This is a CDBG (Community Development Block Grant) construction agreement template issued by the City of Edinburg, Texas, establishing the contractual framework between the City as Owner and a Contractor for construction work. The agreement outlines the general structure for construction contracts, including work descriptions, project identification, engineer oversight, contract timelines, and payment procedures. The document serves as a template with blank fields to be completed for specific projects, incorporating by reference the Engineers Joint Contract Documents Committee (EJCDC) Standard General Conditions for Construction Contracts (2018), supplementary conditions, project specifications, and drawings. Contract times establish that work must reach substantial completion and final completion by specified dates, with milestone completion dates identified as necessary. Progress payments are made monthly on approximately the 25th of each month based on the percentage of work completed, with 95 percent payment issued prior to substantial completion and 5 percent retained. Upon substantial completion, payment increases to 100 percent of completed work less punch list items at 200 percent of estimated remaining work value.
The contract price is structured to accommodate both lump sum and unit price work, with pricing subject to adjustment based on contract modifications. Liquidated damages for delay are assessed on a tiered schedule ranging from $100 per day for contracts valued $5,000–$25,000 up to $800 per day for contracts exceeding $5,000,001. Additional special damages provisions allow the Owner to recover actual costs for engineering, construction observation, and administrative services required due to contractor delays. The agreement incorporates extensive federal compliance requirements applicable to CDBG-funded projects, including Davis-Bacon wage standards, conflict of interest provisions under 24 CFR Part 570.611, Title I of the Housing and Community Development Act of 1974, 2 CFR Part 200 uniform administrative requirements, Build America Buy America (BABA) Act compliance, and certifications regarding debarment status and freedom from corrupt, fraudulent, collusive, or coercive practices. Performance and payment bonds with power of attorney are required, and the contractor must demonstrate compliance with Equal Employment Opportunity, Section 504 of the Rehabilitation Act, HUD Federal Labor Standards, and other applicable federal and state regulations.
View the file
Other files
Show all 28
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CITY OF EDINBURG AGREEMENT
00520- 1
Document 00500
AGREEMENT BETWEEN OWNER AND CONTRACTOR
FOR CONSTRUCTION CONTRACT
This Agreement is by and between CITY OF EDINBURG (“Owner”) and (Contractor Name) (“Contractor”).
Terms used in this Agreement have the meanings stated in the General Conditions and the Supplementary Conditions.
Owner and Contractor hereby agree as follows:
WORK
1.01 Contractor shall complete all Work as specified or indicated in the Contract Documents.
The Work is generally described as follows: (Project Description).
THE PROJECT
2.01 The Project, of which the Work under the Contract Documents is a part, is generally described as follows: (Project Number and Name)
ENGINEER
3.01 The Owner has retained (Engineer Name) (“Engineer”) to act as Owner’s representative, assume all duties and responsibilities of Engineer, and have the rights and authority assigned to Engineer in the Contract.
3.02 The part of the Project that pertains to the Work has been designed by (Engineer Name).
CONTRACT TIMES
4.01 Time is of the Essence
A. All time limits for Milestones, if any, Substantial Completion, and completion and readiness for final payment as stated in the Contract Documents are of the essence of the Contract.
4.02 Contract Times: Dates
A. The Work will be substantially complete on or before (Date), and completed and ready for final payment in accordance with Paragraph 15.06 of the General Conditions on or before (Date).
4.03 Milestones
A. Parts of the Work must be substantially completed on or before the following Milestone(s):
00520- 2
1. Milestone 1 Substantial Completion / (Date)
2. Milestone 2 Final Completion / (Date)
4.04 Liquidated Damages
A. Contractor and Owner recognize that time is of the essence as stated in Paragraph 4.01 above and that Owner will suffer financial and other losses if the Work is not completed and Milestones not achieved within the Contract Times, as duly modified. The parties also recognize the delays, expense, and difficulties involved in proving, in a legal proceeding, the actual loss suffered by Owner if the Work is not completed on time. Accordingly, instead of requiring any such proof, Owner and Contractor agree that as liquidated damages for delay (but not as a penalty):
1. Substantial Completion: Contractor shall pay Owner based on fees below for each day that expires after the time (as duly adjusted pursuant to the Contract) specified above for Substantial Completion, until the Work is substantially complete.
