00_00_01_Ad_RFB_CEP_26081001.pdf

PDF 198 KB Posted

Attached to
Central Energy Plant Construction
Solicitation number
ITB 2026-0810
Issued by
Brevard County, Miramar Beach CDP, Florida

About this file

This is a Request for Bid (RFB20260810-01) issued by the City of Melbourne Airport Authority for the Central Energy Plant Construction Project at Melbourne Orlando International Airport in Melbourne, Florida. The project involves replacing the mechanical, electrical, and plumbing (MEP) and HVAC systems within the original 1989 terminal, specifically by constructing an enclosed Central Energy Plant structure with new water-cooled chillers and cooling towers on the roof. The scope also includes installing a new main distribution electrical panel serving the CEP and existing terminal, and installing a pre-purchased generator. Bid packages became available on August 10, 2026, in PDF format from Sandra Acevedo at 321-723-6227 ext. 123 or sacevedo@mlbair.com. A mandatory pre-bid conference with site visit is scheduled for August 19, 2026, at 11:00 AM EDT at the Airport Authority Board Room. Additional site visits are available on Tuesdays and Thursdays between August 20 and September 3, 2026, by advance appointment with 24 to 48 hours' notice and a government-issued ID requirement. Written questions must be submitted by 2:00 PM on September 10, 2026, with responses provided via addendum. Sealed proposals are due by 2:00 PM EDT on Thursday, September 17, 2026, at which time bids will be publicly opened and read aloud. No bids may be withdrawn for sixty calendar days following the bid deadline.

This is a lump sum contract awarded to the lowest qualified bidder meeting experience and financial responsibility requirements. A bid bond or certified check equal to 5% of the total bid amount must accompany each proposal. A public construction bond equal to 100% of the awarded contract amount will be required prior to contract execution. The project is federally funded with Davis-Bacon wage rates applicable. The successful bidder must demonstrate financial responsibility, relevant experience, qualifications, and satisfactory completion of similar previous projects within five business days of bid opening. The bidder will be responsible for maintenance of traffic, coordination with other active contractors, and maximum support to the Melbourne Airport Authority to maintain operations during construction while the airport remains operational. The Melbourne Airport Authority reserves the right to reject any or all proposals with or without cause.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REQUEST FOR BID – RFB20260810-01

CENTRAL ENERGY PLANT CONSTRUCTION

At

MELBOURNE ORLANDO INTERNATIONAL AIRPORT

MELBOURNE, FLORIDA

NOTICE IS HEREBY GIVEN that sealed proposals from qualified Contractors for the CENTRAL ENERGY PLANT CONSTRUCTION PROJECT will be received by the CITY OF MELBOURNE AIRPORT AUTHORITY at the office of the Executive Director, Melbourne Orlando International Airport, One Air Terminal Parkway, Suite 220, Melbourne, Florida 32901 until Thursday, September 17, 2026, at 2:00 PM EDT at which time proposals will be publicly opened, read aloud, and submitted for evaluation. Late proposals will not be accepted.

Bid packages will be available on Monday, August 10, 2026 in .pdf and may be obtained from Sandra Acevedo, Executive Assistant, who may be contacted at 321-723-6227 ext. 123, or by e-mail at sacevedo@mlbair.com. Paper copies will not be available.

A Mandatory Pre-Bid Conference will be held in the Melbourne Airport Authority Board Room, One Air Terminal Parkway, Suite 220, Melbourne, Florida 32901 on Wednesday, August 19, 2026 at 11:00 AM EDT, at which time a site visit will follow. Additional site visits for bidders needing additional information may visit the site between August 20, 2026, and September 3, 2026, on Tuesdays, or Thursdays only. The site is in a secure area of the Airport requiring escort. To arrange, please contact Sandra Acevedo at 321-723-6227, ext. 123, or sacevedo@mlbair.com and provide 24 to 48 hours advance notice. A government issued ID will be required.

During the bid period, only written questions received by 2:00 PM on Thursday, September 10, 2026 will be accepted. Written responses will be distributed to all Bidders via an addendum. E-mail questions using the included form to Sandra Acevedo at sacevedo@mlbair.com.

The Bidder agrees to comply with the following requirement: “No member, officer, or employee of the Melbourne Airport Authority or the City of Melbourne, during his or her tenure or for one year thereafter shall have any interest, direct or indirect, in this contract or the proceeds thereof”.

A Bid Bond or Certified Check in the amount of 5% of the Total Amount Bid must be submitted with the bid. A Public Construction Bond in a sum equal to 100% of the amount of the Contract awarded, will be required prior to execution of contract.

This project is federally funded, and Davis-Bacon rates apply.

No bids may be withdrawn after the scheduled time for receipt of bids, for a period of sixty (60) calendar days. To be eligible for award of contract, the successful bidder must submit, upon request and within five (5) business days after the bid opening, evidence of financial responsibility, experience, qualifications, and satisfactory completion of previous similar projects, to the satisfaction of the Melbourne Airport Authority.

The Owner reserves the right to reject all proposals with or without cause, to waive technical errors and informalities, and to accept the proposal that best serves the Owner.

MELBOURNE AIRPORT AUTHORITY

Greg Donovan, A.A.E.

Executive Director mailto:sacevedo@mlbair.com mailto:sacevedo@mlbair.com mailto:sacevedo@mlbair.com

File details come from the government source that posted it. Updated .