UFC 4-214-03
17 March 2018
UNIFIED FACILITIES CRITERIA (UFC)
APPROVED FOR PUBLIC RELEASE; DISTRIBUTION UNLIMITED
CENTRAL VEHICLE WASH
FACILITIES
CENTRAL VEHICLE WASH FACILITIES
Any copyrighted material included in this UFC is identified at its point of use.
Use of the copyrighted material apart from this UFC must have the permission of the copyright holder.
U.S. ARMY CORPS OF ENGINEERS (Preparing Activity)
NAVAL FACILITIES ENGINEERING COMMAND
AIR FORCE CIVIL ENGINEER CENTER
Record of Changes (changes are indicated by \1\ ... /1/)
Change No. Date Location
This UFC supersedes UFC 4-214-03, dated JAN 2004 and TM 5-814-9, dated FEB 1992.
FOREWORD
The Unified Facilities Criteria (UFC) system is prescribed by MIL-STD 3007 and provides planning, design, construction, sustainment, restoration, and modernization criteria, and applies to the Military Departments, the Defense Agencies, and the DoD Field Activities in accordance with USD (AT&L) Memorandum dated 29 May 2002. UFC will be used for all DoD projects and work for other customers where appropriate. All construction outside of the United States is also governed by Status of Forces Agreements (SOFA), Host Nation Funded Construction Agreements (HNFA), and in some instances, Bilateral Infrastructure Agreements (BIA.)
Therefore, the acquisition team must ensure compliance with the most stringent of the UFC, the SOFA, the HNFA, and the BIA, as applicable.
UFC are living documents and will be periodically reviewed, updated, and made available to users as part of the Services’ responsibility for providing technical criteria for military construction. Headquarters, U.S. Army Corps of Engineers (HQUSACE), Naval Facilities Engineering Command (NAVFAC), and Air Force \2\ Civil Engineer Center (AFCEC) /2/ are responsible for administration of the UFC system. Defense agencies should contact the preparing service for document interpretation and improvements. Technical content of UFC is the responsibility of the cognizant DoD working group. Recommended changes with supporting rationale should be sent to the respective service proponent office by the following electronic form: Criteria Change Request. The form is also accessible from the Internet sites listed below.
UFC are effective upon issuance and are distributed only in electronic media from the following source:
• Whole Building Design Guide web site http://dod.wbdg.org/.
Hard copies of UFC printed from electronic media should be checked against the current electronic version prior to use to ensure that they are current.
AUTHORIZED BY:
DR. LARRY McCALLISTER, P.E.
JOSEPH E. GOTT, P.E.
Chief, Engineering and Construction Chief Engineer U.S. Army Corps of Engineers Naval Facilities Engineering Command
EDWIN H. OSHIBA, SES, DAF MICHAEL McANDREW Deputy Director of Civil Engineers DASD (Facilities Investment and Management) DCS/Logistics, Engineering & Force Protection
Office of the Assistant Secretary of Defense (Energy, Installations, and Environment) http://www.wbdg.org/pdfs/ufc_implementation.pdf http://www.wbdg.org/ccb/browse_cat.php?o=29&c=4 http://dod.wbdg.org/
REVISION SUMMARY SHEET
Document: UFC 4-214-03, Central Vehicle Wash Facility
Superseding: TM 5-814-9
Description: This criteria is a comprehensive reference for scoping, design, and construction of vehicle wash facilities and their appurtenant structures.
Reasons for Document:
• Criteria formatting was updated to conform to UFC 1-300-01.
• Criteria was updated to include sustainable design features, namely Net-Zero water usage considerations for scoping, design, and construction.
• Criteria was updated to reflect current codes and methodology.
Impact:
• The update to this criteria will provide a path to more sustainable designs by means of water use reduction.
i
TABLE OF CONTENTS
CHAPTER 1 INTRODUCTION
1-1 PURPOSE AND SCOPE
1-2 APPLICABILITY
1-3 GENERAL BUILDING REQUIREMENTS
1-4 BACKGROUND
1-5 REFERENCES
1-6 GLOSSARY
CHAPTER 2 CVWF DESIGN CONCEPT
2-1 OVERVIEW
2-2 PREWASH (OPTIONAL)
2-3 WASTEWATER TREATMENT
2-3.1 Primary Treatment
2-3.2 Secondary Treatment
2-3.3 Water Supply Basin
CHAPTER 3 MASTER PLANNING
3-1 SIZING
3-1.1 User Input
3-1.2 Prewash
3-1.3 Wash Stations
3-2 SITING
3-2.1 Geography
3-2.2 Weather
3-2.3 Geology
3-2.4 Utilities
CHAPTER 4 DESIGN
4-1 VEHICLE PREPARATION AREA
4-1.1 General
4-1.2 Sizing
4-1.3 Staging Area Cleanup
4-1.4 Drainage
4-2 WASH STATION
4-2.1 Function ii
4-2.2 Configuration
4-2.3 Island Design
4-2.4 Tower Design
4-2.5 Protection Against Freezing
4-2.6 Water Supply Piping
4-2.7 Paved Area Drainage
4-2.8 Pavement
4-2.9 Interior Wash Equipment (Optional)
4-2.10 Lighting
4-2.11 Physical Security
4-2.12 Signage
4-2.13 Solid Waste Collection
4-2.14 Operation and Controls
CHAPTER 5 OPTIONAL PREWASH
5-1 TYPES OF PREWASHES
5-1.1 Bath Prewash
5-1.2 Vehicle Spray Stands
5-1.3 Bath Prewash Support Facilities
CHAPTER 6 WASTEWATER TREATMENT
6-1 GENERAL CONCEPTS
6-1.1 Overview
6-1.2 Treatment System
6-2 DESIGN PARAMETERS
