Bellevue Pond Dam Rehabilitation
Closed State & local contract opportunity Posted
- Solicitation number
- Not Provided
- State
- Massachusetts
- Responses due
Opportunity facts
- Jurisdiction
- Points of contact
-
- purchasing@netwonma.gov (617) 796-1440
- Stephen McDonald mcdonalds@worcesterma.gov (508) 929-1300
- Joseph Donahue donahuejm@bwsc.org (617) 989-7213
- Christopher DeTurk christopher.deturk@mass.gov (957) 378-1771
- Jaime Flores jflores@townofwestspringfield.org (413) 495-1732
Opportunity details come from constructionbidsource.com. Updated .
About this opportunity
The City of Newton's Water and Sewer Commission is requesting bids for water main rehabilitation construction at various locations throughout Newton, Massachusetts, with bids due October 15, 2026.
The scope comprises approximately 8,830 linear feet of 8-inch diameter ductile iron water main and approximately 610 linear feet of 6-inch diameter ductile iron water main, along with associated valves, fittings, hydrants, water services, and temporary bypass piping. Work is distributed across eleven streets: Champa Street, Fellsmere Road, Dolphin Road, Mandalay Road, Woodcliff Road, Aspen Avenue, Studio Road, Minot Place, Cheney Street, Cheney Court, and Southwick Road in Newton.
The Project Manual (27-17 and 27-19) establishes detailed specifications, technical requirements, and construction standards governing execution, including material specifications, testing requirements, performance standards, bidding procedures, and contract terms. Bidders must review all provisions in the project manual before submitting sealed bids.
No estimated contract value, incumbent contractor, evaluation criteria, question deadline, pre-bid meeting, or site-visit date is identified in the posted materials.
Opportunity text
5 versions
Update #5 · Latest ·
The project consists of repairs to the existing weir, stoplog bay, spillway structure, culvert pipe, headwalls, and training walls that have deteriorated over time. Repairs will restore its original function to maintain the pond elevation and control flow through the structure before exiting the culvert. Additionally, the walking path north of the dam has become degraded due to erosion from storm events. The proposed work will improve the path to mitigate future erosion, which will result in safe, level, and defined walking paths and will mitigate the potential for sediment to travel from eroding paths to the pond. Bidders must be pre-qualified by the Massachusetts Dept. of Transportation (MassDOT) Highway Division in Dam Construction to bid.
Update #4 ·
The Town of West Springfield, through its Central Maintenance Department, is seeking sealed bids from qualified contractors (Sub-Bids) for the building of a pre-engineered building to be built in conjunction with the Improvements to Mittineague Park, East Entrance project. Filed sub-bidders must be DCAMM certified for the trades listed below and bidders must include a current DCAMM Sub-Bidder Certificate of Eligibility and a signed DCAMM Sub-Bidders Update Statement. Masonry Painting Plumbing Electrical
Update #3 ·
The Boston Water & Sewer Commission intends to hire a company which will provide professional cleaning services for its Headquarters Building, 980 Harrison Avenue, Boston, Massachusetts and Material Handling Facility, 180-220 Alford Street, Boston, Massachusetts including offices, workstations and common areas throughout the buildings. See attached for detailed requirements.
Update #2 ·
The Project scope includes furnishing of labor, materials, equipment, and supervision necessary for the servicing of plumbing related equipment at Union Station which is managed by the Worcester Development Authority (WRA). DCAMM requirement: Plumbing.
Update #1 ·
The work under this contract generally consists of the construction of approximately 8,830 linear feet of 8-inch diameter and approximately 610 linear feet of 6-inch diameter ductile iron water main including associated valves, fittings, hydrants, water services, and temporary bypass piping. The work under this contract will take place on Champa Street, Fellsmere Road, Dolphin Road, Mandalay Road, Woodcliff Road, Aspen Avenue, Studio Road, Minot Place, Cheney Street, Cheney Court, and Southwick Road in Newton, Massachusetts.