This is an Intent to Award document from the Oregon Department of Transportation (ODOT) for the ESB-LaGrande Maintenance Facility Deicer Tank Replacement project, solicitation number S-73000-00014505. The project involves removing and disposing of three existing 10,000-gallon poly deicer tanks, associated pump house, pumps, and miscellaneous infrastructure, followed by site preparation and installation of three new 15,500-gallon deicer tanks. The bid closed on August 19, 2025, at 10:30 AM, with Hamilton Excavation identified as the intended contract awardee. The project requires substantial completion by October 16, 2025, and final completion by October 20, 2025.
The bid tabulation shows five bidders with total bid prices ranging from $135,190 to $194,195, with Hamilton Excavation submitting the lowest bid at $135,190. The procurement is exclusively restricted to Emerging Small Businesses (ESB) certified by Oregon's Certification Office for Business Inclusion and Diversity (COBID), requiring selected contractors to perform at least 51% of labor using their own workforce. Contractors must be licensed with the Oregon Construction Contractors Board, comply with prevailing wage requirements, and provide performance and payment bonds equal to 100% of the contract value, along with comprehensive insurance coverage including $1,000,000 per occurrence commercial general liability and commercial automobile liability.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| ESB_RFCQ_279C.docx | DOCX document | |
| 00014505 Prebid Meeting Agenda.doc | DOC document | |
| ESB_RFCQ_Attachments_279C~1.docx | DOCX document | |
| 00014505 Preliminary Results.xlsx | XLSX spreadsheet | |
| NOIBinder.pdf | ||
| Exhibit 1 Technical Specifications~14.pdf | ||
| 00014505 MandatoryPreBidSignInSheet.docx | DOCX document | |
| Exhibit 2 Plans REVISED~1.pdf | ||
| 00014505A1 Addendum1~1.docx | DOCX document | |
| Exhibit 2 Plans~23.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Date Issued: | 8/19/25 | ||||||
| ITB No. | S-73000-00014505 | BIDDER | |||||
| NAME: | Hamilton Excavation | Paul Mitchell Bartlett | Draco Enterprises LLC | TTE Inc | G Gorndon Construction Company LLC | ||
| Bid Closing: | 8/19/2025:10:30AM | ||||||
| Description: | ESB-LaGrande Maintenance Facility Deicer Tank Replacement | ||||||
| This bid tabulation shall serve as ODOT's notice of intent to award a contract to (Hamilton Excavation) |
| Bid Item # | Description | Est | |
| QTY | UNIT | UNIT | |
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL |
PRICE
| 1 | This project includes removing and disposing of 3 - 10,000 gallon existing poly deicer tanks, pump house, pumps, and miscellaneous plumbing and electrical materials occupying the new construction area. The project will include trenching/general excavation, conduit installation, disposal, preparation of a gravel foundation, construction of a reinforced concrete pad, and delivery and placement of 3 - new 15,500 gallon deicer tanks. The finish grade of the new concrete slab shall match the exiting door elevation and slope away from edges of building structures and slope in a manner to reduce water runoff pooling. All materials that are excavated from the site during preparation and construction shall be the property of the contractor and be disposed of in accordance with all local, state, and federal regulations and Section 00290 | 1 | Lump Sum | $ 135,190.00 | $ 135,190.00 | $ 143,000.00 | $ 143,000.00 | $ 164,000.00 | $ 164,000.00 | $ 190,000.00 | $ 190,000.00 | $ 194,195.00 | $ 194,195.00 | $ - 0 | $ - 0 | $ - 0 | |||
| TOTAL | $ 135,190.00 | $ 143,000.00 | $ 164,000.00 | $ 190,000.00 | $ 194,195.00 | $ - 0 | $ - 0 | $ - 0 |