For Contract of Amount Cost Per Day
$5,000.00 To $25,000.00 $100.00
$25,000.01 To $100,000.00 $200.00
$100,000.01 To $500,000.00 $250.00
$500,000.01 To $1,000,000.00 $300.00
$1,000,000.01 To $2,000,000.00 $400.00
$2,000,000.01 To $3,000,000.00 $500.00
$3,000,000.01 To $4,000,000.00 $600.00
$4,000,000.01 To $5,000,000.00 $700.00
$5,000,000.01 And Over $800.00
2. Completion of Remaining Work: After Substantial Completion, if Contractor shall neglect, refuse, or fail to complete the remaining Work within the Contract Times (as duly adjusted pursuant to the Contract) for completion and readiness for final payment, Contractor shall pay Owner $XX for each day that expires after such time until the Work is completed and ready for final payment.
3. Milestones: Contractor shall pay Owner $XX for each day that expires after the time (as duly adjusted pursuant to the Contract) specified above for achievement of Milestone 1, until Milestone 1 is achieved, or until the time
00520- 3 specified for Substantial Completion is reached, at which time the rate indicated in Paragraph 4.05.A.1 will apply, rather than the Milestone rate.
4. Liquidated damages for failing to timely attain Milestones, Substantial Completion, and final completion are not additive, and will not be imposed concurrently.
B. If Owner recovers liquidated damages for a delay in completion by Contractor, then such liquidated damages are Owner’s sole and exclusive remedy for such delay, and Owner is precluded from recovering any other damages, whether actual, direct, excess, or consequential, for such delay, except for special damages (if any) specified in this Agreement.
4.06 Special Damages
A. Contractor shall reimburse Owner (1) for any fines or penalties imposed on Owner as a direct result of the Contractor’s failure to attain Substantial Completion according to the Contract Times, and (2) for the actual costs reasonably incurred by Owner for engineering, construction observation, inspection, and administrative services needed after the time specified in Paragraph 4.02 for Substantial Completion (as duly adjusted pursuant to the Contract), until the Work is substantially complete.
B. After Contractor achieves Substantial Completion, if Contractor shall neglect, refuse, or fail to complete the remaining Work within the Contract Times, Contractor shall reimburse Owner for the actual costs reasonably incurred by Owner for engineering, construction observation, inspection, and administrative services needed after the time specified in Paragraph 4.02 for Work to be completed and ready for final payment (as duly adjusted pursuant to the Contract), until the Work is completed and ready for final payment.
C. The special damages imposed in this paragraph are supplemental to any liquidated damages for delayed completion established in this Agreement.
CONTRACT PRICE
5.01 Owner shall pay Contractor for completion of the Work in accordance with the Contract Documents, the amounts that follow, subject to adjustment under the Contract:
A. For all Work other than Unit Price Work, a lump sum of $XX for Alternate 2 and $XX for Alternate 3 (If applicable).
All specific cash allowances are included in the above price in accordance with Paragraph 13.02 of the General Conditions.
B. For all Unit Price Work, an amount equal to the sum of the extended prices (established for each separately identified item of Unit Price Work by multiplying the unit price times the actual quantity of that item).
Unit Price Work (Base Bid)
00520- 4
Item No. Description Unit Estimated
Quantity Unit Price
Extended Price
1 24" H.P. DRAIN PIPE (Example) LF 740 $46.51 $34,417.40
Total of all Extended Prices for Unit Price Work (subject to final adjustment based on actual quantities) $XX
The extended prices for Unit Price Work set forth as of the Effective Date of the Contract are based on estimated quantities. As provided in Paragraph 13.03 of the General Conditions, estimated quantities are not guaranteed, and determinations of actual quantities and classifications are to be made by Engineer.
C. Total of Lump Sum Amount and Unit Price Work (subject to final Unit Price adjustment) $XX.
D. For all Work, at the prices stated in Contractor’s Bid, attached hereto as an exhibit.
PAYMENT PROCEDURES
6.01 Submittal and Processing of Payments
A. Contractor shall submit Applications for Payment in accordance with Article 15 of the General Conditions. Applications for Payment will be processed by Engineer as provided in the General Conditions.
