00_52_13_Agreement_Form_P33Z1_final_SAMPLE.pdf
PDF 114 KB Posted
- Attached to
- County Office Building 1 Renovation and Modernization Work Package 2 (WP2) Project (Project No. P33Z1)
- Solicitation number
- 2027-RFP-00118
- Issued by
- San Mateo County, California
About this file
This is an Agreement Form for a general contracting project between San Mateo County and a contractor for the County Office Building 1 Renovation and Modernization Work Package 2 (WP2) Project located at 455 County Center, Redwood City, California. The scope of work encompasses interior remodeling of portions of Level 1 and all of Level 2, including hazardous-materials abatement, demolition, non-load-bearing partitions, suspended acoustic ceilings, lighting, doors, frames, hardware, finishes, and comprehensive mechanical, electrical, and plumbing systems, along with fire suppression systems, fire alarm systems, audiovisual systems, and access control system expansion. The contract time for overall project completion is 204 calendar days from the Notice to Proceed, with a critical Milestone 1 requiring substantial completion of all Level 1 work by May 9, 2027 (125 calendar days from Notice to Proceed). The County Office Building will remain occupied during construction, with Level 2 and Level 5 vacant while Level 1 lobby and stairwells remain in use during phased work. The contractor must establish a web-based project management system using Procore software, submit a startup construction schedule within seven days of commencement, and a detailed Critical Path Method schedule within 60 days.
Compensation is specified as the Contractor's Bid amount, to be determined through the solicitation process, and includes full payment for all labor, materials, equipment, and statutory and administrative obligations required to comply with the County of San Mateo Project Labor Agreement. This project is subject to prevailing wage requirements under California Labor Code Section 1770 and is covered work under the County of San Mateo Project Labor Agreement (Master PLA) entered into with the San Mateo County Building and Construction Trades Council. All contractors and subcontractors must be registered with the Department of Industrial Relations and must execute the Agreement to be Bound (Addendum A), with all subcontractors of every tier required to comply with all terms of the Master PLA prior to working on the project site. Hazardous-materials surveys identified asbestos-containing materials, lead-based paint, PCBs, and universal waste; contractors are solely responsible for verifying actual quantities and locations through site visits prior to bidding. Work is restricted to City of Redwood City working hours, with tobacco and controlled substances prohibited on-site and drug screening of personnel required.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Agreement Page 1 of 3
DOCUMENT 00 52 13
AGREEMENT FORM
THIS AGREEMENT, entered into this day of , 20__, by and between the COUNTY OF SAN MATEO, a Political Subdivision of the State of
California, hereinafter called the "County", and , hereinafter called the "Contractor".
WITNESSETH that the Contractor and the County, in consideration of the mutual covenants, considerations and agreements herein contained, agree as follows:
STATEMENT OF WORK – The Contractor shall furnish all labor and materials and perform all work for:
Project: County Office Building 1 Renovation and Modernization Work Package 2 (WP2) Project (Project No. P33Z1) 455 County Center Redwood City, CA 94063 in strict accordance with the Contract Documents.
TIME FOR COMPLETION – The Work shall be commenced on the date specified in the Notice to Proceed issued by the County. The Contract Time for completion of all the Work of the Project is Two Hundred Four (204) calendar days, starting the day after the date established in the Notice to Proceed issued by the County, defined as sufficiently complete in accordance with the Contract Documents and Project Specifications.
Phased Milestone Completion Requirements:
1. Milestone 1 (Level 1 Work): Substantial Completion of all Level 1 Work, and any related basement or infrastructure work necessary to fully support Level 1 occupancy and operation, is subject to a mandatory fixed completion date of May 9, 2027 (One Hundred Twenty-Five [125] calendar days from Notice to Proceed). May 9, 2027 is a critical constraint for County operations; time is strictly of the essence, and Substantial Completion of Milestone 1 must be achieved on or before May 9, 2027, regardless of the overall Contract Time.
2. Milestone 2 (Overall Project Final Completion): Substantial Completion of all remaining Work (Level 2, finishes, and final punch lists) shall be achieved within Two Hundred Four (204) calendar days following the date established in the Notice to Proceed.
COMPENSATION TO BE PAID TO CONTRACTOR – The County will pay and the Contractor will accept in full consideration for the performance of the contract, subject to additions and deductions and procedures for payment as provided therein, the sum of _____________________________________________ ($_____________) which is the Contractor’s Bid. Said compensation includes full payment for all labor, materials, equipment, and statutory and administrative obligations required to comply with the County of San Mateo Project Labor Agreement. The Contract as defined in paragraph 1.1 of the General Conditions constitutes the sole agreement of the parties hereto relating to said work and correctly states the rights, duties, and obligations of each party as of the document's date. Any prior agreement, promises, negotiations, or representations between the parties not expressly stated in this document are not binding. All subsequent modifications shall be in writing.
PREVAILING WAGE RATES - In accordance with the provisions of Section
1770 of the Labor Code, the Board of Supervisors of the County of San Mateo has ascertained the prevailing rate of wages applicable to the work to be done, which prevailing wage rates have been established as indicated in the Notice to Bidders and are incorporated herein by reference.
The Contractor’s attention is further directed to the following requirements of State
Senate Bill SB 854 (Stat. 2014, chapter 28), effective January 1, 2015:
(1) No contractor or subcontractor may be listed on a bid proposal for a public works project (submitted on or after March 1, 2015) unless registered with the Department of Industrial Relations pursuant to Labor Code section
1725.5 [with limited exceptions from this requirement for bid purposes only under Labor Code section 1771.1(a)].
(2) No contractor or subcontractor may be awarded a contract for public work on a public works project (awarded on or after April 1, 2015) unless registered with the Department of Industrial Relations pursuant to Labor
Code section 1725.5.
(3) This project is subject to compliance monitoring and enforcement by the
Department of Industrial Relations.
PROJECT LABOR AGREEMENT (PLA) - This Project is Covered Work subject to the County of San Mateo Project Labor Agreement (Master PLA) entered into between the
County of San Mateo and the San Mateo County Building and Construction Trades Council along with affiliated Unions, adopted pursuant to Board of Supervisors Resolution No.
081396. The Master PLA is incorporated herein by reference and made an express part of this Contract.
1. The Contractor agrees to be bound by each and every provision of the Master PLA and confirms execution of the Agreement to be Bound (Addendum A) as an express condition of this Agreement.
2. The Contractor shall require all subcontractors of every tier, as a condition of performing work on the Project site, to execute Addendum A and comply with all terms of the Master PLA.
3. Fully executed copies of Addendum A for each subcontractor shall be submitted to the County’s Construction Manager prior to permitting that subcontractor on the
Project site. Any subcontractor refusing to execute Addendum A shall not be permitted on site.
IN WITNESS WHEREOF, the parties hereto on the day and year first above written have executed this agreement in three counterparts, each of which shall, without proof or accounting for the other counterparts, be deemed an original thereof.
COUNTY OF SAN MATEO A Political Sub-Division of the State of California
By Attest: President, Board of Supervisors
Michael Callagy, County Executive Clerk of the Board of Supervisors
By Contractor