6-2.1 Criteria
6-2.2 Wash Period (Tw)
6-2.3 Cleanup Time (K)
6-2.4 Water Usage Factor (Uf)
6-2.5 Storm Water
6-2.6 Stormwater Bypass
6-2.7 Washwater Demand
6-2.8 Water Volume
6-3 PRIMARY TREATMENT
6-3.1 Function iii
6-3.2 Number of Basins
6-3.3 Siting
6-3.4 Sizing
6-3.5 Sediment Basin Influent Structure
6-3.6 Sediment Basin Effluent Structure
6-3.7 Sediment Basin Construction
6-3.8 Sediment Basin Drainage
6-3.9 Sediment Removal
6-3.10 Oil Removal
6-3.11 Waste Oil Storage
6-3.12 Maintenance
6-3.13 Other Considerations
6-4 SECONDARY TREATEMENT
6-4.1 Onsite Secondary Treatment
6-4.2 Objective
6-4.3 Intermittent Sand Filter System
6-4.4 Lagoon System
6-4.5 Discharge System
6-5 WATER SUPPLY BASIN
6-5.1 Introduction
6-5.2 Capacity
6-5.3 Liner
6-5.4 Influent Structure
6-5.5 Service
6-5.6 Security
CHAPTER 7 OTHER DESIGN CONSIDERATIONS
7-1 WATER SOURCE
7-1.1 Type of Facility
7-1.2 Type and Configuration of Treatment System
7-1.3 Climate
7-2 PIPING
7-3 HOSES, WATER CANNONS, AND NOZZLES
7-4 CONTROL SYSTEMS
iv
7-5 SYSTEMS OPERATING MANUAL
CHAPTER 8 DECENTRALIZED WASH FACILITES
8-1 OVERVIEW
8-2 PLANNING
8-2.1 Planning Considerations
8-2.2 Requirements
8-3 DESIGN CONCEPT FOR DECENTRALIZED VEHICLE WASH
STATIONS
8-3.1 Overview
8-3.2 Conceptual Design
8-4 DESIGN & CONSTRUCTION: “DECENTRALIZED” NET ZERO WASH
FACILITY
8-4.1 Design Features
8-4.2 Construction Details
8-5 OPERATION AND MAINTENANCE
8-5.1 Operation and Organization Maintenance Tasks
8-5.2 Maintenance
8-6 PERFORMANCE
8-6.1 Past Performance
8-6.2 Water Quality
APPENDIX A REFERENCES
APPENDIX B BEST PRACTICES
B-1 CASE STUDY: DECENTRALIZED VEHICLE WASH FACILITY
B-1.1 Background
B-1.2 Construction
B-1.3 Performance
B-1.4 Conclusion
B-2 DESIGN EXAMPLE
B-2.1 Introduction
B-2.2 Master Planning Considerations
B-2.3 Engineering and Design
APPENDIX C GLOSSARY
C-1 ACRONYMS
C-2 DEFINITION OF TERMS
v
APPENDIX D “DECENTRALIZED HEAVY SOLIDS WASH RACK SITE SURVEY .. 149
FIGURES
Figure 1-1 Standard Sequence for Tactical Vehicles Figure 1-2 Washing Procedure with Optional Prewash Figure 2-1 Standard Central Vehicle Wash Facility Plan Figure 2-2 Central Vehicle Wash Facility Plan with Bath Prewash Figure 3-1 Cohesive Soil Gradation Curve Figure 3-2 Noncohesive Soil Gradation Curve Figure 3-3 Soil Classification and Soil Type Number Diagram Figure 3-4 Vehicle Processing Rates (Vehicles per Hour) Figure 4-1 Skewed Wash Station Arrangement Figure 4-2 Wash Island Plan Showing Spacing Figure 4-3 Double-Tower Island Figure 4-4 Cross Section of an Island Figure 4-5 Longitudinal Section of an Island Figure 4-6 Tower Detail in Cross Section Figure 4-7 Cross Section of a Trench Drain Figure 4-8 Example Floor Plan for the Control Building Figure 4-9 Control Building Exterior Figure 5-1 Example of Combined Bath Lane Facility, Plan view Figure 5-2 Tracked Bath Lane, Cross Section Figure 5-3 Example Inner Wash Island Figure 5-4 Example of Outer Wash Island Figure 5-5 Example Cross Section of a Cannon Island Figure 5-6 Tracked Bath Lane Figure 5-7 Dual Purpose Lane Figure 5-8 U-Drain Figure 5-9 Bath Cross Section Figure 5- 10 Configuration of U-Drains in the Bath Figure 5-11 Water Level Control Structure Figure 6-1 Single Cell Sediment Basin, Plan View Figure 6-2 Single Cell Sediment Basin, Cross Section Figure 6-3 Dual Cell Sediment Basin, Plan View Figure 6-4 Dual Cell Sediment Basin, Cross Section Figure 6-5 Typical Design Water and Sediment Depths Figure 6-6 Typical Effluent Structure with an Overflow Trench, Sedimentation Basins without Bath Figure 6-7 Typical Effluent Structure with Motorized Gates, Sediment Basins with Bath
Figure 6-8 Sedimentation Basin Drain System Figure 6-9 Components of an Intermittent Sand Filter System Figure 6-10 General Schematic of an Intermittent Sand Filter Recycle System Figure 6-11 Example Equalization Basin, Plan View Figure 6-12 Equalization Basin, Cross Section Figure 6-13 Distribution System Using Grid Arrangement vi
Figure 6-14 Distribution Box Figure 6-15 Distribution System Using Distribution Boxes Figure 6-16 Collection System Figure 6-17 Intermittent Sand Filter Cross Section Figure 6-18 Components of a Lagoon System Figure 6-19 General Flow Schematic of a Lagoon System Figure 6-20 Components of a Total Discharge System Figure 6-21 General Flow Schematic of a Total Discharge System Figure 6-22 Water Supply Basin, Plan View Figure 6-23 Water Supply Basin, Cross Section Figure 8-1 Decentralized Wash Facility Layout Figure 8-2 Single Lane, Heavy Solids Wash Rack Figure 8-3 Dual Lane, Net Zero, Heavy Solids Wash Rack Figure 8-4 Quad Lane, Net Zero, Heavy Solids Wash Rack Figure 8-5 Dual Lane, Net Zero Wash Lane with Heavy Solids and Detailing Lanes Figure B-1 Decentralized Dual Lane Wash Facility Figure B-2 Vehicles Returning from the Training Areas each Month Figure B-3 Site Map with a Proposed Layout – Fort Swampy Figure B-4 Bath Design Figure B-5 Configuration A Figure B-6 Configuration B Figure B-7 Cross Section of the Bath Figure B-8 Water Volume Configuration: (a) Plan View and (b) Cross Section Figure B-9 Overall Cell Configuration Figure B-10 Equalization Basin: (a) Plan View and (b) Cross Section Figure B-11 Water Supply Basin: (a) Plan View and (b) Cross Section Figure B-12 Equalization Basin Water Balance – Water Volume versus Time Figure B-13 Water Supply Basin Capacity
