This is a bidding document package for the City of Scranton, Pennsylvania, for the Scranton Levee Storm Pipe Inspection project. The Work involves furnishing all labor, supervision, equipment, materials, transportation, and incidentals necessary to inspect and document City of Scranton-owned stormwater pipes penetrating the Lackawanna River flood protection levee system. Services include CCTV inspection, sonar inspection where required, visual inspection, pipe cleaning as authorized, condition assessment and PACP coding, location documentation, and preparation of inspection videos, photographs, logs, reports, maps, and deliverables complying with United States Army Corps of Engineers requirements. Sealed bids must be submitted online through the City's e-Procurement Portal by 10:00 am on Thursday, December 3, 2026, with bid opening in City Council Chambers. The contract requires completion of all field inspection activities within 120 calendar days following the Notice to Proceed (Milestone 1) and submission of complete final inspection reports and electronic deliverables within 21 calendar days following field completion (Milestone 2). Site visits are encouraged during normal working hours. The engineer for the project is Reilly Associates. Personnel operating remote pipe inspection equipment must possess current NASSCO Pipeline Assessment Certification Program (PACP) certification or equivalent and demonstrate a minimum of one year of applicable pipe inspection experience. Any required professional engineering oversight must be provided by a Professional Engineer licensed in Pennsylvania.
The contract is on a stipulated price basis using unit pricing for individual bid items, with the Bid Price calculated as the product of estimated quantity and the contractor's unit price. A bid security of 10 percent of the total bid price is required in the form of a certified check, bank money order, or bid bond. Progress payments will be made at 90 percent of work completed with 10 percent retainage (reducible to 5 percent retainage after 50 percent completion if work progress is satisfactory), plus 90 percent of costs for stored materials and equipment under specified conditions. Liquidated damages are assessed at $500 per day for failure to meet Substantial Completion and final completion milestones. The contract documents incorporate standard EJCDC forms, Pennsylvania prevailing wage requirements, and federal requirements. The contractor must comply with all permits and conditions established by the City and other entities controlling the Site, with no adjustment in contract price allowed for delays in permit acquisition or site availability; contract time extension only is the contractor's exclusive remedy for such delays. No DBE set-aside percentage is specified in the document.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Table of Contents
Page 00010-1 of 00010-1
TABLE OF CONTENTS
Section Number
Title
Page Number
INTRODUCTORY INFORMATION
00010 Table of Contents 00010-1 to 00010-1
00015 List of Drawings 00015-1 to 00015-1
BIDDING REQUIREMENTS
00200 Instructions to Bidders 00200-1 to 00200-9
Bid Form Complete Online
00430 Bid Bond (Penal Sum Form) 00430-1 to 00430-2
CONTRACT DOCUMENTS
00510 Notice of Intent to Award 00510-1 to 00510-1
00520 Form of Agreement 00520-1 to 00520-7
00550 Notice to Proceed 00550-1 to 00550-1
00610 Performance Bond 00610-1 to 00610-3
00615 Payment Bond 00615-1 to 00615-3
00620 Contractor’s Application for Payment 00620-1 to 00620-4
00625 Certificate of Substantial Completion 00625-1 to 00625-1
00650 Consent of Surety to Final Payment Form 00650-1 to 00650-1
00700 Standard General Conditions of the Construction
Contract
00700-1 to 00700-65
00800 Supplementary Conditions 00800-1 to 00800-17
00820 Additional State, Federal or Funding Agency
Requirements
00820-1 to 00820-7
00830 Permits 00830-1 to 00830-1
00840 Wage Rate Requirements - Federal 00840-1 to 00840-15
00940 Work Change Directive 00940-1 to 00940-1
00941 Change Order 00941-1 to 00941-1
00942 Field Order 00942-1 to 00942-1
Table of Contents
Page 00010-1 of 00010-1
SPECIFICATIONS
DIVISION 1 – GENERAL REQUIREMENTS
01000 Summary of Work 01000-1 to 01000-5
01270 Unit Prices 01270-1 to 01271-2
01300 Submittals 01300-1 to 01300-6
01570 Maintenance and Protection of Traffic 01570-1 to 01570-6
DIVISION 33 – SITE UTILITIES
33100 Storm Infrastructure Cleaning 33100-1 to 33100-8
33200 CCTC Inspection of Storm Lines 33200-1 to 33200-12
APPENDICES
Appendix A – USACE Guidance for CCTV and Sonar Inspection of Pipes Penetrating Levees
Appendix B – USACE Guidance for Visual Inspection of Pipes Penetrating Levees
Appendix C – USACE Guidelines for Human/Visual Inspection of Conduits
Appendix D – USACE Guidelines for Video Inspection of Conduits
Appendix E – USACE Conduits, Pipes, and Culverts Associated with Dams and Levee Systems
Engineering Manual
Appendix F – City-Owned Stormwater Pipe Penetration Inventory
List of Drawings
Page 00015- 1 of 00015-1
LIST OF DRAWINGS
LEVEE INSPECTION
CITY OF SCRANTON
NOTE:
THE CONTRACT DRAWINGS CONSIST OF SELECTED HISTORICAL U.S. ARMY CORPS OF ENGINEERS
RECORD DRAWINGS THAT HAVE BEEN ANNOTATED BY THE ENGINEER TO IDENTIFY CITY OF SCRANTON-
OWNED STORMWATER PIPE PENETRATIONS INCLUDED IN THE WORK.
THE UNDERLYING RECORD DRAWINGS DEPICT HISTORICAL CONDITIONS AND ARE PROVIDED AS THE
BASIS FOR LOCATING THE EXISTING LEVEE SYSTEM, DRAINAGE STRUCTURES, PIPE PENETRATIONS, AND
OTHER FACILITIES. THE ANNOTATIONS ADDED FOR THIS PROJECT IDENTIFY THE FACILITIES INTENDED
FOR INSPECTION UNDER THIS CONTRACT.
