Central Energy Plant Construction

Closed State & local contract opportunity Posted

Solicitation number
ITB 2026-0810
State
Florida
Responses due

Opportunity facts

Point of contact

Updated .

About this opportunity

The Melbourne Airport Authority is requesting bids on Central Energy Plant construction at Melbourne Orlando International Airport in Melbourne, Florida, with sealed proposals due September 17, 2026, at 2:00 p.m. EDT and a mandatory pre-bid conference and site visit on August 19, 2026, at 11:00 a.m. EDT. Davis-Bacon wage rates apply to this federally funded project. Positive efforts toward utilization of Brevard County businesses, small businesses, minority-owned firms, and women's business enterprises as subcontractors are required. Bidders must be Florida-licensed Division I general contractors.

The scope encompasses demolition of the existing chiller plant and construction of an enclosed Central Energy Plant structure with new water-cooled chillers and cooling towers on the roof, installation of a new main electrical distribution panel, and installation of a pre-purchased generator. Work must comply with the Florida Building Code, Florida Mechanical Code, National Electric Code, NFPA standards, and federal regulations including FAA and TSA requirements. The contractor is responsible for maintenance of traffic, coordination with other active contractors, and continuous support to airport operations during construction while the airport remains operational. The contractor must establish an Environmental Protection Plan within 14 days of award, submit a preliminary construction schedule within 14 days of Notice to Proceed, and a detailed baseline schedule within 21 days using Critical Path Method scheduling in Primavera software. A minimum of 1.5 percent of the original contract amount or $75,000, whichever is less, must be allocated for construction scheduling activities. Monthly schedule updates and progress reports are required throughout the project.

The budgeted project cost is $4,200,000. The anticipated schedule is 52 calendar weeks from Notice to Proceed. Liquidated damages are assessed at $1,000 per day for delays, increasing to $1,500 per day after 30 days beyond substantial completion. A bid bond or certified check equal to 5% of the bid amount must accompany proposals; a public construction bond equal to 100% of the contract award is required before execution. Written questions are due September 10, 2026, at 2:00 p.m. EDT. Additional site visits are available Tuesdays and Thursdays between August 20 and September 3 by advance appointment with 24 to 48 hours' notice.

Opportunity text

The Melbourne Airport Authority (MAA) is seeking to replace the MEP and HVAC systems within the original terminal that was constructed in 1989. Equipment has been prepurchased in the first phase of this multi-phase project. Phasing is based on the grant funding available from both State and Federal resources. This phase of work is to replace the Central Energy Plant (CEP) with an enclosed structure with new water cooled chillers and cooling towers on the roof. This phase of work will also create a new main distribution panel for the electrical serving the CEP and the existing 1989 terminal. A new generator, pre-purchased, will also be installed in this phase. This is a Lump Sum Contract. The successful bidder will be responsible for maintenance of traffic, coordination with other contractors that may be doing work within the area, and for providing maximum support to the Melbourne Airport Authority in maintaining their operations and other functions at times specified by the Owner during installation. Construction will occur while the airport is operational, and provisions will need to be made to accommodate existing airfield activities adjacent to the project zone.

Files

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Similar opportunities
  • Ask GovTribe AI about this opportunity