6.02 Progress Payments; Retainage
A. Owner shall make progress payments on the basis of Contractor’s Applications for Payment on or about the 25th day of each month during performance of the Work as provided in Paragraph 6.02.A.1 below, provided that such Applications for Payment have been submitted in a timely manner and otherwise meet the requirements of the Contract. All such payments will be measured by the Schedule of Values established as provided in the General Conditions (and in the case of Unit Price Work based on the number of units completed) or, in the event there is no Schedule of Values, as provided elsewhere in the Contract.
00520- 5
1. Prior to Substantial Completion, progress payments will be made in an amount equal to the percentage indicated below but, in each case, less the aggregate of payments previously made and less such amounts as Owner may withhold, including but not limited to liquidated damages, in accordance with the Contract.
a. 95 percent of the value of the Work completed (with the balance being retainage).
If 50 percent or more of the Work has been completed, as determined by Engineer, and if the character and progress of the Work have been satisfactory to Owner and Engineer, then as long as the character and progress of the Work remain satisfactory to Owner and Engineer, there will be no additional retainage; and
b. 95 percent of cost of materials and equipment not incorporated in the Work (with the balance being retainage).
B. Upon Substantial Completion, Owner shall pay an amount sufficient to increase total payments to Contractor to 100 percent of the Work completed, less such amounts set off by Owner pursuant to Paragraph 15.01.E of the General Conditions, and less 200 percent of Engineer’s estimate of the value of Work to be completed or corrected as shown on the punch list of items to be completed or corrected prior to final payment.
6.03 Final Payment
A. Upon final completion and acceptance of the Work, Owner shall pay the remainder of the Contract Price in accordance with Paragraph 15.06 of the General Conditions.
6.04 Consent of Surety
A. Owner will not make final payment, or return or release retainage at Substantial Completion or any other time, unless Contractor submits written consent of the surety to such payment, return, or release.
6.05 Interest
A. All amounts not paid when due will bear interest at the rate of [number] percent per annum.
CONTRACT DOCUMENTS
7.01 Contents
A. The Contract Documents consist of all of the following:
1. This Agreement.
2. Bonds:
a. Performance bond (together with power of attorney).
b. Payment bond (together with power of attorney).
3. General Conditions.
00520- 6
4. Supplementary Conditions.
5. Specifications as listed in the table of contents of the project manual (copy of list attached).
6. Drawings (not attached but incorporated by reference) consisting of (Number of Sheets) sheets with each sheet bearing the following general title: (Project Name).
7. Addenda (numbers 1 to 2, inclusive).
8. The following which may be delivered or issued on or after the Effective Date of the Contract and are not attached hereto:
a. Notice to Proceed.
b. Work Change Directives.
c. Change Orders.
d. Field Orders.
e. Warranty Bond, if any.
B. The Contract Documents listed in Paragraph 7.01.A are attached to this Agreement (except as expressly noted otherwise above).
C. There are no Contract Documents other than those listed above in this Article 7.
D. The Contract Documents may only be amended, modified, or supplemented as provided in the Contract.
REPRESENTATIONS, CERTIFICATIONS, AND STIPULATIONS
8.01 Contractor’s Representations
A. In order to induce Owner to enter into this Contract, Contractor makes the following representations:
1. Contractor has examined and carefully studied the Contract Documents, including Addenda.
2. Contractor has visited the Site, conducted a thorough visual examination of the Site and adjacent areas, and become familiar with the general, local, and Site conditions that may affect cost, progress, and performance of the Work.
3. Contractor is familiar with all Laws and Regulations that may affect cost, progress, and performance of the Work.
4. Contractor has carefully studied the reports of explorations and tests of subsurface conditions at or adjacent to the Site and the drawings of physical conditions relating to existing surface or subsurface structures at the Site that have been identified in the Supplementary Conditions, with respect to the Technical Data in such reports and drawings.
5. Contractor has carefully studied the reports and drawings relating to Hazardous Environmental Conditions, if any, at or adjacent to the Site that have been
00520- 7 identified in the Supplementary Conditions, with respect to Technical Data in such reports and drawings.
6. Contractor has considered the information known to Contractor itself;
information commonly known to contractors doing business in the locality of the Site; information and observations obtained from visits to the Site; the Contract Documents; and the Technical Data identified in the Supplementary Conditions or by definition, with respect to the effect of such information, observations, and Technical Data on (a) the cost, progress, and performance of the Work; (b) the means, methods, techniques, sequences, and procedures of construction to be employed by Contractor; and (c) Contractor’s safety precautions and programs.
