000_FL-GLAZING_v1.pdf PDF
081113_FL-HOLLOW_METAL_DOORS_AND_FRAMES_v1.pdf PDF
231123_fuel_gas_piping.pdf PDF
PL101-10090.pdf PDF
230900_hvac_instrumentation_controls.pdf PDF
224000_plumbing_fixtures_JPB.pdf PDF
061600_FL-SHEATHING_v1.pdf PDF
220100_plumbing_requirements_JPB.pdf PDF
232113_hydronic_piping.pdf PDF
EL101-10090.pdf PDF
232300_refrigerant_piping.pdf PDF
General_Bid_Tabulation_Chicopee_2011.xls XLS spreadsheet
220500_plumbing_materials_JPB.pdf PDF
262413_Switchboards.pdf PDF
092216_FL-NON-STRUCTURAL_META_FRAMING_v1.pdf PDF
X-100_SURVEY_CONTROL_PLAN.pdf PDF
AE611-10090.pdf PDF
Addendum_02_combined.pdf PDF
Show 40 more

Latest 50 of 185 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CHICOPEE ARMORY REHABILITATION MMD PROJECT NO. 985101

CHICOPEE, MASSACHUSETTS ISSUED FOR BID - 05/20/11

10090 PRODUCT REQUIREMENTS 016000 - 1

SECTION 016000

PRODUCT REQUIREMENTS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary

Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes administrative and procedural requirements for selection of products for use in

Project; product delivery, storage, and handling; manufacturers' standard warranties on products; special warranties; and comparable products.

B. Related Requirements:

1. Section 012100 "Allowances" for products selected under an allowance.

2. Section 012300 "Alternates" for products selected under an alternate.

3. Section 012500 "Substitution Procedures" for requests for substitutions.

4. Section 014200 "References" for applicable industry standards for products specified.

1.3 DEFINITIONS

A. Products: Items obtained for incorporating into the Work, whether purchased for Project or taken from previously purchased stock. The term "product" includes the terms "material,"

"equipment," "system," and terms of similar intent.

1. Named Products: Items identified by manufacturer's product name, including make or model number or other designation shown or listed in manufacturer's published product literature, that is current as of date of the Contract Documents.

2. New Products: Items that have not previously been incorporated into another project or facility. Products salvaged or recycled from other projects are not considered new products.

3. Comparable Product: Product that is demonstrated and approved through submittal process to have the indicated qualities related to type, function, dimension, in-service performance, physical properties, appearance, and other characteristics that equal or exceed those of specified product.

B. Basis-of-Design Product Specification: A specification in which a specific manufacturer's product is named and accompanied by the words "basis-of-design product," including make or model number or other designation, to establish the significant qualities related to type, function, dimension, in-service performance, physical properties, appearance, and other

10090 PRODUCT REQUIREMENTS 016000 - 2

characteristics for purposes of evaluating comparable products of additional manufacturers named in the specification.

1.4 ACTION SUBMITTALS

A. Comparable Product Requests: Submit request for consideration of each comparable product.

Identify product or fabrication or installation method to be replaced. Include Specification

Section number and title and Drawing numbers and titles.

1. Include data to indicate compliance with the requirements specified in "Comparable

Products" Article.

2. Architect's Action: If necessary, Architect will request additional information or documentation for evaluation within one week of receipt of a comparable product request. Architect will notify Contractor of approval or rejection of proposed comparable product request within 15 days of receipt of request, or seven days of receipt of additional information or documentation, whichever is later.

a. Form of Approval: As specified in Section 013300 "Submittal Procedures."

b. Use product specified if Architect does not issue a decision on use of a comparable product request within time allocated.

B. Basis-of-Design Product Specification Submittal: Comply with requirements in Section 013300

"Submittal Procedures." Show compliance with requirements.

1.5 QUALITY ASSURANCE

A. Compatibility of Options: If Contractor is given option of selecting between two or more products for use on Project, select product compatible with products previously selected, even if previously selected products were also options.

1. Each contractor is responsible for providing products and construction methods compatible with products and construction methods of other contractors.

2. If a dispute arises between contractors over concurrently selectable but incompatible products, Architect will determine which products shall be used.

1.6 PRODUCT DELIVERY, STORAGE, AND HANDLING

A. Deliver, store, and handle products using means and methods that will prevent damage, deterioration, and loss, including theft and vandalism. Comply with manufacturer's written instructions.

B. Delivery and Handling:

1. Schedule delivery to minimize long-term storage at Project site and to prevent overcrowding of construction spaces.

2. Coordinate delivery with installation time to ensure minimum holding time for items that are flammable, hazardous, easily damaged, or sensitive to deterioration, theft, and other losses.

10090 PRODUCT REQUIREMENTS 016000 - 3

3. Deliver products to Project site in an undamaged condition in manufacturer's original sealed container or other packaging system, complete with labels and instructions for handling, storing, unpacking, protecting, and installing.

4. Inspect products on delivery to determine compliance with the Contract Documents and to determine that products are undamaged and properly protected.