TABLES
Table 6-1 Estimated Volume of Material per Vehicle Table B-1 Number of Vehicle Types by Motor Pool Assignment Table B-2 Number of Vehicles Returning from the Field each Month Table B-3 Summary of CVWF Flow Rates Table B-4 Summary of Average Daily Volume Table B-5 Summary of Maximum Volumes
CHAPTER 1 INTRODUCTION
1-1 PURPOSE AND SCOPE.
This manual provides a comprehensive reference source for planning, and designing a central vehicle wash facility (CVWF) and decentralized, net zero wash facilities. The CVWF provides a rapid, economical method for washing tracked and wheeled tactical vehicles. The design elements provide for water pollution control, solid waste disposal, and conservation of manpower and water. This manual is limited to wash facilities and wastewater treatment for cleaning vehicle exteriors only; this design information does not pertain to facilities for treating wastewater from maintenance cleaning activities.
The Original Technical Manual (TM) 5-814-9 was adopted in 1992 to provide for large operational and rapid washing of tracked and wheeled tactical vehicles. The Technical Manual was converted to the current UFC 4-214-03 in 2004 utilizing the same concepts for washing tactical vehicles. The detailed requirements for washing these type vehicles are based on large lay-down areas and large quantities of water with introduction of new water as necessary. This update incorporates Chapter 8 which introduces new Net Zero design capabilities for Installations to meet the current needs for saving water and utilizing smaller lay-down areas for washing tactical vehicles.
Installations are encouraged to review this alternative method of washing tactical vehicles in combination with the modernization of the type of wheeled vehicles necessary for rapid deployments. The Net Zero Concept is especially pertinent for changing climate and for smaller installations with large Reserve Components.
1-2 APPLICABILITY.
Information in this manual applies central vehicle wash facilities and decentralized, net zero wash facilities on all installations that maintain a fleet of tactical vehicles for which there is a consistent washing requirement demanding cost-effective, on- post facilities.
1-3 GENERAL BUILDING REQUIREMENTS.
Comply with UFC 1-200-01, General Building Requirements. UFC 1-200-01 provides applicability of model building codes and government unique criteria for typical design disciplines and building systems, as well as for accessibility, antiterrorism, security, high performance and sustainability requirements, and safety. Use this UFC in addition to UFC 1-200-01 and the UFCs and government criteria referenced therein. All applicable codes and criteria should be followed, including, but not limited to the International Building Code (IBC) and UFC 3-600-01 Fire Protection.
1-4 BACKGROUND.
The Department of Defense has unique vehicle cleaning requirements in terms of numbers, types of vehicles, washing time, and degree to which washing is critical.
Civilian technologies for cleaning off-road tactical vehicles and treating the wastewater created by this washing are not recommended. However, civilian technology may apply to facilities for washing vehicles in a transportation motor pool (TMP), most of which are the wheeled, on-road type such as sedans and buses. Figure 1-1 shows the recommended washing sequence for tactical vehicles. For installations where specific conditions require that a prewash be constructed, the washing procedure is shown in Figure 1-2. The central vehicle wash facility is designed to provide expedient, cost-effective vehicle cleaning for tactical vehicles. The concept incorporates water conservation including recycle techniques and pollution control.
1-5 REFERENCES.
Appendix A contains a list of references used in this document. The publication date of the code or standard is not included in this document. In general, the latest available issuance of the reference is used.
1-6 GLOSSARY.
Appendix C contains acronyms, abbreviations, and terms.
Figure 1-1 Standard Sequence for Tactical
Vehicles
Figure 1-2 Washing Procedure with Optional Prewash
CHAPTER 2 CVWF DESIGN CONCEPT
2-1 OVERVIEW.
The standard CVWF consists of a vehicle preparation area, wash stations, and vehicle assembly area Figure 2-1 Standard Central Vehicle Wash Facility Plan. However, the layout of a facility will be site-specific, based on the installation’s mission and needs.
Information on siting and master planning is found in Chapter 3. A design example is provided in Appendix B.
2-2 PREWASH (OPTIONAL).