EXISTING CONDITIONS, PIPE LOCATIONS, DIMENSIONS, MATERIALS, ELEVATIONS, OWNERSHIP, ACCESSIBILITY, AND OTHER INFORMATION SHOWN ON THE HISTORICAL RECORD DRAWINGS SHALL BE
CONSIDERED APPROXIMATE AND SHALL BE VERIFIED BY THE CONTRACTOR AS NECESSARY TO PERFORM
THE WORK. NO PENNSYLVANIA AMERICAN WATER OWNED FACILITIES ARE TO BE INSPECTED UNDER
THIS CONTRACT.
NAME DATE SHEEET(S) SECTION
LACKAWANNA RIVER
FLOOD PROTECTION
PROJECT
DECEMBER
C-1, C-2, C-3, C-4, C-5, C-6, C-7 GREEN RIDGE
SCRANTON LOCAL
FLOOD PROTECTION
PROJECT
JANUARY
C-1, C-2, C-3, C-4, C-5, C-6 ALBRIGHT
LACKAWANNA RIVER
FLOOD PROTECTION
PROJECT
MARCH
C-8, C-9, C-10, C-11, C-12 PLOT
LOCAL FLOOD
PROTECTION PROJECT
MAY 1966 5605-3 SOUTHSIDE
Instructions to Bidders
Page 00200-i
INSTRUCTIONS TO BIDDERS
Page
ARTICLE 1 – Defined Terms
ARTICLE 2 – Copies of Bidding Documents
ARTICLE 3 – Qualifications of Bidders
ARTICLE 4 – Site and Other Areas; Existing Site Conditions; Examination of Site; Owner’s Safety Program;
Other Work at the Site
ARTICLE 5 – Bidder’s Representations
ARTICLE 6 – Pre-Bid Conference
ARTICLE 7 – Interpretations and Addenda
ARTICLE 8 – Bid Security
ARTICLE 9 – Contract Times
ARTICLE 10 – Liquidated Damages
ARTICLE 11 – Substitute and “Or-Equal” Items
ARTICLE 12 – Subcontractors, Suppliers, and Others
ARTICLE 13 – Preparation of Bid
ARTICLE 14 – Basis of Bid
ARTICLE 15 – Submittal of Bid
ARTICLE 16 – Modification and Withdrawal of Bid
ARTICLE 17 – Opening of Bids
ARTICLE 18 – Bids to Remain Subject to Acceptance
ARTICLE 19 – Evaluation of Bids and Award of Contract
ARTICLE 20 – Bonds and Insurance
ARTICLE 21 – Signing of Agreement
ARTICLE 22 – Wage Rate Requirements
ARTICLE 23 – Disadvantage Business Enterpirse (DBE) Solicitation Requirements
ARTICLE 24 – Other State, Federal & Funding Agency Requirements
Page 00200-1 of 00200-9
This document was generated from the EJCDC® C-200 (Rev. 1), Suggested Instructions to Bidders for Construction Contracts. Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. The original form of this document has been modified herein for this specific project.
ARTICLE 1 – DEFINED TERMS
1.01 Terms used in these Instructions to Bidders have the meanings indicated in the General Conditions and Supplementary Conditions. Additional terms used in these Instructions to Bidders have the meanings indicated below:
A. Issuing Office – The office from which the Bidding Documents are to be issued.
ARTICLE 2 – COPIES OF BIDDING DOCUMENTS
2.01 Complete sets of the Bidding Documents may be obtained from the Issuing Office in the number and format stated in the invitation or advertisement to bid.
2.02 Complete sets of Bidding Documents shall be used in preparing Bids; neither Owner nor Engineer assumes any responsibility for errors or misinterpretations resulting from the use of incomplete sets of Bidding Documents.
2.03 Owner and Engineer, in making copies of Bidding Documents available on the above terms, do so only for the purpose of obtaining Bids for the Work and do not authorize or confer a license for any other use.
ARTICLE 3 – QUALIFICATIONS OF BIDDERS
3.01 To demonstrate Bidder’s qualifications to perform the Work, Bidder shall complete and submit with its Bid the Bidder Qualification Statement included with the Bidding Documents. In addition, within the times indicated in the General Conditions, as may be modified by the Supplementary
Conditions, Bidder shall submit a listing of proposed Subcontractors to be utilized on the project along with similar qualifications and responsibility information on all Subcontractors.
3.02 A Bidder’s failure to submit required qualification information within the times indicated may disqualify Bidder from receiving an award of the Contract.
3.03 No requirement in this Article 3 to submit information will prejudice the right of Owner to seek additional pertinent information regarding Bidder’s qualifications.
3.04 Bidder is advised to carefully review those portions of the Bid Form requiring Bidder’s representations and certifications.
3.05 In addition to the Bidder Qualification Statement, Bidder shall identify the firm and personnel proposed to perform CCTV, sonar, visual inspection, condition assessment, and reporting.
Personnel operating remote pipe inspection equipment shall possess current NASSCO Pipeline
Assessment Certification Program (PACP) certification, or an equivalent certification acceptable to Owner and Engineer, and shall demonstrate a minimum of one year of applicable pipe inspection experience. Bidder shall identify the proposed inspection team leader and provide a summary of experience on similar pipe, culvert, levee, or flood protection system inspection projects. Any professional engineering oversight required by the Contract Documents shall be provided by a Professional Engineer licensed in the Commonwealth of Pennsylvania.
Page 00200-2 of 00200-9
ARTICLE 4 – SITE AND OTHER AREAS; EXISTING SITE CONDITIONS; EXAMINATION OF SITE; OWNER’S
SAFETY PROGRAM; OTHER WORK AT THE SITE
4.01 Site and Other Areas
A. The Site is identified in the Bidding Documents and generally consists of the locations of City of Scranton-owned stormwater pipes and conduits identified for inspection within or adjacent to the Lackawanna River flood protection levee system. By definition, the Site includes rights-of-way, easements, and other lands made available by Owner for performance of the Work. Any additional areas or access required by Contractor for its equipment, vehicles, temporary facilities, or operations shall be the responsibility of
Contractor, unless otherwise indicated in the Contract Documents.
