About this opportunity

The City of Easton, Pennsylvania, solicited sealed bids for the Bushkill Drive KSAT Trail Extension Project (2026-BDTE) in Northampton County, with bids due August 14, 2026 at 1:00 p.m. prevailing time through PennBid. State prevailing wage rates apply. Contractors must obtain a City of Easton business license before the Notice to Proceed and pay a 0.15 percent business privilege tax on gross receipts if work extends 15 days or more. The City requires E-Verify participation for employees hired after January 1, 2013, and a Workers' Compensation compliance certification before contract execution.

The scope covers approximately 750 linear feet of 8-foot-wide asphalt trail, sawcutting of 525 linear feet of existing pavement, 435 linear feet of 7-foot-wide parallel parking, a 2-foot-wide buffer with thermoplastic markings, PennDOT Type C crosswalks, concrete ADA ramps, site clearing with tree and fence removals, flagpole relocation, removal of abandoned railway ties, grading, and restoration. The bid carries 15 base bid items and two alternates: Alternate 1 for two rectangular rapid flashing beacons, and Alternate 2 for a 6-foot-wide asphalt trail connecting the southern KSAT Bridge Approach to the existing paved trail. Barry Isett & Associates, Inc. provided the engineering. Unit prices must fully compensate labor, materials, overhead, taxes, insurance, and profit.

Bid guaranty equals 10 percent of the base bid. Performance and payment bonds each equal 100 percent of the contract price, and the maintenance bond equals 10 percent. All bonds must come from surety companies authorized in Pennsylvania. Alternate pricing must remain firm for 120 days from bid receipt.

The City will award to the responsible bidder submitting the lowest compliant bid and reserves the right to reject any or all bids. The contractor must mobilize within 45 calendar days of the Notice to Proceed and complete all work within 90 calendar days. The specifications set the anticipated Notice to Proceed at August 3, 2026, on-site construction at August 17, 2026, and substantial completion at October 30, 2026. Work hours are 7:00 a.m. to 5:30 p.m., Monday through Saturday, and the City noise ordinance bars equipment operation from 10 p.m. to 7 a.m. Monday through Saturday and all day Sunday.

Opportunity text

The City of Easton is seeking bids for the Bushkill Drive KSAT Trail Extension Project. The Project consists of improvements along Bushkill Drive in Easton, Pennsylvania, intended to construct and connect a new section of the Karl Stirner Arts Trail and associated roadway, parking, pedestrian, and restoration improvements. The work includes installation of approximately 750 linear feet of 8-foot-wide asphalt trail, sawcutting of existing pavement, installation of approximately 435 linear feet of 7-foot-wide parallel parking lane, and installation of a 2-foot-wide pavement-marked buffer between the parking area and adjacent improvements. Contractors must follow all requirements contained in the specification package and comply with applicable safety, environmental, and regulatory standards.