At installations with heavy soiling conditions, high demands for washing, and/or limited washing times, a prewash system is recommended. There are several options for prewash systems which have been constructed for use in tactical vehicle washing: bath, air spray, water spray stand, and automatic washer. The vehicle bath is the most effective prewash system for tactical vehicles. Figure 2-2 shows a typical CVWF plan with the CONUS approved bath prewash system for tactical vehicles. Commercial type, such as those in a TMP, would utilize commercial automatic washers and not facilities described for the CVWF.
2-3 WASTEWATER TREATMENT.
A system for conveying and treating wastewater is included in the CVWF design, since water used to wash the vehicles will become contaminated with dirt, debris, and products related to vehicle operation such as oil, fuels, hydraulic fluid, and grease. All wastewater must receive primary treatment to remove settleable and floating materials.
Following primary treatment, the wastewater is either released to a collection system or further treated onsite and stored for reuse during future washing operations. The water used to wash vehicles should be recycled whenever possible and feasible. However, even in a total recycle system, some of the wastewater may need to be released to a discharge system before or after receiving secondary treatment. This discharge is done to ensure that water quality and water balance are maintained. Measured makeup water is added to the recycle system to compensate for the volume of water carried off on the wet vehicles, released, and loss due to evaporation.
2-3.1 Primary Treatment.
All wastewater must receive primary treatment. A sediment basin that provides primary treatment is required to allow most of the suspended solids to settle and to allow the free grease, oils, and other pollutants to separate from the wastewater.
2-3.2 Secondary Treatment.
For the purposes of this manual, secondary treatment refers to intermittent sand filters, lagoons, or discharges to sanitary sewage systems. Two systems of onsite secondary treatment are used following primary treatment if the water is to be recycled. These methods include intermittent sand filters and lagoons. Lagoons are not the standard system but are included because they have been used as a wastewater treatment method for CVWFs. Lagoons are not allowed in certain states for secondary treatment.
Consult with state regulations. The third system of handling wastewater, discharge to sanitary sewer, may be available at an installation, but this method is not used in conjunction with a recycle system.
For Air Force projects, before discharging to an existing sanitary or stormwater system approval by the base or regional environmental section must be granted prior to discharge
2-3.2.1 Intermittent Sand Filter.
This secondary treatment system is comprised of an equalization basin and an intermittent sand filter. The equalization basin holds the wastewater after primary treatment and before it is applied to the filters to equalize flow rates by dampening the high and low- flow variations.
• A dosing tank may be provided after the flow equalization basin to provide a water volume of one charge or dose to a portion of the sand filter. The dosing tank is a designer’s option which allows for flexibility in sizing the pumping facilities. The sand filter shall not be dosed more than 2 hours in any 8 hour period.
• Water quality testing and metering capabilities are recommended to be provided at a point following the intermittent sand filters to measure the quality and amount of the treated wastewater to be recycled. At this point, facilities should be provided which allow recirculating all or a portion of the filtered water back though filters via the equalization basin. The remaining filtered water flows into the water supply basin and is stored for reuse.
• Water overflow facilities to provide hydraulic protection for the secondary treatment process should be located at the water supply basin for emergency storm release. This overflow system should also be able to make controlled partial wastewater releases to further assist in maintaining the quality and quantity of the recycled water. Hydraulic protection should also be provided at the equalization basin as a backup.
Chapter 6 presents details of the sand filter treatment system.
2-3.2.2 Lagoon System.
This secondary treatment system consists of a basin or a series of basins where the wastewater is held for an extended period of time to achieve the desired water quality.
The treated water is allowed to flow to the water supply basin for reuse. Water quality testing and metering capabilities are recommended to be provided, as well as overflow protection. Chapter 6 explains the lagoon treatment system in greater detail.
Figure 2-1 Standard Central Vehicle Wash Facility Plan
2-3.2.3 Discharge System.
If a recycle treatment system is not economically or technically feasible and/or operationally practical, and if was water supply is available, wastewater from the CVWF may be discharged to a sanitary sewer system or some other conveyance for further treatment elsewhere. Primary treatment is the minimum level of treatment required to ensure that the wastewater discharged into a system is of a quality acceptable to the receiving authority. Quality, however, may not be the only criterion. The rate of discharge may also be a limiting factor, thus requiring an equalization basin prior to the point of release to the discharge system. The discharge type treatment system is discussed in detail in Chapter 6.
For Air Force projects, before discharging into an existing sanitary or stormwater system approval by the base or regional environmental section must be granted prior to discharge.
Figure 2-2 Central Vehicle Wash Facility Plan with Bath Prewash
2-3.3 Water Supply Basin.
After secondary treatment in a recycle system, the water is discharged to a water supply basin for reuse in the CVWF. In a system without recycling, the water supply basin is optional. If a reliable, consistent source of water is not available, a water supply basin may have to be constructed in a size large enough to hold the wash water volume required. This basin can be filled from the water source at a slower rate during nonpeak hours for the high demand required during the washing operations. The design must protect the water source through the use of air breaks or equipment to prevent backflow and back siphonage. In addition, makeup water that enters the water supply should be metered.
CHAPTER 3 MASTER PLANNING
3-1 SIZING.
3-1.1 User Input.
The wash facility must be designed to meet the user's needs. The design will determine the type, size, and configuration of the wash facility and treatment system based on information supplied by the installation. Proper initial planning will result in the best final design. The planner will have to assemble data from many sources and use judgment in applying this data to the guidelines provided for sizing the facility components.
Where data is not available, estimates must be made.
3-1.1.1 Military Missions Data.
The wash facility must support the particular needs of the installation. Troop types, their vehicle types, and their training program, both current and future, must be considered.