4.02 Existing Site Conditions
A. Subsurface and Physical Conditions; Hazardous Environmental Conditions
1. The Supplementary Conditions identify:
a. those reports known to Owner of explorations and tests of subsurface conditions at or adjacent to the Site.
b. those drawings known to Owner of physical conditions relating to existing surface or subsurface structures at the Site (except Underground Facilities).
c. reports and drawings known to Owner relating to Hazardous Environmental
Conditions that have been identified at or adjacent to the Site.
d. Technical Data contained in such reports and drawings.
2. Owner will make copies of reports and drawings referenced above available to any
Bidder on request. These reports and drawings are not part of the Contract Documents, but the Technical Data contained therein upon whose accuracy Bidder is entitled to rely, as provided in the General Conditions, has been identified and established in the
Supplementary Conditions. Bidder is responsible for any interpretation or conclusion
Bidder draws from any Technical Data or any other data, interpretations, opinions, or information contained in such reports or shown or indicated in such drawings. Bidder is responsible for all reproduction costs associated with requested reports and drawings.
3. If the Supplementary Conditions do not identify Technical Data, the default definition of
Technical Data set forth in Article 1 of the General Conditions will apply.
B. Underground Facilities: Information and data shown or indicated in the Bidding Documents with respect to existing Underground Facilities at or adjacent to the Site are set forth in the
Contract Documents and are based upon information and data furnished to Owner and
Engineer by owners of such Underground Facilities, including Owner, or others.
C. Adequacy of Data: Provisions concerning responsibilities for the adequacy of data furnished to prospective Bidders with respect to subsurface conditions, other physical conditions, and
Underground Facilities, and possible changes in the Bidding Documents due to differing or unanticipated subsurface or physical conditions appear in Paragraphs 5.03, 5.04, and 5.05 of the General Conditions. Provisions concerning responsibilities for the adequacy of data furnished to prospective Bidders with respect to a Hazardous Environmental Condition at the
Site, if any, and possible changes in the Contract Documents due to any Hazardous
Environmental Condition uncovered or revealed at the Site which was not shown or indicated
Page 00200-3 of 00200-9 in the Drawings or Specifications or identified in the Contract Documents to be within the scope of the Work, appear in Paragraph 5.06 of the General Conditions.
4.03 Site Visit and Testing by Bidders
A. Bidder shall conduct the required Site visit during normal working hours, and shall not disturb any ongoing operations at the Site.
B. Bidder is responsible to obtain such additional or supplementary examinations, investigations, test borings, explorations, tests, studies and data concerning conditions
(surface, subsurface and underground facilities) at or contiguous to the Site or otherwise, which may affect (1) the cost, progress, and performance of the Work; (2) the means, methods, techniques, sequences, and procedures of construction to be employed by Bidder, including applying any specific means, methods, techniques, sequences, and procedures of construction expressly required by the Bidding Documents; and (3) Bidder’s safety precautions and programs or which the Bidder deems necessary to assume all risks in excavating for the Project and determine its bid for the Work.
C. On request, and to the extent Owner has control over the Site, and schedule permitting, the
Owner will provide Bidder access to the Site to conduct such additional examinations, investigations, explorations, tests, and studies as Bidder deems necessary for preparing and submitting a successful Bid. Owner will not have any obligation to grant such access if doing so is not practical because of existing operations, security or safety concerns, or restraints on
Owner’s authority regarding the Site.
D. Bidder shall comply with all applicable Laws and Regulations regarding excavation and location of utilities, obtain all permits, and comply with all terms and conditions established by Owner or by property owners or other entities controlling the Site with respect to schedule, access, existing operations, security, liability insurance, and applicable safety programs.
E. Bidder shall fill all holes and clean up and restore the Site to its former condition upon completion of such explorations, investigations, tests, and studies.
4.04 Owner’s Safety Program
A. Site visits and work at the Site may be governed by an Owner safety program. As the General
Conditions indicate, if an Owner safety program exists, it will be noted in the Supplementary
Conditions.
4.05 Other Work at the Site
A. Reference is made to Article 8 of the Supplementary Conditions for the identification of the general nature of other work of which Owner is aware (if any) that is to be performed at the
Site by Owner or others (such as utilities and other prime contractors) and relates to the
Work contemplated by these Bidding Documents. If Owner is party to a written contract for such other work, then on request, Owner will provide to each Bidder access to examine such contracts (other than portions thereof related to price and other confidential matters), if any.
ARTICLE 5 – BIDDER’S REPRESENTATIONS
5.01 It is the responsibility of each Bidder before submitting a Bid to:
A. examine and carefully study the Bidding Documents, and any data and reference items identified in the Bidding Documents;
Page 00200-4 of 00200-9
B. visit the Site, conduct a thorough, alert visual examination of the Site and adjacent areas, and become familiar with and satisfy itself as to the general, local, and Site conditions that may affect cost, progress, and performance of the Work;
C. become familiar with and satisfy itself as to all Laws and Regulations that may affect cost, progress, and performance of the Work;
D. carefully study all: (1) reports of explorations and tests of subsurface conditions at or adjacent to the Site and all drawings of physical conditions relating to existing surface or subsurface structures, if any, at the Site that have been identified in the Supplementary
Conditions, especially with respect to Technical Data in such reports and drawings, and (2) reports and drawings relating to Hazardous Environmental Conditions, if any, at or adjacent to the Site that have been identified in the Supplementary Conditions, especially with respect to Technical Data in such reports and drawings;
E. consider the information known to Bidder itself; information commonly known to contractors doing business in the locality of the Site; information and observations obtained from visits to the Site; the Bidding Documents; and the Site-related reports and drawings, if any, identified in the Bidding Documents, with respect to the effect of such information, observations, and documents on (1) the cost, progress, and performance of the Work; (2) the means, methods, techniques, sequences, and procedures of construction to be employed by Bidder; and (3) Bidder’s safety precautions and programs;
F. obtain such additional or supplementary examinations, investigations, test borings, explorations, tests, studies and data concerning conditions (surface, subsurface and underground facilities) at or contiguous to the Site or otherwise, which may affect (1) the cost, progress, and performance of the Work; (2) the means, methods, techniques, sequences, and procedures of construction to be employed by Bidder, including applying any specific means, methods, techniques, sequences, and procedures of construction expressly required by the Bidding Documents; and (3) Bidder’s safety precautions and programs or which Bidder deems necessary to assume all risks in excavating for the Project and determine its bid for the Work;
G. agree, based on the information and observations referred to in the preceding paragraphs, that at the time of submitting its Bid no further examinations, investigations, explorations, tests, studies, or data are necessary for the determination of its Bid for performance of the
Work at the price bid and within the times required, and in accordance with the other terms and conditions of the Bidding Documents;
H. become aware of the general nature of the work to be performed by Owner and others at the Site that relates to the Work as indicated in the Bidding Documents;
I. promptly give Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Bidder discovers in the Bidding Documents and confirm that the written resolution thereof by Engineer is acceptable to Bidder;
J. determine that the Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for the performance and furnishing of the Work;
and
K. agree that the submission of a Bid will constitute an incontrovertible representation by
Bidder that Bidder has complied with every requirement of this Article, that without exception the Bid and all prices in the Bid are premised upon performing and furnishing the
Work required by the Bidding Documents.
