About this opportunity
The State of Arizona is seeking a sole source contract extension with Ark Data Centers (formerly Involta) for a critical disaster recovery data center site located in Tucson. The procurement is specifically focused on securing a fully operational data center that meets stringent technical and infrastructure requirements for state agency business continuity. Detailed assessments conducted per ANSI/BICSI 002-2014 standards have identified specific critical infrastructure needs, including a minimum 66-foot separation for power and carrier connections, multiple meet-me rooms (MMRs), low flood risk, and carrier diversity that matches the state's existing Phoenix data center. The contract opportunity is primarily serving state agencies that require robust disaster recovery capabilities, with a specific focus on ensuring geographic separation and infrastructure resilience that can withstand potential regional disruptions. The current solicitation is for a five-year contract extension, with a posting date of February 6, 2025, and a response deadline of February 11, 2025.
The procurement appears to be a direct sole source procurement with no specific set-aside designations or restrictions on vendor types. The contract involves Pima County and Tucson City jurisdictions, with the primary vendor being Ark Data Centers. While no specific budget range is explicitly stated, the comprehensive infrastructure requirements suggest a significant investment in data center services. The state has conducted extensive assessments to validate that no alternative data center in the Tucson area meets their critical survivability standards, which justifies the sole source approach. The incumbent vendor, originally Involta and now rebranded as Ark Data Centers, has been the state's data center partner since 2020, demonstrating a established relationship and proven capability to meet the state's complex technical requirements. The procurement aims to ensure continuous, uninterrupted data center services that can support state agency operations during potential disaster scenarios.
Opportunity text
The State of Arizona needs to have a full disaster recovery site for any hard metal servers that are needed to support business continuity. To have diverse data centers requires data centers to be located with a geographical separation with a minimum of a 25 mile separation. Even though data centers in Phoenix Metropolitan area could meet the 25 mile separation, a natural disaster could impact the power grid in this area. In 2020, the State signed a 5-year Agreement with Involta and moved their Tucson Data Center from the aging and inadequate location at the 400 Congress building, to the current location.
There are two known potential data center sites in Tucson but one does not meet the critical standards for the State of Arizona for survivability per Data Center assessments conducted by the State, These assessments identified critical requirements that are not available in the other data center. Taking this risk could jeopardize the State of Arizona being survivable during times when the disaster recovery site needs to provide full connectivity to the State of Arizona agencies. Some of the critical requirements are:
- 66' minimum separation for power coming into building (Diverse paths)
- 66' minimum separation for carrier connections coming in to building (Diverse paths)
- Two MMRs that carriers can install diverse paths and equipment for diverse paths out to floor space
- Low flood risk
- Low nearby business risk
- Must have good representation of Carriers that closely mirrors the State's contracted Carriers in its Phoenix Data Center
The Data Center assessments were performed per ANSI/BICSI 002-2014 Data Center Design and Implementation Best Practices.
Because of the stated reasons, the State determines that no reasonable alternative sources exist for a disaster recovery site for agencies' servers and equipment and the State intends on extending its Contract with Involta, now rebranded as Ark Data Centers, for an additional five (5) years.