This includes resident troops as well as transient troops. The combination of numbers of vehicles, types of vehicles, and frequency of washing will determine the type and size wash facility required. A complete list of each military unit which will use the facility is required, along with its vehicular complement and the expected frequency each vehicle would be washed.
3-1.1.2 Wash Frequency Data.
Certain components of the wash facility will be sized based on long term or average numbers of vehicles washed. Other components are sized on short term or peak use numbers. In both cases, the mix of vehicle types is an important consideration.
• The average use of the facility should be provided by the user broken down as weekly or biweekly, monthly, and annually. Seasonal variations must also be a consideration. Where training programs are impacted by seasonal weather or where large numbers of transient units in a particular part of the year impact expected use, the average weekly or monthly numbers would not be a fixed ratio of the average annual numbers. Monthly average should be the average of the six highest use months; weekly should be the average of the ten highest use weeks.
• The peak use of the facility should be provided by the user as the largest number of vehicles to be washed in a continuous short term period. If night washing is to be designed for, the peak use may, for example, be a continuous three day (72 hour) period. The peak use will represent full utilization of the wash facility components for the chosen time period. The planner must consider the length of time it will take for all the vehicles scheduled to wash in this peak exercise to return to the cantonment area after training. The rate of movement of these vehicles will help determine the time period to allow for in the peak use operation. Ideally the CVWF would accommodate all units as they arrived, without excessive backup, and at a continuous full utilization of the washing components. It is important that the planner consider the frequency of the defined peak use; in some cases, a large-scale facility may not be justified based on the low frequency of this peak activity. The peak use should be a condition expected to occur at least three times per year.
3-1.1.3 Vehicle Soiling Data.
The types of soil found in the training ranges along with weather conditions are predictors for the amount of dirt which will have be able to washed off of the vehicles.
This will affect the type of washing components, the time required for washing, the amount of water used and the waste- water treatment components.
• A characterization of the soils is needed. A study of the installation maps showing soil types throughout the total training areas should be made to determine if sands, clays, or combinations of soils occur. Samples of Soils should be taken from the range areas, as well as samples taken directly from dirty vehicles returning to the cantonment area after a heavy rain. Separate samples should be collected for each identifiable soil type (3 to 5 gallons each) and analyzed in a soils laboratory. The laboratory should prepare a standard gradation curve of grain size distribution showing gravel, sand, silt, and clay utilizing both a mechanical analysis and a hydrometer analysis down to 0.001 mm diameter. Both a dispersed and a non- dispersed hydrometer analysis need to be performed. The dispersed, which breaks the particles into individual grains, is used for standard classification. This will be used to categorize the soiling expected on the vehicles. The dispersed, which assesses the agglomerated particles, is used in the treatment analysis (chap 6), since the washing operation does not totally disperse the soil. Figure 3-1 shows an example of a cohesive (silty clay) soil gradation curve both dispersed and dispersed. Figure 3-2 shows an example of a noncohesive (sandy) soil.
Figure 3-1 Cohesive Soil Gradation Curve
Figure 3-2 Noncohesive Soil Gradation Curve
• A classification of the soils expected to be on the vehicles is needed. By taking the particle size curve previously discussed and plotting the percentage of sand, silt, and clay (dispersed) on a triangular classification chart shown on Figure 3-3, a combined classification can be made. As a indicator of soiling potential expected on the vehicles, the chart is divided into 5 categories or soil type numbers (St). The sands and silty sands are given a type number of 1, being the likely to soil a vehicle and being the easiest to clean. The clays are given a type number of 5, being the most likely to soil a vehicle and being the hardest to clean. There a particular analysis may plot on the chart close to the line between two types, interpolation should be applied (i.e. a soil could be given a type number of 2.5). Where different soils occur in the training ranges, an average of those found may be used. The designer should use judgment when making this determination and give due consideration to the extreme adverse effects caused by high clay content soils.
Figure 3-3 Soil Classification and Soil Type Number Diagram
• Actual soiling of vehicles is a function of both soil type and the amount of rain or wet conditions expecting in the training areas. Therefore, climatic data must be provided in order to fully assess the potential for vehicle soiling. Arid regions would have minimum soiling potential where rainy regions would have maximum soiling potential. By assigning a climatic factor (Fc) to the area, ranging from 1 being arid to 2 being very rainy or wet, and multiplying this by the soil type number, a soiling index can be obtained for the installation. This is given by Equation 3.1.
Si = St ∗ Fc (eq. 3-1) The soiling index will be used to predict times and determine the need for prewash.
3-1.1.4 Climatic Data.
As previously stated, climatic data at the installation is necessary. In addition to amount of rain, seasonal variations in moisture and temperature are needed. Areas with long periods of freezing weather will require special design considerations to protect wash components, pumps, and piping. Most of the wash components, particularly the prewash, may not be feasible to operate near freezing conditions because of the safety hazard caused by overspray freezing on the pavement. Enclosed facilities may be warranted, however, they are very expensive from both a capital and operations standpoint. Another climatic consideration in the design is the evaporation rate in the region. In an area with high evaporative losses and low rainfall, certain features of the CVWF may not be practical. For example, a spray stand creates large water losses due to overspray. Use of any prewash system increases the volume required in the treatment system, with the higher water volume, the surface area of the basins must be increased (particularly a lagoon treatment), which promotes evaporative losses even more. The designer must evaluate the potential evaporative loss as it affects the need for make-up water and weigh this against the benefits of either a recycle system or a discharge system.
3-1.2 Prewash.
A prewash is used to reduce the time needed to wash vehicles, since it removes the bulk of the dirt in a timely, efficient way. Its function is to reduce the amount of time each vehicle must spend at the wash stations.
3-1.2.1 Bath Prewash.