Page 00200-5 of 00200-9
ARTICLE 6 – PRE-BID CONFERENCE
6.01 Pre-Bid conference requirements and details are stated in the invitation or advertisement to bid.
If a conference is planned and listed as mandatory in the invitation or advertisement to bid, Bids will not be accepted from any Bidder that did not attend the mandatory conference.
ARTICLE 7 – INTERPRETATIONS AND ADDENDA
7.01 Refer to Project ID on the City of Scranton portal, Procurement Portal (opengov.com), 2. General
Information, 3. General Conditions and 5. Proposal Requirements.
7.02 Addenda may be issued to clarify, correct, supplement, or change the Bidding Documents.
ARTICLE 8 – BID SECURITY
8.01 A Bid must be accompanied by Bid security made payable to Owner in an amount of 10 percent of Bidder’s total of all Bid prices for each bid (not including bid alternates) and in the form of a certified check, bank money order, or a Bid bond (on the form included in the Bidding Documents) issued by a surety meeting the requirements of Paragraphs 6.01 and 6.02 of the General
Conditions.
8.02 The Bid security of the apparent Successful Bidder will be retained until Owner awards the contract to such Bidder, and such Bidder has executed the Contract Documents, furnished the required contract security, and met the other conditions of the Notice of Award, whereupon the
Bid security will be released. If the Successful Bidder fails to execute and deliver the Contract
Documents and furnish the required contract security within 10 days after the Notice of Award, Owner may consider Bidder to be in default, annul the Notice of Award, and the Bid security of that Bidder will be forfeited. Such forfeiture shall be Owner’s exclusive remedy if Bidder defaults.
8.03 The Bid security of other Bidders that Owner believes to have a reasonable chance of receiving the award may be retained by Owner until the earlier of seven days after the Effective Date of the
Contract or 61 days after the Bid opening, whereupon Bid security furnished by such Bidders will be released.
8.04 Bid security of other Bidders that Owner believes do not have a reasonable chance of receiving the award will be released within seven days after the Bid opening.
ARTICLE 9 – CONTRACT TIMES
9.01 The number of days within which, or the dates by which, Milestones are to be achieved and the
Work is to be substantially completed, and completed and ready for final payment, are set forth in the Agreement.
ARTICLE 10 – LIQUIDATED DAMAGES
10.01 Provisions for liquidated damages, if any, for failure to timely attain a Milestone, Substantial
Completion, or completion of the Work in readiness for final payment, are set forth in the
Agreement.
ARTICLE 11 – SUBSTITUTE AND “OR-EQUAL” ITEMS
11.01 The Contract for the Work, as awarded, will be on the basis of materials and equipment specified or described in the Bidding Documents without consideration during the bidding and Contract award process of possible substitute or “or-equal” items. In cases in which the Contract allows
Page 00200-6 of 00200-9 the Contractor to request that Engineer authorize the use of a substitute or “or-equal” item of material or equipment, application for such acceptance may not be made to and will not be considered by Engineer until after the Effective Date of the Contract.
11.02 All prices that Bidder sets forth in its Bid shall be based on the presumption that the Contractor will furnish the materials and equipment specified or described in the Bidding Documents, as supplemented by Addenda. Any assumptions regarding the possibility of post-Bid approvals of
“or-equal” or substitution requests are made at Bidder’s sole risk.
ARTICLE 12 – SUBCONTRACTORS, SUPPLIERS, AND OTHERS
12.01 A Bidder shall be prepared to retain specific Subcontractors, Suppliers, or other individuals or entities for the performance of the Work if required by the Bidding Documents (most commonly in the Specifications) to do so. If a prospective Bidder objects to retaining any such Subcontractor, Supplier, or other individual or entity, and the concern is not relieved by an Addendum, then the prospective Bidder should refrain from submitting a Bid.
12.02 Subsequent to the submittal of the Bid, Owner may not require the Successful Bidder or
Contractor to retain any Subcontractor, Supplier, or other individual or entity against which
Contractor has reasonable objection.
12.03 The apparent Successful Bidder, and any other Bidder so requested, shall within five days after
Bid opening, submit to Owner a list of the Subcontractors or Suppliers proposed for the various portions of the Work. If requested by Owner, such list shall be accompanied by an experience statement with pertinent information regarding similar projects and other evidence of qualification for each such Subcontractor, Supplier, or other individual or entity. If Owner or
Engineer, after due investigation, has reasonable objection to any proposed Subcontractor, Supplier, individual, or entity, Owner may, before the Notice of Award is given, request apparent
Successful Bidder to submit an acceptable substitute, without an increase in Bid price.