7. Based on the information and observations referred to in the preceding paragraph, Contractor agrees that no further examinations, investigations, explorations, tests, studies, or data are necessary for the performance of the Work at the Contract Price, within the Contract Times, and in accordance with the other terms and conditions of the Contract.
8. Contractor is aware of the general nature of work to be performed by Owner and others at the Site that relates to the Work as indicated in the Contract Documents.
9. Contractor has given Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Contractor has discovered in the Contract Documents, and of discrepancies between Site conditions and the Contract Documents, and the written resolution thereof by Engineer is acceptable to Contractor.
10. The Contract Documents are generally sufficient to indicate and convey understanding of all terms and conditions for performance and furnishing of the Work.
11. Contractor’s entry into this Contract constitutes an incontrovertible representation by Contractor that without exception all prices in the Agreement are premised upon performing and furnishing the Work required by the Contract Documents.
8.02 Contractor’s Certifications
A. Contractor certifies that it has not engaged in corrupt, fraudulent, collusive, or coercive practices in competing for or in executing the Contract. For the purposes of this Paragraph 8.02:
1. “corrupt practice” means the offering, giving, receiving, or soliciting of anything of value likely to influence the action of a public official in the bidding process or in the Contract execution;
2. “fraudulent practice” means an intentional misrepresentation of facts made (a) to influence the bidding process or the execution of the Contract to the detriment of Owner, (b) to establish Bid or Contract prices at artificial non-competitive levels, or (c) to deprive Owner of the benefits of free and open competition;
00520- 8
3. “collusive practice” means a scheme or arrangement between two or more Bidders, with or without the knowledge of Owner, a purpose of which is to establish Bid prices at artificial, non-competitive levels; and
4. “coercive practice” means harming or threatening to harm, directly or indirectly, persons or their property to influence their participation in the bidding process or affect the execution of the Contract.
8.03 Standard General Conditions
A. Owner stipulates that if the General Conditions that are made a part of this Contract are EJCDC® C-700, Standard General Conditions for the Construction Contract (2018), published by the Engineers Joint Contract Documents Committee, and if Owner is the party that has furnished said General Conditions, then Owner has plainly shown all modifications to the standard wording of such published document to the Contractor, through a process such as highlighting or “track changes” (redline/strikeout), or in the Supplementary Conditions.
8.04 Notice of Governing Law
A. The Contractor agrees to abide by the following applicable laws and regulations and to make all records, invoices, materials, payrolls, records of personnel, conditions of employment and other documentary data available at any time for the purpose of an audit and to ensure compliance with relevant laws:
1. Title I of the Housing and Community Development Act of 1974, as amended.
2. 2 CFR Part 200 Uniform Administrative Requirements, Cost Principles and Audit
Requirements for Federal Awards.
3. Agrees to comply with the Federal Contract Provisions found at 2 CFR Part 200-
Appendix II, attached as part of this contract, where applicable.
4. Debarment, Suspension and Ineligibility. The Contractor represents and warrants that Contractor and its subcontractors are not debarred, suspended, or placed in ineligibility status under 24 CFR Part 24, government debarment and suspension regulations.
5. Conflict of Interest. The general rule is that no persons described in 24 CFR Part 570.611(c) who exercise or have exercised any functions or responsibilities with respect to CDBG activities, or who are in a position to participate in a decision-making process or gain inside information with regard to such activities, may obtain a financial interest or benefit from a CDBG-assisted activity, or have a financial interest in any contract, subcontract, or agreement with respect to a CDBG-assisted activity, or with respect to the proceeds of the CDBG-assisted activity, either for themselves or those with whom they have business or immediate family ties, during their tenure or for one year thereafter.
6. Compliance with HUD Federal Labors Standards Provisions (HUD Form 4010), including the Davis-Bacon and Related Acts, Copeland Anti-Kickback Act and Contract Work Hours and Safety Standards Act.