A bath prewash is currently the most efficient and effective method to remove dirt from the exteriors of tactical vehicles. A large volume of water is required to fill the bath, but because of the reduced wash time required, the overall water volume required for cleaning a large number of vehicles may be reduced. Lanes specifically designed for washing tracked vehicles can be provided; lanes which can accommodate both tracked and wheeled vehicles (referred to as dual purpose lanes) can also be provided. These are described further in Chapter 5. Wheeled vehicles under 2.5 tons would not normally use the prewash bath.
3-1.2.1.1 Process Rate.
In a tracked bath lane, six to ten tracked vehicles per hour can be washed. In a dual-purpose lane, ten to fifteen wheeled vehicles per hour can be washed. The amount of soiling will determine the actual number of vehicles that can be processed through the facility; the heavier the soiling, the slower the vehicles can be processed. By using the Soiling Index (Si) in conjunction with the processing rate chart shown on Figure 3-4, the throughput rate can be determined for a particular design.
Figure 3-4 Vehicle Processing Rates (Vehicles per Hour)
• The number of lanes for the prewash will depend on two factors: The maximum number of vehicles that must be washed at the facility in a time specified by the installation (peak wash period) and the expected process rate through the facility. Equations 3-2 and 3-3 will help the designer determine the number of each type of lane needed for the prewash system. The installation’s requirements will dictate how the result should be treated. If the maximum washing time is critical, the number should be rounded up, otherwise, the number of lanes should be rounded to the nearest whole number.
No. of tracked Lanes = Max.No.Tracked Vehicles to be Washed Process Rate∗Peak Washing Period
(eq. 3-2)
• In equation 3-3, only the tracked and wheeled vehicles expected to use the dual-purpose lane should be considered in the equation. The number of tracked vehicles using the lane should not be included, since they will not be washed twice in the prewash.
No. Dual Purpose Lanes = 1 Peak Wash Period
∗ No.Tracked Process Rate
∗ No.Wheeled Process Rate
(eq. 3-3)
3-1.2.1.2 Equation Example.
An example will better explain how to use the equations. Consider an installation that needs to wash 42 heavy tracked vehicles, 88 light tracked vehicles, and 125 wheeled vehicles in the prewash during peak use. The installation requires that all of the vehicles be washed in 9 hours. Soils at the installation are extremely cohesive clays, so the process rates through the prewash are expected to be slow. The designer had determined that the soiling index (Si) is 8 and from the chart (Figure 3-4 estimates that five heavy tracked vehicles per hour can be washed in each lane; seven light tracked vehicles per hour per lane can be washed; and eleven wheeled vehicles per hour per lane can be washed in a dual-purpose lane. For initial calculations the following will be used.
42 heavy tracked
5 veh hour lane ∗ 9 hr
88 light tracked
7 veh hr lane ∗ 9 hr
= 0.93 + 1.40 = 2.33 tracked lanes
125 wheeled vehicles
11 veh hr lane ∗ 9 hr
= 1.26 dual pupose lanes
• The designer realizes that, with three tracked vehicle lanes one dual-purpose lane, the tracked vehicles will be washed in less than 9 hours, but the wheeled vehicles will require more than 9 hours. To achieve a more even distribution of vehicle washing, the designer recalculates the number of lanes needed by assuming that some of the light tracked vehicles will use the dual-purpose lanes. The designer adjusts the process rate for the light tracked vehicles in a dual-purpose lane. It will take longer to process a tracked vehicle in dual-purpose lane than in a tracked lane, since the flexors in a dual-purpose lane are not as effective as those in a tracked lane at removing the embedded soil from the tracks.
42 heavy tracked
5 veh hour lane ∗ 9 hr
65 light tracked
7 veh hr lane ∗ 9 hr
= 0.93 + 1.03 = 1.96 tracked lanes
125 heavy tracked
11 veh hour lane ∗ 9 hr
23 light tracked
5 veh hr lane ∗ 9 hr
= 1.26 + 0.5 = 1.76 dual purpose lanes
• Two tracked vehicle lanes and two dual-purpose lanes would offer a more efficient use of the bath than would the results given by the first calculations.
3-1.2.2 Automatic Washers.
The types and number of vehicles in the motor pool must be considered in sizing the automatic wash area. Administrative-type vehicles in a TMP usually return one at a time and are washed as they return. Thus, large numbers of units will not be waiting to be washed in a limited amount of time as is the case with tactical vehicles at CVWFs.
Civilians usually are employed to do the washing at TMP wash facilities; therefore, all of the daily washing normally will occur during an 8-hour period during daylight. A one-or-two position automatic prewash unit may be all that is required. Again, the number of vehicles per cycle and average time of washing are used to determine the size of the prewash unit.
3-1.3 Wash Stations.
Before sizing the facility, with or without a prewash, the designer must have a clear understanding of the installation's washing requirements. The number of stations needed at the wash facility will depend on whether a prewash system is provided. A prewash will lessen the time that these vehicles must spend at the wash stations, thus reducing the number of stations needed
3-1.3.1 Sizing with a Prewash.
Sizing with a prewash. When a bath prewash is provided, the number of wash stations should be between two and five per tracked vehicle bath lane. A process rate of 3 to 6 vehicles per hour at each wash station can be expected after the vehicles have been washed in the bath. Since all vehicles will not go through the prewash bath, calculations of lanes must account for longer wash times for these vehicles. A process rate of 2 to 4 vehicles per hour for large, odd shaped, or tandem units can be expected.