C. Storage:

1. Store products to allow for inspection and measurement of quantity or counting of units.

2. Store materials in a manner that will not endanger Project structure.

3. Store products that are subject to damage by the elements, under cover in a weathertight enclosure above ground, with ventilation adequate to prevent condensation.

4. Protect foam plastic from exposure to sunlight, except to extent necessary for period of installation and concealment.

5. Comply with product manufacturer's written instructions for temperature, humidity, ventilation, and weather-protection requirements for storage.

6. Protect stored products from damage and liquids from freezing.

7. Provide a secure location and enclosure at Project site for storage of materials and equipment by Owner's construction forces. Coordinate location with Owner.

1.7 PRODUCT WARRANTIES

A. Warranties specified in other Sections shall be in addition to, and run concurrent with, other warranties required by the Contract Documents. Manufacturer's disclaimers and limitations on product warranties do not relieve Contractor of obligations under requirements of the Contract

Documents.

1. Manufacturer's Warranty: Written warranty furnished by individual manufacturer for a particular product and specifically endorsed by manufacturer to Owner.

2. Special Warranty: Written warranty required by the Contract Documents to provide specific rights for Owner.

B. Special Warranties: Prepare a written document that contains appropriate terms and identification, ready for execution.

1. Manufacturer's Standard Form: Modified to include Project-specific information and properly executed.

2. Specified Form: When specified forms are included with the Specifications, prepare a written document using indicated form properly executed.

3. See other Sections for specific content requirements and particular requirements for submitting special warranties.

C. Submittal Time: Comply with requirements in Section 017700 "Closeout Procedures."

10090 PRODUCT REQUIREMENTS 016000 - 4

PART 2 - PRODUCTS

2.1 PRODUCT SELECTION PROCEDURES

A. General Product Requirements: Provide products that comply with the Contract Documents, are undamaged and, unless otherwise indicated, are new at time of installation.

1. Provide products complete with accessories, trim, finish, fasteners, and other items needed for a complete installation and indicated use and effect.

2. Standard Products: If available, and unless custom products or nonstandard options are specified, provide standard products of types that have been produced and used successfully in similar situations on other projects.

3. Owner reserves the right to limit selection to products with warranties not in conflict with requirements of the Contract Documents.

4. Where products are accompanied by the term "as selected," Architect will make selection.

5. Descriptive, performance, and reference standard requirements in the Specifications establish salient characteristics of products.

6. Or Equal: For products specified by name and accompanied by the term "or equal," or

"or approved equal," or "or approved," comply with requirements in "Comparable

Products" Article to obtain approval for use of an unnamed product.

B. Product Selection Procedures:

1. Products:

a. Restricted List: Where Specifications include a list of names of both manufacturers and products, provide one of the products listed that complies with requirements. Comparable products or substitutions for Contractor's convenience will not be considered unless otherwise indicated.

2. Manufacturers:

a. Restricted List: Where Specifications include a list of manufacturers' names, provide a product by one of the manufacturers listed that complies with requirements. Comparable products or substitutions for Contractor's convenience will not be considered unless otherwise indicated.

3. Basis-of-Design Product: Where Specifications name a product, or refer to a product indicated on Drawings, and include a list of manufacturers, provide the specified or indicated product or a comparable product by one of the other named manufacturers.

Drawings and Specifications indicate sizes, profiles, dimensions, and other characteristics that are based on the product named. Comply with requirements in "Comparable

Products" Article for consideration of an unnamed product by one of the other named manufacturers.

C. Visual Matching Specification: Where Specifications require "match Architect's sample", provide a product that complies with requirements and matches Architect's sample. Architect's decision will be final on whether a proposed product matches.

10090 PRODUCT REQUIREMENTS 016000 - 5

1. If no product available within specified category matches and complies with other specified requirements, comply with requirements in Section 012500 "Substitution

Procedures" for proposal of product.

D. Visual Selection Specification: Where Specifications include the phrase "as selected by

Architect from manufacturer's full range" or similar phrase, select a product that complies with requirements. Architect will select color, gloss, pattern, density, or texture from manufacturer's product line that includes both standard and premium items.

2.2 COMPARABLE PRODUCTS

A. Conditions for Consideration: Architect will consider Contractor's request for comparable product when the following conditions are satisfied. If the following conditions are not satisfied, Architect may return requests without action, except to record noncompliance with these requirements:

1. Evidence that the proposed product does not require revisions to the Contract Documents, that it is consistent with the Contract Documents and will produce the indicated results, and that it is compatible with other portions of the Work.

2. Detailed comparison of significant qualities of proposed product with those named in the

Specifications. Significant qualities include attributes such as performance, weight, size, durability, visual effect, and specific features and requirements indicated.

3. Evidence that proposed product provides specified warranty.

4. List of similar installations for completed projects with project names and addresses and names and addresses of architects and owners, if requested.

5. Samples, if requested.

PART 3 - EXECUTION (Not Used)

END OF SECTION 016000