7. Agrees to pay wage rates on construction work for this project at least equal to the applicable wage decision, by the Department of Labor and any wage decision that supersedes this decision before the contract is awarded.
https://www.law.cornell.edu/cfr/text/24/570.611#c https://www.law.cornell.edu/definitions/index.php?width=840&height=800&iframe=true&def_id=be6bf21fb6e802a6caa6a65a99a9e110&term_occur=999&term_src=Title:24:Subtitle:B:Chapter:V:Subchapter:C:Part:570:Subpart:K:570.611
00520- 9
8. Equal Employment Opportunity - Title VII of the Civil Rights Act of 1964.
9. Section 504 of the Rehabilitation Act of 1973, as amended.
10. Section 3 of the Housing and Urban Development Act of 1968 (if applicable).
11. The Contractor must comply with the requirements of the Build America, Buy
America (BABA) Act, 41 USC 8301 note, and all applicable rules and notices, as may be amended, if applicable to the infrastructure project. Pursuant to HUD’s Notice, “Public Interest Phase Implementation Waiver for FY 2022 and 2023 Build America, Buy America Provisions as Applied to Recipients of HUD Federal Assistance” (88 FR 17001), any funds obligated by HUD on or after the applicable listed effective dates, are subject to BABA requirements, unless excepted by a waiver.
12. Clean Water, Clean Air, Executive Order 11738 and Regulations Provision.
Failure to comply with any applicable federal requirements can and may result in the termination of the contract and disbarment of contractor.
To the extent any language in the agreement is in conflict with State or Federal law, then State and Federal law will control.
Attachments
Exhibit A
Exhibit B Wage Decision
Exhibit C Federal Contract Clauses
00520- 10
IN WITNESS WHEREOF, Owner and Contractor have signed this Agreement.
This Agreement will be effective on (Month) (Date), (Year) (which is the Effective Date of the Contract).
Owner: Contractor:
City of Edinburg (typed or printed name of organization) (typed or printed name of organization)
By: By:
(individual’s signature) (individual’s signature) Date: Date:
(date signed) (date signed) Name: Name:
(typed or printed) (typed or printed)
Title: Title:
(typed or printed) (typed or printed)
(If (Contractor Name) is a corporation, a partnership, or a joint venture, attach evidence of authority to sign.)
Attest: Attest:
(individual’s signature) (individual’s signature) Title: Title:
(typed or printed) (typed or printed) Address for giving notices: Address for giving notices:
City of Edinburg
415 W. University Drive
Edinburg, TX 78539 Designated Representative: Designated Representative:
Name: Name:
(typed or printed) (typed or printed)
Title: Title:
(typed or printed) (typed or printed) Address: Address:
Phone: Phone:
Email: Email:
(If City of Edinburg is a public body, attach evidence of authority to sign and resolution or other documents authorizing execution of this Agreement.)
License No.:
(where applicable)
State:
00520- 11
Page Intentionally Blank
| WORK |
| 1.01 Contractor shall complete all Work as specified or indicated in the Contract Documents. The Work is generally described as follows: (Project Description). |
| THE PROJECT |
| 2.01 The Project, of which the Work under the Contract Documents is a part, is generally described as follows: (Project Number and Name) |
| ENGINEER |
| 3.01 The Owner has retained (Engineer Name) (“Engineer”) to act as Owner’s representative, assume all duties and responsibilities of Engineer, and have the rights and authority assigned to Engineer in the Contract. |
| 3.02 The part of the Project that pertains to the Work has been designed by (Engineer Name). |
| CONTRACT TIMES |
| 4.01 Time is of the Essence |
| A. All time limits for Milestones, if any, Substantial Completion, and completion and readiness for final payment as stated in the Contract Documents are of the essence of the Contract. |
| 4.02 Contract Times: Dates |
| A. The Work will be substantially complete on or before (Date), and completed and ready for final payment in accordance with Paragraph 15.06 of the General Conditions on or before (Date). |
| 4.03 Milestones |
| A. Parts of the Work must be substantially completed on or before the following Milestone(s): |
| 1. Milestone 1 Substantial Completion / (Date) |
| 2. Milestone 2 Final Completion / (Date) |
| 4.04 Liquidated Damages |
| A. Contractor and Owner recognize that time is of the essence as stated in Paragraph 4.01 above and that Owner will suffer financial and other losses if the Work is not completed and Milestones not achieved within the Contract Times, as duly modified.... |
| 1. Substantial Completion: Contractor shall pay Owner based on fees below for each day that expires after the time (as duly adjusted pursuant to the Contract) specified above for Substantial Completion, until the Work is substantially complete. |
| 2. Completion of Remaining Work: After Substantial Completion, if Contractor shall neglect, refuse, or fail to complete the remaining Work within the Contract Times (as duly adjusted pursuant to the Contract) for completion and readiness for final pay... |
| 3. Milestones: Contractor shall pay Owner $XX for each day that expires after the time (as duly adjusted pursuant to the Contract) specified above for achievement of Milestone 1, until Milestone 1 is achieved, or until the time specified for Substanti... |
| 4. Liquidated damages for failing to timely attain Milestones, Substantial Completion, and final completion are not additive, and will not be imposed concurrently. |
B. If Owner recovers liquidated damages for a delay in completion by Contractor, then such liquidated damages are Owner’s sole and exclusive remedy for such delay, and Owner is precluded from recovering any other damages, whether actual, direct, exces...