A process rate of 4 to 10 vehicles per hour for small wheeled vehicles such as jeeps or ½ tons can be expected. Installations with a limited washing time or a large percentage of wheeled vehicles to wash will require more wash stations. In any case, the number of stations can be calculated using the processing rates for each type of vehicle and its type of wash, as shown on Figure 3-4, and following the same logical steps used to size the prewash.
3-1.3.2 Sizing without a Prewash.
If no prewash is provided, the planner predicts the number of wash stations needed based on soiling conditions and process rates.
• The process rate for vehicles at the wash stations will depend on several factors, but usually will be between 1 and 10 vehicles per hour. This range is given to allow an adjustment for the vehicle types and soiling index at the site. Installations that have vehicles soiled with large amounts of cohesive soils (clays) will have slower processing rates than those with only noncohesive soils (sand) or dust on the vehicles. By using the Soiling Index (Si) in conjunction with the processing rate chart shown on Figure 3-4, the throughput can be determined for each vehicle type. The mission of the installation also will affect the rate. At some installations, vehicles may return to the motor pool immediately for inspection. In this case, the processing rate will be slower than if the vehicle were not being inspected, since the troops will most likely perform a detailed washing.
Less time will be taken to clean the vehicles if they will be returned directly to the field for further training.
• The number of tracked and wheeled vehicles to be washed is used in equation 3-4 to estimate the number of wash stations needed at the facility:
No. Stations =
Max. Wash Period
No. tracked Tracked Process Rate
No. Wheeled (Lg. )
Lg. Wheeled Process Rate
No. Wheeled (Sm. ) Sm. Wheeled Process Rate
(eq. 3-4) The user’s requirements will determine how this number should be rounded. If the maximum washing time is critical, the number should be rounded up; otherwise, it should be rounded to the nearest whole number.
3-2 SITING.
3-2.1 Geography.
All future development and land uses at the installation must be considered when siting a CVWF. These future plans must not adversely affect the vehicle and equipment movement inside and outside the facility. At the same time, the facility must not interfere with activities in the cantonment and training areas and vice-versa; the land uses should be compatible. Vehicle noise and movement must not interfere with family housing, hospitals, and other installation activities. If night washing is planned, it must not disrupt local activities; for example, the lighting at the facility must not disturb the surrounding area.
3-2.1.1 Space Requirements.
Planners and designers must consider overall space requirements for the facility.
Large, open areas will be needed if a total recycle treatment system is to be installed.
Lagoon treatment systems require even larger areas than intermittent sand filter systems. Smaller areas will suffice for partial or total discharge systems. A CVWF with eight wash stations, no prewash, and no recycle system can require 2 to 4 acres; one with 20 wash stations, 4 lane prewash, and a complete recycle treatment system can require as much as 50 acres.
3-2.1.2 Cantonment Boundary.
The wash facility should be located near the permanent cantonment boundary and between the training areas and maintenance shops/motor pools. The vehicles must be cleaned before they enter the cantonment area; otherwise, the dirt will fall onto the roads and trails within this area. Future changes in the cantonment boundary must also be considered when siting the CVWF.
3-2.1.3 Training Area.
The facility should be located as close as possible to the main tank trails, access roads from the training areas, or similar sites. The vehicles are washed as they return from the training field areas prior to entry onto cantonment roads. Future locations for training areas also must be considered with respect to the CVWF site.
3-2.1.4 Transportation Arteries.
Several routes usually enter the cantonment area from many different training areas. A CVWF usually cannot be constructed at each entry point, so new roads or tank trails may have to be built to link the primary routes from the training areas with the wash facility. To prevent the vehicles from becoming soiled immediately after washing, they must return from the wash facility to the maintenance shops/motor pools on paved roads or tank trails. If the exit from the facility is placed close to existing roads or tank trails that are paved, new construction will be kept to a minimum. The facility must also be located to minimize the distance that dirty vehicles must travel on major transportation arteries. Otherwise, the dirty vehicles will drop soil on roads over which other vehicles travel. The number of tank-trail crossings over major roads, both to and from the wash facility, must also be minimized. The entrance and exit of the wash facility should be sited to avoid adverse effects on traffic both there and in the cantonment area. The facility should not be located in congested areas such as near the main gates, major intersections, hospitals, administration offices, and other high traffic areas.
3-2.1.5 Maintenance Shops/Motor Pools.
Present and future locations for tactical maintenance shops and motor pools must be considered in siting the CVWF. The facility should be located between the training areas and the maintenance shops/motor pools. The vehicles should return from the training areas and, after washing, return to the maintenance shops/ motor pools with minimal travel on cantonment roads.
3-2.2 Weather.
The wash facility must be designed with due consideration to all local and regional weather conditions.
3-2.2.1 Temperature.
If the installation is in a region with long periods of freezing temperatures, some standard CVWF components, such as the prewash bath may not be useable since the CVWF is not intended to be operated continuously at temperatures below 40 F. In areas with seasonal or occasional freezing temperatures, special piping and plumbing fixtures must be installed at the outdoor facilities to drain the exposed pipes and keep them from freezing. South-facing slopes should be considered for construction sites to take the greatest advantage of the sun for heating during the winter months. The washing structures and treatment system still must be protected from freezing temperatures to prevent pipes and other vulnerable components from freezing and rupturing.
3-2.2.2 Winds.
The designer should consider locating the wash facility and treatment system to minimize adverse effects from wind. Wind blowing over basins increases the rate of evaporation. In addition, winds that blow over the long axis of an elongated basin can create waves that will erode the banks. Wind can be used to move surface oil toward the oil skimmer in sediment basins provided the oil skimmer is located properly.
Strategically placed vegetation, structures, and fences can reduce the adverse effects of wind. However, vegetation must not interfere with pipes, trenches, pavement, liners, or other functional parts of the facility.