12.04 If apparent Successful Bidder declines to make any such substitution, Owner may award the
Contract to the next lowest Bidder that proposes to use acceptable Subcontractors, Suppliers, or other individuals or entities. Declining to make requested substitutions will not constitute grounds for forfeiture of the Bid security of any Bidder. Any Subcontractor, Supplier, individual, or entity so listed and against which Owner or Engineer makes no written objection prior to the giving of the Notice of Award will be deemed acceptable to Owner and Engineer subject to subsequent revocation of such acceptance as provided in Paragraph 7.06 of the General Conditions.
ARTICLE 13 – PREPARATION OF BID
13.01 The Bid Pricing Table shall be uploaded to the City of Scranton portal, Procurement Portal
(opengov.com)
13.02 A Bid by a corporation shall be executed in the corporate name by a corporate officer (whose title must appear under the signature), accompanied by evidence of authority to sign. The corporate seal shall be affixed and attested by the corporate secretary or an assistant corporate secretary.
The corporate address and state of incorporation shall be shown.
13.03 A Bid by a partnership shall be executed in the partnership name and signed by a partner (whose title must appear under the signature), accompanied by evidence of authority to sign. The partnership’s address for receiving notices shall be shown.
13.04 A Bid by a limited liability company shall be executed in the name of the firm by a member or other authorized person and accompanied by evidence of authority to sign. The state of formation of the firm and the firm’s address for receiving notices shall be shown.
Page 00200-7 of 00200-9
13.05 A Bid by an individual shall show the Bidder’s name and address for receiving notices.
13.06 A Bid by a joint venture shall be executed by an authorized representative of each joint venturer in the manner indicated on the Bid Form. The joint venture’s address for receiving notices shall be shown.
13.07 All names shall be printed in ink below the signatures.
13.08 The Bid shall contain an acknowledgment of receipt of all Addenda, the numbers of which shall be filled in on the Bid Form.
13.09 Postal and e-mail addresses and telephone number for communications regarding the Bid shall be shown.
ARTICLE 14 – BASIS OF BID
14.01 Unit Price
A. Bidders shall submit a Bid on a unit price basis for each item of Work listed in the unit price section of the Bid Form.
B. The “Bid Price” (sometimes referred to as the extended price) for each unit price Bid item will be the product of the “Estimated Quantity” (which Owner or its representative has set forth in the Bid Form) for the item and the corresponding “Bid Unit Price” offered by the
Bidder. The total of all unit price Bid items will be the sum of these “Bid Prices”; such total will be used by Owner for Bid comparison purposes. The final quantities and Contract Price will be determined in accordance with Paragraph 13.03 of the General Conditions.
ARTICLE 15 – SUBMITTAL OF BID
15.01 With each copy of the Bidding Documents, a Bidder is furnished one separate unbound copy of the Bid Form, and, if required, the Bid Bond Form. The unbound copy of the Bid Form is to be completed and submitted with the Bid security and the other documents required to be submitted under the terms of Article 7 of the Bid Form.
15.02 A Bid shall be received no later than the date and time prescribed and at the place indicated in the invitation or advertisement to bid and shall be enclosed in a plainly marked package with the
Project title, the name and address of Bidder, and shall be accompanied by the Bid security and other required documents. If a Bid is sent by mail or other delivery system, the sealed envelope containing the Bid shall be enclosed in a separate package plainly marked on the outside with the notation “BID ENCLOSED.” A mailed Bid shall be addressed as described in the invitation or advertisement to bid.
15.03 Bids received after the date and time prescribed for the opening of bids, or not submitted at the correct location or in the designated manner, will not be accepted and will be returned to the
Bidder unopened.
ARTICLE 16 – MODIFICATION AND WITHDRAWAL OF BID
16.01 A Bid may be withdrawn by an appropriate document duly executed in the same manner that a
Bid must be executed and delivered to the place where Bids are to be submitted at least sixty minutes prior to the date and time for the opening of Bids. Upon receipt of such notice, the unopened Bid will be returned to the Bidder.
Page 00200-8 of 00200-9
16.02 If a Bidder wishes to modify its Bid prior to Bid opening, Bidder must withdraw its initial Bid in the manner specified in Paragraph 16.01 and submit a new Bid prior to the date and time for the opening of Bids.
16.03 If within 24 hours after Bids are opened any Bidder files a duly signed written notice with Owner and promptly thereafter demonstrates to the reasonable satisfaction of Owner that there was a material and substantial mistake in the preparation of its Bid, that Bidder may withdraw its Bid, and the Bid security will be returned. Thereafter, if the Work is rebid, that Bidder will be disqualified from further bidding on the Work.
ARTICLE 17 – OPENING OF BIDS
17.01 Bids will be opened at the time and place indicated in the invitation or advertisement to bid and, unless obviously non-responsive, read aloud publicly. An abstract of the amounts of the base Bids and major alternates, if any, will be made available to Bidders after the opening of Bids.
ARTICLE 18 – BIDS TO REMAIN SUBJECT TO ACCEPTANCE
18.01 All Bids will remain subject to acceptance for the period of time stated in the Bid Form, but Owner may, in its sole discretion, release any Bid and return the Bid security prior to the end of this period.
ARTICLE 19 – EVALUATION OF BIDS AND AWARD OF CONTRACT
19.01 Owner reserves the right to reject any or all Bids, including without limitation, nonconforming, nonresponsive, unbalanced, or conditional Bids. Owner will reject the Bid of any Bidder that
Owner finds, after reasonable inquiry and evaluation, to not be responsible. If Bidder purports to add terms or conditions to its Bid, takes exception to any provision of the Bidding Documents, or attempts to alter the contents of the Contract Documents for purposes of the Bid, then the Owner will reject the Bid as nonresponsive; provided that Owner also reserves the right to waive all minor informalities not involving price, time, or changes in the Work.
19.02 If Owner awards the contract for the Work, such award shall be to the responsible Bidder submitting the lowest responsive Bid.