| 4.06 Special Damages |
| A. Contractor shall reimburse Owner (1) for any fines or penalties imposed on Owner as a direct result of the Contractor’s failure to attain Substantial Completion according to the Contract Times, and (2) for the actual costs reasonably incurred by Ow... |
| B. After Contractor achieves Substantial Completion, if Contractor shall neglect, refuse, or fail to complete the remaining Work within the Contract Times, Contractor shall reimburse Owner for the actual costs reasonably incurred by Owner for engineer... |
| C. The special damages imposed in this paragraph are supplemental to any liquidated damages for delayed completion established in this Agreement. |
| CONTRACT PRICE |
| 5.01 Owner shall pay Contractor for completion of the Work in accordance with the Contract Documents, the amounts that follow, subject to adjustment under the Contract: |
| A. For all Work other than Unit Price Work, a lump sum of $XX for Alternate 2 and $XX for Alternate 3 (If applicable). |
| B. For all Unit Price Work, an amount equal to the sum of the extended prices (established for each separately identified item of Unit Price Work by multiplying the unit price times the actual quantity of that item). |
| The extended prices for Unit Price Work set forth as of the Effective Date of the Contract are based on estimated quantities. As provided in Paragraph 13.03 of the General Conditions, estimated quantities are not guaranteed, and determinations of actu... |
| C. Total of Lump Sum Amount and Unit Price Work (subject to final Unit Price adjustment) $XX. |
| D. For all Work, at the prices stated in Contractor’s Bid, attached hereto as an exhibit. |
| PAYMENT PROCEDURES |
| 6.01 Submittal and Processing of Payments |
| A. Contractor shall submit Applications for Payment in accordance with Article 15 of the General Conditions. Applications for Payment will be processed by Engineer as provided in the General Conditions. |
| 6.02 Progress Payments; Retainage |
| A. Owner shall make progress payments on the basis of Contractor’s Applications for Payment on or about the 25th day of each month during performance of the Work as provided in Paragraph 6.02.A.1 below, provided that such Applications for Payment have... |
| 1. Prior to Substantial Completion, progress payments will be made in an amount equal to the percentage indicated below but, in each case, less the aggregate of payments previously made and less such amounts as Owner may withhold, including but not li... |
| a. 95 percent of the value of the Work completed (with the balance being retainage). |
| If 50 percent or more of the Work has been completed, as determined by Engineer, and if the character and progress of the Work have been satisfactory to Owner and Engineer, then as long as the character and progress of the Work remain satisfactory to ... |
| b. 95 percent of cost of materials and equipment not incorporated in the Work (with the balance being retainage). |
B. Upon Substantial Completion, Owner shall pay an amount sufficient to increase total payments to Contractor to 100 percent of the Work completed, less such amounts set off by Owner pursuant to Paragraph 15.01.E of the General Conditions, and less 20...
