Niwot Loop Concrete Bridge Approaches
Closed State & local contract opportunity Posted
- Solicitation number
- BID-314-26
- State
- Colorado
- Responses due
Opportunity facts
- Jurisdiction
- NIGP codes
- 90976 Site Work
- 91051 Masonry, Concrete, And Stucco Maintenance, Finishing, And Repair (Includes Inside Concrete Sawing And Grouting Work)
- 912 Construction Services, General, Including Maintenance And Repair Services)
- 91216 Boring, Drilling, Testing, And Soundings, Including Concrete Coring
- 91223 Construction, General (Backfill Services, Digging, Ditching, Road Grading, Rock Stabilization, Etc.)
- 91313 Construction, Bridge And Drawbridge (Includes Reconstruction/Rehabilitation)
- 91327 Construction, Highway And Road
- 91347 Construction, Sidewalk And Driveway (Includes Pedestrian And Handicap Ramps)
- 91361 Construction, Vertical, Concrete, Pour-In-Place, Form/Place/Finish
- 91371 Maintenance And Repair, Highway And Road (To Include The Removal Of Asphalt, Concrete, Bitumens, Etc)
Opportunity details come from bouldercounty.bonfirehub.com. Updated .
About this opportunity
Boulder County Parks & Open Space Department is requesting proposals for concrete bridge approach construction at the Niwot Loop Trailhead (7901 Mineral Road, Unincorporated Niwot, Colorado), with proposals due October 8, 2026 at 3:00 p.m. via electronic submittal through the Boulder County Bonfire portal and public bid opening via Microsoft Teams.
The project replaces unsustainable crusher-fines approaches at two bridges (Bridge 1811 and 1812, each 40 feet long and 8 feet wide with 10,000-pound gross vehicle weight capacity) with concrete construction to address drainage, trail sustainability, and accessibility for all users including those with mobility challenges. The contractor must complete all work within thirty consecutive calendar days following issuance of a Notice to Proceed, with a minimum fourteen-day advance notice required to BCPOS for public notifications and trail closures. Work hours are restricted to Monday through Friday, 6:00 a.m. to 7:00 p.m.
Key deliverables include mobilization and demobilization, excavation and subgrade preparation, six-inch Class 6 aggregate base course installation, concrete placement conforming to CDOT Class B specifications (minimum 4,500 psi compressive strength at twenty-eight days) totaling approximately 24 cubic yards, proctor density testing at 95 percent standard compaction for three locations, seven-day and twenty-eight-day compressive strength testing, Emergency Management Plan, Field of Debris Sediment track-out control, temporary fencing and barricades, portable restroom facilities, site restoration, and utility locates. The contractor must possess experience in civil and concrete construction, CDOT Class B flat work, and heavy and light equipment operation.
Payment and performance bonds equal to 100 percent of the proposed cost are mandatory and must be included in the total bid amount. The contractor will receive payment as a single lump sum upon project completion and inspection approval. Contractors must submit a W-9 form dated within the past twelve months and, if awarded, provide a current Certificate of Good Standing from the State of Colorado. Insurance requirements include Commercial General Liability ($1,000,000 per occurrence, $2,000,000 aggregate), Workers' Compensation at statutory limits with $100,000 Employer's Liability, and Pollution Liability ($1,000,000 per occurrence and aggregate), with Boulder County named as additional insured. No pre-bid meeting will be held. All questions must be submitted through the Bonfire portal.
Opportunity text
Boulder County Parks & Open Space (BCPOS) Department is seeking proposals for Concrete Bridge Approaches near the Niwot Loop Trailhead. The property address is 7901 Mineral Rd Unincorporated, Niwot, CO, 80503. The current crusher-fines approaches to the bridges have proven unsustainable due to the steep gradation leading in and out at both bridge locations. Trail sediment encroaches and settles onto the bridges which raises public safety concerns and premature degradation of the bridge decking. The proposed concrete improvements will ensure proper drainage, long-term trail sustainability, and improved accessibility for all trail users including those with mobility challenges. If you have any questions about the Boulder County procurement process, please email procurement@bouldercounty.gov. [Submittal Instructions](https://bouldercounty.gov/government/budget-and-finance/procurement/bid-opportunities/submittal-instructions/) [Americans with Disabilities Act and Equal Opportunity Notice](https://bouldercounty.gov/government/ada-eeo-notices/)
Files
| File | Type | Posted |
|---|---|---|
| 6-5. Public Opening Information.pdf | ||
| 4-3. Bid Tab.docx | DOCX document | |
| 5-4. Boulder County Construction Sample Contract.docx | DOCX document | |
| 9-BID-314-26 Addendum 1.pdf | ||
| 8-BC Exhibit A Niwot Loop Concrete Bridge Approaches 2938.pdf | ||
| 7-Attachment A, B, C, D, E, F, G.pdf | ||
| 2-1. BID Information.pdf | ||
| 1-Vendor Information for Bonfire - Fillable.pdf | ||