19.03 Evaluation of Bids
A. In evaluating Bids, Owner will consider whether or not the Bids comply with the prescribed requirements, and such alternates, unit prices, and other data, as may be requested in the
Bid Form or prior to the Notice of Award.
B. For the determination of the apparent low Bidder when unit price bids are submitted, Bids will be compared on the basis of the total of the products of the estimated quantity of each item and unit price Bid for that item, together with any lump sum items.
C. In the comparison of Bids, alternates will be applied in an order of priority as established solely by Owner. After determination of the Successful Bidder based on this comparative process and on the responsiveness, responsibility, and other factors set forth in these
Instructions, the award may be made to said Successful Bidder on its base Bid and the combination of its additive alternate Bids as established by Owner.
19.04 In evaluating whether a Bidder is responsible, Owner will consider the qualifications of the Bidder and may consider the qualifications and experience of Subcontractors and Suppliers proposed for those portions of the Work for which the identity of Subcontractors and Suppliers must be submitted as provided in the Bidding Documents.
Page 00200-9 of 00200-9
19.05 Owner may conduct such investigations as Owner deems necessary to establish the responsibility, qualifications, and financial ability of Bidders and any proposed Subcontractors or Suppliers.
ARTICLE 20 – BONDS AND INSURANCE
20.01 Refer to City of Scranton RFP, 3. General Conditions, Q. Proposal Insurance Requirements.
ARTICLE 21 – SIGNING OF AGREEMENT
21.01 When Owner issues a Notice of Award to the Successful Bidder, it shall be accompanied by the unexecuted counterparts of the Agreement along with the other Contract Documents as identified in the Agreement. Within 10 days thereafter, Successful Bidder shall execute and deliver the required number of counterparts of the Agreement (and any bonds and insurance documentation required to be delivered by the Contract Documents) to Owner. Within ten days thereafter, Owner shall deliver one fully executed counterpart of the Agreement to Successful
Bidder, together with printed and electronic copies of the Contract Documents as stated in
Paragraph 2.02 of the General Conditions.
ARTICLE 22 – WAGE RATE REQUIREMENTS
22.01 Refer to Section 00840 for any wage rate requirements applicable to this contract.
ARTICLE 23 – DISADVANTAGE BUSINESS ENTERPIRSE (DBE) SOLICITATION REQUIREMENTS
23.01 Refer to City of Scranton’s Construction Service Agreement for any Disadvantaged Business
Enterprise (DBE) solicitation requirements.
ARTICLE 24 – OTHER STATE, FEDERAL & FUNDING AGENCY REQUIREMENTS
24.01 Refer to Section 00820 for any other State, Federal or Funding Agency requirements.
Form of Agreement Between Owner and Contractor for Construction Contract (Stipulated Price)
Page 00520-1 of 00520-8
FORM OF AGREEMENT
BETWEEN OWNER AND CONTRACTOR
FOR CONSTRUCTION CONTRACT (STIPULATED PRICE)
THIS AGREEMENT is by and between City of Scranton (“Owner”) and
(“Contractor”).
Owner and Contractor hereby agree as follows:
ARTICLE 1 – WORK
1.01 Contractor shall complete all Work as specified or indicated in the Contract Documents.
The Work is generally described as follows: Furnishing all labor, supervision, equipment, materials, transportation, access equipment, inspection equipment, traffic control, mobilization, and demobilization and incidentals necessary to inspect and document City of Scranton-owned stormwater pipes penetrating through or beneath the Lackawanna
River flood protection levee system. Work includes CCTV inspection, sonar inspection where required, visual inspection where applicable, necessary pipe cleaning as authorized, condition assessment and PACP coding, location documentation, and preparation of inspection videos, photographs, logs, reports, maps, and other deliverables required by the Contract Documents and applicable United States Army
Corps of Engineers requirements.
ARTICLE 2 – THE PROJECT
2.01 The Project, of which the Work under the Contract Documents is a part, is generally described as follows: City of Scranton Levee Pipe Penetration Inspection Project -inspection and documentation of City-owned stormwater pipe penetrations associated with the Lackawanna River flood protection system.
ARTICLE 3 – ENGINEER
3.01 The part of the Project that pertains to the Work has been designed by Reilly Associates.
3.02 The Owner has retained Reilly Associates (“Engineer”) to act as Owner’s representative/
Engineer shall assume all duties and responsibilities, and have the rights and authority assigned to Engineer in the Contract Documents in connection with the completion of the Work in accordance with the Contract Documents.
ARTICLE 4 – CONTRACT TIMES
4.01 Time of the Essence
A. All time limits for Milestones, if any, Substantial Completion, and completion and readiness for final payment as stated in the Contract Documents are of the essence of the Contract.
4.02 Contract Times: Milestone
A. Parts of the Work will be substantially on or before the following Milestone.
Page 00520-2 of 00520-8
1. Milestone 1: Complete all required field inspection activities within 120 calendar days following the Notice to Proceed.
2. Milestone 2: Submit complete final inspection reports and all required electronic deliverables within twenty-one (21) calendar days following completion of the field inspection activities.
4.03 Liquidated Damages
A. Contractor and Owner recognize that time is of the essence as stated in Paragraph 4.01 above and that Owner will suffer financial and other losses if the Work is not completed and Milestones not achieved within the times specified in Paragraph 4.02 above, plus any extensions thereof allowed in accordance with the Contract. The parties also recognize the delays, expense, and difficulties involved in proving in a legal or arbitration proceeding the actual loss suffered by Owner if the Work is not completed on time. Accordingly, instead of requiring any such proof, Owner and Contractor agree that as liquidated damages for delay
(but not as a penalty):
1. Substantial Completion: Contractor shall pay Owner $_500______ for each day that expires after the time (as duly adjusted pursuant to the Contract) specified in
Paragraph 4.02.A above for Substantial Completion until the Work is substantially complete.