3-2.2.3 Precipitation.
Gently sloping ground which is elevated slightly with respect to the surrounding grounds should be chosen to ensure that stormwater can be controlled. Stormwater collected on the pavement during washing operations should be directed toward the treatment system since this water may require treatment; in addition, it can be used as makeup water for a recycle system. Curbing should be installed where the soil and pavement interface, and where it is needed to control the drainage flow and to prevent erosion.
Rainwater falling on the surrounding area should be directed away from the facility unless it is to be used as a source of makeup water.
3-2.2.4 Vegetation.
The site layout should make effective use of existing vegetation to protect the buildings, personnel, and basins against wind and sunlight. Trees, shrubs, and grass should not be removed except as necessary for construction or operation. The roots hold soil in place, thus preventing sheet wash and soil deposition onto the paved surfaces and into the stormwater collection system. Moisture in the treatment basins will promote growth of vegetation such as trees and shrubs on the surfaces and along the edges of the basins. Trees and shrubs that grow very close to the filters and the basins must be cleared because their root systems may penetrate the liners and cause leaks. Slopes for berms should be designed to allow convenient maintenance.
3-2.2.5 Fauna.
The abundance of water will promote insect and animal life in the area around the basins. Fences may have to be constructed around the basins, especially in arid regions, to prevent wildlife from entering the area to drink or bathe since their activities could damage the slopes and liners. The water also may attract burrowing animals that can damage liners and berms; their presence may, in time, increase maintenance needs.
3-2.2.6 Evaporation Rates.
The region’s evaporation rate must be considered when siting and designing the facility.
3-2.2.6.1 Arid Regions.
Wash facilities in arid regions must have the wash structures and treatment system designed to minimize the effects of evaporation. Water from the pavement should be directed toward the treatment system; in this way, stormwater can be collected and used as an additional source of makeup water. In hot, arid regions, the pavement should be light-colored to reflect heat; the evaporation rate will be less when the wash water hits a cooler, lighter surface than when it hits a hotter, darker one. Another major point of evaporation is from the basins in the treatment system. A high rate of evaporation from the basins can increase the concentration of dissolved solids in the water. This higher dissolved solids content can result in spotting on vehicles after washing and increased corrosion. The exposed surface area of the basins should be minimized. The basins’ depth can be increased to the upper limits to allow them to hold the required volume while reducing the exposed surface area. Wind blowing over the basins also can raise the evaporation rate. Fences and shrubs can be placed around the basins to help block winds. Vented covers also can be placed over the basins to reduce evaporation. Basin liners and the materials used for filters should be light-colored.
3-2.2.6.2 Water-Rich Regions.
In water-rich areas, provisions must be made to handle a heavy water volume. Onsite control to prevent stormwater damage to the treatment system becomes critical when heavy rainfalls are expected.
3-2.3 Geology.
3-2.3.1 Topography.
The site should have some fall if the designer is to consider using a gravity-controlled recycle wastewater treatment system. A 2 to 3 percent slope across the site is desirable, with the high side being adjacent to access roads or tank trails. If the terrain is too flat, the treatment system would require extra pumping in order to recycle the water. This requirement would increase costs for initial construction and for operation.
It is essential that the wastewater flow by gravity from the wash structures to the sediment basins. Should the wastewater be pumped before primary treatment, any oils in the water would become emulsified and thus more difficult to remove. Low-lift pumps can be used elsewhere in the facility if necessary. The entire site should be elevated with respect to the surrounding area. Slopes in the immediate area should fall away from the site to help move stormwater and cold air away from the site. It is desirable that the local topography not funnel water or strong winds toward the site.
3-2.3.2 Soils.
Soil borings must be taken at the proposed site to determine the soil types, the depth of the bedrock, and the depth of the water table. The soil should be able to support concrete, bentonite, and similar sealers that will be applied to the bottoms of basins, sand filters, and facilities such as pump houses and control buildings. Large soil particles tend to slide and shift more than small ones; therefore, in sandy areas, the walls of excavated basins will have to be built with a low-sloped angle to prevent this problem. Excavation of a basin at a site with cohesive soils may be more expensive than a site with non-cohesive soils. However, it may be more expensive to stabilize the slopes at the site with non-cohesive soils. It may also be more cost- effective to use native, cohesive soils for basin construction than other types of liners or imported soil.
Bentonite liners may be difficult to seal on non-cohesive soils; later, settling and shifting of the soils may create leaks in the liner. Bentonite liners can also be damaged by hydraulic pressure from groundwater, especially when non-cohesive soils are present.
3-2.3.3 Bedrock.
The site should have deep bedrock since shallow bedrock hinders excavation. An excavation into bedrock may penetrate into fissures that are part of a subsurface water recharge network for a public water supply; this supply could become contaminated by wastewater from the facility. Excavation into bedrock also increases construction costs.
If no other site is available, fill material may be used to increase the soil depth at the site. Another alternative would be to excavate material that is easy to remove down to the bedrock, then use the excavated material to build a berm around the basins. The gradient of the berm slopes must be low enough to avoid interfering with operations and maintenance (O&M) and to prevent sheet erosion of the slope.
3-2.3.4 Water Table.
The planner must know the depth of the water table at the proposed construction site.
Sites near marshes, swamps, or low areas should be studied to determine if the water table will have an adverse effect on construction or O&M of the facility. The facility must be placed above the maximum height of the seasonal and permanent water tables.
Areas with high water tables may require complex drainage systems, usually with high construction costs. Should the basins and filters be constructed when the water level is low and then water rises and surrounds the structures, the hydraulic pressure can damage the liners and cause leaks. Clay lenses or other impervious sub-surface features can create a high, perched water table.