| 6.03 Final Payment |
| A. Upon final completion and acceptance of the Work, Owner shall pay the remainder of the Contract Price in accordance with Paragraph 15.06 of the General Conditions. |
| 6.04 Consent of Surety |
| A. Owner will not make final payment, or return or release retainage at Substantial Completion or any other time, unless Contractor submits written consent of the surety to such payment, return, or release. |
| 6.05 Interest |
| A. All amounts not paid when due will bear interest at the rate of [number] percent per annum. |
| CONTRACT DOCUMENTS |
| 7.01 Contents |
| A. The Contract Documents consist of all of the following: |
| 1. This Agreement. |
| 2. Bonds: |
| a. Performance bond (together with power of attorney). |
| b. Payment bond (together with power of attorney). |
| 3. General Conditions. |
| 4. Supplementary Conditions. |
| 5. Specifications as listed in the table of contents of the project manual (copy of list attached). |
| 6. Drawings (not attached but incorporated by reference) consisting of (Number of Sheets) sheets with each sheet bearing the following general title: (Project Name). |
| 7. Addenda (numbers 1 to 2, inclusive). |
| 8. The following which may be delivered or issued on or after the Effective Date of the Contract and are not attached hereto: |
| a. Notice to Proceed. |
| b. Work Change Directives. |
| c. Change Orders. |
| d. Field Orders. |
| e. Warranty Bond, if any. |
| B. The Contract Documents listed in Paragraph 7.01.A are attached to this Agreement (except as expressly noted otherwise above). |
| C. There are no Contract Documents other than those listed above in this Article 7. |
| D. The Contract Documents may only be amended, modified, or supplemented as provided in the Contract. |
| REPRESENTATIONS, CERTIFICATIONS, AND STIPULATIONS |
| 8.01 Contractor’s Representations |
| A. In order to induce Owner to enter into this Contract, Contractor makes the following representations: |
| 1. Contractor has examined and carefully studied the Contract Documents, including Addenda. |
| 2. Contractor has visited the Site, conducted a thorough visual examination of the Site and adjacent areas, and become familiar with the general, local, and Site conditions that may affect cost, progress, and performance of the Work. |
| 3. Contractor is familiar with all Laws and Regulations that may affect cost, progress, and performance of the Work. |
| 4. Contractor has carefully studied the reports of explorations and tests of subsurface conditions at or adjacent to the Site and the drawings of physical conditions relating to existing surface or subsurface structures at the Site that have been iden... |
| 5. Contractor has carefully studied the reports and drawings relating to Hazardous Environmental Conditions, if any, at or adjacent to the Site that have been identified in the Supplementary Conditions, with respect to Technical Data in such reports a... |
| 6. Contractor has considered the information known to Contractor itself; information commonly known to contractors doing business in the locality of the Site; information and observations obtained from visits to the Site; the Contract Documents; and t... |
| 7. Based on the information and observations referred to in the preceding paragraph, Contractor agrees that no further examinations, investigations, explorations, tests, studies, or data are necessary for the performance of the Work at the Contract Pr... |
| 8. Contractor is aware of the general nature of work to be performed by Owner and others at the Site that relates to the Work as indicated in the Contract Documents. |
| 9. Contractor has given Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Contractor has discovered in the Contract Documents, and of discrepancies between Site conditions and the Contract Documents, and the written ... |
| 10. The Contract Documents are generally sufficient to indicate and convey understanding of all terms and conditions for performance and furnishing of the Work. |
| 11. Contractor’s entry into this Contract constitutes an incontrovertible representation by Contractor that without exception all prices in the Agreement are premised upon performing and furnishing the Work required by the Contract Documents. |
| 8.02 Contractor’s Certifications |
| A. Contractor certifies that it has not engaged in corrupt, fraudulent, collusive, or coercive practices in competing for or in executing the Contract. For the purposes of this Paragraph 8.02: |
| 1. “corrupt practice” means the offering, giving, receiving, or soliciting of anything of value likely to influence the action of a public official in the bidding process or in the Contract execution; |
| 2. “fraudulent practice” means an intentional misrepresentation of facts made (a) to influence the bidding process or the execution of the Contract to the detriment of Owner, (b) to establish Bid or Contract prices at artificial non-competitive levels... |
| 3. “collusive practice” means a scheme or arrangement between two or more Bidders, with or without the knowledge of Owner, a purpose of which is to establish Bid prices at artificial, non-competitive levels; and |
| 4. “coercive practice” means harming or threatening to harm, directly or indirectly, persons or their property to influence their participation in the bidding process or affect the execution of the Contract. |
| 8.03 Standard General Conditions |
| A. Owner stipulates that if the General Conditions that are made a part of this Contract are EJCDC® C-700, Standard General Conditions for the Construction Contract (2018), published by the Engineers Joint Contract Documents Committee, and if Owner is... |
| 8.04 Notice of Governing Law |
| Attachments |
| Exhibit A |
| Exhibit B Wage Decision |
| Exhibit C Federal Contract Clauses |
File details come from the government source that posted it. Updated .