2. Completion of Remaining Work: After Substantial Completion, if Contractor shall neglect, refuse, or fail to complete the remaining Work within the Contract Times (as duly adjusted pursuant to the Contract) for completion and readiness for final payment, Contractor shall pay Owner $___500____ for each day that expires after such time until the Work is completed and ready for final payment.
3. Liquidated damages for failing to timely attain Substantial Completion and final completion are not additive and will not be imposed concurrently.
ARTICLE 5 – CONTRACT PRICE
5.01 Owner shall pay Contractor for completion of the Work in accordance with the Contract
Documents the amounts that follow, subject to adjustment under the Contract:
A. For all Work, at the prices stated in Contractor’s Bid, attached hereto as an exhibit.
ARTICLE 6 – PAYMENT PROCEDURES
6.01 Submittal and Processing of Payments
A. Contractor shall submit Applications for Payment in accordance with Article 15 of the
General Conditions. Applications for Payment will be processed by Engineer as provided in the General Conditions.
6.02 Progress Payments; Retainage
A. Owner shall make progress payments on account of the Contract Price on the basis of
Contractor’s Applications for Payment on or about the 2nd Tuesday of each month during performance of the Work as provided in Paragraph 6.02.A.1 below, provided that such
Applications for Payment have been submitted in a timely manner and otherwise meet the requirements of the Contract. All such payments will be measured by the Schedule of
Values established as provided in the General Conditions (and in the case of Unit Price
Page 00520-3 of 00520-8
Work based on the number of units completed) or, in the event there is no Schedule of
Values, as provided elsewhere in the Contract.
1. Prior to Substantial Completion, progress payments will be made in an amount equal to the percentage indicated below but, in each case, less the aggregate of payments previously made and less such amounts as Owner may withhold, including but not limited to liquidated damages, in accordance with the Contract.
a. 90 percent of Work completed (with the balance being retainage). If the Work has been 50 percent completed as determined by Engineer, and if the character and progress of the Work have been satisfactory to Owner and Engineer, then as long as the character and progress of the Work remain satisfactory to Owner and
Engineer, the retainage may be reduced to 5 percent; and
b. 90 percent of cost of materials and equipment not incorporated in the Work (with the balance being retainage) provided the quantity of stored material does not exceed the total estimated quantity required to complete the project, the cost is at least $1,000 but does not exceed 90 percent of the contract price of the applicable contract item and/or component item, and the accumulative costs do not exceed 25 percent of the current contract amount. The cost of the material is that amount to be paid by the Contractor as evidenced by invoices. Fabricated structural steel that is to receive a protective coating may be approved for prepayment at 75 percent of the contract price of the applicable contract item, before application of the coating, provided the structure has been fully fabricated and preassembly of field connections has been made.
B. Upon Substantial Completion, Owner shall pay an amount sufficient to increase total payments to Contractor to 100 percent of the Work completed, less such amounts set off by Owner pursuant to Paragraph 15.01.E of the General Conditions, and less 150 percent of
Engineer’s estimate of the value of Work to be completed or corrected as shown on the punch list of items to be completed or corrected prior to final payment.
6.03 Final Payment
A. Upon final completion and acceptance of the Work in accordance with Paragraph 15.06 of the General Conditions, Owner shall pay the remainder of the Contract Price as recommended by Engineer as provided in said Paragraph 15.06.
ARTICLE 7 – INTEREST
7.01 All amounts not paid when due shall bear interest at the rate of 0.5 percent plus the
Federal short-term rate as determined under Title 26, Subtitle F, Chapter 67, Subchapter
C, § 6621 of the U.S. Code.
A. Contractor has been prequalified by Pennsylvania Department of Transportation as a prime contractor.
ARTICLE 8 – CONTRACTOR’S REPRESENTATIONS
8.01 In order to induce Owner to enter into this Contract, Contractor makes the following representations:
A. Contractor has examined and carefully studied the Contract Documents, and any data and reference items identified in the Contract Documents.
Page 00520-4 of 00520-8
B. Contractor has visited the Site, conducted a thorough, alert visual examination of the Site and adjacent areas, and become familiar with and is satisfied as to the general, local, and
Site conditions that may affect cost, progress, and performance of the Work.
C. Contractor is familiar with and is satisfied as to all Laws and Regulations that may affect cost, progress, and performance of the Work.
D. Contractor has carefully studied all: (1) reports of explorations and tests of subsurface conditions at or adjacent to the Site and all drawings of physical conditions relating to existing surface or subsurface structures, if any, at the Site that have been identified in the
Supplementary Conditions, especially with respect to Technical Data in such reports and drawings, and (2) reports and drawings relating to Hazardous Environmental Conditions, if any, at or adjacent to the Site that have been identified in the Supplementary Conditions, especially with respect to Technical Data in such reports and drawings.
E. Contractor has considered the information known to Contractor itself; information commonly known to contractors doing business in the locality of the Site; information and observations obtained from visits to the Site; the Contract Documents; and the Site-related reports and drawings, if any, identified in the Contract Documents, with respect to the effect of such information, observations, and documents on (1) the cost, progress, and performance of the Work; (2) the means, methods, techniques, sequences, and procedures of construction to be employed by Contractor; and (3) Contractor’s safety precautions and programs.
F. Contractor has obtained such additional or supplementary examinations, investigations, test borings, explorations, tests, studies and data concerning conditions (surface, subsurface and underground facilities) at or contiguous to the Site or otherwise, which may affect (1) the cost, progress, and performance of the Work; (2) the means, methods, techniques, sequences, and procedures of construction to be employed by Contractor, including applying any specific means, methods, techniques, sequences, and procedures of construction expressly required by the Contractor Documents; and (3) Contractor’s safety precautions and programs or which Contractor deems necessary to assume all risks in excavating for the Project and determine its bid for the Work.
G. Based on the information and observations referred to in the preceding paragraphs, Contractor agrees that no further examinations, investigations, explorations, tests, studies, or data are necessary for the performance of the Work at the Contract Price, within the
Contract Times, and in accordance with the other terms and conditions of the Contract.
H. Contractor is aware of the general nature of work to be performed by Owner and others at the Site that relates to the Work as indicated in the Contract Documents.
I. Contractor has given Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Contractor has discovered in the Contract Documents, and the written resolution thereof by Engineer is acceptable to Contractor.
J. The Contract Documents are generally sufficient to indicate and convey understanding of all terms and conditions for performance and furnishing of the Work.
K. Contractor’s entry into this Contract constitutes an incontrovertible representation by Contractor that without exception all prices in the Agreement are premised upon performing and furnishing the Work required by the Contract Documents.
Page 00520-5 of 00520-8
ARTICLE 9 – CONTRACT DOCUMENTS
9.01 Contents
A. The Contract Documents consist of the following:
1. This Agreement (pages 00520-1 to 00520-7_, inclusive).
2. Performance bond (pages 00610-1 to 00610-3, inclusive).
3. Payment bond (pages 00615-1 to 00615-3, inclusive).
4. Other bonds.
a. None
5. General Conditions (pages 00700-1 to 00700-65, inclusive) (not attached but incorporated by reference).
6. Supplementary Conditions (pages 00800-1 to 00800-_16__, inclusive) (not attached but incorporated by reference).
7. Additional State, Federal or Funding Agency Requirements (pages 00820-1 to 00820-
_5__, inclusive) (not attached but incorporated by reference).
8. Permits as listed in the table of contents of the Project Manual (not attached but incorporated by reference). None.
9. Wage Rate Requirements (pages 00840-1 to 00840-15, inclusive) (not attached but incorporated by reference).
10. Specifications as listed in the table of contents of the Project Manual (not attached but incorporated by reference).
11. The Drawings as listed in the table of contents of the Project Manual (not attached but incorporated by reference).
12. The Appendices as listed in the table of contents of the Project Manual (not attached but incorporated by reference).
13. Addenda (numbers __ to ___, inclusive).
14. Exhibits to this Agreement (enumerated as follows): _________
15. The following which may be delivered or issued on or after the Effective Date of the
Contract and are not attached hereto:
a. Notice to Proceed.
b. Contractor’s Application for Payment
c. Certificate of Substantial Completion
d. Consent of Surety to Final Payment
e. Work Change Directives.
f. Change Orders.
g. Field Orders.
B. The documents listed in Paragraph 9.01.A are attached to this Agreement (except as expressly noted otherwise above).
C. There are no Contract Documents other than those listed above in this Article 9.
Page 00520-6 of 00520-8
D. The Contract Documents may only be amended, modified, or supplemented as provided in the General Conditions.
ARTICLE 10 – MISCELLANEOUS
10.01 Terms
A. Terms used in this Agreement will have the meanings stated in the General Conditions and the Supplementary Conditions.
10.02 Assignment of Contract
A. Unless expressly agreed to elsewhere in the Contract, no assignment by a party hereto of any rights under or interests in the Contract will be binding on another party hereto without the written consent of the party sought to be bound; and, specifically but without limitation, money that may become due and money that is due may not be assigned without such consent (except to the extent that the effect of this restriction may be limited by law), and unless specifically stated to the contrary in any written consent to an assignment, no assignment will release or discharge the assignor from any duty or responsibility under the Contract Documents.
10.03 Successors and Assigns
A. Owner and Contractor each binds itself, its successors, assigns, and legal representatives to the other party hereto, its successors, assigns, and legal representatives in respect to all covenants, agreements, and obligations contained in the Contract Documents.
10.04 Severability
A. Any provision or part of the Contract Documents held to be void or unenforceable under any Law or Regulation shall be deemed stricken, and all remaining provisions shall continue to be valid and binding upon Owner and Contractor, who agree that the Contract
Documents shall be reformed to replace such stricken provision or part thereof with a valid and enforceable provision that comes as close as possible to expressing the intention of the stricken provision.
10.05 Contractor’s Certifications
A. Contractor certifies that it has not engaged in corrupt, fraudulent, collusive, or coercive practices in competing for or in executing the Contract. For the purposes of this Paragraph
10.05:
1. “corrupt practice” means the offering, giving, receiving, or soliciting of any thing of value likely to influence the action of a public official in the bidding process or in the
Contract execution;
2. “fraudulent practice” means an intentional misrepresentation of facts made (a) to influence the bidding process or the execution of the Contract to the detriment of
Owner, (b) to establish Bid or Contract prices at artificial non-competitive levels, or (c) to deprive Owner of the benefits of free and open competition;
3. “collusive practice” means a scheme or arrangement between two or more Bidders, with or without the knowledge of Owner, a purpose of which is to establish Bid prices at artificial, non-competitive levels; and
4. “coercive practice” means harming or threatening to harm, directly or indirectly, persons or their property to influence their participation in the bidding process or affect the execution of the Contract.
Page 00520-7 of 00520-8
Page 00520-8 of 00520-8
IN WITNESS WHEREOF, Owner and Contractor have signed this Agreement.
This Agreement will be effective on __________ (which is the Effective Date of the Contract).
OWNER: CONTRACTOR:
City of Scranton
By: By:
Title: Title:
(If Contractor is a corporation, a partnership, or a joint venture, attach evidence of authority to sign.)
Attest: Attest:
Title: Title:
Address for giving notices: Address for giving notices:
(If Owner is a corporation, attach evidence of authority to sign. If Owner is a public body, attach evidence of authority to sign and resolution or other documents authorizing execution of this Agreement.)
The Form of Agreement document was generated from the EJCDC® C-520 (Rev. 1), Agreement Between
Owner and Contractor for Construction Contract (Stipulated Price). Copyright © 2013 National Society of
Professional Engineers, American Council of Engineering Companies, and American Society of Civil
Engineers. All rights reserved. The original form of this document has been modified herein for this specific project.
Supplementary Conditions
Page 00800-i
SUPPLEMENTARY CONDITIONS
Page
SC- 2.02 Copies of Documents
SC- 2.03 Before Starting Construction
SC- 2.05…